You are on page 1of 8

DAILY PROGRESS REPORT OF RDI MUGHALSARAI (16/06/2015-15/07/201

Date

Description

Manufacturing of stairs parts is in process.Pipes i.e. 3',4',6',8' and 10' has been
reached in site at RDI-MGS.Hand railings are attached with stairs in Tank no16-Jun-15
104.Assembling and tacking of stairs is in process in Tank no-104, 106.Civil work
for the foundation of the tank no-105 is in progress.
Top resting landing is start attaching.Manufacturing of stairs parts is in
process.Hand railings are attached with stairs in Tank no-104.Assembling and
17-Jun-15
tacking of stairs is in process in Tank no-104.Civil work for the foundation of the
tank no-105 is in progress.
Top resting landing is start attaching.Manufacturing of stairs parts is in
process.Hand railings are attached with stairs in Tank no-104.Assembling and
18-Jun-15
tacking of stairs is in process in Tank no-104.Civil work for the foundation of the
tank no-105 is in progress.
Top resting landing attachment is hold due the practical problem as
discuss.Pump house civil work starts.Manufacturing of stairs parts is in
19-Jun-15
process.Hand railings are attached with stairs in Tank no-106.Assembling and
tacking of stairs is in process in Tank no-106.
Top resting landing attachment is hold due the practical problem as
discuss.Welding of roof plates B7 welding is done.Pump house civil work is in
20-Jun-15
progress.Manufacturing of stairs parts is in process.Assembling and tacking of
stairs is in process in Tank no-106.
Top resting landing attachment is hold due the practical problem as
discuss.Welding of roof plates B7 welding is done.Pump house civil work is in
21-Jun-15
progress.Manufacturing of stairs parts is in process.Assembling and tacking of
stairs is in process in Tank no-106.
Top resting landing attachment is hold due the practical problem as
discuss.Pump house civil work is in progress.Assembling and tacking of stairs is
22-Jun-15
in process in Tank no-106.Manhole tacking and welding is in progress in Tank no104.Marking of manholes in Tank no-106 is in process.
Pump house civil work is in progress.Assembling and tacking of stairs is in
process in Tank no-106.Manhole tacking and welding is in progress in Tank no23-Jun-15
104.Welding of manholes in Tank no-106 is in process.Marking and cutting of
flanges are in progress.

Total
Man
Power

signature of TPI
Engineer Incharge

Pump house civil work is in progress.Assembling and tacking of stairs is in


process in Tank no-106.Manhole tacking and welding is in progress in Tank no24-Jun-15
104.Welding of manholes in Tank no-106 is in process.Marking and cutting of
flanges are in progress.
Pump house civil work is in progress.Assembling and tacking of stairs is in
process in Tank no-106.Manhole tacking and welding is in progress in Tank no25-Jun-15
104.Welding of manholes in Tank no-106 is in process.Marking and cutting of
flanges are in progress.
Pump house civil work is in progress.Assembling and tacking of stairs is in
process in Tank no-106.Manhole tacking and welding is in progress in Tank no26-Jun-15
104.Welding of manholes in Tank no-106 is in process.Marking and cutting of
flanges are in progress.
Work has been hold some times due to heavy raining in the site.Pump house civil
work is in progress.Assembling and tacking of stairs is in process in Tank no27-Jun-15 106.Manhole tacking, grinding and welding is in progress in Tank no-106.Welding
of manholes in Tank no-106, 104 is in process.Marking, drilling and cutting of
flanges are in progress.
Work has been hold some times due to heavy raining in the site.Pump house civil
work is in progress.Assembling and tacking of stairs is in process in Tank no28-Jun-15 106.Manhole tacking, grinding and welding is in progress in Tank no-106.Welding
of manholes in Tank no-106, 104 is in process.Marking, drilling and cutting of
flanges are in progress.
29-Jun-15 Work has been hold due to non-stop raining since morning in the site.
Premixing in foundation of Tank no-105 is done.Pump house civil work is in
progress.Manhole's welding is in progress in Tank no-106.Marking and cutting of
30-Jun-15 stairs parts are in progress.Welding of roof plates is completed.
After premixing, sheets are shifted on the foundation of Tank no-105.Measuring
& Cutting of rafters is starts.Pump house civil work is in progress.Manhole's
welding is in progress in Tank no-106.Roof manholes assembling is done.Welding
1-Jul-15 of roof plates is completed.
Welding of stairs is in Tank no-104 is going on.Rafters welding for roof structure
for tank no-105 is in process.After premixing, sheets are shifted on the
foundation of Tank no-105.Measuring & Cutting of rafters is starts.Pump house
2-Jul-15 civil work is in progress.
Welding of stairs is in Tank no-104 is going on.Rafters welding for roof structure
for tank no-105 is in process.After premixing, sheets are shifted on the
foundation of Tank no-105.Measuring & Cutting of rafters is starts.Pump house
3-Jul-15 civil work is in progress.

