TM.P. Workshop
Done by:
Name
Faris Al-Abdulaali
Abdullah Al-Esmail
Badge no.
100756
93362
Table of Contents
Brief Description of The Problem: ................................................................................................... 3
Visit Report: ..................................................................................................................................... 3
Disassembly of the pump parts: .................................................................................................. 3
Damaged Parts: ........................................................................................................................... 5
-
2-
3-
4-
5-
6-
7-
Cleaning of parts............................................................................................................ 16
8-
9-
Conclusion: .................................................................................................................................... 17
Visit Report:
A visit to the workshop has been conducted by Project team with a joined team from
Generation to inspect the issue and see the root cause of this failure. The same
representative from TM.P who was at PP10 site was also present for disassembly and
assembly of the pump at Al-Jubail Workshop.
Below are photos with remarks of the visit.
Damaged Parts:
Two (2) wear rings have been effected and strong rubbing marks observed on both sides
diameters (ID & OD) due to the great jamming occurred between the Suction casing
(stationary) wear ring and 1st stage impeller (rotating) wear ring. See below photos.
st
st
The replacement of these damage rings has already been done by the vendor and TIG welded to
the casing and the impeller.
Assembly of BFP:
After inspection of the damaged parts, TM.P started the assembly of the pump. The pump
assembly activity requires a 3 days minimum to finish. See below photos which illustrate the
assembly process.
st
Figure 15: Starting the vertical assembly of 1 stage impeller & following inter-stages impellers and diffusers casing
10
Approximately half of the inter-stages have been observed and the complete installation
observation could not done due to time concern of visit.
11
General Observations:
1- No procedure papers available to implement it during installation.
Wrong machining in the shaft noted and it was left as it is. Vendor commented that it
will not affect the assembly process or performance of the pump.
Clarification is required whether to accept this or not.
12
13
14
15
7- Cleaning of parts
Poor tools of cleaning by air and cotton waste.
16
8- Arrangement of visit
The inspection was carried out without the presence of BEMCO. While TM.P claims that the
issue root cause was during the installation work done by BEMCO. This visit shall be joint visit by
BEMCO.
9- Workshop Facility
The workshop of TM.P at Al-Jubail does not have the proper equipment in order to test the
pump after installation. The machines available there are only sufficient for machining for small
prepares and maintenance.
Conclusion:
Jamming of the BFP A112 took place at Site while commissioning stage. The wear rings
damage/rubbing of the Suction & 1st stage have been occurred due to foreign materials went
inside the suction nozzle of the pump during the installation or hot working or re-instatement of
the pump at Site by BEMCO as per TM.P claim.
TM.P has already replaced the damaged wear rings and install them.
A better arrangement of the visit with the presence of BEMCO was expected.
Balancing of the Shaft assembly needs to be checked static or dynamic.
Hydrostatic test of the Pump shall be done.
Furthermore, high standards, quality and safety was expected than the reality.
17