Professional Documents
Culture Documents
Subsoil profile:
0-3m, silty SAND, SPT=1- 5
3-6m, silty SAND, SPT= 15 - 50
6-20m, highly weathered sandstone
Schematic Detail
Soil becoming
weathered rock
L = 20.0m
API Pipe
O.D.
Thickness
fy (min)
Grade
=
=
=
=
127.0mm
9.2mm
552 Mpa
N-80
Cementitious Grout
W/c
=
0.45
Fcu
=
25 Mpa
Safe Working Load
Pa
=
80 tonnes
Lsocket
=
20m
Page 1
Material Properties
1.1
1.1.1
1.1.2
1.1.3
Micropile Diameter, D
Pile Composite Modulus Ep
Moment of Inertia, Ip
1.2
Cementitious Grout
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.2.6
1.3
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
1.3.7
1.3.8
1.3.9
Source
Outer Diameter, OD
Wall Thickness. t
Inner Diameter. ID
Cross Sectional Area, As
API Specification
Grade Designation
Mm. Yield Strength, fy
Elastic Modulus. Es
1.4
1.4.1
1.4.2
1.4.3
1.4.4
1.5
1.5.1
1.5.2
1.5.3
1.5.4
2.0
Structural Design
Assuming that the applied vertical load is carried by the API Pipe alone.
Ultimate Load Capacity Pu
= 0.87 x fy x As
= 1633450 N
= 1633.5 kN
= 163.3 tonnes
Use the Factor of Safety prescribed in Section 1.5 on Plate 2
Allowable Load Capacity Pa
= 82 tonnes
2.1
2.2
= 200mm
= 41
GPa
= 7.85E+07 mm^4
=
=
=
=
=
=
0.45
Adogroud 100g 150kg bag
45686
mm"2
25
MPa
2000
kg /M^3
28
GPa
=
=
=
=
=
=
=
=
=
127
9.19
108.62
3401
5A-80
N-80
552
210
=
=
=
=
2.00
1.60
2.00
2.50
mm
mm
mm
mm^2
MPa
GPa
Req. Min.
(Max)
Source
BS8110
BS8004
BS8004
BS8004
Skin Friction
End Bearing
Page 2
2.3
= 80 tonnes
3.0
Geotechnical Design
Refer Piler Analysis for derivation of Geotechnical Safe Working Load -Appendix ......
3.1
Design Length
3.1.1
3.1.2
3.1.3
3.2
3.2.1
3.2.2
3.2.3
3.2.4
P
D
Ls
= 800
= 200
= 20.0 m
kN
mm
= 2.0
= 2.5
= 0.8
= 2.5
< 20.0 m
OK
MPa
MPa
m
4.0
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.2
4.2.1
4.2.2
Effective radius
Euler Critical Load
4.3
4.3.1
4.3.2
4.3.3
4.3.4
4.3.5
FOS available
5.0
5.1
5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
5.1.7
Outer Diameter
Wall Thickness
Internal Diameter
Cross sectional Area
API Specification
Grade Designation
Min Yield Strength
r
Pe
FOS available
O.D.
t
I.D.
As
fy
=
=
=
=
Fixed
Fixed
1m
0.7 m
=41.8
=@pi^2 - Ep l(Lelr)^2 = 1428 kN
=9.78
OK
=
=
=
=
=
=
=
50
6 ' N kPa 300 kPa
67*Cu
20.1 MPa
2 x @sgrt (Ep x Ip x kh x d)
16014 kN
20.02 OK
=
=
=
=
=
=
=
127.0
9.2
108.6
3401
5A-80
N-80
552
mm
mm
mm
mm^2
MPa
Page 3
5.1.8
5.1.9
Elastic Modulus Es
=
210
GPa
Allowable Axial Working Stress (Clause 7.4.6.3.1 BS8004)
Fa
=
50% of Yield Strength
=
276 MPa
5.2
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
=
=
=
=
=
Asc
O.D.
Tc
0.01
800
2899
124.5
255
mm/year
kN
mm^2
mm
years
Summary
800
kN
=
=
=
x
25
6.85
116800
350
MPa
MPa
mm^2
OK
155
MPa
6.1
6.1.1
6.1.2
6.1 3
6.2
Thickness of Stiffners
6.2.1
6.2.2
6.2.3
6.2.4
6.3
6.3.1
6.3.2
6.3.3
125
=
=
Adopt
6.4
6.4.1
6.4.2
6.4.3
3401 mm^2
184
mm
2.4
mm
10
mm
(4No. MS Stiffeners)
MPa
210
MPa
=
=
10761 mm^2
74
MPa
< All. Bearing Stress, OK
Page 4
6.5
6.5.1
6.5.2
6.5.3
6.5.4
6.5.5
6.5.6
6.5.7
6.5.8
6.6
6.6.1
6.6.2
6.6.3
6.6.4
6.7
6.7.1
6.7.2
=
=
=
Adopt
2xd
280
0.49
7
mm per stiffener
kN/mm
mm Fillet Weld
Page 5
Design Report
1.
Introduction
This report presents the design criteria and design calculations for pile foundation for
Interchange 3 of Project B 15 Road Upgrading Works.
Interchange 3 is a cloverleaf interchange with arch shaped R.C bridge as shown below
From structural analysis the compression load coming over the piles from one half of the
bridge is 12600 ton while the other half is 2800 ton in tension.
2.
Site Condition
The topograph of the site is rolling to undulating. The subsoil condition is generalized as
shown above.
The top 12m to 16m from the OGL of the residual soil is clayey silt with SPT 6-39 (aver
age SPT=20): This is underlain by hard clayey silt sith SPT exceeding 50 up to 28m bgi.
3.
4.
Analysis
Shallow foundation is not suitable because part of the formation is on filled ground and also
part of the foundation is in tension or high compression.
Driven spun piles cannot or not practical to provide adequate tension required. Large diam
eter bored piles are suitable for high compression and tension required.
Design Calculations
4.1
Compression piles
The allowable compression load carrying capacity of the single pile has been cal
culated based on the SPT 'N" values, using the following formula.
Page 6
Allowable load
Ab
Ab, af + As,fs
3
2
2
base area (m )
qf
=
=
Nb
As
fs
=
=
Nave
Tension piles
The allowable tension load carrying capacity of single pile has been calculated
based on SPT 'N' values, using following formula
Allowable load
=
As . fs 2
As
fs
=
=
Nave
Design Calculations
5.1
General
5.2
Compression load tests and pull out tests were carried out at the Interchange bridge site to
assess the performance of the piles installed to the design lengths.
Page 7
(a)
West Abutment
The tension Test Piles (No.81) located on the west abutments satisfied the per
formance criteria. Based on Prof Chin's Stability Plot:
Ultimate load
: 1141 tonne
Average Unit Shaft Friction
16 tonne/m2
The compression Test Pile No. 15 located ont the west abutments satisfied crite
ria at work load and 2 x work load but just failed to satisfy the recovery criteria.
Based on stability plot.
Ultimate capacity
: 2,490 tonne
Ultimate Shaft capacity
1,945 tonne
548 tonne
39 tonne/m2
310 tonne/m2
RL 31.00
East Abutment
Tension Pile No. 71 was tested. Pile satisfy the deflection criteria at working load
but however failed to attain the 2 x working load without excessive movement.
Based on Stability Plot, the following capacitities can be estimated:
Ultimate Shaft capacity
624 tonne
9 tonne/m2
This is much less than the 16.0 tonne/m2 value of tension pile No. 81. Based on
the evaluated value of 9.0 tonne/m2, all remaining working tension
piles are installed to RL 21.00 toe level, l O.Om longer than the test pile.
Compression pile No. 65 was first tested. It failed to satisfy the performance cri
teria. Estimated capacities are:
Ultimate capacity
: 1600 tonne
Ultimate Shaft capacity
625 tonne
1041 tonne
Page 8
12 tonne/m2
Mobilised Unit Toe Resistance589 tonne/m2 Based on above results, Test Pile
No. 2 (Pile No.66) located 4.50m from P65 was installed to toe level RL 33.00
(5.Om longer). Theoretical ultimate capacity should be of the order of 1,900
tonnes. The test showed the following:
Ultimate capacity
: 1520 tonne
Ultimate Shaft capacity
730 tonne
790 tonne
10 tonne/m2
447 tonne/m2
These are less than values obtained from P65, indicating significant variation in the sub
soil strength. Concreting procedures are satisfactory and concrete batch records
and test indicate supplied concrete complied with the requirements of the specification.
Concreting volume of pile does not indicate occurrence of collapse of borehole or neck
ing. Since the pile was concrete immediately after boring, strength relaxation due to
aging should not occured.
Based on above, all remaining piles are to be installed to toe levels 23. Pile No. P52 will
be test to assess amount of pile head movement at working load and 2 x working load.