Inlets and outlets nozzles are marked and cut in the bottom shell.Welding of
stairs is in Tank no-104 is going on.Base plates are painted with black bituminius
for Tank no-105.Measuring & Cutting of rafters is starts.Pump house civil work is
4-Jul-15 in progress.
Roof manholes are assembled in Tank no-106.Inlets and outlets nozzles are
marked and cut in the bottom shell.Tacking and welding of stairs flat bar is
inTank no-104 is going on.Base plates are painted with black bituminius for Tank
5-Jul-15 no-105.Pump house civil work is in progress.
Roof manholes are assembled in Tank no-106.Inlets and outlets nozzles are
marked and cut in the bottom shell.Tacking and welding of stairs flat bar is in
Tank no-104 is going on.Base plates are painted with black bituminius for Tank
6-Jul-15 no-105.Pump house civil work is in progress.
Second platform on the top side is in progress.Roof manholes are assembled in
Tank no-106.Inlets and outlets nozzles process is in process.Tacking and welding
7-Jul-15 of stairs flat bar is going on.Pump house civil work is in progress.
Second platform on the top side is in progress.Roof manholes are assembled in
Tank no-106.Inlets and outlets nozzles process is in process.Tacking and welding
8-Jul-15 of stairs flat bar is going on.Pump house civil work is in progress.
Top resting platform on the top side is in progress.Bottom plats of Tank no-105 is
assembled with 40 mm overlapping.Roof manholes are assembled in the
Tank.Inlets and outlets nozzles process is in process.Tacking and welding of stairs
9-Jul-15 flat bar is going on.Pump house civil work is in progress.
Work has hold due to heavy raining in the site.Top resting platform on the top
side is in progress.Bottom plats of Tank no-105 is assembled with 40 mm
overlapping.Inlets and outlets nozzles work is in process.Pump house civil work is
10-Jul-15 in progress.
Work has hold due to heavy raining in the site.Top resting platform on the top
side is in progress.Bottom plats of Tank no-105 is assembled with 40 mm
overlapping.Inlets and outlets nozzles work is in process.Pump house civil work is
11-Jul-15 in progress.
Bottom plats of Tank no-105 is assembled.Shell erection work is in progress in
Tank no-105.First and second shell is assembled in Tank no-105.Hydraulic jacks
12-Jul-15 fitment in Tank no-105 is completed.Pump house civil work is in progress.
Bottom plats of Tank no-105 is assembled.Shell erection work is in progress in
Tank no-105.First and second shell is assembled in Tank no-105.Hydraulic jacks
13-Jul-15 fitment in Tank no-105 is completed.Pump house civil work is in progress.
Bottom plats of Tank no-105 is assembled.Shell erection work is in progress in
Tank no-105.First and second shell is assembled in Tank no-105.Hydraulic jacks
14-Jul-15 fitment in Tank no-105 is completed.Pump house civil work is in progress.

Shell erection work is in progress in Tank no-105.Vertical welding of shell plates


is in process.Bottom plats of Tank no-105 is assembled.Hydraulic jacks fitment in
15-Jul-15 Tank no-105 is completed.Pump house civil work is in progress.

7/2015)
signature of IOCL
Remarks
Engineer Incharge

You might also like