You are on page 1of 66

EHV SWITCHYARD EQUIPMENTS, SWITCHING SCHMES & LAYOUTS

BY: Ms. Anita Pal Deputy General Manager PE(ELECT) NTPC

Switchyard Type

Conventional Air Insulated Type. Gas Insulated type. Outdoor Gas Insulated type.

Selection of Bus Switching Scheme

PRE-REQUISITES
1)System security 2)Operational flexibility 3)Simplicity of protection arrangements 4)Ability to limit short circuit levels (ease of sectionalizing) 5)Maintenance Its effect on system security 6)Ease of extension 7)Total land area 8)cost

DESIGN GUIDELINES CONTD

OPTIONS/ALTERNATIVES 1)Single sectionalised bus 2)Main and transfer bus 3)Sectionalised Main bus with transfer bus 4)Sectionalised double main and transfer bus 5)Double Bus Scheme 6)Ring bus 7)One and a half breaker 8)Double bus, double breaker

CONTD

DESIGN PRACTICES/PHYLOSOPHY
1) Consideration in Selection of Bus Switching Scheme

2) Comparison of Schemes
a) Sectionalized main bus with transfer bus (Scheme-I) b) Sectionalized double main and transfer bus (Scheme-II) c) One and a half breaker (SchemeIII)

DISCUSSIONS OF SCHEMES

SCHEME 1

Main and Transfer Bus Scheme

SCHEMES CONTD

SCHEME 2

Sectionalised Double Main and Transfer Bus Scheme

SCHEMES CONTD
SCHEME 3

One and Half Breaker Bus Scheme

System Security (Reliability

Main & Transfer

Double Main & Transfer i) require operation of one breaker ii) supply would be interrupted until all the feeders are transferred to the healthy bus iii) No alternate path (Offline redundancy available)

One & Half Breaker i)require operation of two breakers ii) continuity of supply is maintained because each circuit gets fed through two paths iii) Alternate path is available (Online redundancy available)

i) feeder fault ii) Bus fault

iii) Redundancy in design

i) require operation of one breaker ii) supply would be interrupted until all the feeders are transferred to the healthy bus iii) No alternate path (Offline redundancy available)

Operational Flexibility:

Switching operation to take out the breaker from the bay more extensive

Switching operation to take out the breaker from the bay more extensive

A breaker can be taken out of service without the need for additional switching
Protection arrangement is simplified as no AC & DC switching involve and Bus differential protection is simple. Sectionalising of bus bars or introduction of reactors in buses with a view to limit short circuit level is adoptable.

Simplicity of Protection Arrangements

Protection arrangement involves AC & DC switching .

Ability to limit Short Circuit Levels (Ease of Sectionalizing)

Protection arrangement involves AC & DC switching & bus differential protection is complicated as it involves CT switching. Sectionalising of bus bars or introduction of reactors in buses with a view to limit short circuit level is adoptable.

Sectionalising of bus bars or introduction of reactors in buses with a view to limit short circuit level is adoptable.

Ease of extension

Switchyard shall be suitable for future extension without loss of feeders. This scheme is flexible for such future additions

Switchyard shall be suitable for future extension without loss of feeders. This scheme is flexible for such future additions

Switchyard shall be suitable for future extension without loss of feeders. This scheme is flexible for such future additions

Total land area

This scheme occupy more or less the same land area as of the other two schemes. one breaker per feeder is required

This scheme occupy more or less the same land area as of the other two schemes. one breaker per feeder is required

This scheme occupy more or less the same land area as of the other two schemes. Three breaker per 2 feeder is required

Cost

Switchyard layout
Objective:
Substation layout consists essentially in arranging a number of switchgear components in an orderly pattern governed by their function and rules of spatial separation as described in electrical single line diagram.

Pre-requisites: 1) single line diagram 2) general layout plan of power plant 3) orientation of line evacuation 4) control room building

LAYOUT CONTD

1)

2)

Options / Alternatives The layout will vary for the following: Switching schemes Type of insulation - Air Insulated/Gas Insulated.