Estimated ultimate capacity of piles to toe level RL 23.00 is order 2,100 tonnes.
(c)
Results of loads tests carried out at Interchange No. 3 are shown in Figure T1 to
T.
Page 9
Road B -15
= 2*Nave (SI-Unit s)
fs
62
61
60
59
58
57
26
27
28
29
30
39
38
37
36
35
50
50
50
50
50
50
50
50
50
50
50
50
50
47
47
32
32
28
28
31
31
29
29
23
23
17
17
16
16
16
75
75
75
75
75
75
75
75
75
32.5
32.5
32.5
32.5
31
31
23.5
23.5
21.5
21.5
23
23
22
22
19
19
16
16
15.5
15.5
15.5
C o r r ect ed
37.53
36.28
34.95
33.52
31.98
30.33
28.54
26.6
24.5
22.2
21.71
21.18
20.58
19.92
19.26
18.53
18.2
17.82
17.54
17.21
16.68
16.05
15.39
14.56
13.93
13.08
12.5
11.63
10.33
7.75
N ave
A ver ag e
75.06
72.57
69.9
67.04
63.96
60.65
57.08
53.21
49
44.41
43.43
42.35
41.16
39.83
38.53
37.06
36.4
35.64
35.08
34.42
33.36
32.1
30.78
29.13
27.86
26.17
25
23.25
20.67
15.5
f s=2 N
141.37
136.66
131.95
127.23
122.52
117.81
113.1
108.38
103.67
98.96
94.25
89.54
84.82
80.11
75.4
70.69
65.97
61.26
58.55
51.84
47.12
42.41
37.7
32.99
28.27
23.56
18.85
14.14
9.42
4.71
As
10612
9917
9223
8529
7837
7146
8456
5767
5080
4395
4093
3792
3491
3191
2905
2620
2401
2184
1984
1784
1572
1361
1160
961
788
817
471
329
195
73
Qs
U LT I M A T E S HA F T R E S I S T A N C E
25
Not e:
24
20
45
41
19
40
18
47
46
23
17
48
42
16
49
21
15
51
50
22
14
52
43
13
53
44
11
12
54
63
10
64
55
65
56
D ep t h
Level ( m)
SPT
Db
2.00
A llowable load = Ult imat e load along base/ 3.0 + Ult imat e load along shaf t / 2.0
As
= 400*Nb(SI-Unit s)
qf
Nb
Ab
R ed uced
where
P ILE LE N G T H E S T IM A T IO N A LO N G T H E IN T E R C H A N G E # 3
75
75
75
75
70
64
59
54
48
43
36
30
29
27
26
25
24
23
22
21
21
20
19
18
17
15
14
13
13
12
10
Nb
30000
30000
30000
30000
27875
25750
23625
21500
19300
17100
14525
11950
11400
10850
10375
9900
9450
9000
8775
8550
8275
8000
7625
7250
6925
5825
5571
5233
5000
4650
4133
q f =4 0 0 N b
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
1.767
Ab
53014
53014
53014
53014
49259
45504
41749
37994
34106
30218
25668
21117
20145
19174
18334
17495
16700
15904
15507
15109
14623
14137
13474
12812
12237
10294
9846
9248
8836
8217
7304
Qb
U LT I M A T E E N D B E A R I N G R E S I S T A N C E
17671
17671
17671
17671
16420
15168
13916
12665
11369
10073
8556
7039
6715
6391
6111
5832
5567
5301
5169
5036
4874
4712
4491
4271
4079
3431
3282
3083
2945
2739
2435
B ase
5306
4958
4611
4265
3918
3573
3228
2883
2540
2197
2047
1896
1746
1596
1453
1310
1201
1092
992
892
786
681
580
480
394
308
236
164
97
37
S haf t
22977
22630
22283
21936
20338
18741
17144
15548
13909
12270
10602
8935
8461
7987
7564
7141
6767
6393
6161
5928
5660
5393
5072
4751
4473
3739
3517
3247
3043
2776
2435
T o t al ( kN )
A LLO W A B LE LO A D
B oring
B H-13(Eest side)
24
26
2
0
22
20
16
14
12
10
6
4
28
26
24
22
20
18
16
14
12
10
RD Level 66.50m
B H-13(West side)
Dept h(m)
B oring
18
28
26
24
22
20
18
16
14
12
10
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
54
56
58
60
62
64
66
68
Level(m)
Reduced
S UB S O IL P R O F ILE A LO N G T H E B R ID G E LO C A T IO N
A ppe ndix B
Page 10
Road B -15
= 2*Nave (SI-Unit s)
fs
26
27
28
29
30
-1
-2
-3
-4
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
38
38
32
31
21
21
11
11
11
75
75
75
75
75
75
75
75
75
75
75
75
32.5
32.5
32.5
32.5
26.5
26.5
23.5
23
18
18
11
11
11
C o r r ect ed
39.82
38.65
37.4
36.05
34.61
33.06
31.38
29.56
27.59
25.43
23.07
20.48
17.61
16.78
15.85
14.81
13.63
12.71
11.65
10.67
9.55
8.7
7.67
7.25
6.71
5.4
4.5
N ave
A ver ag e
79.65
77.3
74.79
72.11
69.22
66.12
62.76
59.13
55.17
50.86
46.14
40.95
35.21
33.56
31.71
29.63
27.27
25.43
23.31
21.33
19.09
17.4
15.33
14.5
13.43
12
10.8
f s=2 N
113.1
109.33
105.56
101.79
98.02
94.25
90.48
86.71
82.94
79.17
75.4
71.63
67.86
64.09
60.32
58.55
52.78
49.01
45.24
41.47
37.7
33.93
30.16
26.39
22.62
18.85
15.08
11.31
7.54
3.77
As
9008
8451
7895
7340
6785
6231
5678
5127
4576
4027
3479
2933
2389
2151
1912
1675
1439
1246
1054
885
720
590
462
383
304
226
163
102
60
23
Qs
U LT I M A T E S HA F T R E S I S T A N C E
25
Not e:
24
20
19
18
23
17
16
10
21
15
11
22
14
12
13
13
11
12
15
14
10
17
18
16
22
19
23
24
25
21
26
20
D ep t h
Level ( m)
SPT
Db
2.00
A llowable load = Ult imat e load along base/ 3.0 + Ult imat e load along shaf t / 2.0
As
= 400*Nb(SI-Unit s)
qf
Nb
Ab
R ed uced
where
P ILE LE N G T H E S T IM A T IO N A LO N G T H E IN T E R C H A N G E # 3
75
75
75
75
75
75
75
70
64
59
54
48
42
35
29
27
25
22
20
18
16
14
12
10
Nb
30000
30000
30000
30000
30000
30000
30000
27875
25750
23625
21500
19075
16650
14075
11475
10750
10025
8950
7875
7100
6225
5500
4650
4050
3450
2900
2686
2400
2160
1800
1600
q f =4 0 0 N b
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
Ab
33929
33929
33929
33929
33929
33929
33929
31528
29123
26719
24316
21573
18831
15918
12978
12158
11338
10122
8906
8030
7040
6220
5259
4580
3902
3280
3037
2714
2443
2036
1810
Qb
U LT I M A T E E N D B E A R I N G R E S I S T A N C E
11310
11310
11310
11310
11310
11310
11310
10509
9708
8906
8105
7191
6277
5306
4326
4053
3779
3374
2969
2677
2347
2073
1753
1527
1301
1093
1012
905
814
679
603
B ase
4504
4226
3947
3670
3393
3116
2839
2563
2288
2013
1740
1467
1195
1075
956
838
720
623
527
442
360
295
231
191
152
113
81
51
30
11
S haf t
15814
15535
15257
14980
14702
14425
14149
13072
11996
10920
9845
8658
7472
6381
5282
4890
4499
3997
3496
3119
2707
2369
1984
1718
1452
1206
1094
956
844
690
603
T o t al ( kN )
A LLO W A B LE LO A D
B oring
B H-13(Eest side)
24
26
2
0
22
18
16
14
12
10
20
4
28
26
24
22
20
18
16
14
12
10
RD Level 66.50m
B H-13(West side)
Dept h(m)
B oring
28
26
24
22
20
18
16
14
12
10
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
54
56
58
60
62
64
66
68
Level(m)
Reduced
S UB S O IL P R O F ILE A LO N G T H E B R ID G E LO C A T IO N
A ppe ndix B
Page 11
Road B -15
= 2*Nave (SI-Unit s)
fs
29
30
19
18
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
32.5
32.5
32.5
32.5
32.5
C o r r ect ed
68.15
67.92
67.67
67.41
67.13
66.83
66.5
66.15
65.76
65.34
64.88
64.38
6..82
63.19
62.5
61.72
60.83
59.82
58.65
57.29
55.68
53.75
51.39
48.44
44.64
39.58
32.5
32.5
32.5
32.5
32.5
N ave
A ver ag e
136.29
135.83
135.34
134.82
134.26
133.65
133
132.29
131.52
130.68
129.76
128.75
127.63
126.39
125
123.44
121.67
119.64
117.31
114.58
111.36
107.5
102.78
96.88
89.29
79.17
65
65
65
65
65
f s=2 N
113.1
109.33
105.56
101.79
98.02
94.25
90.48
86.71
82.94
79.17
75.4
71.63
67.86
64.09
60.32
56.55
52.78
49.01
45.24
41.47
37.7
33.93
30.16
26.39
22.62
18.85
15.08
11.31
7.54
3.77
As
15414
14850
14287
13723
13160
12597
12034
11471
10908
10346
9784
9222
8661
8100
7540
6980
6421
5864
5307
4752
4198
3647
3100
2558
2020
1492
980
735
490
245
Qs
U LT I M A T E S HA F T R E S I S T A N C E
28
20
Not e:
26
27
21
25
22
24
23
20
28
24
19
29
23
18
30
25
17
31
21
16
32
22
