You are on page 1of 6

12th FLR

ITEM BAL. OF WORK


1 100 MM. THK, 813.21 SQ.M.
2 150 MM. THK. 1535.38 SQ.M.
3 150 MM. THK. ELEVATOR WALL 131.824 SQ.M.
4 Flexible Cementitious Waterproofing ZOCALO 328 S.QM.
5 Capillary Water proofing PIPE CHASE 28.98
6 Rubbed Concrete with smooth, flat finish STAIR 1,2&3 856.00 SQ.M.
7 Rubbed Concrete with smooth, flat finisH AUX/IDF ROOM 192.00 SQ.M.
8 Skimcoating 1250.00 SQ.M .
9 Lineal Plastering to CHB Walls 1250.00 SQ.M .
10 Plain Cement Fire Exit Stair 1, 2 & 3 856.00 SQ.M.
11 Plain Cement EE Room and AUX/IDF Room 3.7 SQ.M
12 Plastering to Wall specified surface 5454 SQ.M.
13 Tile Works 18.135 SQ.M.
14 Ceiling System 18.136 SQ.M.
15 Supply and Application of Interior Walls 365 SQ.M.
16 Supply and Application of Interior Walls for 150 mm basepaint 19.15 SQ.M.
17 Interior Paintings of Ceiling 131.00 SQ.M.
18 Painting for Floor-mounted Railing F.E. 1,2 &3 24.68 LM.
19 Painting for Wall Mounted Railings F.E. 1,2 &3 23.85 LM.
20 Interior Painting Floor Fire Exit Stair 1, 2 & 3 133.664 SQ.M.
21 Interior Painting EE Room and AUX/IDF Room 14.91 SQ.M.

ROOF DECK
ITEM BAL. OF WORK
1 100 MM. THK, Roof Deck Level including pump room and machine room
2 150 MM. THK. Roof Deck Level including pump room and machine room
3 150 MM. THK. ELEVATOR WALL 131.824 SQ.M.
4 Flexible Cementitious Waterproofing ZOCALO 328 SQM.
5 Capillary Water proofing PIPE CHASE 28.98
6 Rubbed Concrete with smooth, flat finish STAIR 1,2&3 856.00 SQ.M.
7 Rubbed Concrete with smooth, flat finisH AUX/IDF ROOM 192.00 SQ.M.
8 Skimcoating 1250.00 SQ.M .
9 Lineal Plastering to CHB Walls 1250.00 SQ.M .
10 Plain Cement Fire Exit Stair 1, 2 & 3 856.00 SQ.M.
11 Plain Cement EE Room and AUX/IDF Room 3.7 SQ.M
12 Plastering to Wall specified surface 5454
13 Tile Works 18.135 SQ.M.
14 Ceiling System 18.136 SQ.M.
15 Supply and Application of Interior Walls 365 SQ.M.
16 Supply and Application of Interior Walls for 150 mm basepaint 19.15 SQ.M.
17 Interior Paintings of Ceiling 131.00 SQ.M.
18 Painting for Floor-mounted Railing F.E. 1,2 &3 24.68 LM.
19 Painting for Wall Mounted Railings F.E. 1,2 &3 23.85 LM.
20 Interior Painting Floor Fire Exit Stair 1, 2 & 3 133.664 SQ.M.
21 Interior Painting EE Room and AUX/IDF Room 14.91 SQ.M.
BAL. OF WORK
813.21 SQ.M.
1535.38 SQ.M.
131.824 SQ.M.
328 S.QM.
28.98
856.00 SQ.M.
192.00 SQ.M.
1250.00 SQ.M .
1250.00 SQ.M .
856.00 SQ.M.
3.7 SQ.M
5454 SQ.M.
18.135 SQ.M.
18.136 SQ.M.
365 SQ.M.
19.15 SQ.M.
131.00 SQ.M.
24.68 LM.
23.85 LM.
133.664 SQ.M.
14.91 SQ.M.

