DILIP BUILDCON LIMITED

Project Name :CRP : -

MUNDARAGI TO HARPANHALLI PROJECT CRP:-34


34

COMULATIVE PRODUCTION

53719.696 COMMULATIVE 10MM

COMULATIVE GSB

SANDVIK CRUSHER CRP-34


Day Shift : 8AM-8PM

COMULATIVE WMM

Night Shift : 8PM-8AM

COMULATIVE AGGREGATE

50963.160 COMULATIVE 20MM


0 COMULATIVE 40MM
2756.536 COMULATIVE DUST
COMULATIVE WASTAGE

Sr. No.

Time Up

Time Down

Time Duration (In hrs)

Working Description

8:00

9:00

1:00

MAINTENANCE

9:00

12:00

3:00

PLANT RUNING

12:00

13:00

1:00

PLANT STOP DUE TO WATER TANKER NOT AVILABLE

13:00

14:00

1:00

LUNCH TIME

14:00

18:00

4:00

PLANT RUNING

18:00

21:00

3:00

PLANT STOP DUE TO BOLDER NOT AVILABLE

21:00

23:00

2:00

PLANT RUNING

23:00

0:20

1:20

PLANT STOP EXAVATOR BREAK DOWN

0:20

6:00

5:40

PLANT RUNING

10

6:00

8:00

2:00

PLANT STOP DUE TO BOLDER NOT AVILABLE

Total Time Duration

24:00:00

NOTE- TOTAL PLANT RUNING HOURS-: 14:40


NOTE- TOTAL PLANT STOP HOURS -:09:20

NO. OF TRIPS

137

CRUSHING PRODUCTION

3005.960

GSB

3005.960

WMM

AGGREGATE

TPH
AMIT MISHRA (INCHARGE )

208.7472222222
G C MANDAL (MINING)

Incharge

Stone Crusher

Mining

153

DPR
DATE:-14/10/2016

DILIP( WEIGHTBRIDGE)
Incharge

Weigh Bridge

10/15/2016