15
33
27
14
34
26
12
13
35
11
37
36
10
38
40
39
41
45
44
46
47
42
48
43
D ep t h
Level ( m)
SPT
Db
2.00
A llowable load = Ult imat e load along base/ 3.0 + Ult imat e load along shaf t / 2.0
As
= 400*Nb(SI-Unit s)
qf
Nb
Ab
R ed uced
where
P ILE LE N G T H E S T IM A T IO N A LO N G T H E IN T E R C H A N G E # 3
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
70
64
59
54
48
45
40
33
33
33
Nb
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
30000
27875
25750
23625
21500
19375
17857
15833
13000
13000
13000
q f =4 0 0 N b
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
Ab
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
33929
31526
29123
26719
24316
21913
20196
17907
14703
14703
14703
Qb
U LT I M A T E E N D B E A R I N G R E S I S T A N C E
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
11310
10509
9708
8906
8105
7304
6732
5969
4901
4901
4901
B ase
7707
7425
7143
6662
6580
6298
6017
5735
5454
5173
4892
4611
4330
4050
3770
3490
3211
2932
2653
2376
2099
1824
1550
1278
1010
746
490
368
245
123
S haf t
19017
18735
18453
18171
17890
17608
17327
17045
16764
16483
16202
15921
15640
15360
15080
14800
14520
14242
13963
13686
13409
12332
11257
10185
9115
8050
7222
6337
5146
5023
4901
T o t al ( kN )
A LLO W A B LE LO A D
B oring
B H-13(Eest side)
24
26
2
0
22
18
16
14
12
10
20
4
RD Level 66.50m
28
26
24
22
20
18
16
14
12
10
28
26
24
22
20
18
16
14
12
10
Dept h(m)
B H-13(West side)
B oring
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
54
56
58
60
62
64
66
68
Level(m)
Reduced
S UB S O IL P R O F ILE A LO N G T H E B R ID G E LO C A T IO N
A ppe ndix B
Page 12
Page 13
Page 14
Page 15
Page 16
5)
Where
Qub
Allowable Qb
Cu El
CU
=
=
10
15 kPa
210 kN/mm2
1/64 B (d14 - d24)
15 x 210 x
B (101.64 - 85.444)
64
106
10
907 kN
907
___
2
PL
P
L
=
=
300 kN
10m
EP
31416 mm2
Ep
= 35.3 kN/mm2
3 mm
Page 17
Project :
2.
Piled embankment
Sand Lenses
C
L
Bridge
Stiff to hard
Sandstone/shale
3.
Top 24m consists of soft to very soft alluvium with few localized sandy lenses (Cu =
10-20 kPa with an average of about 15 kPa except at lenses of sand). Stiff to hard
strata of about 2 - 4m thick overlying on highly to moderately weathered
sandstone/shale bedrock. WT is near the ground surface.
Analysis
Stability and settlement analysis have concluded that simple ground treatments by partial
sand replacement with high strength woven polyester geotextile reinforcement or vertical
drains are not possible to achieve FOS = 1.5 and or post construction settlement to be less
than 200mm for the first 5 years of service if height of embankment exceeds 4.2m.
Piled raft embankment is adopted in preference to EPS, elevated structure and stone column
treatment because:
a)
EPS embankment is technically not acceptable because the site is subject to flooding
& the cost is high.
4.
b)
c)
Design calculation
Analysis has shown that driven R.C piles will be the most cost effective.
The site has no vibration or noise or ground heave constraints. Pile capacity of about
600 kN is chosen to get optimum pile spacing of 2 to 3m and raft thickness of 350 450mm for pile depth of about 30m.
Use 250X250 R.C piles at spacing "x" bothways Max design capacity - 625 kN.
Page 18
625
= x2.20.h
x
For h
For h
For h
For h
For h
=
=
=
=
=
=
x
d
=
=
=
=
spacing
soil density
20kN/m3 h
embankment height
(31.25/h)1/2
6.5m, x = 2.19m, say 2.0m
6.0m, x = 2.2m, say 2.0m
5.5m, x = 2.38m, say 2.25m
5.0m, x = 2.50m, say 2.25m
4.5m, x = 2.64m, say 2.25m (allow some traffic load of 10 kPa)
Conclusion:
Use 250x250 R.C x 30m long at 2.0m spacing for h=6.5 - 6.0m & 2.25m spacing for h = 4-6m
(Pile capacity calculations enclosed).
R.C piles (MS 1314, Class 1) are designed as end bearing piles driven to set.
Page 19
Page 20
Design of Micropile
a) Design load per pile
b) Diameter of micropile
c) Main reinforcement
= 800kN
= 200mm
= 3 Nos of 50mm diam. deformed bars of yield
stress fy = 410N/mm2.
d) Factor of safety
= 2.5 (min)
= 20N/mm2.
= B/4 x 502 x 3
= 5892mm2
= 20N/mm2
= B /4 x 2002
= 31,416mm2
= 31,416 - 5892
= 25,524mm2
Area of grout, Ag
..Area of net grout
..
Page 21
Drilling
Initial drilling involves installation of 242mm diam conductor casing through loose soil
(about 1.5m) by means of rotary boring or equivalent. Upon reaching hard/stiff formation
down the hole hammer will be used to advance the borehole till a minimum penetration of
10m in very hard decomposed granite. The drilled hole will be flush clean by compressed
air before the reinforcement bars are inserted into the hole. Suitable coupling device will be
used. During drilling, a complete record of soil strata will, be taken for Engineer's inspec
tion.
3.
Grout Mix
Ordinary Postland cement with water cement ratio of 0.5 will be used Non-shrink cement
admixture will be added to improve bonding.
4.
Grouting Procedure
A high speed Koken grout mixer is used for the mixing of the cement grout. The capacity
of the grout mixer is about 25-0 litres.
For grout mixing, 100 litres of water with some non shrink admixture is poured into the
mixer follow by 4 bags of 50 kg. ordinary Portland cement then allow to mix throughly,
normally a few minutes. After mixing, the cement grout, a pressure hose is connected to the
grouting pipe which acts as tremie pipe for grouting. The other end of the pressure hose is
connected to a diesel engine high pressure pump.
Page 22
Page 23
Micropile details
Diameter of micropile
Design load of micropile
Pipe diameter
Pipe wall thickness
Steel grade (API pipe)
=
=
=
=
=
Yield strength
= 500 N/mm2
(a)
200 mm
300 kN
101.6 mm
8.08 mm
N80
= 1187
2.5
= 475 kN > 300 kN
OK
(b)
0.05 qa B D x L + 0.5qa B D2
4
Page 24
Qa
qa
Bond stress
D
2.5 x 300
= 5% of UCS of rock
= Diameter of micropile hole
= 0.05 x 7.5 x 103 x B x0.2 L +
0.5 x 7.5 x 103 x B x 0.22
4
750
L
= 235.6 L + 117.8
= 2.68 m
= 95
= 2,000
95
= 21 tons
Check for anchorage bond between underpinning pile and the existing foundatic
Since epoxy grout is used to fill the hole formed by the micropile in the existir foundation
and the strength of epoxy grout is much higher than the concrete strength, it can be consid
ered as monolithic for the whole foundation.
Page 25
Critical section
for shear check
Existing
Column
Stump
650mm
Proposed 200mm
micropile
100
mm
1900mm
4)
= 1900 mm
= 300 kN
= V
Pd
= 300 x 103
1900 x 990
= 0.16 N/mm2
OK
In grouting operation, the cement grout is pumped into the borehole through the pipe by
tremie method. All loose material, cuttings and water in the borehole are displaced by the
cement grout. Pressure applied should be just adequate to displace the cutting and water
from the borehole. Temporary casings should be withdrawn where cement grout overflow
from the casing and top up cement grout if necessary.