LAYOUT CONTD

Design Philosophy / Practice 1) Space around the switchyard 2) Switchyard location 3) Switchyard fencing. 4) Clearance. i) phase to earth clearance ii) phase to phase clearance iii) section clearance iv) ground clearance

TABLE I: INSULATION LEVELS & CLEARANCE REQUIREMENTS AT DIFFERENT VOLTAGE LEVELS


INSULATION LEVELS

NOMINA L SYSTEM VOLTAG E KV

LIGHTNING IMPULSE LEVEL (kVp)

SWITCHING SURGE LEVEL (kVp)

POWER FREQUEN CY IMPULSE LEVEL (kVrms)

HIGHEST SYSTEM VOLTAGE KV

MINIMUM CLEARANCE

BETWEEN PHASE AND EARTH (MM)

BETWE EN PHASES (MM)

GROUND CLEARA NCE (MM)

SECTION AL CLEARA NCE (MM)

HEIGHT OF SUPPOR TS (mm)

33 66 132 220 400 765

170 325 650 1050 1425 2100

1050 1550

70 140 275 460 630 830

36 72.5 145 245 420 800

320 630 1300 2100 3500 6400

320 630 1300 2100 4000 9400

3700 4000 4600 5500 8000 --

2800 3000 3500 4300 6500 10300

2500 2500 2500 2500 2500 2500

Clearance contd
5) Equipment spacing a) Ease of maintenance/removal of equipment. b) Equipment foundation & their cable trenches. c) Distance between LA and equipment based on the protection reach of LA. d) The spacings are generally kept in order to achieve various clearances specified at Table-I.

Clearance contd
6) Bus bars:
The bus bars of 400 kV switchyard are generally made up 4 IPS aluminum tube or Quad Moose rated for 3000 A. The bus bars of 220/132kV switchyard are generally made up of 3 IPS aluminum tube or quad/ twin moose conductor. Bus bars are placed at right angles to the feeders for tapping the power.

7) Equipment Interconnection

8) Spacer spans and locations


9) Connection Level 10) Land & Road Layout 11) Sequence and mounting of line traps

Clearance contd.
12) Control Room Layout 13) Lighting System 14) Cabling Philosophy

15) Gravel Filling


16) Earthing System 17) Lightning Protection System

EVOLVING A SUBSTATION LAYOUT


LAYING OUT A SUBSTATION INVOLVES STEP-BY-STEP PROCEDURE. MOST IMPORTANT POINTS TO BE CONSIDERED ARE BRIEFLY DESCRIBED BELOW: THE IMPORTANT ELECTRICAL PARAMETERS ARE ESTABLISHED BY THE SYSTEM DESIGN. THE MAIN PARAMETERS ARE: 1) THE VOLTAGE AND BASIC INSULATION LEVEL OR SWITCHING SURGE LEVEL., THE SITE AND CLIMATIC CONDITIONS, THE METHOD OF CIRCUIT CONNECTION, AND SWITCHING OVER-VOLTAGE CONDITIONS. 2) THE BUS BAR SYSTEM DIAGRAM, THE NUMBER OF CIRCUITS AND THEIR PURPOSE I.E. THE CONTROL OF GENERATORS, TRANSFORMERS, FEEDERS, ETC. THE DIAGRAM SHOULD INCLUDE DETAILS OF EXTENSIONS AND FUTURE CONVERSION TO A DIFFERENT BUS BAR SYSTEM, IF INTENDED.

EVOLVING A SUBSTATION LAYOUT


1) 2) 3) THE CONTINUOUS CURRENT RATING OF THE BUS BARS AND CIRCUITS. THE SHORT CIRCUIT RATING OF BUS BARS AND EQUIPMENTS. PARTICULARS OF REACTORS, NEUTRAL EARTHING EQUIPMENT AND REACTING, Interconnecting Transformers REQUIRED. METHOD OF CONNECTION OF CIRCUITS, WHETHER BY OVERHEAD LINES OR BY CABLES.

