ELECTRICAL ENGINEER

Alexius Lewi Silvanus Adjie

Career Summary

More than thirteen (13) years of experience in the electrical system design in bidding
stage and basic/detail engineering design stage, for industry, power substation and
oil/gas project. The experience includes preparation of electrical design criteria,
analysis of electrical power system such as short circuit, load flow and relay
coordination studies. Included development equipment specification and data sheet.

Experience

Senior Electrical/Application Engineer :


June 2009 - Now (2 years)
Areva T&D / Schneider Electric (Oil and Gas Division), Jakarta. Responsible for
electrical engineering support for project on tender stage and execution stage.

As Tender support : Review client Material Request, Review vendor quotation,


Technical Bid Evaluation, Technical clarification. Participate on some projects.

As Project support : Technical coordinator, Technical clarification, Design


engineering review. Major project (still on going) is :

Air Liquid France, (end user : RasGas) - Rhea Project,


Technical Support on Tendering and Execution Project.
Areva supply equipments : 6.6kV MV Switchgear (Indonesia), 415V LV
Switchgear, 6.6kV/415V Busduct (China), 6.6kV/415V Transformer (China)
Assigned as technical coordinator.

SK Engineering and Construction Korea, (end user : ADCO) - BAB Gas


Compression Project,
Technical Support on Tendering and Execution Project.
Areva supply equipments : 33kV GIS Switchgear (Germany), 3.3kV Switchgear
(Germany), Harmonic Filter Equipment [33kV Capacitor Bank (Finland), Reactor
(Canada), Disconnecting Switch (Italy) and support/accessories], LV Switchgear
(France), LV Distribution Board (Jakarta), Busduct (Malaysia).
Assigned as technical coordinator, stay 6 months in Skec Seoul Korea.

SBM - Deep Panuke Project,


Technical Support on Execution Project.
Areva scope of supply : Medium and Low Voltage Switchgear, Study of short
circuit calculation and protection coordination

Page 1 of 6
ELECTRICAL ENGINEER

Senior Electrical Engineer :


January 2006 - December 2008 (3 years)
McDermott Indonesia, Jakarta. Responsible for electrical engineering activities
such as technical bid evaluation, mechanical package review, electrical specification
and datasheet review, input data to drafting and review. Major projects included are:-

Cuu Long Joint Operating Company (CLJOC), Sutu Field Development –


Su Tu Den Northeast Vietnam,
Preliminary and Detail engineering design of Well Head Platform B (WHPB) that
tie to the existing CPP through WHPA. WHPB is designed with 480V power
supply, feed by CPP through step-down transformer 13.8kV-480V and 480V
Standby Diesel Engine Driven Generator for emergency power.
Responsible for Review/Update Calculation (Load Calculation, Load Flow, Motor
Starting and Short Circuit), Specification (Liquid Filled Transformer, Electrical
Requirement for Offshore Facilities and Package Equipment, Marine Aids to
Navigation, Grounding and Bonding, Neutral Grounding Resistor, Cable,
Electrical Equipment Proofing, Electrical Testing and Commissioning,
Synchronous Generator, MV Load Break Disconnect Switch, Switchgear and
MCC, UPS, DC Supply System, Small Power and Lighting) and Data sheet (MV
Load Break Disconnect Switch, Switchgear and MCC) included Request for
Quotations (Load Break Disconnect Switch, Power Transformer, Small Power
and Lighting, Navigation Aid and Foghorn), Technical Bid
Clarification/Evaluation, Material Requisition, also input data to drafting and
review, review electrical bulk material and vendor data.

Ras Laffan LNG Company, Ras Gas Alpha Offshore Platform Expansion
Project
Detail engineering design to add One 3000kW Diesel Engine Generator, to
extend and add infrared thermography facility on 6.6kV existing Switchgear and
fireproofing on 6.6kV existing cables.
Responsible for review/study/technical bid evaluation and detail design of new
diesel engine generator to operate island mode or parallel with existing
generators, investigate existing system and detail design of switchgear
extension by installing new cubicles via enclosed busbars included order
material, investigate of 6.6kV existing cables for fireproofing, investigate back
cover of existing 6.6kV switchgear to install infrared thermography included
order material.

Proposal : Bid Engineering Support


Project : Carigali-PTTEPI Operating Company (CPOC) SDN BHD - Central
Processing Platform Topside and Jacket for Block B-17 Gas Field Development
Project

Page 2 of 6
ELECTRICAL ENGINEER

Responsible for Request for Quotation and Technical Bid Evaluation of


Distribution Board, Power Transformer and Switchgear Building. Also Review
of some mechanical package quotation.

PETRONAS, Kepodang Gas Development Project

Detail early engineering design of Central Production Platform (CPP), Satellite


Wellhead Tower (WHT) and Onshore Receiving Facility. The CPP will be
equipped with 380V two Duty Gas Engine Main Generator and Single Diesel
Driven Services Generator.
Responsible for review/update data sheet (Static UPS and Batteries, Standby
Generator, Process and Utilities Switchboard, Navigation Aids, Fuel Gas
Composition, DC Power Supply Unit, Essential Services Generator, Main
Generator, Motor) and mechanical package review for Air Compressor, FG
Heater, Gas Turbine and Glycol.

