You are on page 1of 3

Lethargy paragdism88 jjplihgtra

From eopithuys k
I didmt ead
Nhh 65
From the epi glotis
1889sg

998 gff

NOTES & DECISION


Ref- BKN/OS/Raisingnagar

Date: - 8-09-2014

Sub: - Turn down of compound wall due to rainfall of BO campus at Raisinghnagar


As per the information received, the left side compound of BO campus of Raisinghnagar
Branch has been turn down due to excessive load of earth filling during the rainfall on 4-92014 evening. I have visited the site on 6-9-2014 as per the instructions of the competent
authorities and observed the position of compound wall.

Total area of plot is 38.130m X 45.


The left side wall is 45.745 m in length and having 230mm thickness with 345 mm
thick columns 3.00m C/C and having 10-3 including 2ft height of MS grill from inner
formation level. The RCC Retaining wall was partially constructed in left side up to 10.00 m
from front corner in 230 mm thick up to 7ft height from inner formation level and reaming
height has match with 1ft height of brick work of 230 mm thick and 2 ft height of MS
grill. Earlier the retaining wall was taking the pressure of 4 to 2-6 filling on outer side but
now the Road work is in progress and filling has been done up to 6-6 at outer side. The
excessive filling has been done on outer side of compound wall, therefore the wall up to
50ft has turn sour due to excessive earth pressure during heavy rainfall.
The remaining portion of Brick wall is also not in good condition and neither it
is safe. The entire left side brick compound wall should be replaced with retaining wall. The
above wall should be redesign as a retaining wall before construction is taken up. If
competent authority accord principal approval for above works thereafter we may arrange to
get work done though the Engg. Depptt. , Jaipur.

Engg.Asstt.

Proposal of Reconstruction of Ramp and Entrance Steps in BO Raisinghnagar


We have received notice dated 28-3-2014 from Municipality Office, Raisinghnagar regarding
removal of approach road and Entrance steps of BO. The Plot of Branch Office is having
10ft in depression and Branch Office was contracted with stilt parking. During construction
of BO, the ramp was provided with an approach road in front side of compound wall for
using of stilt parking area and steps was also provided for approach of Office.
Now, The Municipal Board is providing a road in font of our Office. Therefore The
Municipal Board is removing the approach road and steps. We have required to reconstruct
the approach road and Entrance steps with small gradient.
In view of the facts stated above the competent authority is requested to accord the approval
for carry out the above work.

Submitted for consideration.

Engineering Asstt.

Manager (O.S.)

Sr. Divisional Manager

You might also like