Project Status Report

SAKSON VGE-01 : WORK PROGRESS REPORT


08.01.2013

Description
J/no.

%
Cplt

Expected
Date Of
Completion

Skid - Bottom Frame


Skid legs

100
100

10.1.2014

Skid -top frame

100

10.1.2014

25

16.1.2014

Stand Platforms

100

13.1.2014

Handrails

100

9.1.2014

95

9.1.2014

18.1.2014

80

18.1.2014

Slide

Caged Ladder
Painting
Summary

Status
completed
1. 50mm and 10mm stiffeners pending gas
cutting and welding
2. Platform support hinges pending
Fitment & welding of stopper pipes.
In progress
Gratings 50% complete (in progress).
Platform support hinges gas cutting in
progress. Handrail pockets to be fitted &
welded to platforms
3 handrails fabricated. One pending
Kick plate fitment and welding onto handrail
pending
40mm tubular profile to be welded.
Not started.