Professional Documents
Culture Documents
Cementing Best Practice Jorge Sierra
Cementing Best Practice Jorge Sierra
Contents
Introduction
Engineering
and Planning
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
Table of Contents
Table of Contents
Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Tips for Using This Document . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reminders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Time-Saving Navigation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of
Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1
2
2
2
Introduction
Engineering
and Planning
Mud Removal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Drilling Fluid Conditioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Pipe Movement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Pipe Centralization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Spacers and Flushes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Operational Priorities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Job Volume Excess . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Flow Rate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Downhole Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Centralizers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Wiper Plugs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Shoe Joint . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Considerations for Liner Jobs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Cement Design Priorities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Priority No. 1Density . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Priority No. 2Pump Time (Thickening Time) . . . . . . . . . . . . . . . . . . . . . . . . 9
Priority No. 3Mixability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Priority No. 4Rheology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Priority No. 5Fluid Loss Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Priority No. 6Compressive Strength . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Priority No. 7Free Fluid and Settling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Cement Slurry Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Evaluation of Cementing Job Proposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Data Review and Verification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Review of Cement Job Simulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Interpretation of Pilot Test Results and Laboratory Reports . . . . . . . . . . . 12
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Job Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
14
15
15
15
16
17
17
17
18
19
21
Contractor
Requirements
ii
Table of Contents
Plug Cementing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
22
22
22
23
24
25
25
26
26
27
Table of
Contents
Introduction
Squeeze Cementing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
29
29
30
30
32
32
34
34
35
Engineering
and Planning
Job
Procedures
Contractor Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
37
38
39
40
40
41
42
43
45
45
48
50
53
56
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
iiii
Introduction
Introduction
Job
Procedures
Engineering
and Planning
This document is a guide for planning and executing cementing operations for
worldwide operations. It is realized that, in some well situations, the preferred
Best Practice may not achieve the best results. Every cement job should be
designed for the wellbore characteristics and the cementing objectives
desired.
Introduction
The purpose of this document is to teach and promote a Best Practices philosophy throughout the Unocal Global Drilling Community. Unocal spends
millions of dollars each year on cementing operations. Poor planning and
operational execution not only can lead to cement failure but can result in the
loss of hydrocarbon recovery from the wellbore.
Table of
Contents
Purpose
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
11
Introduction
Table of Contents
Introduction
Engineering and Planning
Job Procedures
Plug Cementing
Squeeze Cementing
Contractor Requirements
Engineering and Planning and Job Procedures cover all the basics
involved in planning and executing a primary cementing job. Plug Cementing and Squeeze Cementing, as the names suggest, contain information
specific to these techniques.Contractor Requirements provides information
about contractors responsibilities in ensuring the job is carried out as
planned.
Reminders
Job
Procedures
In many of the sections, you will find white text in the blue column at the left
of the page, topped with an orange bar. These comments are emphasized to
indicate their importance in the success of the job.
Time-Saving Navigation
Table of Contents
The Table of Contents allows you to view the subtopics discussed within each
major section. To navigate to a particular topic, just click on the entry.
The blue and orange tabs at the right of each page offer quick navigation to
any major section of the document, including the Table of Contents, from any
page in the document.
Contractor
Requirements
Where Am I?
The title of the section you are viewing is always located in the upper right
hand corner of the page, in the same color as its corresponding tab.
Squeeze
Cementing
Colored Tabs
Plug
Cementing
This document is easily navigated from either the Table of Contents or the
color tabs located at the right side of every page.
22
Engineering
and Planning
Application of the following guidelines for mud removal, cement and spacer
design, in conjunction with a cementing software program, will enhance the
displacement process and improve the probability of successful primary
cementing. Cementing software can be used to help determine the optimum
displacement parameters and safe operating equivalent circulating densities
(ECD).
Introduction
Table of
Contents
The cementing
contractors role
begins with the Engineering and Planning
stage, and his work
will parallel that of the
Drilling Engineer. For
details, see the Contractor Requirements
section.
Mud removal is best achieved through proper drilling fluid conditioning, pipe
rotation or reciprocation, pipe centralization, and the use of properly designed
spacers and flushes.
Job
Procedures
Mud Removal
Pipe Movement
33
Contractor
Requirements
Squeeze
Cementing
The condition of the drilling fluid is one of the most important variables in
achieving good displacement during a cement job. Regaining and maintaining
good mobility is the key. An easily displaced drilling fluid will have low gel
strengths and low fluid loss. Pockets of gelled fluid, which commonly exist
following the drilling of a wellbore, make displacement difficult and must be
broken apart.
Plug
Cementing
Table of
Contents
Pipe Centralization
Drilling fluid displacement is best achieved when annular tolerances are
approximately 1.5 to 2 in. Centralization of very small annuli is very difficult,
and pipe movement and displacement rates may be severely restricted. Very
large annuli may require extreme displacement rates to generate enough flow
energy to remove the drilling fluid and cuttings.
Run a centralizer calculation program and reference well deviation surveys to determine the number of centralizers necessary to achieve the recommended standoff and their ideal placement.
For liner jobs, include centralizers in the lap area to aid in the displacement of cement all around the casing perimeter either in the primary
cement job or subsequent squeeze job.
For highly deviated wells in which cuttings beds are likely, place the centralizer on the lower joints to hold the landing shoe off of the bottom of
the wellbore. This design will allow cuttings to pass underneath and help
eliminate any snowplowing effect.
44
Contractor
Requirements
Squeeze
Cementing
Plug
Cementing
Good pipe standoff ensures uniform flow around the casing and helps equalize the force that the flowing spacer and cement exerts around the casing,
increasing drilling fluid removal. In a deviated wellbore, standoff is even
more critical to prevent a solids bed from accumulating on the low side of the
annulus. The industry benchmark for standoff is approximately 70%, however the preferred standoff for a given well should be developed from computer modeling and will vary with well conditions.
Job
Procedures
Engineering
and Planning
Introduction
Engineering
and Planning
Density
Set spacer density 0.5 to 1.0 ppg above the drilling fluid weight and at least
0.5 ppg less than the cement slurry density. In situations that require the difference between cement weight and drilling fluid weight to be less than 1.0
ppg, design the spacer density to be mid-way between the two densities.
Job
Procedures
Provide a contact
time and volume of
spacer that will provide optimum amount
of drilling fluid
removal.
