Item Action Items Designation Assigned To Due Date
Firefighting water tank(256m3_8*8*6) foundation of pump house 1. 03/01 – S&L requested SEPCO for the GA drawing of the tank to proceed for the foundation Wadi design.Solar PV Solar Photovoltaic Independent Power Project AD Dawasir Update complete BOQ of Plumbing system so as to purchase all equipment 27/12 – S&L is updating the BOQ. S&L to check the standard for the valves. MEETING TITLE: Weekly Co-ordination Meeting #36 SEPCO is proposing for above ground tank for the portable water system. S&L to check the feasibility. 2.MEETING LOCATION: 03/01 – S&L willOnline check and revert for the standard forMOMindoorREFERENCE NO. : #36 Week plumbing system. MEETING S&LDATE: requested SEPCO to provide the vendor input drawings for 03/Jan/2024 overhead tank and above ground tank. Based on vendor REPORT inputDATE: S&L 03/01/2024 MEETING willTIME: check10.30 A.M (India) the feasibility of above ground tank. Pumps flow rate and head is already indicated in the plumbing REPORTED BY: Rahul Mandal CONFIDENTIAL: No specification document. There is no dimension of door frame and window frame in the BOQ. Please confirm that THE PARTIES S&L remarkACKNOWLEDGE THIS ISfor the exact parameters ANpurchase ACCURATE REPORT OF THIS MEETING 3. or SEPCO purchases them as per the market products. Sargent03/01- & LundyS&L will reply today. SEPCO Hydrology reprot has updated and S&L to confirm whether it can meet requirement to cancel the drainage system. 4.Name: 03/01 Rakesh– Raghav S&L explained that drainage will not be required Name:as per the Title: Renewables Manager latest hydrology report. S&L will close the related pending Title :CRS Name: accordingly. Rahul Mandal Pending Civil Documents Status: (electronic initial) (electronic initial) (Every civil document shall be attached the BOQ and AutoCAD drawing.) GA & RC Details for Internal Cable Trench & Tunnel - Control room and Administration building : by 20/1 ATTENDEES GA & RC Details of Foundation, Column (upto FFL), Plinth Beam and Organization Name Email Address Grade slab for 33kV Substation Building: by 20/1 SAMT Fouad Maksoud Design calculation of Foundation for 33 KV Substation Building:by 20/1 Wang Guodong Xia Mingwen GA & RC Details of Foundation, Column (upto FFL), Plinth Beam and Grade SEPCO slab for NG Room :12/01 Zhang Mingfei Design calculation of Foundation for NG Room:12/01 Guan Shousuo FoundationZhangDrawing for 132kV "SA" Support Structure:05/01 Shuhao FoundationRakesh Drawing for 132kV "DIS-SW" Support Structure:08/01 Raghav Sargent & FoundationRahulDrawing for 132kV "EARTH SWITCH" Support Mandal 5. Lundy Structure:08/01 Imran Mushtaq Foundation Drawing for 132kV "CVT" Support Structure:05/01 Other Foundation Drawing for 132kV "CT" Support Structure:10/01
Foundation Drawing for 33kV SVG Container and Equipment.:
SEPCO shall share comments response by today. 03/01- S&L will submit all the AIS drawings progressively by 12/01. GA & RC Details for Lighting Pole Foundation: Foundation Drawing for Lightning Mast.:S&L to follow SEC standard drawing for lightning mast. GA & RC Details for External Cable Trench, Tunnel and Duct bank: No tunnels are applicable. GA & RC Details of Fire water pipe trench:Fire water pipe layout required from HCIS contractor. Minutes of Meeting (date) Page PAGE 1 of NUMPAGES 3
Confirm soil resistivity value for PV area and substation.
6. 03/01- S&L to check and confirm the highest possible resistivity Minutes of Meeting