AL KHOR HOUSING PROJECT, ZONE 14 & 15.

BILL NO 3 INFRASTRUCTURE ZONE - 14

Item

Description LANDSCAPING (Cont'd) Hard Landscaping Kerbs Approved type hydraulically pressed pre-cast concrete kerb including excavation, backfilling, disposal, concrete foundation and backing, dowel bars and cement/sand mortar filling at joints as specified.

Qty

Unit

Rate QR

Amount QR

A Driveways parking and pavement areas - straight B Ditto, - curved Shaded parking Construction of mock-up shading for parking as indicated in drawing including all civil works, frameworks, finishes and all other related works excluding pavements as per drawing and specification C 6000 mm x 11200 mm size D 6000 mm x 8400 mm size Road markings Road marking entry and exit signs, direction indication arrows with approved coating system as specified The application and thickness of coatings to be as per Qatar Traffic Manual. E To driveways and parking areas

4441 541

m m

23 28

No No

Item

TO COLLECTION

QR

13,000,000

827/10

3/1/3

AEB-QS