Introduction
Spacers and flushes are effective displacement aids because they separate
unlike fluids such as cement and drilling fluid, and enhance the removal of
gelled drilling fluid, allowing a better cement bond. Spacers can be designed
to serve various needs. For example, weighted spacers can help with well
control, and reactive spacers can provide increased drilling fluid-removal
benefits. Compatibility of the drilling fluid/spacer as well as the compatibility
of the spacer/cement slurry is of prime importance. Application of the compatibility procedures as outlined in the API SPEC RP10B, 22nd Edition,
December 1997 is highly recommended.
Table of
Contents
Compatibility of the
drilling fluid/spacer
as well as the
compatibility of the
spacer/cement slurry
is of prime
importance.
Contact Time
Provide a contact time and volume of spacer that will provide optimum
amount of drilling fluid removal. Typically 8 to 10 minutes contact time or
1,000 feet of annular space are adequate.
Rheology
Spacer must be fully compatible with drilling fluid and cement. Contact with
drilling fluid must not result in flocculation, settling, or excessive rheology.
Contact with cement must not decrease pump time.
Stability
Spacer must remain stable with no excessive settling or separation. For all
liner and tieback jobs, the spacer must be tested by hot-rolling at circulating
temperature.
Wettability
55
Contractor
Requirements
Compatibility
Squeeze
Cementing
Plug
Cementing
Design spacer rheology that will provide turbulent flow where hole geometry
allows. Turbulent flow of spacer is required on all liner jobs.
Operational Priorities
Introduction
% Excess with
Oil-Based Mud
0 to 4,000
100
50
4,000 to 8,000
75
25
8,000 to 10,000
50
15
10,000 to 18,000
35
15
25
15
Engineering
and Planning
% Excess with
Water-Based Mud
Design spacer to be in turbulent flow as it rounds the shoe and passes the
sections to be isolated.
66
Contractor
Requirements
Squeeze
Cementing
Cement flow is characterized by three flow rate regimes: turbulent flow, laminar flow, and plug flow. High-energy displacement rates are most effective in
ensuring good displacement. Turbulent flow conditions are desirable, but are
not required. When turbulent flow is not a viable option for a formation, use
the highest pump rate that is feasible for the wellbore conditions. The best
results are obtained when the spacer and/or cement is pumped at maximum
energy, the spacer or flush is appropriately designed to remove the drilling
fluid, and a good competent cement is used.
Plug
Cementing
Flow Rate
Job
Procedures
For cementing operations on offshore wells that use subsea housing, try to
plan the wells programs so that cement returns are not transported through
the subsea housing. In such cases, the surface casing is usually cemented only
to 500 ft above the conductor shoe. The presence of cement in the recesses of
subsea housing can cause great difficulty in setting subsequent hangers or
packoffs.
Table of
Contents
Determining how the cement will be placed in the hole is as important as the
design of the cement itself. This section discusses the operational factors that
should be determined in planning a successful job.
Displace at high rates (8 bbl/min and higher) without exceeding the formation breakdown pressure.
Table of
Contents
Downhole Equipment
Choose all downhole equipment (float collars, shoes, guide shoes, centralizers, liner hanger systems, and wiper plugs) for fit, operation, and proper
installation.
Wiper Plugs
Top and bottom cement plugs are recommended for every primary cementing
job, when possible. The bottom plug minimizes contamination of the cement
as it is pumped. The top plug prevents contamination of the cement slurry by
the displacement fluid and provides a positive indication that the cement has
been displaced. Use composite body plugs that are easy to drill out with PDC
bits.
Squeeze
Cementing
Plug
Cementing
Job
Procedures
Engineering
and Planning
Bowspring-type
centralizers provide
an acceptable
balance between cost
and standoff for most
standard cementing
operations.
Introduction
Centralizers
Contractor
Requirements
77
> 18 5/8
Tag in
> 13 3/8
2 joints
> 9 5/8
3 joints
> 7 5/8
6 joints
Introduction
Table of
Contents
A shoe joint is
recommended for all
primary casing/liner
jobs.
On all liner float shoes, verify that holes exist on the side of the float shoe,
allowing circulation and preventing a hydraulic lockup in the event that
the liner hanger fails and the liner lands on the bottom of the hole.
Use or design autofill float equipment that can be activated without setting the liner hanger, should a well control condition arise while going in
hole.
Design liner hanger systems with a tieback sleeve length that allows the
bottom of the tieback stem to be partially stung into the tieback sleeve
when cementing the tieback casing. This will enhance the process of
slacking off the tieback casing after the cement job has been completed.
Buckling of the lower portion of the tieback casing after cementing can
make it difficult to stab the tieback stem into place.
For ultradeep liners on directional wells with relatively high torque and
drag, use a pressure-indicating method to verify that a liner is released
from the running tool. The actual liner weight may be small in comparison to the drag forces, making it difficult to determine if the liner is actually released.
Plug
Cementing
Ensure that the liner hanger set pressures are well above the circulation
pressures that could be required while running the liner to prevent premature setting of the liner hanger.
Job
Procedures
Squeeze
Cementing
Contractor
Requirements
Engineering
and Planning
A liner hanger must be designed for the combined loading of the liner weight
to be hung off and the mud weight differential on the slip area to avoid
exceeding the elastic limit on the ID of the casing in which the slips are
engaged.
88
Cement slurry density must be within range to maintain well control. If hole
conditions allow, cement slurry density should be a minimum of 1.0 ppg
greater than drilling fluid weight and 0.5 ppg greater than the spacer weight.
Consider the total placement time for the lead slurry (mixing and pumping
of lead + mixing and pumping of tail + displacement).
99
Contractor
Requirements
Cement must be easy to mix at the cementing unit in order to achieve density
control at a mixing rate that allows cement slurry placement within the available pump time.
Squeeze
Cementing
Plug
Cementing
Job
Procedures
Engineering
and Planning
Introduction
Table of
Contents
A slurry design must address a broad assortment of well conditions and wellcontrol parameters. To maximize the performance of a slurry, adhere to these
seven guidelines, listed in the order of importance:
Engineering
and Planning
Conductor
and Surface
Casings
Intermediate
Casings and
Drilling
Liners
Production
Deep
Casings and
Production
Liners
Liners and for
Gas Control
Job
Procedures
Density
0%
0%
Fluid Loss
NA
< 250
< 100
< 50
Rheol. (PV)
< 150
< 150
< 100
< 100
Rheol. (YP)
< 50
< 40
< 25
< 20
Comp.
Strength
WOC
(hr to 500 psi)
< 12
<8
<8
<8
24-hr Comp.
Strength (psi)
1,000
2,000
2,000
2,000
Contractor
Requirements
< 1.0%
Squeeze
Cementing
Free Water
Plug
Cementing
Introduction
The goal is to achieve rapid compressive strength development after placement. The minimum requirement is a WOC time (time to achieve 500 psi) of
less than 12 hours and 24-hr strength greater than 1,000 psi.