Senior Electrical Engineer :


November 2003 - January 2006 (2 years and 2 months)
VA Tech Transmission and Distribution Company, Jakarta, Indonesia.
Responsible for electrical detail design for High Voltage (150kV-500kV) Substation
project. The projects are located in Indonesia, Vietnam and Africa.
The mainly activities in electrical design consist of:
 Electrical estimation in tender process
 Arrange technical specification for HV Circuit breaker, HV Current
transformer, HV Capacitor Voltage Transformer, HV Disconnecting Switch,
HV Surge Arrester, Line Trap, Disc Insulator, MV Cable, MV Cubicle, Neutral
Ground Resistor, Power Line Carrier, Post Insulator, Power Transformer,
Station Service Transformer, 110Vdc/48Vdc Battery and Charger and
Panel/Distribution Board.
 Arrange Calculation Note for HV Current Transformer, MV Cable, High
Voltage Conductor, Earthing Grid, 110Vdc/48Vdc and Charger.
 Determine high voltage tension/suspension string set and connector.
 Prepare technical document for material order and involved in material
purchasing process with local and worldwide suppliers.
 Review electrical drawing such single line, earthing grid, control room layout,
control/relay panel layout, cable route, lighting layout and installation detail.
 Review electrical diagram/schematic of HV Substation
 Review detail electrical design/specification from supplier/contractor such
three line diagram of distribution panel, MV cubicle, Circuit Breaker, Battery
and charger, Electrical Equipment, HV Equipment.
 Determine protection setting of some protection relays such distance
protection, phase over current, earth fault, directional over current/earth fault,
transformer differential protection and busbar protection.

Major projects included :


 500kV/220kV Phu My Substation, 220kV Nha be Substation, 500kV Phu lam
Substation, Vietnam
 220kV/110kV Dai Ninh Substation, Vietnam

Page 3 of 6
ELECTRICAL ENGINEER

 132kV Sondu Miriu Substation, Africa


 150kV Tulungagung Substation
 150kV Panaran Substation, 150kV Sagulung Substation and 150kV Sei
Harapan Substation
 150kV Tasikmalaya Substation
 150kV Praya Substation, 150kV Ampenan Substation and 150kV Endok
Substation
 150kV Bungus Substation
 500kV Muara Tawar Substation
 500kV Ungaran Substation

Electrical Consultant :
April 2003 - November 2003 (8 months)
Bandung Institute of Technology
Responsible for calculation of Jawa Bali Power System Reliability using Fortran
Programming Language.
Client : Electrical Government Company (PLN)

Senior Electrical Engineer :


September 1996 - August 2001 (5 years)
Freeport Indonesia Company, Tembagapura Papua, Indonesia.
Responsible for system and detail design of electrical system various internal
projects.
The mainly activities consist of :
 Estimation of project on electrical scope
 Concept design of electrical system included calculation of electrical source
availability
 System or Detail of Electrical Design drawing such LV/MV/HV Single Line,
Switchgear/Motor Control, Layout, Installation Detail, Grounding and Lightning
Protection.
 Short Circulation Calculation/Study
 Determine Protection Relay Setting and Over Current Coordination for some
relays i.e., General Electric Multilin Relay 469 (motor protection),
745(transformer protection) and 750 (switchgear protection).
 Power System/Load Flow Study/Analysis
 Troubleshooting of electrical control wiring
 Technical advise for improving electrical system
 Electrical technical authority for additional extension on customer installation
 Arrange some internal electrical trainings such Basic electrical circuit, Three
phase system, Short circuit calculation, Lighting, Transformer, Motor and
Protection, Over Current Protection, Over Current Coordination

Major projects included :


 Underground Mining Expansion
 5kV Dom Fans
 Mess hall
 12 Bay Truck Shop

Page 4 of 6
ELECTRICAL ENGINEER

Electrical Engineer :
June 1996 - August 1996 (3 months)
Truba Jurong Indonesia Company, Jakarta, Indonesia.
Support in the design of industrial building.

Education
Bachelor degree (ST) in Electrical Power Engineering
Bandung Institute of Technology (ITB), 1990

Master degree (MT) in Electrical Power Engineering


Bandung Institute of Technology (ITB), 2001

Qualification/Professional Activities
Ikatan Alumni ITB

On Job Training and Courses


Power System Protection Course
Industrial Power System Analysis
Power Flow Analysis
Power Distribution System
Engineer In Trainee
Management and Safety
Internal Audit

Electrical Software Experience


ETAP
SKM Power Tool
Easy Power
Luxicon Lighting
Hubbel Lighting

Referee

Name Company Contact No

Andreas Tjoa Areva T&D / Schneider -


Electric

Chandra Barlean McDermott Indonesia +62 (0) 816 1325 118

Page 5 of 6
ELECTRICAL ENGINEER

Frontry Sudjatmiko Schneider Indonesia +62 (0) 817 004 2004


(ex VATECH T&D) +62 (0) 817 634 9531

Yostiarto Tamba BHP Biliton Australia +61 (8) 8405 24224


(ex Freeport Indonesia)

Firms
Jun. 2009 – Now Areva T&D and continue to Schneider Electric.
Jan. 2006 – Dec 2008 McDermott Indonesia.
Nov. 2003 – Jan. 2006 VA TECH Transmission and Distribution Company.
Apr. 2003 - Nov. 2003 Bandung Institute of Technology
Sep. 1996 - Aug. 2001 Freeport Indonesia Company.
Jun. 1996 - Aug. 1996 Truba Jurong Company.

Personal Details
Address : Jl. Deme 12A Bandung 40273
Place/Date of Birth : Solo February 16, 1972
Contact no. : +62 (0) 817 630 9989
Permanent email : alexius.lewi@gmail.com
Age : 39
Status : Single
Religion : Katolik
Nationality : Indonesia

Page 6 of 6