4)

5)
6)

DETAILS OF LIGHTNING PROTECTION EQUIPMENT.


DETAILS OF PROTECTIVE EQUIPMENT, DETERMINING THE INSTRUMENT TRANSFORMERS REQUIREMENTS, CARRIER CURRENT EQUIPMENT ETC.

EVOLVING A SUBSTATION LAYOUT


THE EXTENT TO WHICH CIRCUIT AND BUSBAR OUTAGES FOR MAINTENANCE WILL BE POSSIBLE. SOME PARAMETERS WHICH INFLUENCE THE FORM OF THE LAYOUT ARE DETERMINED BY THE LOCAL CONDITIONS. THESE ARE: 1) THE AVAILABLE LAND AREA, SITE AND CLIMATE CONDITIONS, PLANNING AUTHORITY REQUIREMENTS AND AESTHETIC CONSIDERATIONS DETERMINE THE TYPE OF SUBSTATION. THE DIRECTION OF OVERHEAD LINE ENTIRES POSITION AVAILABLE FOR TERMINAL TOWERS, LOCATION OF TRANSFORMERS AND REACTORS, ETC. THE AVAILABILITY OF MATERIALS AND THE TRANSPORT AND ACCESS FACILITIES. THE CAPABILITY AND SKILL OF THE MAINTENANCE STAFF DETERMINES THE IMPORTANCE OF CLARITY OF LAYOUT AND SIMPLICITY OF MAINTENANCE ZONING.

2)

3) 4)

PREPARATION OF BASIC LAYOUT

WHILE MEETING ALL THE NEEDS ESTABLISHED THE FOLLOWING IDEALS SHOULD BE AIMED AT IN MAKING THE BASIC CIRCUIT LAYOUT. MINIMUM GROUND AREA MINIMUM QUANTITIES OF CONDUCTOR, JOINTS AND STRUCTURE MINIMUM NUMBER OF INDEPENDENT INSULATORS, ESPECIALLY IN THE BUS BAR ZONE. AFTER HAVING DETERMINED THE ELECTRICAL CLEARANCE BE USED A ROUGH CIRCUIT LAYOUT IS MADE. SEVERAL POSSIBLE ALTERNATIVES ARE PREPARED FROM WHICH THE MOST SUITABLE ONE WILL BE SELECTED. SOME VARIATION IS NEEDED, TO MEET THE REQUIREMENTS OF DIFFERENT TYPES OF CIRCUIT. IT IS ALSO NECESSARY TO CALCULATE SHORT CIRCUIT AND ATMOSPHERIC FORCES TO DETERMINE THE STRESSES IN CONDUCTORS, INSULATORS AND STRUCTURES. THESE HELD IN DECIDING THE MOST OPTIMUM DIMENSIONS.

PURPOSE OF EARTHING

THE OBJECT OF EARTHING IS TO MAINTAIN A LOW POTENTIAL ON ANY OBJECT. THE PURPOSE OF A EARTHING SYSTEM IN A SUBSTATION AREA IS TO LIMIT THE POTENTIAL GRADIENT WITHIN AND IMMEDIATELY OUTSIDE THE AREA IS A VALUE, SAFE FOR THE WORKING PERSONNEL. SAFETY IS TO BE ENSURED UNDER NORMAL AS WELL AS ABNORMAL OPERATING CONDITION.