Table of
Contents
1010
Plug
Cementing
Job
Procedures
Engineering
and Planning
Introduction
1. Check the accuracy of Subject, Field, Well and Rig entries. Well data
include the following:
Table of
Contents
Evaluation and quality control of the service companys job plan, simulator
runs, slurry design, and laboratory test results is necessary to ensure that the
cement slurry design fits the planned operation.
pumping rates
ECDs
placement pressure at the pump
spacer contact time
c. Change planned pumping rates as necessary.
Contractor
Requirements
1111
Table of
Contents
Run the simulator to test equivalent circulating densities (ECD), flow regime
of the different fluids, required rheological properties of the fluids, maximum
pumping rates, centralizer standoff requirement, displacement efficiency,
anticipated pumping pressures at surface, pressure to shear or bump plugs,
BHCT, etc. Using this tool will aid in job design and will help identify any
potential problems with the design.
Introduction
Job
Procedures
Cement type
Additive types and concentrations
Water source and concentration
2. Check cement slurry pilot test results against specifications as listed in
the following table.
Engineering
and Planning
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
1212
Slurry Property
Task
Check test value.
Thickening Time
Table of
Contents
Density
Notes
Test temperature must be
at BHCT.
Fluid Loss
Rheology
PV and YP must be
reported.
Engineering
and Planning
Introduction
Compressive
Strength
Free Water
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
1313
Job Procedures
Job Procedures
Use the following checklist to ensure that all pertinent job data is captured at
the appropriate time as each job is executed.
Prejob Preparations
Engineering
and Planning
Pumping Operations
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
Pressure testing
Start and stop of each fluid pumped
Pumping rates for each fluid
Any pumping rate changes
Any pressure changes
Volume of spacer pumped
Dropping any plug, dart or ball
Start of cement slurry mixing
Cement slurry density
Mix water volume
Start of displacement
Surface pressures
Displacement rate
Landing of plugs
Pressure to release liner wiper plugs
Pressure to bump top plug
Reverse circulation
Total displacement
Job time
Returns
Any shutdown
Safety issues or incidents
Job
Procedures
Introduction
Table of
Contents
This section contains basic procedures for every step of a job, from prejob
preparations to pumping and displacement. Throughout each phase, it is very
important to monitor and record various measurements, times, and events.
This information allows the job to be tracked as it is carried out, and is invaluable in troubleshooting an unexpected problem.
1414
Job Procedures
Prejob Preparations
Cement Design Verification
Table of
Contents
1. Verify that the following cement design and test conditions coincide with
current well conditions.
a. BHCT and BHST
b. Thickening time and job time
Introduction
c. WOC time
2. Verify the following calculations.
a. Volumes for all fluids to be pumped
Engineering
and Planning
Job
Procedures
e. Volume to catch liner wiper plugs, and displacement volume from that
point
Contractor
Requirements
4. Check wiper plugs, the bottom plug (hollow), and the top plug (solid).
5. Witness the loading of plugs.
6. Confirm the delivery rates for water and mud.
7. Confirm what type of displacement fluid will be used and the parties
responsible for routing and pumping downhole.
Squeeze
Cementing
1515
Job Procedures
8. Confirm that all density devices have been calibrated properly with fresh
water.
1. Clean and stabilize the wellbore by circulating during wiper trips, before
and after logging.
Table of
Contents
Wellbore Circulation
2. Run the casing at a controlled rate, and circulate drilling fluid at intervals.
3. Condition the drilling fluid until drilling fluid properties are optimized
(PV < 15; YP < 10).
Introduction
If there is known potential for lost circulation, run the casing at less than 1
minute per stand.
Engineering
and Planning
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
1616
Job Procedures
Pumping Operations
Pressure Testing
2. If running two bottom plugs, load the first bottom plug into the casing at
this time.
Introduction
3. Connect (reconnect) the cement head. The bottom and top plugs should
have already been loaded during prejob preparations.
Table of
Contents
4. Clear the rig floor and the area surrounding the lines.
5. Pressure-test the lines as follows:
a. Increase pressure to a predetermined level.
Engineering
and Planning
Job
Procedures
5. Measure the mix water for the cement slurry through the displacement
tanks and record the measurement.
Plug
Cementing
4. Start to mix and pump the cement slurry. The standard pump rate is 5 to 8
bbl/min, depending upon the specific job.
6. Control the density within 0.2 lb/gal accuracy throughout the job.
Contractor
Requirements
Squeeze
Cementing
1717
Job Procedures
CautionNear the end of the job, bulk delivery may decline. Never sacrifice
density control to use up the cement. If the designed density cannot be maintained, discontinue cement slurry mixing.
11.Displace the top plug out of the cementing head with minimal down time.
Table of
Contents
12.Do not open the cementing head to drop the top plug.
Introduction
13.Begin displacement.
Displacement
Measure the displacement volume with the cementing unit displacement
tanks or rig pumps. DO NOT use a barrel counter.
Engineering
and Planning
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
1818
Job Procedures
Engineering
and Planning
1. Drill the conductor hole section with MWD so that sand depths are
known.
Introduction
Table of
Contents
Consider the following standard shoe track, centralizer, and wiper plug
requirements for use in shallow water flow cementing:
5. Once the casing point is reached, pump out of hole with kill-weight mud
that has low gel strength (i.e. yield point of 8 to 10 lbf/100 ft2, 10 ft, 10 in.
and 30 in. gels flat and < 25 lbf/100 ft2).
Job
Procedures
6. After pulling out of hole before running casing, observe for flow.
Plug
Cementing
9. Before running in hole, displace the drillpipe and casing below with the
same mud weight as that in the hole.
1919
Contractor
Requirements
10.Circulate in hole and fill the drillpipe with the same mud weight as that in
the hole.
Squeeze
Cementing
Job Procedures
12.Run the designated cement system with a foamed lead slurry (1.0 ppg
heavier than the drilling mud) and a non-foamed tail slurry.
Table of
Contents
Introduction
Engineering
and Planning
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
2020
Job Procedures
Know the WOC (500-psi time) for the cement slurries pumped.
In some areas, regulations specify minimum WOC times that may exceed,
and thus supercede, these guidelines.
During the WOC period, perform operations that can help minimize the
time and cost of WOC, such as
Plug
Cementing
Job
Procedures
Engineering
and Planning
Introduction
For a cement slurry, WOC is the time necessary for the cement to solidify and
attain a compressive strength of 500 psi. This is most effiiciently determined
through laboratory testing with a UCA, which plots strength development vs.
time.