Page 26
Item
No.
A.
Description
Quantity Unit
Rate
B.
Page 27
Projek :
1.0
Tujuan
Laporan ini bertujuan untuk menyampaikan laporan penyiasatan tanah dan syor-syor
asas yang sesuai bagi:Projek blok tambahan pada hospital bersalin, Kuala Lumpur.
2.0
Skop Projek
Perlaksanaan projek ini melibatkan pembinaan blok tambahan 2 tingkat di Hospital
Bersalin. Blok yang dicadangkan ini dikelilingi oleh bangunan sedia ada.
3.0
Keadaan Tanah
3.1 Sebanyak 3 ujian gerekan dalam telah dijalankan. Hasil ujian menunjukkan
keadaan lapisan tanah seperti berikut :Jenis Tanah
SPT (blows/ft.)
Ukurdalam(m)
0 - 4.5
Very soft CLAY
0-4
4.5 - 9/10.5
Loose SAND
1-7
9/10.5-13.5/16.0
Stiff silt or CLAY
1-9
13.5/16.0
Limestone
RQD = 73 - 100%.
>16.0
Limestone
3.2
4.0
syor-syor Asas
4.1 Penapak konkrit tetulang adalah tidak sesuai kerana keupayaan galas yang rendah
dan jugs paras air bawah-tanah adalah tinggi.
"Driven R.C. or steel piles" adalah juga tidak sesuai kerana masalah "noise &
vibration" dikawasan Hospital sukar diterima. "Inclined bedrock" juga mungkin
mengakibat "excessive pile deviations".
Syor-syor asas yang dicadangkan adalah seperti berikut :-
Jenis Bangunan
Jenis Asas
Geseran
Kulit
negatif
Beba
Ujian
400kN
4.2
4.3
4.4
Page 28
5.0
Syor-syor Tambahan
5.1 Jika rongga (cavity) ditemui, cerucuk hendaklah dipanjangkan
melebihi rongga dan dikunci (keyed) minima 3m ke dalam batukapur
tanpa rongga. (rujuk Fig. 1).
5.2
6.0
Hal-hal lain
Satu set rekod penanaman cerucuk-cerucuk yang diuji berserta ujian beban hendaklah
dihantar ke Unit Makmal bagi tujuan dokumentasi.
Page 29
Lampiran A
Micropile Specfication
1.
General
The work involves the construction of 200mm (8") diameter micropile. The micropile shall
be fabricated using steel tube and the bond length of micropile shall be 16m or directed
by the S.O. The working load of micropile is 200 kN and factor of safety used in design is
2.0. The whole of work and materials shall be in, accordance with curreht Malaysian or
British Standard or other National Standards approved by the S.O.
2.
Reinforcement
Steel grade - HFS 16 (BS: 1775 - 1964)
External diameter 139mm (51/2)
Thickness - 9.5mm (3/8") 2
Yield strength - 250 N/mm (16 Tsi)
3.
Grout
The grout shall be thcFoughly mixed with Ordinary Portland Cement (MS522) and water
(MS28). The grout shall be Antishrink cement grout. The water cement ratio shall be 0245 0.50. The 28 days. Strength for cement grout shall be 25N/mm (3570 psi). The representa
tive cubes shall be collected on each day of grouting works for testing on the 28th days.
Details of admixture shall be submitted to the S.O. for approval before commencement of
works. The use of the admixture shall comply with instruction by the manufacturer & MS
922. The grout shall be free from segregation, slumping, & bleeding of water and fine
materials during and after placing.
4.
Installation
a)
Drilling
The drilling for installation of micropile shall guarantee the absence of Vibration
which may cause damage to the existing building. Adequate precaution must be
taken to ensure boreholes for micropile do not collapse during drilling.
If necessary, temporary casing shall be used. During drilling of borehole, the con
tractor shall maintain complete record of soil profile. The logging shall include
depth of soil and water table. This drilled hole Viand! soil bore log shall be
signed by contractor's site representative and a copy of which shall be deposited
with the S.O. The contractor shall be required to keep representative sample of
soil for each soil profil in plastic bag for inspection by.the S.O. Sample may only
be disposed after the S.O. is satisfied that the logging has been properly done.
The type-of drilling equipment shall be approved by the S.O. The drilled hole
shall be flushed ckean.with air or water.
b)
Page 30
c)
Grouting
The contractor shall also provide details on method and equipment used in grout
mixing. Further information such as grouting pressure, grouting procedure, grout
ing equipment and techniques employed in grouting under water shall also be
furnished and approved by the S.O.
'To prevent deterioration of strength of soil, soil coring, installation of reinforce
ment and cement grouting shall be carried out in one continous operation.
5.
Load Testing
Micro-pile shall be load tested to 2 times design load using the Maintain Load Test.
Minimum of one (1) load test shall be carried out. The contractor shall also specify and pro
vide details of the method of load testing. Micropile shall be constructed only after the pre
liminary pile pass the load test requirements of JKR standard specification for building
Works.
Page 31
Description
Unit
Quantity
Rate
MICROPILES
(ALL PROVISIONAL)
A.
B.
Item
C.
Item
MR
NO
Page 32
Lampiran E1
Pile Design
for
SMK (Perempuan Raja Zarina)
Kelang
1.
2.
3.
This is a typical coastal alluvium site where first 60ft to 100 ft consists of very soft clay
4.
Deep Sounding is very suitable and 4 nos of D/S results give consistent results as shown in
Lampiran E-1
5.
The site is a flat land and the first 4 ft is imported fill (about 5 years ago) Negative friction
has to be checked.
6.
7.
6.2
Timber pile also not suitable bacause its max length is about 40 ft. only.
6.3
Use 12" x 12" x 100 ft R.C. piles Design load = 30 Ton/pile (max)
= Qs + Qp
where Qu
= ultimate capacity
Qs
= skin friction
Qp
= end resistance
Page 33
7.1
Skin friction, Qs
Based on total friction (remoulded)
At 30m (100ft), total friction = 3,000 kg.
Qs
Sensitivity = Qs (undisturbed)
Qs (remoulded)
= 70
30
= 2.3, within usual range
Q's = " Qs, where " = 0.7 (Bjerrum)
= 0.7 x 70
= 49 Ton
7.2
Page 34
7.3
Negative friction
Negative friction for piles at spacing more than 3 x diameters is
fn
0.2 Po (Bjerrum)
where Po
= effective overburden
= h
= 100' (100psf - 62.4 psf)
= 3760 psf
Max. fn
= 0.2 Po
= 0.2 x 3760
= 752 psf
Average fn
= (0 + 752)/2
= 376 psf
7.4
=
=
=
=
fn x As
376 x (100 x 4)
150,400 lb
67 Ton
Allowable load, Qs
The negative skin friction, QN should only considered in combination with dead
load because QN acts mainly at the lower portion of the pile and would only affect
the settlement.
2.5 QD.L = Qu - QN
QD.L = 70% Qa
2.5 x 0.7Qa = Qu - QN
Qa
= (Qu - QN) /1.75
= (122.6 - 67)/1.75
= 31 Ton
say 30 Ton/pile
Notes :
The filling is done about 5 years ago. At least 60 - 70% consolidation com
pleted.
fn used is about the same as the undrained shear strength. Hence QN estimated is on the
light side.
To prevent tensile stress and buckling during driving, free drop hammers is preferred.
8.
Recommendation
Use 12" x 12" x 100 ft R.C. piles
Friction piles, driven to the required pene:,tration and load test to verify the capacity. (No
"set" required).# Load tests after 4 weeks of driving.
Page 35
Page 36
Memo
Daripada:
Kepada:
Bil surat:
Tarikh :
26.3.1983
2.
2.1
Syor-syor asas
Jenis - jenis asas yang disyorkan adalah seperti dicatitkan di dalam Lampiran A.
Sebelum kerja - kerja piling dimulakan sekurang - kurangnya satu ujian Proba JKR
perlu dijalankan di setiap kedudukan tiang untuk menentukan paras batu dasar (>400
blows/kaki). Sekiranya paras batu dasar didapati kurang daripada 4.5m dibawah per
mukaan bumi, adalah dicadangkan supaya menggunakan R.C.cylinder foundation
(sila lihat Lampiran A & B)
2.2
2.3
Untuk memperolehi pengawasan yang lebih baik semasa memacu cerucuk tukul jatuh
bebas(free drop hammer) dicadangkan supaya digunakan. Ini ialah supaya cerucuk tidak
menerima hentaman dan menyimpang berlebihan (overdriving and excessive deviation)
oleh kerana keadaan batu dasar yang mencerun (inclined bedrock surfaces).