REQUIREMENTS OF A GOOD EARTHING SYSTEM


FOLLOWING BASIC REQUIREMENTS ARE TO BE SATISFIED SO AS TO ENSURE A PROPER AND SOUND EARTHING SYSTEM. 1) THE EARTH RESISTANCE FOR THE SWITCHYARD AREA SHOULD BE LOWER THAN A CERTAIN LIMITING VALUE RA IN ORDER TO ENSURE THAT A SAFE POTENTIAL GRADIENT IS MAINTAINED IN THE SWITCHYARD AREA AND PROTECTIVE RELAY EQUIPMENT OPERATE SATISFACTORILY. FOR MAJOR SWITCHYARDS AND SUBSTATIONS IN INDIA, THIS LIMITING VALUE OF EARTH RESISTANCE (RA) IS TAKEN TO BE LESS THAN 0.5 OHM. THE GROUNDING CONDUCTOR MATERIAL SHOULD BE CAPABLE OF CARRYING THE MAXIMUM EARTH FAULT CURRENT WITHOUT-OVERHEATING AND MECHANICAL DAMAGE. THE MAXIMUM FAULT LEVEL IN THE 400 KV SYSTEM HAS BEEN ESTIMATED TO BE 40 KA AND THIS VALUE OF FAULT CURRENT TO USED IS THE DESIGN OF EARTH MAT FOR THE 400 KV SUBSTATION.

2)

REQUIREMENTS OF A GOOD EARTHING SYSTEM

ALL METALLIC OBJECTS WHICH DO NOT CARRY CURRENT AND INSTALLED THE SUBSTATION SUCH AS STRUCTURES, PARTS OF ELECTRICAL EQUIPMENTS, FENCES, ARMOURING AND SHEATHS OF THE LOW VOLTAGE POWER AND CONTROL CABLES SHOULD BE CONNECTED TO THE EARTHING ELECTRODE SYSTEM.

THE DESIGN OF THE GROUND CONDUCTOR SHOULD TAKE CARE OF THE EFFECT OF CORROSION FOR THE TOTAL LIFE SPAN OF THE PLANT.

Switchyard Equipments.

Circuit Breaker. Disconnectors (Isolators) Current Transformers. Capacitor Voltage Transformers (CVT). Lightning Arrestors. Post Insulators. Wave Traps

General Parameters

Dielectric Parameters .(IEC 694) Power Frequency Voltage. Lightning Impulse Voltage. Switching Impulse Voltage. Corona Extinction Voltage. RIV Level.

General Parameters (Contd.)

Rated Current. Short Time Current. Creepage Distance.

400kV Equipments
a. b. c. d. Rated voltage Rated frequency Rated short time withstand current capacity Insulation levels for 420kV Circuit breakers and Disconnecting Switches i) Rated one minute power Frequency withstand voltage 420 kV 50 Hz 40 kA rms for one (1) second

e.

a)

520 kV rms between live terminals and earth.

ii) Rated lightning impulse withstand voltage

iii) Rated switching impulse withstand voltage

f.

Max. Radio interference voltage at 266kVrms

g.

Corona extinction voltage

610 kV rms across isolating distance. a) +/- 1425 kVp between live terminals and earth. b) +/- 1425 kVp impulse on one terminal and 240 kVp power frequency of opposite polarity on other terminal (across isolating distance). a) +/- 1050 kVp between live terminals and earth. b) +/- 900 kVp impulse on one terminal and 345 kVp power frequency of opposite polarity on other terminal (across isolating distance). 1000 micro volts for frequency between 0.5 Mhz and 2.0 Mhz for all equipment. However, for insulator strings the measurement would be at 305 kV . Not less than 320 kV rms

b)

Circuit Breakers Type (IEC: 62271-100)


MOCB. ABCB. SF6
Rated operating duty cycle- O-0.3 secCO-3 min.-CO Operating mechanism Total Break Time Pre Insertion Resistor ( 300-450)

Disconnectors

HCB Type. Double Break Type. Pantograph type. Vertical Break type. Provision of Earth Switches. Motor / manual operated. Gang operated/Single pole type.

Current Transformer ( IEC 60044, IS 2705)


Dead tank/Live tank type. Bar Primary type. Ring Type. No. of Cores. Ratio. Accuracy. rated primary current Rated burden for metering Knee Point voltage

Capacitor Voltage Transformer (IEC 60044, IS 3156)

Capacitance. Voltage Ratio. No. Of Cores. Accuracy. Output Burden Rated Secondary Voltage

Lightning Arrestor ( IEC 60099)

Gap Type / Gapless Type. Voltage Rating. Energy Capability. Monitoring. Location. Nominal Discharge Current.