Table of
Contents
For operations, waiting on cement (WOC) is the waiting time required after
cementing in order to safely remove well control equipment or to allow the
well to be underbalanced.
Squeeze
Cementing
Contractor
Requirements
2121
Plug Cementing
Plug Cementing
Placement
Use a small workstring to balance cement plugs for optimal displacement.
The length of the tail pipe must be at least equal to the plug length with tubing
in place.
Tubing vs. Drillpipe
Plug Length
Assume that the top and bottom 100 ft of cement will be contaminated with
spacer.
2222
Contractor
Requirements
A diverter sub can improve the success of cement plug setting by directing the
flow and preventing the jetting of cement downhole. Use a distribution
(diverter) tool to direct flow up the annulus, such as a bull plug with four to
eight small (approximately 1-in.) horizontal side holes greater than the flow
area of tailpipe and at 90-degree phasing. If a wiper plug catcher is used,
place it below the holes.
Squeeze
Cementing
Diverter Sub
Plug
Cementing
Run the tail pipe to the planned bottom of plug depth. Tubing diameters of
2 7/8 in. should be used in slim holes of 8 1/2 in. or less; 3 1/2-in. tubing
should be used for larger hole sizes. Tubing is preferred over drillpipe in plug
jobs because the displacement of the tubing reduces swabbing and reduces the
weight of pipe to be pulled. For 17 -in. or larger open plugs, this is not critical and thus, they can be set using drillpipe. Coupling ODs of the tubing
should be minimized. If no tubing is available, 3 -in. drillpipe may be used.
If a stinger is to be run through open hole or in casing after a milling operation, break circulation every 5 to 10 stands to prevent plugging of the stinger.
Job
Procedures
Tubing diameters of
2 7/8 in. should be
used in slim holes of
8 1/2 in. or less; 3 1/2in. tubing should be
used for larger hole
sizes.
Engineering
and Planning
Plan a plug job based on hole conditions to pull out of cement. Many methods
are available and consideration should be given to prevention of contamination, risk exposure, environmental spill considerations, etc. The well depth,
the mud type, and many other factors will determine which procedure should
be used.
Introduction
Table of
Contents
Plug Cementing
Cement plugs set across perforations should be set from 100 ft below the perforations to 200 feet above the perforations.
Table of
Contents
If large quantities of cement are observed above the top of cement when circulating the well clean, channeling has likely occurred, and the area contaminated by the spacer will be larger than normal. This will increase the risk for
failing to tag the plug and/or for obtaining a pressure test.
In 8 1/2-in. and smaller open holes, plugs of up to 800 ft have been set and
successfully tagged to ensure a minimum volume criterion is met.
Plugs in extended reach wells are special cases and where plug setting
depth exceeds 14,500 feet and hole angle exceeds 45, plug length should
be 600 to 750 ft, with 300 ft of contamination allowance on top of the
plug.
Plug
Cementing
Whenever possible, use a caliper log to determine the cement volumes and to
help determine where to set a plug. Setting a plug in a section of the hole that
is near gauge will increase the chances for success.
Contractor
Requirements
If no caliper is available, refer to the following table for recommended percentages of excess volume.
Squeeze
Cementing
Cement Volumes
Job
Procedures
Engineering
and Planning
Plugs of 300 to 600 ft have been used for 8 -in. to 36-in. open holes for
abandonment, suspension and sidetracking in wells that are less than
14,500 ft deep and have less than a 45 inclination.
Introduction
2323
Plug Cementing
Calculation of Volume Excess
% Excess
(Water-Based Mud)
% Excess
(Synthetic-Based Mud)
30 to 36
200
24 to 30
100
14 3/4 to 17 1/2
50
20
12 1/4
30
20
6 to 8 1/2
30
20
Table of
Contents
Introduction
Always consider the particular area and hole conditions such as sloughing
shales or losses when determining the actual excess to be used.
Engineering
and Planning
Temperature
Make sure the
BHST and BHCT are
accurate for proper
job design.
Make sure the BHST and BHCT are accurate for proper job design.
Select the temperature for your design on the basis of deviation, operation,
and local experience.
Job
Procedures
Plug
Cementing
Slurry Properties
For kick-off plugs, the density of the slurry is important for rapid, high
strength development.
Plug and abandonment plugs and squeeze plugs are generally designed at normal density for the cement available, but may be adjusted for specific well
conditions. Dispersants and retarders are the most common additives used. A
fluid loss control additive may also be required for some open hole and
squeeze operations.
2424
Contractor
Requirements
Squeeze
Cementing
Plug Cementing
Fluid loss is required in plugs set across permeable formations; a fluid loss
less than 150 ml is adequate for abandonment / suspension plugs. However,
squeeze slurries should have less than 75 ml.
For all cement plugs that are to be spotted and balanced, the required thickening time is based on the calculation:
40 Bc time (in the lab report) must be greater than or equal to
job pump time + time to pull out of plug + 1 hr (safety factor).
Introduction
Calculated pump time is based on time cement is moving, and does not
include static time.
The recommended pulling rate is 30 to 50 ft/min.
Engineering
and Planning
Spacers
Separate mud and cement with adequate spacer/wash.
For sea-water mud, pump water as a spacer/wash.
Plug
Cementing
Job
Procedures
Squeeze
Cementing
2525
Contractor
Requirements
Table of
Contents
Thickening Time
Plug Cementing
Mechanical Tools for Supporting Cement Plugs
Introduction
Inflatable packers and mechanical bridge plugs are not suitable for use in
open holes.
Waiting On Cement
Engineering
and Planning
Plugs should not be tagged until they have at least 1,000-psi compressive
strength. A total of 1,500-psi compressive strength is required for pressuretesting the plug.
Kick-off plugs require
a compressive
strength of 3,000 psi.
Table of
Contents
Mechanical tools should be used only where necessary. Setting a reactive pill
may be more economical and easier, if support is necessary. The simplest tool
is a small sub run on the end of the tubing stinger that holds a short
umbrella like tool. When a ball is dropped, the umbrella extrudes and then
springs open to an approximate 20-in.diameter. This tool can be run in open
hole and casing. In casing, inflatable packers or mechanical bridge plugs set
on wireline can be used.
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
2626
Plug Cementing
Job Procedure
1. Make sure the stinger is run at least 300 feet below the plug-setting depth.
Table of
Contents
4. Pump cement.
Engineering
and Planning
Introduction
2727
Contractor
Requirements
NoteFor ultradeep jobs, a ball catcher sub and wiper plugs may be required
to effectively verify displacement.
