This document summarizes a bridge assessment analysis for Anywhere Bridge. It provides key structural dimensions and calculations of factors like the span/rise factor, profile factor, material factor, and joint factor. These factors are then used to calculate the provisional axle load, modified axle load, and allowable axle loads for single axles and 2 axle bogies. The maximum gross vehicle weight is also determined from provided tables.

Uploaded by

joshua humirang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Arch Bridge Excel

This document summarizes a bridge assessment analysis for Anywhere Bridge. It provides key structural dimensions and calculations of factors like the span/rise factor, profile factor, material factor, and joint factor. These factors are then used to calculate the provisional axle load, modified axle load, and allowable axle loads for single axles and 2 axle bogies. The maximum gross vehicle weight is also determined from provided tables.

Uploaded by

joshua humirang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
  • Bridge Assessment Data

Project:

Bridge Assessment
Anywhere Bridge

Structure:

Sheet No.

MEXE Analysis to BA 16/97


(All dimensions in metres)
rc = 1.57
L = 5.23

rq = 1.373

d = 0.34

h+d = 0.725

1
Calculations are based on an h+d value of 0.68
Fw = 0.9
Fmo = 0.9
Fd = 1
FCM = 0.7

as h > d then MEXE may be unconservative (Cl. 6.17). Limit h+d to 2*d ? (1=Yes, 2=No)

Fb = 0.8

Ff = 0.7

Clause No:
3.10)

Provisional Axle Load = 740(d+h)2/L1.3 =

39.83

tonnes

3.11)

Span/Rise Factor L/rc =

3.12)

Profile Factor Fp = 2.3((rc - rq)/ rc )0.6 =

3.13)

Material Factor Fm = ((Fb * d)+(Ff * h)) / (d+h) =

3.16)

Joint Factor Fj = Fw * Fd * Fmo =

3.24)

Modified Axle Load = Fsr * Fp * Fm * Fj * FCM * PAL =

3.27)

Axle Lift-Off
(Fig 3/5a & 3/5b)

Hence Fsr =

3.33

1.00

(Fig 3/3)

11.2

tonnes

0.66
0.75

0.81

Af for 2 axle bogie =

a)

Single Axle

Af =

0.00

Allowable Axle =

0.0

tonnes

b)

2 Axle bogie

Af =

0.00

Allowable Axle =

0.0

tonnes

From Table 3/6 Max Gross VehIcle Weight =

tonnes

Project:
Bridge Assessment
Structure:
Anywhere Bridge 
      Sheet No.
L = 5.23
1.57
1.373
d = 0.34
h+d = 0.725
as h > d then