Post Insulators

Voltage Rating. Cantilever Strength. Fixing Details.

Wave Trap (IEC 60353)

Rated Inductance(0.5/1.0 mH). Rated current. Band Width. Coupling (Phase to Phase).

SWITCHYARD AUXILIARY SYSTEMS

CONTROL ROOM HVAC FOR CONTROL ROOM A RELIABLE 415V AC SUPPLY ( LT SWGR) 220 V & 48 V DC SUPPLY( BATTERY & BATTERY CHARGER) POWER & CONTROL CABLE LIGHTING ( Yard lighting & indoor lighting of control room) Other items-Clamps, connectors , Insulator strings , BMK etc.

COMPARASON BETWEEN AIS AND GIS SUBSTATION FOOTPRINT FOR HECTOR

192
400kV AIS

400kV GIS Trfr 1 275kV GIS 275kV AIS Trfr 2 Trfr 3 Trfr 4 SVC Trfrs

69

~10%

INDOOR GIS

OUTDOOR GIS - SEISMIC AREAS

PHASE SPACING
Conductor Phase Spacing

OVERHEAD STRUNG BUSBARS

SAG DUE TO CONDUCTOR


Lc T 9,81.mi

fs

fs = 9,81.mi.Lc2 8.T fs = maximum conductor sag (m) mi = mass of conductor (kg/m) Lc = conductor span length (m) T = tension per conductor (N)

LOW PROFILE SUPPORTED TUBULAR BUSBAR SUBSTATIONS

TUBE SAG EXCESSIVE INCORRECTLY SELECTED

TYPICAL TUBULAR BB BUS SECTION BAY

CANTILEVER FORCES DUE TO FAULT CURRENT COMBINATION SUPPORT STRUCTURE FOR 3 PHASES

Attraction

Repulsion

TUBULAR BUSBAR EXPANSION CLAMP

TUBE

TRANSFORMER FIRE AT MINERVA

Upgradation of transmission voltage from 400kV AC to 765kV AC.

Presently the highest AC Transmission voltage is 400kV only. NTPC is fully geared up for implementing next AC voltage of 765kV. Advantages: Step up from generation voltage to 765kV. High Capacity Transmission to the order of 2500MW per line with lower right of way requirement. 765kV Transmission system is techno economically better option whenever power transmission system requires multi point tapping at various location for catering the load requirement of high growth area. 765kV system offers low transmission losses, resulting in higher utilisation of generating capacity and optimises the resource required for capacity addition.

765kV Major Parameters


Highest system voltage Lightning Impulse voltage Switching impulse voltage Power frequency withstand for 1 min. (rms) : Max. fault level (1 sec.)

: : : :

800 kV rms 2100 kVp 1550 kVp : 830kV(rms) 40 kA

Minimum creepage distance : 20000 mm Max. Radio Interference Voltage : 2500 micro volts. level at 508kV (rms). Corona extinction voltage : 508kV (rms minimum) Phase to earth clearance : 4900 mm Conductor to Structure : 6400 mm Rod to Structure Phase to phase clearance : 7600 mm Conductor to Conductor : 9400 mm Rod to Conductor Section clearance : 10300 mm Average electric field at 1.8 m from ground 10kV/m Average magnetic field 500 micro tesla

((((

ADOPTION OF CONTROLLED SWITCHING OF TRANSFORMER AND REACTORS. Switching of transformer, shunt reactors, capacitors and uncharged overhead lines is normally a 'three-phase' process, where all three phases are switched simultaneously. The actual circuit closing or opening instant is left up to chance. This results in high inrush currents or switching surges causing undue repercussions to switchgear equipment and networks system. For overcoming this the switching in and out is done at desired point on wave so that the overvoltages are reduced.

765KV CIRCUIT BREAKER

765KV DISCONNECTOR WITH 1E/S

THANK YOU!

You might also like