Squeeze
Cementing
For hole sizes less than 12 1/4-in, pump at 2 bbl/min for the last 20
bbl.
For hole sizes greater than 12 1/4-in, pump at 3 bbl/min for the last 40
bbl.
7. Under-displace by 1 to 3 bbl, excluding the volume of surface lines,
unless using a latchdown sub, to ensure the plug is not contaminated and
that the pipe pulls dry.
Plug
Cementing
Job
Procedures
Plug Cementing
10.When going in hole to tag a cement plug, start washing down and rotating
pipe at the previous depth of last bottoms-up circulation or 500 to 1,000 ft
above the calculated top of cement.
CautionDo not run back into a cement plug with the stinger until the
cement has set. When the plug has been tagged, do not run back into the
cement without circulation.
Squeeze
Cementing
Plug
Cementing
Where a plug is being tagged with a kick-off assembly, use minimum flow
rates.
Job
Procedures
Engineering
and Planning
Introduction
Reverse circulation
can only take place if
the ECD would not
induce losses.
Contractor
Requirements
2828
Squeeze Cementing
Squeeze Cementing
Before a squeeze cement job is designed, it is important to identify the objectives to be met and to perform a risk analysis.
Introduction
Table of
Contents
Squeeze cementing is the process of placing cement into a confined area with
hydraulic pressure. Often this cementing process does not attempt to
squeeze or dehydrate the slurry at all but to place high quality, noncontaminated cement in the proper location to provide isolation or achieve other
objectives.
Add to the height of the cement column in place to produce upper zones.
Plug all, or part, of one or more zones in a multi-zone injector or production well.
Plug
Cementing
Contractor
Requirements
Squeeze
Cementing
Placement
There are two basic squeezing techniques: the Bradenhead squeeze and the
Bull Head squeeze.
Job
Procedures
Engineering
and Planning
2929
Squeeze Cementing
For squeeze jobs in which the operator plans to squeeze away the cement
into the formation, the total slurry volume should equal the amount to be
squeezed, so that only a minimal volume of excess cement will have to be circulated out.
The properties of the cement slurry must be tailored according to the characteristics of the formation to be squeezed and the technique that will be used.
Low-pressure squeezes do not exceed formation fracture pressures. They are
recommended for depleted wells with low bottomhole pressures and for
squeezing existing voids in any well where cement is not desired within the
formation.
High-pressure squeezes have no pressure limitations other than that of the
casing or tubing. Final squeeze pressure is either the maximum that can be
3030
Contractor
Requirements
Squeeze
Cementing
Slurry Design
Plug
Cementing
For squeeze cement jobs in which the cement is to be held in place, a total
slurry volume of approximately four times the volume of casing below the
work string is recommended. This should represent 60 to 80% of the work
string volume.
Job
Procedures
Engineering
and Planning
Cement Volume
Introduction
Table of
Contents
Squeeze Cementing
obtained or a predetermined value based on experience and calculations.
Depending on the type of squeeze job performed and operational objectives,
the formation fracture pressure may or may not be exceeded.
For a high-pressure squeeze, use a slurry with fluid loss of 200 to 500 ml/
30 min.
Use a slurry with high fluid loss for fast cake buildup in a fracture. A fluid
loss of 300 to 800 ml/30min at 1,000-psi differential pressure is recommended.
Slurries with a low yield point, or thin slurries, are preferred for most squeeze
jobs. Thin slurries can flow into narrow cracks or channels. Thick slurries are
more useful when cementing large voids.
Plug
Cementing
Dispersion
Job
Procedures
Engineering
and Planning
Introduction
Fluid loss is
extremely important
when a low-pressure
squeeze is used
against highpermeability zones.
Table of
Contents
Thickening Time
3131
Contractor
Requirements
Compressive Strength
Squeeze
Cementing
Squeeze Cementing
Washes and Spacers
As in primary cementing, washes and spacers are normally recommended for
two reasons:
to clean the perforation and surrounding voids of mud so that the cement
can get to the formation face and dehydrate properly
Prejob Considerations
Reduce the risk for cement contamination by using spacers, plugs, excess
cement or other tools.
Estimate the pressure differential between the fracture gradient and the
mud weight at depth.
Make calculations to set the bottom of the drillpipe or work string off bottom by 15 to 20% of work string volume below the drillpipe.
3232
Contractor
Requirements
Squeeze
Cementing
Plug
Cementing
Plan the job in detail with the service contractor to define the objectives
and operational procedures and pressures.
Job
Procedures
Engineering
and Planning
Table of
Contents
Squeeze Cementing
Plan to test the casing with worst-case pressure to reverse out excess
cement or develop a contingency plan that can be used if reversing out is
not practical.
Establish a plan for circulating out cement. Never circulate out cement the
long way if it cannot be reversed. Leaving cement on the inside of a work
string is not advised, but a cemented-up work string on the rigs pipe rack
is better than cementing up a drillstring in an active well thats being
drilled.
Job
Procedures
In planning cement squeeze jobs, always allow for a 10% error in displacements based on the volume of the work string, unless some mechanical devices are used to calculate displacements more accurately.
Engineering
and Planning
When unexpected
problems arise in
performing a squeeze
cementing job,
reverse out the
cement and start over.
Introduction
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
3333
Squeeze Cementing
Job Procedures
Bradenhead Cement Squeeze
Introduction
Table of
Contents
4. Pull two to three stands above the plug and reverse out the excess.
5. Pump away 1/3 of the cement volume while monitoring for pressure
increase as the cement feeds into the formation.
Engineering
and Planning
6. Wait for 15 minutes and pump 1/6 of the cement volume again while
monitoring for pressure increase.
7. Again, wait for 15 minutes and then pump 1/6 of the cement volume
while monitoring for pressure increase.
8. Let the well remain static until the cement sets up.
Job
Procedures
Hesitation Cycle
When stabilized pressure does not increase, lengthen the hesitation cycle.
Pump Cycle
Pump at the slowest rate possible.
Squeeze
Cementing
When the cement volume in the casing is used, STOP. This is all the
squeezing possible for the volume of cement selected. NEVER overflush
perforations.
3434
Contractor
Requirements
Squeeze Cementing
Table of
Contents
When maximum
allowable pressure is
attained without significant leak-off,
STOP.
When maximum allowable pressure is attained without significant leakoff, STOP. This is all the squeezing possible within the preset pressure
limit.
2. Mix enough cement so that you can squeeze the volume into the formation on the first squeeze. Use excess.
3. Stop and wait 15 minutes; then, pump the remaining volume in the tubing and/or drillpipe while monitoring for a pressure increase.
