AHP STATUS AS ON 05-01-2012

1. DRAWING STATUS: TOTAL DRAWINGS Drawings submitted Approved drawings INFORMATION CATEGORY PENDING DRAWINGS % OF COMPLETION
Pending from MB Vendor Drawings for PMCC Vendor Drawings for MCC Vendor Drawings for Battery Charger Vendor Drawings for 7.2KV Bus Duct Vendor Drawings for 415V Bus Duct Data Sheets of Lighting Fixtures Cable Interconnection diagram QAP of PMCC/MCC panels QAP of Battery charger 1-Jul-11 1-Jul-11 1-Jul-11 11-Jul-11 11-Jul-11 6-Aug-11 15-Sep-11 1-Jul-11

86 Nos 76 Nos 51 Nos 23 Nos 10 Nos 88%

2.MATERIAL STATUS : SUPPLY -70 NOS

MATERIALS RECEIVED 11 /6.9 Kv Transformer 5 MVA, ONAN type 11KV & 6.6KV HT Cables % OF COMPLETION -1 No -2Nos

- 03NOS

- 4%

3. ERECTION STATUS:

-NIL