Professional Documents
Culture Documents
H o su c 3 tng hm
Bi tp
H O SU
(3 TNG HM 3 TNG CHNG BEAM STEELS)
Bc 1: Thit lp m hnh
Vo File General Settings
Vo Geometry Workplanes
GV: O NGUYN V
H o su c 3 tng hm
Bc 3: V mt bng 24m*60m
Khong cch cc thanh chng theo phng X: 16m
Khong cch cc thanh chng theo phng Z: 8m
Vo Geometry Geometry Lines
Bc 4: Khai bo h khoan
Vo Geometry Borehole. Kch chut tri vo mt v tr bt k trn khu t to Borehole.
H khoan cu to gm 3 lp t, mc nc ngm cao -2m.
GV: O NGUYN V
H o su c 3 tng hm
Lp 1: St, do nho
Lp 2: Ct pha, cht va
Lp 3: Ct cht
GV: O NGUYN V
H o su c 3 tng hm
GV: O NGUYN V
H o su c 3 tng hm
GV: O NGUYN V
H o su c 3 tng hm
Bc 6: Chia li
Vo Mesh generate 2D mesh Update
Vo Mesh generate 3D mesh Update
Bc 7: Chn Calculation Yes
Phase 1: Thi cng tng vy
Mt phng lm vic: 0.00 12.00
GV: O NGUYN V
H o su c 3 tng hm
H o su c 3 tng hm
GV: O NGUYN V
GV: O NGUYN V
H o su c 3 tng hm