Engineering
and Planning
4. Let the well remain static until the cement sets up.
5. Pull two to three stands above the plug and reverse out the excess.
Cement Retainer
Job
Procedures
What are the wellbore conditions (mud weights and fracture gradients)?
Contractor
Requirements
3535
Squeeze
Cementing
To use a cement retainer for a squeeze job, set the cement retainer close to the
squeeze interval (40 to 60 ft above the interval) to minimize cement contamination. A lesser volume of cement slurry can be used since less contamination
will take place below the work string (usually 40 to 50% of the work string
volume). The pumping schedule should allow the cement slurry to be underdisplaced by 10% of the work string volume to avoid over-displacement with
the excess cement slurry reversed out.
Plug
Cementing
Introduction
Contractor Requirements
Contractor Requirements
Included in this section are:
Engineering
and Planning
flowcharts illustrating the roles and responsibilities of various parties during the job planning, mobilization, and implentation
Introduction
Table of
Contents
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
3636
Contractor Requirements
OFFICE
Yes
Job
Procedures
Cementing
contractor
conducts "new"
slurry design
pilot testing
using lab
materials.
Plug
Cementing
Need a new
cement slurry
design?
Engineering
and Planning
Unocal Drilling
Engineer reviews
output, verifies input
data and updates
cementing contractor
as appropriate.
LAB
Introduction
Cementing
contractor conducts
cement job
simulation,
centralizer
placement, etc.
Cementing
contractor receives
and reviews cement
job data.
Table of
Contents
FAIL
Simulation
OK?
No
Pilot test
design check.
Squeeze
Cementing
No
PASS
Yes
Contractor
Requirements
Unocal Drilling
Engineer approves
simulation output.
3737
Contractor Requirements
Introduction
Cementing contractor
conducts lab pilot test
using actual materials to
be used for the job.
Engineering
and Planning
No
Adjust slurry
design.
Job
Procedures
Unocal Drilling
Engineer issues
bulk blending order.
Plug
Cementing
REBLEND
Confirmation
test check
FAIL
Squeeze
Cementing
Contractor
Requirements
3838
Contractor Requirements
A
Introduction
Cementing
contractor performs
final job calculations.
Engineering
and Planning
Unocal Drilling
Engineer or
Supervisor approves
job calculations.
Job
Procedures
Cementing contractor
conducts all tasks on
prejob checklist.
Plug
Cementing
Cement job
performed.
Squeeze
Cementing
Cementing contractor
completes post job lab
test and job report.
Contractor
Requirements
Unocal Drilling
Engineer approves
job report.
3939
Contractor Requirements
Cementing Recommendation
Contents
The Cementing Recommendation should contain the following:
detail of well geometry, including hole, casing, and annular volumes, and
pore and fracture pressures
proposed cement and spacer formulations with details as to how they meet
the job objectives; this proposal should include the following
4040
Contractor
Requirements
Squeeze
Cementing
Plug
Cementing
Job
Procedures
Engineering
and Planning
Introduction
The Cementing Coordinator be fully capable of running the simulator, analyzing the output data and making the appropriate job recommendations, and
must use standardized software for generating this recommendation.
Table of
Contents
The Cementing Coordinator is responsible for preparing a Cementing Recommendation as requested for upcoming wells, and communicating with the
UNOCAL Engineer as required to obtain all necessary information for preparation of this document.
Contractor Requirements
Reporting Responsibilities
Prior to each cementing job the Cementing Coordinator shall update the
respective portion of the recommendation. Updates must be referenced to initial recommendation and pertinent lab testing.
Job
Procedures
Presentation of this report must include a hard copy and an electronic file in
either Microsoft Word or Excel format. Graphs may be generated to supplement the reports.
Engineering
and Planning
Introduction
Well control
exceptions must be
clearly highlighted and
brought to
UNOCAL Engineers
attention.
Table of
Contents
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
4141
Contractor Requirements
Perform compatibility tests between the cement and spacer and between
the spacer and drilling fluid for all jobs in which oil-based or syntheticbased drilling fluids are in the hole.
For all liner and tieback jobs, test the spacer for stability by hot-rolling
at circulating temperature.
Whenever possible, design the cement job to achieve turbulent flow of the
spacer in the open hole.
4242
Contractor
Requirements
Squeeze
Cementing
Plug
Cementing
Use the standard Unocal laboratory report form when submitting laboratory reports.
Job
Procedures
Engineering
and Planning
Clearly reference all pilot testing data to the appropriate cementing recommendation with a unique project or job number.
Introduction
Table of
Contents
Pilot testing (laboratory testing to develop cement designs that meet the
required criteria for the given well parameters) is required for all cementing
operations and shall include thickening time, rheologies, free fluid, fluid loss
(when fluid loss additive is included in formulation), 24-hour compressive
strength and WOC (time to 500 psi) by UCA for tail slurries and kick-off
plugs.
Contractor Requirements
Unless otherwise specified, all laboratory testing of cement slurries for UNOCAL operations must be performed in accordance with the latest revision of
API RP10B. The following are the required minimum laboratory testing procedures for cement slurry designs, as applicable.
Mixing
Introduction
Mix slurry as per standard API procedure (4000 rpm for 15 seconds and
12000 rpm for 35 seconds). If the slurry contains microspheres, the 12000
rpm requirement may be replaced by 4000 rpm.
Density
Squeeze
Cementing
4343
Contractor
Requirements
Test as per the appropriate API RP 10 B Schedule or as per a calculated temperature and pressure schedule using the equations in sections 9.5.3.2 and
9.5.3.4 through 9.5.3.7 of the API RP 10B. Report the time required to reach
40 Bc, 70 Bc, and 100 Bc.
Plug
Cementing
Contractor Requirements
Compressive Strength at BHST and 3000 psi
Table of
Contents
Attach documented results of UCA testing required for WOC 500-psi values
and UCA charts to the slurry test result sheets. A crush test is required for 12hr or 24-hr compressive strength. Cure and test according to API RP 10B,
excluding section 7.6.
Introduction
Engineering
and Planning
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
4444
Contractor Requirements
On-Location Procedures
Engineering
and Planning
Validating Materials
Verify that the following criteria are met for all materials to be blended:
Lot numbers of bulk cement and all additives are recorded on the blend
sheet.
Additives are of the same lot or batch number used in laboratory tests.
Only one lot number is used per each critical additive, i.e., fluid loss additives, retarders.
Job
Procedures
The UNOCAL Drilling Engineer and Foreman will approve the volume of
cement to be blended for the job.
