Professional Documents
Culture Documents
Robert Brown
Submitted By:
ABRAR AKRAM
H00029875
Online Programmes
University of Liverpool
Table of Contents
1.
2.
3.
4.
5.
6.
7.
List of Figures
Figure 1: WBS for Seismic Resistant Foundation Model Project ................................................. 3
Figure 2: Gantt Chart for Seismic Resistant Foundation Model Project ..................................... 3
Figure 3: PI Matrix to Show the Impact of Risks at Project ......................................................... 8
List of Tables
Table 1: Resource Management Plan for Seismic Resistant Foundation Model Project ................ 5
Table 2: Cost Estimate for Seismic Resistant Foundation Model Project ....................................... 6
Table 3: Risk Identification and Mitigation Plan .............................................................................. 7
Table 4: Project Communication Plan ............................................................................................. 8
1.
Flexible model (FM) has to produce foundation box of size 300 x 250 x 200 cm
with a slot of 10 x 10 x 25 cm. Boxes should be smooth in appearance and made
of 5 x 5 x 5 cm cubes of cardboard and metal sheet. Foundation boxes should
meet the strict quality control requirements with respect to dimensions defined by
PDDG. Boxes should have outer dimension tolerance +/-2cm and slot dimension
tolerance 0 to -3 mm making slot not more than 10 x 10 cm. However,
functionality of these boxes and quality of material used (defined by PDDG) is not
the responsibility of FM.
Project team should analyze detailed project requirements and develop a design
to implement by the Cutting Department and Assembly Department. Project will
complete in 50 working days and work will be carried out only at weekdays,
which is expected to cost 40,656 USD including administration costs. Foundation
boxes will be delivered to site for final implementation of project. However, site
preparation will be the responsibility of PDDG and FM will assemble the boxes at
site as required.
2.
WBS for the project is prepared and shown in Figure 1 as WBS confirms the path
to success of project by documenting required activities (Portny, 2010). WBS
shows different parts of work required to complete the project according to
different departments in the FM organization. Relationship between different
activities shown in WBS was established to produce project schedule and Gantt
Chart shown in Figure 2. Project schedule has shown that project will be
completed in 50 working days.
3.
Staffing or resource management plan identifies the responsible person for each
task and required effort for the completion of task (Sanghera, 2010) which help to
complete project successfully. Therefore, a resource management plan was
developed as shown in Table 1.
Task
Task
Duration
(Days)
Responsible
Department
Required
Effort
(Days)
Responsible
Person
Requirements
Analysis
Interview client
stakeholders
Product detail
analysis
Refinement of the
final draft
Designing and
Drafting
Designing and
Drafting,
Assembly
Designing and
Drafting
Roy Benjamin
10
Roy Benjamin,
Philip Cloony
10
Roy Benjamin
Design and
Concept
Roy Benjamin
High level design
Designing and
Drafting
Designing and
Drafting
Roy Benjamin
Details with
operation designs
12
Roy Benjamin
Cardboard sheet
Supply Chain
Management
Supply Chain
Management
Supply Chain
Management
Material
Cost
Material
Cost
Material
Cost
Jim Stanford
Metal sheets
Cubes
Set up
Cutting and parts
development
Sub-assembly 1
Sub-assembly 2
Sub-assembly 3
Assembly
integration
4
3
Assembly
Cutting
6
9
6
6
4
3
Assembly
Assembly
Assembly
Assembly
12
12
8
6
Philip Cloony
Michael
Gartner
Philip Cloony
Philip Cloony
Philip Cloony
Philip Cloony
Pre-delivery
Jim Stanford
Shipment/Deliver
y
Implementation
14
Supply Chain
Management
Supply Chain
Management
Design and
Drafting,
Assembly
Outsourced
Jim Stanford
18
Roy Benjamin,
Philip Cloony
Material
Purchase
Jim Stanford
Jim Stanford
Production
Delivery
4.