2.4
Hujung cerucuk keluli hendaklah dikelulikan dengan plat yang lebih. Ini adalah perlu
untuk menahan tegasan yang berlebihan (withstand overstressing) apabila cerucuk sam
pai ke paras batu dasar.
2.5
Sekurang - kurangnya 2 nos. kumpulan cerucuk (pile group, NCT single pile) perlulah
dipilih untuk ujian beban. Satu set driving records dan keputusan ujian beban hendak
lah dihantar kepada Unit Makmal ini untuk analisa dan sebagai rekod di Unit Makmal.
2.6
Perhatian hendaklah diberi kepada pengalaman yang lepas iaitu cerucuk - cerucuk tam
bahan mungkin diperlukan untuk menggantikan cerucuk - cerucuk yang menyimpang
Page 37
berlebihan dan cerucuk - cerucuk yang masih tidak set diparas yang dalam (>10m).
Adalah dicadangan supaya tambahan sebanyak 25m disertakan didalam B.Q.
2.7
Oleh kerana keadaan tanah yang rumit (tricky) jurutera tapak bina hendaklah selalu
rujuk kepada keputusan penyelidikan tapak semasa menyelia kerja - kerja pembinaan
asas. Apabila cerucuk dijangka sampai paras batu dasar, kejatuhan pemukul (drop of
hammer) hendaklah dikurangkan. Tujuan langkah ini ialah untuk better keying & bed
ding effect on rock surface. Langkah ini juga akan mengurangkan cerucuk daripada
menyimpang berlebihan.
......................................................
(Ir. Neoh Cheng Aik),
Jurutera Kerja Kanan (R1),
bp. Penolong Pengarah (Makmal),
Ibu Pejabat JKR, K.L.
Page 38
Lampiran A
1.
2.
Page 39
Page 40
General
The project consists of extension of International and Domestic Transper Corridor for
Subang International Airport. The proposed-site is situated approximately 13 miles west of
Kuala Lumpur.
Due to the close proximity of the proposed site to the existing terminal building v where the
Control Tower for the airport is located, severe vibration such as driving piles is unaccept
abldo Bored and Cast-in-situ piles were considered most suitable.
2.
Soil Condition
The site consists of residual soils of granite.
Lampiran E5-1 represents the generalised poil profile. The top layer of the soil consists of
brown firm sandy silty clay with some organic matters. The depth of this top soil varies
from 6" to 2ft. Beneath this top soil underlies the yellowish with patches of grey medium
sandy clayey silt with some gravelse This medium sandy clayey silt extend to a depth of 40
to 85 ft. below R.L. 86.00'. Between these layers of medium sandy clayey silt and the frac
tured or slightly weathered granite bedrocksq lies the greyish very stiff decomposed granite
residual soil. The thickness of this decomposed granite residual soil varies. Water table is
about Oft. b.g.l.
3.
The factor of safety for the purpose of computing the working load shall be taken
as 2.5.
b) Working Load
The working load adopted for single pile shall not be greater than the ultimate
load divided by the safety factor of 2.5 and the ultimate load is defined as:
(i)
Load at which the gross settlement continues to increase without any further
increase in load.
(ii)
c) Settlement Criteria
(i)
Gross settlement of the pile at working load during the first cycle of load
ing, loading to one time working load, shall not exceed 0.5".
(ii)
The residual settlement of the pile at the end of the first cycle of loading
shall not exceed 0.10".
(iii)
The gross settlement of the pile at twice the working load shall not exceed
1.5"
Page 41
d) Group Effect
Negligible because of small group (2 or 3 pile per group) & large spacing 2.5 .
4.
5.
Where Acc
Uw
=
=
=
For d
d
d
=
=
=
80 Ton.
150 Ton
230 Ton.
fs As.+ Op Ap
N As + N. Ap
50
where N =
average SPT near pile base (4 above pile base & 2 below pile base).
As
As
Page 42
Based on DB12
18" x 75'
= 0.32 TSF
16
fs = N
50
50
qp = 50 TSB
Qs
=
=
fs As
0.32 x (1.5' x 3.1416 x 75) = 113 Ton
Qp
Qa
=
Qs/20 + Qp/3.0
=
56.5 + 29.3
=
85.8 Ton
say 80 Ton
Based on DB 10
18" x 55ft
N
20
fs
= 0.4 TSF
=
=
80
qp
= 80 TSF
0-4 x (1o5 x 301416 x 55)
Qp
Qa
Qs/2.0 + Op/3.0 = 52 + 47
=104 Ton
= 99 Ton
say 80 Ton.
Based on DB 13
18 x 80ft.
N
23
fs
= 0.46 TSF
35
qp
= 35 TSF
Qs
Qp
Qa
Qs / 2.0 + Qp / 3.0
=173 Ton
=173/2 + 62/3.0
= 86 + 31
= 117 Ton
> 80 Ton.
Page 43
6.
Founding Level
Founding level should be determined by observing the soil type from the boring. Suitable
founding soil should be weathered granite bedrock or oompacted/cemented clayey silt with
gravels, or up to a max depth of eft'. In case of dou7gt, SPT should be carried in the bored
base.
7.
Recommendation
Use 18 bored pile Vrith max capacity 80 Ton per pile. Site engineer should use the DB
results to determine the founding level. Para 6 above can be used as a guide. 4 Nos load
tests should be carried out to verify the capacity.
Page 44
DB 13
DB 12
DB 11
DB 8
DB 7
DB 6
DB 5
DB 4
DB 3
DB 2
DB 1
Page 45
Lampiran E 6
1.
Objective
To design the foundation system for the proposed Dewan Orang Ramai in Kampung
Cheras Baru
2.
Introduction
2.1 The proposed.structure is a one-storey assembly-hall'situated on Lot 405 in
Kampung Ceras Baru, M11rim Ampang, Daerah Hulu Langat
2.2
Column loads
Maximum
Minimum
3.
- 68T
- 30T
Site Condition
3.1
Surface Condition
The terrain is generally flat. It was formerly an old building site that has been
cleared. Springs of water are visible which suggest the ground water table is
very near the ground surface. The only visible form of undergrowth are bushes
and shrubs.
3.2
Subsurface Condition
3.2.1
3.2.2
3.2.3
Page 46
4.
With reference-to the results obtained from the S.I. done the first 5 metres com
prises of compressible material which is of insufficient strength to sustain the
intended imposed loads. Hence an ordinary shallow foundation in the form of a
pad footing would not suffice. A piled foundation system is warranted here in
order to transfer the loads to the stronger material found below 15m of the
ground-level. In selecting the particular type of pile'to be used, particular consid
eration has been made to
(a)
Cost.
(b)
Driving lengths
(c)
(d)
(e)
(see T able 1)
Max. length
Resistance
Structural
Merit as
Merit as
Cost
of
of
to Hard
Capacity
frictional
end
(per m run)
pile
Driving possible
Driving
pile
bearing
(18m)
R.C.
Steel
pile
T imber X
From Table 1, the most apparent' choice would be to use steel piles. However,
based on the soil variation (profile) and the intended loading system which is rel
atively small, the .use of steel' piles is overly conservative. Furthermore hard
driving is not expected.RC piles would be more appropriate in this case because;
(a)
it is more economical
(b)
(c)
Due to its rougher surface texture RC piles can mobilise frictional resist
ance better than steel piles
Page 47
Hence RC Piles would serve better and cheaper than-steel piles as both a friction
al and end-bearing pile in this particular sub-soil condition.
4.2
(c)
Due to the inconsistency in the soil variation for the three boreholes, the
piles were designed based on each individual borehole result and the worst
(or lowest)' calculated working load per pile was adopted for use.
(d)
The criteria for design was only to consider both frictional and end-bear
ing piles. Totally frictional or totally end-bearing-piles were not consid
ered.
(e)
Assumed that piles would achieve safe and bearing resistance in soil lay
ers with SPT values of N-~ 15 i.e. in medium dense coesionless soils or
stiff cohesive layers.
(f)
Factor of safety adopted is 2.5 (para 4.6 pg. 149 of. ref. 1)
(g)
(h)
Type of Silts
V.loose to loose
0 - 10
27 - 29
Medium Dense
10 - 30
29 - 34
Dense to V.Dense
30
34 - 39
Page 48
where
Qs a Ultimate akin resistance
As = .Area, of shaft
.
Avg. unit skin friction is obtained from Fig. 4.19
Pg. 139 of Ref. 1)
*The foriaula (Ref. 1 Pg. 136 Eln. 4.13)
where
Qs = Ultimate End,-Bearing Resistance.
Pd = Effective Overburden Pressure
Nq = Bearing Capacity Factor
(obtained from Berezantsevs' Curves in Ref. 1 Pg 134
Fig. 4.14 (b) )
Ab = Area of pile base
It should be noted that value of Qb at penetration depths of 20
diameters is taken as the peak value for ultimate end bearing
resistance but shall not exceed 100 tons/ft2.
