CONSTRUCTION OF 132/33 KV GRID STATION AT QURIYAT AREA AND INSTALLATION OF REQUIRED OVERHEAD LINES IN MUSCAT
GOVERNORATE
CONCRETE PROGRAMME
Location: Quriyat.- OHL
Date: 29.09.2011
Sl.No.
Description
Grade of concrete
Quantity(M)
Time
1/10/2011
Pad at 29/2
C35
19
07.30 AM
1/10/2011
Pad at 18/2
C35
08.00 AM
1/10/2011
Pad at 1/1
C35
5.5
03.00 PM
1/10/2011
Chimney at 18/1
C35
2.5
08.00 AM
1/10/2011
PCC at AP-1A
C15
5.5
04.00 PM
1/10/2011
PCC at 24
C15
03.00 PM
2/10/2011
PCC at AP-1B
C15
5.5
01.00 PM
2/10/2011
Pad at 20/1
C35
15
09.00 AM
2/10/2011
Pad at AP-1
C35
49
02.00PM
10
2/10/2011
Chimney at 1/1
C35
2.5
04.00 PM
Remarks/Pump
requirement
With Pump
11
2/10/2011
Chimney at 29/2
C35
4.5
09.00 AM
12
3/10/2011
PCC at 24A
C15
08.00 AM
13
3/10/2011
Pad at AP-23
C35
15
02.00 PM
14
3/10/2011
Chimney at 18/2
C35
2.5
09.00 AM
15
3/10/2011
Chimney at AP-1
C35
04.00 PM
16
4/10/2011
PCC at 6/8
C15
02.00 PM
17
4/10/2011
Pad at AP-1A
C35
44
09.00 AM
18
4/10/2011
Chimney at AP-20/1
C35
02.00 PM
19
5/10/2011
PCC at 26/1
C15
04.00 PM
20
5/10/2011
Pad at AP-24
C35
14
02.00 PM
21
5/10/2011
Chimney at AP-1A
C35
09.00 AM
22
6/10/2011
Chimney at AP-23
C35
02.00 PM
23
6/10/2011
Pad at AP-1B
C35
44
09.00 AM
With Pump
With Pump