Professional Documents
Culture Documents
NT
Earthing
System
DAILY/WEELY
Equipment grounding
conneections Visual
Inspections
MONTHLY
Earth Resistance,
record and remedies
ANNUALLY
Shield Wire grounding
connections Check
5 YEARS
Physical digging of the
earth to see the mesh
burried joints and
connections
10 YEARS
____________________
NON-SCHEDULED
As and when
abnormality observed
be attended
immidiately
STANDARD
11 KV
Breakers
(11 KV &
33 KV)
Power
Transforme
rs
Visual
inspection
SF6 gas
pressure
check
Oil level
check
Ground
connections
check
Operating
mechanism
inspection
Visual
inspection
Oil level
check
Temp. gauge
and temp.
check
Silicagel
colour check
Oil leakage
check
Lightening
arrestor
readings
_____________________
Cooling
system
check
O.L.T.C
counter
reading
check
Operating
Mechanism
Adjustment
Oil DES test
Operating test
Contact
Resistance test
Timing test
Contact
inspection
Busbar
coneections
check and
tightening
Oil DES test
OLTC test
operation
IR/TTR/C&DF
tests
Bucholz relay
operation test
Oil
replacement
for oil
breaker
Major over
hauling
Major
over
hauling of
SF6 gas
and
vacuum
circuit
Breakers.
Oil be
replaced
after 10
heavy fault
trippings
Contact
inspection
after 10
heavy faults
Chemical
analysis of
oil
Over hauling
of OLTC
contact
inspection
and check of
transition
resistance
value
Over hauling of
Power Transformer
Tightening of earth
connections as and
when required
Circuit
Breakers
(66 KV &
Visual
inspection
SF6 gas
Earth connection
tightness be checked
Operating
mechanism
adjustment
Oil
replacement
Major over
After 10
heavy faults
trips oil be
No damage be left
unattended
Earth resistance
be <02.00 ohms
better results are
in between 0.2 to
0.5 ohm
Mesh burried
joints and
connections be
kept intact firmly
> 30 KV at 2.5
mm gap
Local and Remote
operation be OK
Timing (trip &
close as per
manufacturers
specificationsalon
g with contact
resistance)
No dust be
allowed in
operating
mechanism
Oil level be correct
as per oil level
indication
Cooling system&
temp. gauges be
OK
Silicagel be
Healthy
Oil DES should be
> 50 KV at 2.5
mm gap
Chemical analysis
should be as per
wapda
specifications
IR/TTR/C&DF
must correspond
to manufacturer
specification/value
s
Rated pressure at
200 C
Oil level be as per
Above)
pressure
check
Oil level
check
Ground
connections
check
hauling
Breakers.
replaced and
contact
checked
Oil DES test
Rectifier
and
Battery
Ventilation
check
Cell
appearance
Electrolyte
level
Specific
gravity of
pivot cell
Volt per cell &
specific
gravity
Cleaning of
rectifier
(thorough)
Float and
Boost
charge
check
Voltage
regulation
and current
limiting
Ripple check
Indication
check
Replacement of
Battery
Apply the
anticorrosive
vaseline to
all terminals
Cleaning of
battery room
Protection
System
Visual
inspection for
flage and
indications
Contact
inspection
11 KV Feeders
protection check
_______________________
____________________
Check of
indiscriminat
e tripping
Failure of
any
protective
oil indicator
Ground
connections be
intact
No damage in
operating
mechanism
Operating
mechanism
adjustment
contact resistance
closing and
tripping timing be
as per
manufacturer
specification
DES > 50 KV for
2.5 mm gap
Thermovision
survey to see hot
spots at Busbar
etc
In capacity test
voltage per cell
should be > 1.8 V
Exhaust fan be
Healthy
No leakage from
cells
Level of
electrolyte to be
near the max. acid
level
Voltage per all be
>2V
Specific gravity be
1.100 at 25 C
0.010
Nominal voltage
be 110/220 V
Al connections be
kept tight through
torque wrench for
correct torque
Checking should
be carried by the
trained P & I staf
All relays be
calibrated if
required
Current
Transforme
rs (CTs) &
Pottential
Transforme
rs (PTs)
Setting of
relay and
inspection
Visual
inspection
Oil level
check
Ground
connections
check
Dust
removal and
thorough
cleaning
Insulation
resistance test
Busbars
connections
check
C&DF test
Nitrogen gas
pressure
check
Oil DES test
equipments
be checked
Problem in
wiring be
attended
Oil leakage
attending
Attending
accidental
damages
____________________
Training
Lightning
Arrestor
On job training be
conducted by AE/RE
incharge to the
operating staf on the
equipment during duty
hours
Visual
inspection
Counter
reading
Ground
connections
Earth
resistance
measureme
nt
Dust
removal &
cleaning of
the surface
Busbar connections
check
T.S.G training be
imparted to all AEs
and operators in a
phase wise program
___________________
Settings be
reviewed if
needed
Calibration of the
protective
equipments be
done through
T.S.G
No damage be left
unattended
Insulation,
Resistance C&DF
test, Nitrogen gas
Pressure oil DES
be as per
manufacturer
specification
Training be objective type
and
should be given in a
language understandable.
Diferent equipment & the
working be shown to the
whole operating staf to
make them conversent for
day to day operations
Insulation
resistance
check
Leakage
current
monitoring
check
__________________
_____________________
No damage should
prevailed
Thermovision
survey be
conducted for
Busbar
connections
tightness
Insulation
resistance be as
per wapda
Isolator
Visual
inspection
Alignment
Ground
connections
Remote operation
check
Cleaning of
male and
female blades
Light
Mechanism
Operating
mechanism
check
Replacement of male
and female blades
Dust removal
___________________
specification
No dust be
allowed on the
Porceline of LA to
avoid its damage
Alignment be
checked to avoid
pitting on blades
Greasinging of
mechanism and
blades to ensure
smooth operation