Method Statement For Pipe Culvert Works PDF
Method Statement For Pipe Culvert Works PDF
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 1 of 7
2. PROCEDURE
The procedure for construction of Pipe culverts is elucidated as under:
Four Laning of Hyderabad Karimnagar Ramagundam Road on SH-01 in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500 to 197+000
Client
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 2 of 7
on each side of the pipe of not less than five times the diameter of pipe, after
which a trench shall be excavated and the pipe shall be laid.
The pipe shall be placed where the ground for the foundation is reasonably firm. If
the soil at the bed level of the pipe is soft, spongy or other unsuitable soil, it shall
be removed to such depth, width and length as directed by the Engineer and the
extra depth shall be backfilled with approved granular material and compacted up
to specified level.
If bed-rock or boulder strata are encountered, excavation shall be taken down to at
least 200 mm below the bottom level of the pipe in accordance with the Para-4 of
the Cl. No. 2904 of MORT&H.
Excavation shall consist of the removal of the material for the construction of
foundation for apron, head wall and other similar structures, in accordance with
the requirement of MORT&H specifications and the lines and dimensions shown on
the drawings or as indicated by the Engineer. The work shall include draining and
pumping. The removal of all logs, stumps, grubs and other deleterious matter and
obstructions, necessary for placing the foundations, trimming of excavations,
backfilling and clearing up the site and disposal of all surplus material.
FORM WORK:
Formwork of required length and size shall be provided for laying and placing of
lean concrete layer. Side formwork shall be used for apron as well as the head wall
concrete work. All materials for formwork will conform to IRC:87
Formwork shall be removed not earlier than 24 hours after placing of concrete. The
design and erection of formwork shall be as per IRC-87 and conforming to Section1500 of the Technical Specifications (MORT&H).
LAYING OF LEVELLING COURSE / HEAD WALL:
i.
ii.
iii.
Four Laning of Hyderabad Karimnagar Ramagundam Road on SH-01 in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500 to 197+000
Client
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 3 of 7
iv.
v.
Four Laning of Hyderabad Karimnagar Ramagundam Road on SH-01 in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500 to 197+000
Client
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 4 of 7
The entire operations will be in accordance with the Clause No. 2905 of the
MORT&H.
PIPE JOINTING:
The pipe shall be jointed by flush joint. Flush joint may be internal flush joint or
external flush joint. In either case, the ends of the pipes shall be specially shaped
to form a self centering joint with a jointing space 13 mm wide. The jointing space
shall be filled with cement mortar, I cement to 2 sand, mixed sufficiently dry to
remain in position when forced with a trowel or rammer. Care shall be taken to fill
all voids and excess mortar shall be removed
BACK FILLING:
Immediately after the pipes have been laid and the jointing material has hardened
the trench will be backfilled. The backfilling will be done in accordance with Cl.
No. 2907 of the MORT&H.
Backfilling up to 300 mm above the top of the pipe shall be done carefully and the
soil shall be thoroughly rammed, tamped or vibrated in layers not exceeding 200
mm. The gaps between two adjacent pipes shall also be filled in the same
procedure as explained above.
The entire operation will be in accordance with the Cl. No. 2907 of the MORT&H.
PROTECTION AND CURING:
As per section 1713.1, exposed surface of concrete shall be kept continuously in a
damp or wet condition by ponding or by covering with a layer of gunny bags or
similar materials and shall be kept constantly wet for a period of not less than 14
days from the date of placing of concrete.
3. EQUIPMENT/MACHINERY:
a.
b.
c.
d.
e.
Four Laning of Hyderabad Karimnagar Ramagundam Road on SH-01 in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500 to 197+000
Client
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 5 of 7
f. De-Watering Pump
g. Transit Mixer of Capacity 4 M3
h. Other relevant tools
4. RECORDS AND DOCUMENTS MAINTAINED:
i. RFIs
ii. Level control sheets (if reqd.)
iii. Concrete Pour card / Concrete cube results
5. QUALITY CONTROL PROCEDURES:
To ensure the suitability of materials / concrete, tests would be conducted at
field/laboratory as per Cl.1000 & Cl.1700 of MoRT&H. And the same is detailed
in Inspection test plan.
6. SAFETY MANAGEMENT ACTION PLAN
In order to minimize the occurrence of site accident, the provision of a safe
working environment for workers to work is essential. Our company endeavors
to make a zero accident record in each site. In addition to the above, the
following safety precautions must also be implemented in achieving the
minimization of site accidents.
SAFETY MEASURES:
a) Provisions for workmen:
i. It is required that all persons working at the site shall be provided with
the safety equipments, protection means such as safety jackets, hand
gloves, safety helmets and other necessary kinds.
ii. All persons working on the site shall be trained by conducting the training
course for safety to ensure that they are fully aware of the contents.
b) Provisions for Equipment, Machine:
a. All equipment will be ensured to operate safely, maintained and
repaired periodically.
b. All power equipment should be insulated and covered to all exposed live
parts.
Four Laning of Hyderabad Karimnagar Ramagundam Road on SH-01 in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500 to 197+000
Client
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 6 of 7
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
7. ENVIRONMENT CONTROL
i.
ii.
Four Laning of Hyderabad Karimnagar Ramagundam Road on SH-01 in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500 to 197+000
Client
Independent Engineer
Concessionaire
EPC Contractor
Rev. : 0
W.e.f: 03-03-2011
Page 7 of 7
iii.
iv.