Appendix 1.

2
MahmoodRobinsonOritsejafor v5
Start: 04/06/12 Finish: 25/09/12 Comp: 0% ID: 0 Dur: 81 days

Baseline Network Path


Set up Project
Start: 04/06/12 Finish: 29/06/12 Res: ID: 1 Dur: 20 days

Shoaib Mahmood, William Robinson, Bawo Oritsejafor


Install Life Support in Module Final Test and Debugging
Start: 05/09/12 Finish: 25/09/12 Res: ID: 12 Dur: 15 days

Construct Shell of Module


Start: 02/07/12 Finish: 10/08/12 ID: 2 Dur: 30 days

Wire Module
Start: 13/08/12 Finish: 16/08/12 ID: 5 Dur: 4 days

Start: 17/08/12 Finish: 22/08/12

ID: 8 Dur: 4 days

Engineers, Technicians, Component Costs[5], Other Costs[1] Engineers[400%], Technicians[500%], Component Costs[50], Engineers[400%], Technicians[700%], Component Costs[6.5],Engineers[200%], Technicians[300%], Component Costs[2], Facilities Costs[2], Other Costs[3.2] Res: Res: Facilities Costs[4], Other Costs[0.5] Res: Facilities Costs[5], Other Costs[3]

Engineers[300%], Technicians[500%], Component Costs[6], F

Install Experimentation Package in Module


Start: 17/08/12 Finish: 22/08/12 Res: ID: 9 Dur: 4 days

Install Control and Navigational System into Module


Start: 23/08/12 Finish: 04/09/12 ID: 11 Dur: 8 days

Engineers[200%], Technicians[500%], Component Costs[2], Facilities Costs[2], Other Costs[5.1] Res: Engineers[300%], Technicians[600%], Component Costs[5], Facilities Costs[3], Other Costs[3.6]

Procure Life Support System and Experimentation Package Preliminary Test of Life Support System
Start: 02/07/12 Finish: 13/07/12 Res: ID: 3 Dur: 10 days Start: 16/07/12 Finish: 18/07/12 ID: 7 Dur: 3 days

Preliminary Test of Control and Navigational System


Start: 16/08/12 Finish: 20/08/12 ID: 10 Dur: 3 days

Engineers, Technicians, Component Costs[60], Other Costs[10] Res: Engineers[200%], Technicians[400%], Component Costs[2], Facilities Costs[10], Technicians[400%], Component Costs[2], Facilities Costs[15], Other Costs[2.4] Res: Engineers[200%], Other Costs[4.4]

Procure Components of Control and Navigational SystemControl and Navigational System Assemble
Start: 02/07/12 Finish: 03/08/12 Res: ID: 4 Dur: 25 days Start: 06/08/12 Finish: 15/08/12 ID: 6 Dur: 8 days

Engineers, Technicians, Component Costs[90], Other Costs[10] Res: Engineers, Technicians[500%], Component Costs[5.5], Other Costs[5]

Project: MahmoodRobinsonOritsejafor Date: Thu 22/03/12

Critical Noncritical

Critical Milestone Milestone

Critical Summary Summary

Critical Inserted Inserted

Critical Marked Marked


Page 1

Critical External External

Project Summary Highlighted Critical

Highlighted Noncritical