Cost Estimates
Task Duration
(Days)
Task
Required Effort
(Days)
Cost
Requirements
Analysis
Interview client
stakeholders
Product detail analysis
10
1200
2400
10
600
4200
Design and
Concept
High level design
600
12
1800
2400
Material Purchase
Cardboard sheet
50 sheets
1000
Metal sheets
50 sheets
1250
Cubes
900 pieces
9000
11250
Production
Set up
12
1800
Sub-assembly 2
12
1800
Sub-assembly 3
1200
Assembly integration
900
900
810
7410
Delivery
Pre-delivery
Shipment/Delivery
14
Implementation
Out sourced
3000
6000
18
2700
11700
36960
3696
5.
40,656
A risk may occure anytime in a project which could cause schedule slippage,
additional cost or some other losses (Wysocki, 2012, p. 75). Therefore, risks in
6
the project and mitigation techniques were identified and as mentioned in Table
3. A PI matrix shown in Figure 3 also developed to evaluate the impact of risks at
project. Also there is 0.3 probability of material damage during shipment which
will increase the cost by 30% due to additional requirement of material therefore
an additional cost of 3,375 USD (30% of material cost 11,250 USD) should be
budgeted to cover this cost.
Table 3: Risk Identification and Mitigation Plan
Risk ID
R1
Risk Description
Delay in Material Supply
R2
Damage of components
during shipment
R3
R4
R5
R6
R7
Risk Mitigation
Responsible person should
follow up with supplier
regularly and clearly
mentioned the supply date
in contract.
Responsible person should
communicate the impact of
damaging to delivery sub
contractor and ensure that
sub contractor implement
best practices to handle the
material.
Head of department should
be given required schedule
before many days to
arrange for skilled labor at
required time.
Specifications should be
finalized with client and strict
scope change process
should be defined.
Responsible person should
communicate the delivery
date to client and ensure
that client make all
arrangement for
implementation.
Responsible person should
ensure that experienced
staff is assigned to
implementation task.
Schedule should be
communicated to all
departments before some
time and project manager
should carefully observe the
progress at daily basis.
Responsible Person
Jim Stanford
Jim Stanford
Michael Gartner
Roy Benjamin
Philip Cloony
Roy Benjamin,
Philip Cloony
Project Manager
Probability
0.9
0.8
0.7
0.5
0.4
0.3
0.2
Priority Key
0.18
0.16
0.14
0.10
0.08
0.06
0.04
0.2
0.36
0.32
0.28
0.20
0.16
0.12
0.08
0.4
0.45
0.40
0.35
0.25
0.2, R5
0.15
0.10, R1
0.5
Low
Threats
0.63
0.56
0.49
0.35
0.28
0.21, R4
0.14
0.7
0.72
0.64
0.56
0.40, R6
0.32
0.24, R7
0.16
0.8
Medium
0.81
0.72
0.63, R3
0.45
0.36
0.27, R2
0.18
0.9
High
Communication Plan
Project success requires team work and good coordination between all
departments which could be ensured only by sharing required information to all
stakeholders. Therefore, a communication plan is prepared as shown in Table 4.
Table 4: Project Communication Plan
Communication
Kick off Meeting
Mode
Face to face
Frequency
Once
Progress Review
Meeting
Progress Report
Design Review
Meeting
Budget Review
Meeting
Face to face
Daily
Email
Face to face
Weekly
Once
Face to face,
Telephone, Email
As Required
7.
Stakeholders
Client, Project
Manager
Project Team
Project Manager
Design Team, Client,
Project Manager
Project Manager,
Supply Chain
Manager, Marketing
Lead
Quality Plan
References:
Portny, S.E. (2010), 'Improving Project Performance With Three Essential Pieces
of Information', Journal for Quality & Participation, 33, 3, pp. 1825, Business
Source Premier, EBSCOhost, (Accessed: 31 March 2011).
Sanghera, P. (2010), PMP in depth: project management professional study
guide for the PMP exam. 2nd ed.Boston: Course Technology/Cengage
Learning.
Wysocki, Robert K. (2012) Effective Project Management Traditional, Agile,
Extreme. 6th ed. Indiana: Wiley.