BAL. OF WORK

131.824 SQ.M.
328 SQM.
28.98
856.00 SQ.M.
192.00 SQ.M.
1250.00 SQ.M .
1250.00 SQ.M .
856.00 SQ.M.
3.7 SQ.M
5454
18.135 SQ.M.
18.136 SQ.M.
365 SQ.M.
19.15 SQ.M.
131.00 SQ.M.
24.68 LM.
23.85 LM.
133.664 SQ.M.
14.91 SQ.M.
10th FLR
ITEM BAL. OF WORK
1 100 MM. THK, 760 SQ.M.
2 150 MM. THK. 1,139 SQ.M.
3 150 MM. THK. ELEVATOR WALL 70.69 SQ.M.
4 Flexible Cementitious Waterproofing ZOCALO 337.83 SQ. M.
5 Capillary Water proofing PIPE CHASE 44.28
6 Rubbed Concrete with smooth, flat finish STAIR 1,2&3 856.00 SQ.M.
7 Rubbed Concrete with smooth, flat finisH AUX/IDF ROOM 192.00 SQ.M.
8 Skimcoating 1136.00 SQ.M .
9 Lineal Plastering to CHB Walls 2001.00 SQ.M .
10 Plain Cement Fire Exit Stair 1, 2 & 3 68.00 SQ.M.
11 Plain Cement EE Room and AUX/IDF Room 15.29 SQ.M
12 Plastering to Wall specified surface 3,984 SQ.M.
13 Tile Works 19.00 SQ.M.
14 Ceiling System 19.01 SQ.M.
15 Supply and Application of Interior Walls for 150 mm basepaint 18.5 SQ.M.
16 Interior Paintings of Ceiling 131.00 SQ.M.
17 Painting for Floor-mounted Railing F.E. 1,2 &3 24.68 LM.
18 Painting for Wall Mounted Railings F.E. 1,2 &3 23.85 LM.
19 Interior Painting Floor Fire Exit Stair 1, 2 & 3 133.664 SQ.M.
20 Interior Painting EE Room and AUX/IDF Room 14.91 SQ.M.
BAL. OF WORK
760 SQ.M.
1,139 SQ.M.
70.69 SQ.M.
337.83 SQ. M.
44.28
856.00 SQ.M.
192.00 SQ.M.
1136.00 SQ.M .
2001.00 SQ.M .
68.00 SQ.M.
15.29 SQ.M
3,984 SQ.M.
19.00 SQ.M.
19.01 SQ.M.
18.5 SQ.M.
131.00 SQ.M.
24.68 LM.
23.85 LM.
133.664 SQ.M.
14.91 SQ.M.
10th FLR
ITEM BAL. OF WORK
1 100 MM. THK, 760 SQ.M.
2 150 MM. THK. 1,139 SQ.M.
3 150 MM. THK. ELEVATOR WALL 70.69 SQ.M.
4 Flexible Cementitious Waterproofing ZOCALO 337.83 SQ. M.
5 Capillary Water proofing PIPE CHASE 44.28
6 Rubbed Concrete with smooth, flat finish STAIR 1,2&3 856.00 SQ.M.
7 Rubbed Concrete with smooth, flat finisH AUX/IDF ROOM 192.00 SQ.M.
8 Skimcoating 1136.00 SQ.M .
9 Lineal Plastering to CHB Walls 2001.00 SQ.M .
10 Plain Cement Fire Exit Stair 1, 2 & 3 68.00 SQ.M.
11 Plain Cement EE Room and AUX/IDF Room 15.29 SQ.M
12 Plastering to Wall specified surface 3,984 SQ.M.
13 Tile Works 19.00 SQ.M.
14 Ceiling System 19.01 SQ.M.
15 Supply and Application of Interior Walls for 150 mm basepaint 18.5 SQ.M.
16 Interior Paintings of Ceiling 131.00 SQ.M.
17 Painting for Floor-mounted Railing F.E. 1,2 &3 24.68 LM.
18 Painting for Wall Mounted Railings F.E. 1,2 &3 23.85 LM.
19 Interior Painting Floor Fire Exit Stair 1, 2 & 3 133.664 SQ.M.
20 Interior Painting EE Room and AUX/IDF Room 14.91 SQ.M.
BAL. OF WORK
760 SQ.M.
1,139 SQ.M.
70.69 SQ.M.
337.83 SQ. M.
44.28
856.00 SQ.M.
192.00 SQ.M.
1136.00 SQ.M .
2001.00 SQ.M .
68.00 SQ.M.
15.29 SQ.M
3,984 SQ.M.
19.00 SQ.M.
19.01 SQ.M.
18.5 SQ.M.
131.00 SQ.M.
24.68 LM.
23.85 LM.
133.664 SQ.M.
14.91 SQ.M.