You are on page 1of 1

MCLEAN.

qxd:Layout 1 1/19/09 11:59 AM Page 79

MCLEAN CONTRACTING CO.

which is about 200,000 cubic yards, that and help them achieve the best possible “We build every crane we have, and
will be pumped to the specified site locat- goal that can be achieved within the con- we have to maintain our equipment
ed at the facility.” fines of the project site.” from the ice in the wintertime, while
Once that work is completed, McLean These questions often plague marine keeping the barges ice-free.
will build a 3,000-foot retention dike. contractors on projects, but companies Marine construction also provokes sev-
“Following us, another subcontractor unfamiliar with the trade would be baf- eral safety hazards, Phillips adds.
will place rip rap on the outboard face fled at the complexities of McLean’s This is where McLean’s award-win-
of it,” Phillips says. work, Phillips says. ning safety program comes in handy.
“Then, following that, about 585,000 “Such things as building a footing for a According to the company, its most
to 780,000 cubic yards of material will structure on land is totally different when valuable resource is its employees and
be dredged out of the inside of this facility you place it in the water,” he notes. “Then, McLean makes every effort to ensure
to build the dikes,” he continues. to add to the problem, moving it to a they remain safe.
“Finally, we’ll finish off the side slopes minus-53-foot elevation. In April, McLean received three awards
and dress it up to make it look like the pro- “This requires months of preparation from the National Safety Council in recog-
posed dike.” to build a cofferdam structure, excavate nition of its stellar safety record – one
the structure and then place a tremie con- being the Million Work Hours Award,
Making it Look Easy crete footing – even before you start with given to the firm after operating for more
Phillips says the greatest challenge of all the actual footing that you really need to be than 1 million man hours without occupa-
on this project is defining where and if building,” Phillips adds. tional injury or illness.
there is enough suitable material to work “There are a lot of fall hazards in cof-
with in the first place. True Professionals ferdam construction, especially in this
“You have to strip many feet off of the Adding to these challenges are the harsh time of year,” Phillips says. “It’s winter
river bottom to get the good material need- weather conditions of Maryland’s relent- and it’s windy. It’s fairly open water and
ed to build the dike,” he explains. less winters. you get a lot of wind and waves and
“It is extremely important to the owner “We often have ice to deal with, frozen shipping traffic.
that we recover as much good material pumps, walkways, etc., that need constant “But we’re a marine contractor, we’ve
from this site as possible, and it is McLean’s attention,” Phillips states. “We have to been doing marine work for over 100 years,
responsibility to work with the owner tie off in areas that are true hazards. and we know what we’re doing.” ■

FEBRUARY 2009 ■ WWW.CONSTRUCTION-TODAY.COM ■ 79

You might also like