4.2.2.2
In Cohesive Soil
For frictional resistance
Qs = Cu As
where
Qs = Ultimate skin resistance
Page 49
where
No = Bearing Capacity factor (taken = 9)
Cb = Undisturbed undrained cohesion of soil at pile
toe
Ab = Area of pile base
4.2.3 Recommendation
Scope of work done on S.I. were 6 Nos. JO -Probes and 3 Nos. Deep
Boring. On compilation of the results, the soil profile was generalized as
Table 2 : Generalized Soil Profile
Soil Type and Condition
Depth (m)
0-9
9 - 13
> 13
Penetration
Depth (m)
BH 1
BH 2
BH 3
15" x 15"
21.5
101
12" x 12"
20
69
37
42
21.5
70
40
52
16.5
32
28
31
19.5
42
26
31
10" x 10"
Page 50
4.3
40T - 70T
Settlement Analysis
In the case of (a), settlement checks were not done as the piles are not totally fric
tional and generally the recommended foundation system would result in only 2
Nos* of piles to a . group. Furthermore, work done by X.Je Tomlinson have
shown that for piles of small to medium (up to 600mm) diameter the settlement
under the working load will not exceed 10mm or 3/8" if the safety factor is not
lower than 2.500..-00.00. (Ref- 1 Pg. 149)
4.3.2
Settlement. of tho sub-soil due to the surcharge weight of the fill material
4.3.2.1 Essumptions made
(a)
Soil layers with an SPT value of N48 were taken as compressible lay
ers
(b)
(c)
Effective area of fill was approximated to be the same as the plan area
of the proposed Dewan Orang Ramai
i.e. B - 17m and L . 321x.
(d)
Depth of fill was not constant throughout the site. This is because the
original ground level is not the same over the intended site.
0.3m
Plane DB 2
qf2
DB 2
Plane DB 3
0.6m
qf3
Formation Level
DB 3
1m
O.G.L
qf1
DB 1
Fill Material
12m
Compressible Layer
Page 51
(f)
(g)
(h)
(i)
(j)
(k)
4.3.2.2
Estimation of settlement
To obtain the average immediate _settlement the method of Janbu, Jerrum and
Kjaernsli was adopted where
Average settlement = p1 = U1 U1 of B ....(5)
E
U1 Uo are obtained from Refs 1 Pg. 180 Fig. 5.10
qf = net surcharge of the fill
B = width of fill area
E = Modulus of Elasticity of clay
Values of E were obtained from Ref. 1 Pg. 186 BU- 5 .17
For Consolidation Settlement, Terzaghils conventional 1-D consolidation theory
was used.
So = Co
1 t e,
H. Log Po +z ......(6)
Po
Page 52
where,
Co = Compression Index
Eo = Initial voids ratio
H = Thickness of compressible layer (m)
Po = Effective overburden pressure (kN/m2)
z =
z = qfI o
From the settlement analysis. done on the effect of the surcharge weight of the fill material, the following were obtained
settlement under plane DB1 - 92mm (3.6")
settlement under plane DB2 - 30am (1.2")
settlement under plane DB3 - 232 am (9")
(centre of fill)
Obviously, there is substantial total and differential settlement of the soft layer
due to the effect of the fill surcharge.
In the light. of this estimation, it is advisable to design a suspended floor for the
proposed structure and to use tie-beams (ground beams) for the foundation sys
tem (tied in two cUreotions) in order to have a more rigid structure.
4.4
4.4.1
4.4.2
The test loadings should be done at least 4 weeks after the test piles are
driven, to fully mobilise frictional resistance between soil and pile
interface.
Page 53
4.5
Associated Designs
4.5.1
4.5.2
Structural Recommendations
In order to deal with the expected settlement of the soft sub-soil due to
the surcharge of the fill material, it is advisable to design a suspended
floor system for the structure.
Further precautions should be taken in the form of tying the columns
in two-directions with ground beams so as to' haves. more rigid struc
ture.
5.
Conclusion
From the-analysis done based on assumptions laid down in Clause ~4.2.1, the recommen
dations are
i) For the load range of
30T - 40T Use 10'1 x 10" RC piles with a working load of 20T/pile
40T - 702'
ii) The piles shall function as partly frictional and partly end-bearing.
iii) Piles are to be driven to set below the formation level
iv) Specify tender lengths to be 20m and an additional 10% should be added to the number
of piles specified in the BQ or summary of tender to cater for pile deviations during
driving.
v) Use suspended floor and tie beams are to be provided in two directions between the col
umn positions.
6.
Appendices
Appendix A : Location Plan
Appendix B :
Page 54
Appendix C :
7.
Bibliography
Ref. 1
:
Ref. 2
Ref. 3
Ref. 4
Page 55
33.05
28.5
22.5
13.5
9.0
6.0
4.0
5.0
-30.6
25.50
19.50
15.00
13.50
12.00
9.00
7.50
5.00
6.00
2.45
3.15
29.45
Proposed Pile
Granite
-34.25
-21.6
28.70
27.00
18.00
18.00
4.50
2.00
3.00
Granite
Page 56
Introduction
The project site is located off the Pekan - Kuantan trunk road. From the site plan an earth
filling of 1' to 5' is proposed for the whole site. The project consists of construction of
6 Blocks of JKR Standard 5-storey Class G Quarters.
2.
Site Conditions
6 nos of boreholes were carried out to determine the subsoil conditions. The sub soil con
sists of soft silty clay with organic matters from ground level to 6m below ground level.
From 6m to 12m below ground level the soil consists of loose silty sand with decayed mat
ters and from 12m to 28m the soil is of loose to medium stiff sandy clay with SPT N aver
ages from 6 to 12. From 28m_to,36m the soil strata consists of dense sandy'silt with traces
of gravel. SPT N ranges from 18 to 50.
3.
Geotechnical Evaluation
Due to the 1' to 5' of fill, consolidation settlement may occur for the compressible layers of
soil. Hence negative skin friction on piles is to be accounted for.
12" x 12" r.c. piles are evaluated for the bearing capacities. It is found that the founding
depths of the piles varies from 28.5m to 36m.
The following table is abstracted from the calculations for which the estimated founding
depths Ultimate loads (Qu) and allowable loads (Qa) are tabulated. A factor of safety of 2.5
and negative skin friction of 16 tons are used in the calculations.
BH nos.
Estimated depths
Ultimate load
Allowable load
(m)
Qu (tons)
Qa = Qu/2.5 - Qn
1
33
197.54
65.59
2
31.5
178.65
55.03
3
28.5
166.84
50.31
4
28.5
183.87
57.12
5
36
208.56
67.00
6
35
204.62
65.42
From the above it is noted that the calculated bearing capacities of the 12" x 12" r.c. piles
ranges from 50.00 to 67 tons. Hence it is proposed that 12" x 12" JKR r.c: piles of Grade 40
concrete be used.
The allowable working load of the 12" x 12" JKR r.c. piles shall be 49 tons per pile.
Calculations for the geotechnical evaluations for the 6 boreholes are attached.
4.
Conclusion
12" x 12" JKR Standard R.C. piles grade 40 with tender length of 36m shall be used.
Allowable load per pile is 49 tons.The estimated negative friction load is 16 Ton per pile.
Hence the test load shall 2 x (49 + 16) = 130 Tons. At least 4 piles shall be selected for load
tests.
All piles are designed as end bearing piles. All piles shall be driven to set which can be
achieved at about 28.5m to 36m below ground level.
