ADMIN BUILDING

Billing No. 5
1 CONCRETE
Roof Beam at El. + 17.22m
Terrace Floor Slab at El. + 17.22m
Columns
1st Floor - 2nd Floor
2nd Floor - Terrace Floor
Terrace Floor - Terrace Floor (C4 & SC)
Staircase
Flight-5 & 6
Landing 3 & 4
Mid-landing Beam
Parapet Wall
El. + 13.17m
El. + 17.22m
Concrete upstand at CW3
2 BLOCK WORKS
Cavity Wall 350mm
Ground Floor Level
First Floor Level
Block Wall 200mm
Ground Floor Level
First Floor Level
Block Wall 100mm

Billing No. 6
1 CONCRETE
Headroom Beam
Concrete Canopy
Headroom Slab
Headroom Parapet Wall