This document contains a risk register for a BRT project from Tichborne Way to Gosport Ferry. It lists 12 risks organized by risk ID. For each risk it identifies the risk owner, describes the potential risk event and consequences, provides a current assessment of the risk level and financial score, and outlines the proposed response strategy and tasks to manage the risk. The total combined risk score according to the register is 375.
This document contains a risk register for a BRT project from Tichborne Way to Gosport Ferry. It lists 12 risks organized by risk ID. For each risk it identifies the risk owner, describes the potential risk event and consequences, provides a current assessment of the risk level and financial score, and outlines the proposed response strategy and tasks to manage the risk. The total combined risk score according to the register is 375.
This document contains a risk register for a BRT project from Tichborne Way to Gosport Ferry. It lists 12 risks organized by risk ID. For each risk it identifies the risk owner, describes the potential risk event and consequences, provides a current assessment of the risk level and financial score, and outlines the proposed response strategy and tasks to manage the risk. The total combined risk score according to the register is 375.
STEP 1: Risk Details STEP 3: Response Risk Source L e v e l P r o b a b ilit y *
F in a n c ia l Im p a c t *
S c h e d u le
Im p a c t *
P e r f o r m a n c e
Im p a c t *
E n v ir o n m e n t a l Im p a c t H e a lt h &
S a f e t y Im p a c t C u r r e n t
C o m b in e d
S c o r e F in a n c ia l S c o r e A p p r o v e d
B a s e lin e
L o w c o s t
e s t im a t e
k H ig h c o s t
e s t im a t e
k E v e n t
p r o b a b ilit y
( P ) % M e a n
F in a n c ia l Im p a c t P * I 1 P r o je c t M a n a g e m e n t Delay to statutory undertaker services at south end of Spring Garden Lane Delay to contract. Increased disruption to members of the public M L H 12 6 12 5 100 40% 21 O p e n Lead Design (MC) Manage Start negotiations with service providers as soon as possible to plan works. 2 P r o je c t M a n a g e m e n t Objection to signals at south end of Spring Garden Lane on environmental grounds Application for judicial review Delay to contract &legal fees L L H 8 4 8 10 100 20% 11 O p e n Lead Design (MC) Avoid Carry out public consultation 3 P r o je c t M a n a g e m e n tRisk of Public Safety during Construction Injuries/ fatalities to members of the public Injury compensation costs +poor local and national PR L M VL H 8 6 8 10 250 20% 26 O p e n Main Contractor Transfer Maintain site security as per contractural requirement 4 P r o je c t M a n a g e m e n t Difficultly of accurately pricing contract Market forces affecting tender prices Tender price exceeds cost budget Additional funding required - poor PR for HCC M M VL 9 9 9 1 300 30% 45 O p e n Lead Design (MC) Escalate Reviewcosts and risks at key stages. 5 P r o je c t T e c h n ic a l Unknown services encountered during construction Delay to contract Increased disruption to members of the public L L L L 4 4 4 1 100 20% 10 O p e n Lead Design (MC) Escalate To be managed on site. 6 S tr a te g ic
Objections to TROs on Grove Road and Stoke Road delay scheme/require revised designs Possible delay to contract award Delay to Contract and/or reduced scope of works VH L H VH L 25 10 25 1 50 80% 20 O p e n Lead Design (MC) Combinati on Public consultation and effective TRO processes 7 P r o je c t M a n a g e m e n tConstruction noise expected from machinery during site hours Stop notice may be issued by Local Authority. Section 61 requirements restricting activities. Delay and additional costs during construction L L L M 6 4 6 5 100 10% 5 O p e n Main Contractor Transfer To be managed on site. 8 P r o je c t M a n a g e m e n t Some specialist products are required for the scheme eg. bus stops, kerbs There may be difficulties securing and aquiring specialist products Delay of delivery of materials to Contractor Delay to Contract VL L M 3 2 3 1 50 5% 1 O p e n Lead Design (MC) Manage Management Plan 9 P r o je c t M a n a g e m e n tDelay to programme causes works to extend beyond funding window. out funding Dft Funding window HCC need to find additional funding VL M L 3 3 3 200 500 5% 18 O p e n Project Steering Group Escalate To be managed by Project Steering Group 10 P r o je c t M a n a g e m e n t Optimistic programming Subcontractors not available Delay to contract M VL 5 25 45% 7 O p e n Lead Design (MC) Avoid Management Plan 11 P r o je c t T e c h n ic a l Insufficient protection provided to trees Trees damaged during construction Additional costs/delay to contract L VL 1 5 25% 1 O p e n Main Contractor Escalate To be managed on site. 12 P r o je c t T e c h n ic a l Impact of temporary works on existing highway network. Long traffic delays on highway network. Poor PR for HCC and additional costs to provide extra temp traffic management systems H L M 12 8 12 200 500 60% 210 O p e n Lead Design (MC) Manage Prepare Traffic Management Plan and consult with area office and co-ordinate works with other work in the area. Total 375 Response Plan Key Tasks * Root Cause/s * (Known factors/ weaknesses) Risk Event * (What might happen if not corrected) Consequences * (Impact on scheme objectives/ WBS requirements) O w n e r W B S / D is c ip lin e BRT Tichborne Way to Gosport Ferry Risk Register R e s p o n s e S t r a t e g y
( A v o id , T r a n s fe r , M a n a g e , E s c a la te , A c c e p t)
*
Current/ Baseline Scoring QRA S t a t u s *
( O p e n ,A c k n o w le d g e d ,T r a n s fe r r e d ,C lo s e d ,Im p a R is k O w n e r *
STEP 2: Assessment (current) R is k ID Project Risk Register, BRT Tichborne Way to Gosport Ferry_(HF000004264873)