Page 57
Soil Description
1.5
Ditto
4.5
6
S.P.T
(Na)
Fs
Ap
(ft)
Qs
(Tons)
Qs
(tons)
Fb
Ab
(sq ft)
Qb (tons)
Qu
(tons)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
7.5
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
10.5
0.00
0.00
0.00
0.00
0.00
0.00
12
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
13.5
Ditto
2.5
0.05
0.98
0.98
20
20.00
20.98
8.39
15
5.5
0.11
2.16
3.15
24
24.00
27.15
10.86
16.5
Ditto
0.14
2.76
5.90
32
32.00
37.90
15.16
Qa
(tons)
18
Ditto
7.5
0.15
2.95
8.86
28
28.00
36.86
14.74
19.5
Ditto
0.14
2.76
11.61
28
28.00
39.61
15.84
21
Ditto
6.5
0.13
2.56
14.17
24
24.00
38.17
15.27
22.5
Ditto
7.5
0.15
2.95
17.12
36
36.00
53.12
21.25
24
Ditto
18
13.5
0.27
5.31
22.44
72
72.00
94.44
37.77
25.5
Ditto
16
17
0.34
6.69
29.13
64
64.00
93.13
37.25
27
Ditto
30
23
0.46
9.05
38.18
120
120.00
158.18
63.27
28.5
25
27.5
0.55
10.82
49.00
100
100.00
149.00
59.60
30
Ditto
24
24.5
0.49
9.64
58.65
96
96.00
154.65
61.86
31.5
Ditto
21
22.5
0.45
8.86
67.50
84
84.00
151.50
60.60
33***
*
Ditto
30
25.5
0.51
10.04
77.54
120
120.00
197.54
79.02
34.5
Ditto
50
40
0.80
15.74
93.28
200
200.00
293.28
117.31
36
Ditto
50
50
1.00
19.68
112.96
200
200.00
312.96
125.19
1869.6
79.02
16.43
62.59
Page 58
Ap
(ft)
Qs
(Tons)
Qs
(tons)
Fb
Ab
(sq ft)
Qb
(tons)
Qu
(tons)
Qa
(tons)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Depth
(m)
Soil Description
1.5
S.P.T
(Na)
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
4.5
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
7.5
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
10.5
0.00
0.00
0.00
0.00
0.00
0.00
12
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
13.5
Ditto
0.04
0.79
0.79
16
16.00
16.79
6.71
15
11
7.5
0.15
2.95
3.74
44
44.00
47.74
19.10
16.5
Ditto
12
11.5
0.23
4.53
8.27
48
48.00
56.27
22.51
18
Ditto
9.5
0.19
3.74
12.00
28
28.00
40.00
16.00
19.5
Ditto
0.12
2.36
14.37
20
20.00
34.37
13.75
21
Ditto
4.5
0.09
1.77
16.14
16
16.00
32.14
12.86
22.5
Ditto
0.10
1.97
18.11
24
24.00
42.11
16.84
24
Ditto
0.12
2.36
20.47
24
24.00
44.47
17.79
25.5
Ditto
5.5
0.11
2.16
22.63
20
20.00
42.63
17.05
27
Ditto
24
14.5
0.29
5.71
28.34
96
96.00
124.34
49.74
28.5
26
25
0.50
9.84
38.18
104
104.00
142.18
56.87
30
Ditto
24
25
0.50
9.84
48.02
96
96.00
144.02
57.61
31.5
Ditto
30
27
0.54
10.63
58.65
120
120.00
178.65
71.46
33****
Ditto
50
40
0.80
15.74
74.39
200
200.00
274.39
109.76
34.5
Ditto
50
50
1.00
19.68
94.07
200
200.00
294.07
117.63
36
Ditto
50
50
1.00
19.68
113.75
200
200.00
313.75
125.50
71.46
16.43
55.03
Page 59
Depth
(m)
Soil Description
0
1.5
Fs
Ap
(ft
)
Qs
(Tons)
Qs
(tons)
Fb
Ab
(sq ft)
Qb
(tons)
Qu
(tons)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(Na)
Qa
(tons)
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
4.5
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
7.5
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
10.5
0.00
0.00
0.00
0.00
0.00
0.00
12
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
13.5
Ditto
0.08
1.57
1.57
32
32.00
33.57
13.43
15
8.5
0.17
3.35
4.92
36
36.00
40.92
16.37
16.5
Ditto
12
10.5
0.21
4.13
9.05
48
48.00
57.05
22.82
18
Ditto
10.5
0.21
4.13
13.19
36
36.00
49.19
19.67
19.5
Ditto
11
10
0.20
3.94
17.12
44
44.00
61.12
24.45
21
Ditto
9.5
0.19
3.74
20.86
32
32.00
52.86
21.14
22.5
Ditto
0.14
2.76
23.62
24
24.00
47.62
19.05
24
Ditto
5.5
0.11
2.16
25.78
20
20.00
45.78
18.31
25.5
Ditto
5.5
0.11
2.16
27.95
24
24.00
51.95
20.78
27
Ditto
30
18
0.36
7.08
35.03
120
120.00
155.03
62.01
28.5
30
30
0.60
11.81
46.84
120
120.00
166.84
66.74
30
Ditto
50
40
0.80
15.74
62.58
200
200.00
262.58
105.03
31.5
Ditto
50
50
1.00
19.68
82.26
200
200.00
282.26
112.90
33
Ditto
50
50
1.00
19.68
101.94
200
200.00
301.94
120.78
34.5
Ditto
50
50
1.00
19.68
121.62
200
200.00
321.62
128.65
36
Ditto
50
50
1.00
19.68
141.30
200
200.00
341.3 0
136.52
66.74
16.43
50.31
Page 60
Soil Description
1.5
S.P.T
(Na)
Fs
Ap
(ft)
Qs
(Tons)
Qs
(tons)
Fb
Ab
(sq ft)
Qb
(tons)
Qu
(tons)
Qa
(tons)
4.5
0.08
1.51
1.51
36
36.00
37.51
15.00
Ditto
15
12
0.20
4.01
5.52
60
60.00
65.52
26.21
4.5
Loose clayey
sand
11
0.19
3.68
9.20
28
28.00
37.20
14.88
Ditto
0.09
1.67
10.87
12
12.00
22.87
9.15
7.5
Ditto
3.5
0.06
1.17
12.04
16
16.00
28.04
11.22
Ditto
0.00
0.67
12.71
0.00
12.71
5.09
10.5
0.03
0.00
12.71
0.00
12.71
5.09
12
Ditto
2.5
0.00
0.84
13.55
20
20.00
33.55
13.42
13.5
Ditto
5.5
0.04
1.84
15.39
24
24.00
39.39
15.76
15
0.09
2.01
17.40
24
24.00
41.40
16.56
16.5
Ditto
0.10
2.34
19.74
32
32.00
51.74
20.70
18
Ditto
0.12
2.34
22.08
24
24.00
46.08
18.43
19.5
Ditto
10
0.12
2.68
24.76
40
40.00
64.76
25.90
21
Ditto
11
10.5
0.14
3.51
28.27
44
44.00
72.27
28.91
22.5
Ditto
10
10.5
0.18
3.51
31.78
40
40.00
71.78
28.71
24
Ditto
0.18
3.01
34.79
32
32.00
66.79
26.72
25.5
Ditto
0.15
2.68
37.47
32
32.00
69.47
27.79
27
Ditto
35
21.5
0.14
7.19
44.66
140
140.00
184.66
73.87
28.5
32
33.5
0.37
11.21
55.87
128
128.00
183.87
73.55
30
Ditto
50
41
0.57
13.72
69.59
200
200.00
269.59
107.84
31.5
Ditto
50
50
0.70
16.73
86.32
200
200.00
286.32
114.53
33
Ditto
50
50
0.85
16.73
103.04
200
200.00
303.04
121.22
34.5
Ditto
50
50
0.85
16.73
119.77
200
200.00
319.77
127.91
36
Ditto
50
50
0.85
16.73
136.50
200
200.00
336.50
134.60
73.55
16.43
57.12
Page 61
Soil Description
1.5
S.P.T
(Na)
Fs
Ap
(ft)
Qs
(Tons)
Qs
(tons)
Fb
Ab
(sq ft)
Qb
(tons)
Qu
(tons)
Qa
(tons)
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
4.5
Loose clayey
sand
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
7.5
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
10.5
0.00
0.00
0.00
0.00
0.00
0.00
12
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
13.5
Ditto
0.08
1.57
1.57
32
32.00
33.57
13.43
15
7.5
0.15
2.95
4.53
28
28.00
32.53
13.01
16.5
Ditto
6.5
0.13
2.56
7.08
24
24.00
31.08
12.43
18
Ditto
0.12
2.36
9.45
24
24.00
33.45
13.38
19.5
Ditto
6.5
0.13
2.56
12.00
28
28.00
40.00
16.00
21
Ditto
6.5
0.13
2.56
14.56
24
24.00
38.56
15.43
22.5
Ditto
0.12
2.36
16.92
24
24.00
40.92
16.37
24
Ditto
10
0.16
3.15
20.07
40
40.00
60.07
24.03
25.5
Ditto
13
11.5
0.23
4.53
24.60
52
52.00
76.60
30.64
27
Ditto
28
20.5
0.41
8.07
32.67
112
112.00
144.67
57.87
28.5
32
30
0.60
11.81
44.48
128
128.00
172.48
68.99
30
Ditto
18
25
0.50
9.84
54.32
72
72.00
126.32
50.53
31.5
Ditto
22
20
0.40
7.87
62.19
88
88.00
150.19
60.08
33
Ditto
20
21
0.42
8.27
70.45
80
80.00
150.45
60.18
34.5
Ditto
21
20.5
0.41
8.07
78.52
84
84.00
162.52
65.01
36
Ditto
30
25.5
0.51
10.04
88.56
120
120.00
208.56
83.42
83.42
16.43
67 .00
Page 62
Soil Description
1.5
S.P.T
(Na)
Fs
Ap
(ft)
Qs
(Tons)
Qs
(tons)
Fb
Ab
(sq ft)
Qb
(tons)
Qu
(tons)
Qa
(tons)
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
4.5
Loose clayey
sand
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
7.5
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
10.5
0.00
0.00
0.00
0.00
0.00
0.00
12
Ditto
0.00
0.00
0.00
0.00
0.00
0.00
13.5
Ditto
10
0.10
1.97
1.97
40
40.00
41.97
16.79
15
8.5
0.17
3.35
5.31
28
28.00
33.31
13.33
16.5
Ditto
6.5
0.13
2.56
7.87
24
24.00
31.87
12.75
18
Ditto
6.5
0.13
2.56
10.43
28
28.00
38.43
15.37
19.5
Ditto
0.12
2.36
12.79
20
20.00
32.79
13.12
21
Ditto
4.5
0.09
1.77
14.56
16
16.00
30.56
12.23
22.5
Ditto
4.5
0.09
1.77
16.33
20
20.00
36.33
14.53
24
Ditto
11
0.16
3.15
19.48
44
44.00
63.48
25.39
25.5
Ditto
15
13
0.26
5.12
24.60
60
60.00
84.60
33.84
27
Ditto
27
21
0.42
8.27
32.87
108
108.00
140.87
56.35
28.5
26
26.5
0.53
10.43
43.30
104
104.00
147.30
58.92
30
Ditto
16
21
0.42
8.27
51.56
64
64.00
115.56
46.22
31.5
Ditto
20
18
0.36
7.08
58.65
80
80.00
138.65
55.46
33
Ditto
18
19
0.38
7.48
66.12
72
72.00
138.12
55.25
34.5
Ditto
23
20.5
0.41
8.07
74.19
92
92.00
166.19
66.48
36
Ditto
30
26.5
0.53
10.43
84.62
120
120.00
204.62
81.85
81.85
16.43
65.42
Page 63
Introduction
The project consists of construction of 2 blocks. of 4-storey JKR Std. School buildings. The
site is generally flat with about 2m fill some 5 years ago. The generalized subsoil proper
ties are as follows:0 - 12m
:
loose clayey sand with localized very dense layer. Average SPT, N = 5.