4545
Contractor
Requirements
Squeeze
Cementing
Plug
Cementing
Introduction
For smaller jobs (400 sk or less), consider the use of 220-ft3 portable tanks for
loading, transporting and pumping the job. This will place the final quality
control point at the bulk plant, eliminating the need for quality control checks
between the bulk plant and the rig and consequently, the lead time required
for those checks.
Table of
Contents
The cement bulk blending and loadout procedures that are performed on location are an integral part of quality control, and must be
Contractor Requirements
ImportantThe bulk volume of each batch of cement and additives must not
exceed 60% of scale tank capacity.
To determine the total volume of cement and additives required:
Table of
Contents
1. Based on total volume of cement blend required, bulk load factor, and
blending capacity, determine the batch size and quantity.
Preparing Equipment
4. Check air compressor and/or vacuum system for proper operation, and
drain of any moisture.
Engineering
and Planning
3. Verify that the scales have been calibrated and certified within the past six
months. A certification stamp must be on the scale.
Introduction
2. Use the cement blend formulation to calculate total cement and additives
required.
1. Empty, clean, and inspect all blending equipment, including cutting pods,
scale tanks, boxing tanks, silos and sampling devices.
Job
Procedures
2. Open and visually inspect all tanks immediately prior to the job to ensure
that they are empty and clean.
Plug
Cementing
5. Check aeration pads for moisture; if wet, blow air through until dry.
Squeeze
Cementing
6. Inspect air-jets for build-up. Clean or replace jets and rubbers as necessary.
7. Purge, empty, and clean all transfer lines.
8. Clean or replace dust sacks.
Contractor
Requirements
Weighing
1. Make sure calibration and certification records for all weighing devices
are available.
2. Zero the scale tank prior to the blending operation.
4646
Contractor Requirements
3. Once the scale is zeroed, this same zero point MUST be maintained during the entire blending operation.
Introduction
Engineering
and Planning
6. Calculate weights of cement and additives for each step. Double check
calculations.
7. Weigh all additives into the bulk tank.
Weigh all additives
into the bulk tank.
Never use the weight
indicated on the bag
for calculations.
Table of
Contents
4. Cement and additives are to be layered into the scale tank in the following
order:
Job
Procedures
8. Take into account bag weight or weight of any other weighing container.
Example: For small amounts of additives, the material should be weighed
using a clean plastic or steel container (bucket, garbage can, etc.) after
adjusting (tarring) the scale for the weight of the container.
10.Record scale tank readings after each step, actual cumulative weight.
Contractor
Requirements
14.Purge the lines of all material after each transfer of material (cement or
additives). Repeat this purging procedure if it is suspected that some of
the material is remaining in the line.
Squeeze
Cementing
12.For large volume additives such as silica sand, the weigh tank scale may
be used to measure the weight of the material. Example: 3700 lbs. silica
flour, record current scale tank weight, add 36 sacks of 100 lbs. net
(labeled) each, check scale tank weight, weigh out and add any additional
silica flour to bring weight added up to 3700 lbs.
Plug
Cementing
11.During the weighing process, document and compare the target and
actual cumulative weights after each addition of additives or cement to
the blend.
4747
Contractor Requirements
Blending
Engineering
and Planning
4. Check and record weight of blend each time it comes back into the scale
tank.
Plug
Cementing
ImportantThe weight of the material remaining in the scale tank after the
transfer must be recorded. This weight will be added to the cumulative
weights of the next batch of blended material.
Job
Procedures
3. During the last transfer, take bulk blend samples as detailed in the following section on sampling.
Introduction
1. After all cement and additives have been placed in the scale tank, use
approximately 30 psi to transfer the material to the blend tank. If
extremely light additives are being used (microspheres, silica fume, etc.)
the transfer pressure should be reduced to 6 to 8 psi to minimize segregation and losses of these light additives through the vents.
Table of
Contents
Squeeze
Cementing
Contractor
Requirements
4848
Contractor Requirements
Sampling
Always take samples for lab analysis and confirmation testing. A sample
MUST be taken for each batch blend when it is transferred from the scale tank
to the holding tank prior to load-out.
An automatic or manual sampling valve may be used. A pneumatic in- line
sampler is operated through the complete transfer. A manual 1- or 2-in. valve
sampler located on the discharge line, should be opened intermittently
throughout the transfer.
Table of
Contents
Introduction
The minimum total sample quantity is three gallons (three plastic sample
bags)two to send to the lab and one to keep at the bulk plant.
To take a sample, perform the following steps:
Engineering
and Planning
5. Label the sample containers and storage tanks with the following information:
Job
Procedures
a. date
Plug
Cementing
b. formulation
c. quantity
d. batch number
e. bulk plant operator
g. cementing job
In some cases sampling should be witnessed by a UNOCAL representative or
designated third party inspector.
Bulk blend testing is required for application of dry-blended bulk blends for
all casing strings.
Bulk blend testing is to include the following, as a minimum:
4949
Contractor
Requirements
Squeeze
Cementing
f. well number
Contractor Requirements
thickening time test at BHCT
Table of
Contents
The Cementing Contractor must not load out a dry cement blend until
approved by a UNOCAL representative.
Documentation
Job
Procedures
The Cementing
Contractor must not
load out a dry cement
blend until approved
by a UNOCAL
representative.
final quantity and the number of the storage tank into which it was loaded
Preloading
1. Prepare a load ticket detailing type, content, volume, and weight and bulk
load factor of each cement or blend to be loaded.
5050
Contractor
Requirements
In the event bulk trucks are used to transport the cement blend to the boat
dock, a bulk plant operator shall accompany the trucks and uphold responsibilities.
Squeeze
Cementing
The bulk plant operator is responsible for loading out cement and must ensure
that cement quality is not diminished during or because of this operation. On
the rig, the cementer is responsible for the preparation and execution of
cement offloading procedures from the boat onto the rig. They must promptly
report any problems to UNOCAL.
Plug
Cementing
Engineering
and Planning
Contractors Cementing Supervisor shall monitor bulk blending and coordinate the lab testing.
Introduction
The Cementing Contractor shall ensure that there is sufficient time between
field blending and the actual cement job to allow for blending, testing, and
when necessary, modifications, re-blending, and re-testing, without jeopardizing the execution of the cement job itself.
Contractor Requirements
2. Prior to loading or inspecting tanks, present a copy of the load ticket to
boat captain and discuss which tanks are to be loaded.
4. Verify hose hookup and valve alignment with boat captain or designated
representative.
Table of
Contents
3. Verify tank volumes and calculate cement volume to be loaded into each
tank.
3. Inspect air-jets for cement or other buildup; if found, clean or replace the
jets and their rubbers.
