Critical Path Analysis
Critical Path Analysis
IB Operations Management
Crashing is when you shorten the time taken to complete certain jobs
on he critical path by assigning extra labour and /or equipment.
Node number
Activity Latest finish time (LFT) of preceding activities Node (circles) - to show start and end of activities, and also carry information about earliest start times (EST) and latest finish times (LFT) Arrows to show the flow of activities Hatching ( // ) drawn on the arrows of those activities on the critical path
A A B
3 4
1 3
Neither B nor C can be started until A has been completed, B and C can be carried out concurrently
A C B
1 4 2
3
B D
2
A and B are both independent of each other but both must be completed before C can start
A and B are independent of each other but both must be completed before either C or D is started. C and D can be carried out concurrently
A fitted to B
Screwed to C
A 5 mins
B 3 mins
D 4 mins
//
Critical path = C, D
A 6 C 4 B 10
2
E 2
D 8
0 0
A 6 C 4 B 10
10 2 10
14 3 16
E 2
18 4 18
D 8
0 0
A 6 C 4 B 10
10
14 3 16
E 2
18 4 18
//
D 8
10
//
FLOAT TIME
Float is the spare time available for any activity.
AQA specification states knowledge of TOTAL FLOAT Total float measures the spare time available so that there is no delay to the project as a whole.
CALCULATION
LFT Duration EST = Total Float (This activity) A B C D E 16 10 16 18 18 6 10 4 8 2 (this activity) 0 0 10 10 14 = = = = = 10 days 0 days 2 days 0 days 2 days
Advantages of CPA Time between tasks is reduced to produce a smoothly run, coordinated project links to time based management Improved decision making - construction of the network forces managers to plan forward and to consider all relevant tasks By readjusting float the amount of resources can be minimised, thus improving efficiency Improved working capital control as stock can be ordered on JIT basis The network acts as a control technique to check the progress of the project, which is particularly important if there are penalty clauses for late completion, ie motorway construction