Job
Procedures
2. Check aeration pads for moisture; if they are wet, blow air through them
until they are dry.
Engineering
and Planning
6. Pressurize tanks that are to be loaded to 10 psi and check for leaks.
7. Blow down tanks through discharge and hoses that will be used at the rig.
Plug
Cementing
5. Blow air through all purge lines until they are dry.
Loading Cement
5151
Contractor
Requirements
2. After loading, request the boat crew to open hatches and verify the
amount of cement in each tank, reseal hatch covers, pressure check seal,
and then vent pressure.
Contractor Requirements
CautionLeave pressure off tanks until preparing to off-load cement at the
rig.
Table of
Contents
3. Verify that the boat crew caps and stows the cement discharge hoses
before getting underway.
Offloading Cement at Rig
1. Calculate available rig tank capacities based on bulk load factor of cement
to be loaded.
3. Conduct a visual inspection of the rig tanks prior to loading. and make
sure that any necessary cleanup or repair operations are witnessed.
4. For a liner job, sweep down the rig tank and completely clean it out prior
to loading. Inspect all air pads and jets and replace them as necessary.
6. Install a rock catcher in-line between the boat and the rig tank. The rock
catcher should be positioned on the rig.
During the loading, catch two sets of samples by taking two 1-gal samples at
the beginning, middle, and end of each tank load for a total of six samples.
Plug
Cementing
Rigsite Sampling
Job
Procedures
5. Go on board the boat to inspect the air system and to verify the location
and type of cement or blend in each tank. Check the hose hookups, valve
alignment, and hoses and capped hoses and lines.
Engineering
and Planning
2. Meet with the company man to discuss volume calculations for the
cement and verify the rig tanks into which cement is to be loaded.
Introduction
b. Open the access hatch on the top and open the lower feed line from the
bottom of the tank; take three 1-gal samples from each, labeling them
as top and bottom.
5252
Contractor
Requirements
a. Transfer the loaded cement from the rig tank to a portable cement tank
(pod).
Contractor Requirements
Labeling Samples
3. Send one set of samples (three cement samples, one mix-water sample,
and one drilling fluid sample) to the laboratory and retain the other set on
the rig.
Introduction
2. Take two 5-gal samples of mix water and two 2-gal samples of drilling
fluid in clean, sealable containers that are labeled with date, rig, and
source.
Table of
Contents
1. Place the samples of cement blend in the standard sample bags that are
prelabeled with the date, job type, formulation, amount, rig tank number,
and at what interval the sample was taken during the loading process
beginning, middle, or end.
Prejob Procedures
Plug
Cementing
Job
Procedures
1. Prior to the cement job, obtain up-to-date well information and cementing
objectives from the UNOCAL Drilling Supervisor. This information
should include
Engineering
and Planning
3. Verify equipment and material requirements and confirm that they will be
on location for the job.
Squeeze
Cementing
2. Conduct a prejob meeting for all service personnel (mud loggers, etc.) to
provide information or add value to the process.
5353
Contractor
Requirements
5. Review laboratory test results from the rig samples with the cementing
coordinator, paying special attention to the thickening time (available
pumping time) and the required WOC (wait on cement time, time to 500psi).
Contractor Requirements
6. Calculate cement volumes in barrels, in cubic feet, and in sacks of cement
required for the lead and tail formulations. Include a breakdown of these
volumes showing cased hole, open hole, and shoe track volumes.
10.Verify that the suction rates required for the job can be achieved with both
drilling fluid and water.
5454
Contractor
Requirements
Squeeze
Cementing
rig-up procedure
safety concerns
pressure testing procedure
spacer type, density, and volumes to be pumped
wiper plugs, dart- or ball-dropping sequence and procedure
cement slurry formulation(s) densities and volumes
conversion factors for calculating sacks per barrel of slurry and barrels
of slurry per barrel of mix water
pumping schedule indicating rates, volumes, and times for pumping
and displacing each fluid
total job time including time to drop plugs and flush lines
anticipated job pressures during pumping, shearing or bumping of
plugs and darts
in-hole hydrostatic pressures of each fluid after placement
personnel requirements for the job
Plug
Cementing
Job
Procedures
NoteThe cementing contractors equipment will be used for all mixing and
pumping.
Engineering
and Planning
Introduction
9. Check the available water supply and verify that sufficient quantities of
water will be available for the job.
Table of
Contents
Contractor Requirements
contingency plans for the unexpected: liner top packer fails, float
equipment fails, loss of returns while going in the hole, etc.
WOC criteria prior to rigging down any well-control devices
16.Load the wiper plugs in the presence of the UNOCAL Drilling Supervisor.
17.Review checklists, laboratory test results (available pumping time and
WOC time), and job plan with the UNOCAL Drilling Supervisor.
18.Prepare spacer as required and check the weight with a pressurized drilling fluid balance.
Introduction
Table of
Contents
15.If supplying the wiper plugs and cementing head, verify that the correct
equipment is on location and that the cementing head and associated connections have been tested.
Engineering
and Planning
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
5555
Contractor Requirements
Job Procedure
Table of
Contents
1. Hold a safety meeting on the rig floor to review the job procedure and
address safety concerns.
NoteMaintain an open line of communication to rig floor at all times.
2. Pump spacer to break circulation.
Introduction
3. Pressure test the lines and the operating system to a pressure above that
expected during the cementing operation.
4. Pressure up the bulk tanks.
5. Pump the job according to the job plan.
NoteThe cementer is responsible for seeing that wiper plugs darts or balls
are released at appropriate times.
6. Use a data acquisition system to record pressure, rate, density and volumes pumped during job.
Job
Procedures
Plug
Cementing
8. Count and record the volume of mix water by the number of displacement
tank volumes used.
5656
Contractor
Requirements
9. Measure the cement slurry density with a pressurized drilling fluid balance.
Squeeze
Cementing
Engineering
and Planning
The cementer is
responsible for
seeing that wiper
plugs darts or balls
are released at
appropriate times.
Contractor Requirements
12.Label and retain samples for possible laboratory testing until the well is
completed.
CautionDo not pump any fluids lighter in weight than the drilling fluid in
the hole, unless previously agreed upon by respective parties that a lighterweight spacer or flush is to be used.
Do not open the cement head after a cementing fluid (spacer or slurry) has
been pumped downhole, until after the job is completed.
Introduction
Engineering
and Planning
Table of
Contents
Do not sacrifice
cement slurry
density for pump rate.
Job
Procedures
Plug
Cementing
Squeeze
Cementing
Contractor
Requirements
5757