12m - 17m :
17m - 27m :
very dense grey spotted yellowish fine to coarse silty sand with gravel
(N = 40 - 50). Water table 15m bgl.
Design Calculations
460mm diameter bored piles are proposed.
2.1
Design Criteria
2.2
Geotechnical Capacity
N1
K1
K2
N2
As
Ab
=
=
=
=
Pilecap Design
Single Pilecap for Pile Diameter 460mm (18" Diam x 24m Bored Pile)
No. of Pile
Pile Diameter
=
1
= 460mm
Size of Pilecap
Steel Reinforcement
Main Bars
= 0.15% x b x d = 792mm2
.. Provide 4 Y 16 Bothways
Horizontal Links
.: Provide 3 Y 10
Excavation
Volume of Concrete
= 0.41 m3
= 0.39 m3
= 134 lb/yd3
Page 65
Page 66
LAPORAN GEOTEKNIK
MAKTAB PER GUR UAN SRI PIN ANG ,
BUKIT MIER TAJAM,
SEBERANG PERA1,
PULAU PIN ANG
DISEDIAKAH OLEH :
IR. ANNIES MD. ARIFF
EH. AHMAD AZLAN AHMAD
(INSTITUT LATIHAN & PENYELIDIKAN JKR)
Cawangan Jalan, Ibu Pejabat JKR, K.L
Page 67
Pendahuluan
Laporan ini adalah 'bertujuan untuk menyampaikan keterangan ringkas sumbangan yang
telah diberi oleh Pusat ini di dalam menentukan
pemilihan asas-asas yang sesuai bagi bangunan-bangunan yang dicadangkan untuk projek
yang disebut di atas. Sumbangan ini. adalah
bersesuaian dengan peranan utama pusat ini
sebagai satu organisasi.sokongan kepada semua
cawangan di dalam JKR dalam hal- hal yang
bersangkut-paut dengan bidang geoteknikal.
Laporan ini akan' ketengahkan juga masalahmasalah parancangan yang dihadapi semasa
pusat ini menjalankan kerja penyiasatan -tapak
dan kerja merekabentuk asas yang sesuai bagi
bangunan bangunan yang terlibat
Bagi 'projek ini permintaan untuk menjalankan
penyiasatan tapak dan seterusnya'pen gesyoran
syor-syor asas telah dikemukakan oleh
Cawangan Kerja Pendidikan melalui surat
PKR(KP)MP/PP/87/17(102) bertarikh
27/02/1989.
Skop Projek
Pelaksanaan projek ini melibatkan pembinaan
32 bush bangunan dengan ketinggian bangunan-bangunan di antara 1-tingkat hingga 4tingkat. Lingkungan beban-beban tiang pula
adalah dari serendah-rendah 50.0 kN sehingga
setinggi 1800.0 kN. Penyediaan tapak melibatkan kerja-kerja pemotongan se dalam di
antara 0.0 hingga 6.Om dan penimbusan setinggi di antara 0.0 hingga 6.0m.
Butiran bangunan mengikut bilangan tingkat
adalah seperti berikut:1-tingkat
- 16 unit
2-tingkat
- 7 unit
4-tingkat
- 8 unit
Tangki Air - 1 unit
Skop Penyiasatan Tapak/Tanah
Berpandukan lukisan punca tatatur yang dikemukakan, satu skop kerja penyiasatan tapak,
berupa 33 bil. ujian gerekan dalam, 3 bil. ujian
gerimit tangan dan 89 bil. ujian proba
Mckintosh, telah dirancangkan. Perancangan
e) Jenis struktur
f) tapak timbusan atau potongan
g) ekonomik
Oleh yang demikian sebelum menentukan
sebarang sistem asas yang hendak digunakan,
faktor-faktor di atas perlu diteliti terlebih dahulu bagi setiap bangunan supaya satu sistem asas
yang sesuai dan ekonomik dapat ditentukan.
Perlu dinyatakan disini bahawa di dalam hal
membuat perkiraan rekabentuk geoteknik
adalah mustahak ciri-ciri jenis tanah serta butiran kekuatan tanah-tanah yang dipilih di dalam
perkiraan rekabentuk diperolehi daripada kepuCawangan Jalan, Ibu Pejabat JKR, K.L
Lampiran 'D'-
LAPURAN PENYIASA
TAN TAPAK YANG
TELAH DIJALANKAN
Page 70
Lampiran 'A'
F.F.L. = 16.0m;
Central Block
F.F.L. = 17.5m;
Southern Block :
F.F.L. = 19.0m;
Column Load
Deep Boring
Q =
b) SILT
c) SAND
Q. = N/50*A.
2. 5iN*Ab
c) SAND Qb,
4N*Ab
Design Analysis
Adopt DB/4 since worst case and assume.height of fill = 2.0m Try R.C. Pile of size B" x B"
Shaft Resistance
For depth 0 - 2.0m b. F. F. L. : FILL
For depth 2 - 5.0m ; CLAY ; assume N = 13
take Cu = 82.0 kN/m2 (Terzaghi)
adopt
= 1.0 (Tomlinson)
= 0.4 (McClalland)
= 0.7
Q = 0.7*82.0*4*B*3.0
39.37*9.81
= 1.783B tonnes
Page 71
Q. = 7*4*B*4.0*3.281
50* 12
= 0.612B tonnes
= 0.219B tonnes
Q = 0.65*82.0*4*B*7.0
39.37*9.81
Q
= 6.478B tonnes
Base Resistance
At depth 21.Om b.F.F.L. take N = 13 and since proportion of SAND is quite high (> 30%) adopt
Qb = 2.0*N*Ab (i.e. between CLAY & SILT).
Qb = 2.0*13*B*B = 0.130B2
144
Ultimate Resistance Qa
If B = 12 inches;
= Qp + Qb
= G.478B-+ 0.180B2
Page 72
Page 73
Lampiran `B'
Page 74
Lampiran C
( )dlm. PKR.RPM.
85/ 173/GO5/03
30hb. Jun. 1989
Pengarah,
Cawangan Kerja Pendidikan,
Ibu Pejabat JKR,
Jalan Sultan Salahuddin,
50582 KUALA LUMPUR.(u.p: Ir. Lam Yok Lon)
Tuan,
Perkara : CadanganMaktab Perguruan Sri Pinang, Bukit Mertajam, Pulau Pinang.
Merujuk perkara di atas dengan segala hormatnya disampaikan keputusan penyiasatan tapak dan
syor-syor asas untuk tindakan tuan selanjutnya.
2.0
Selaras dengan penguatkuasaan surat pekeliling KPKR 2/88, sistem cerucuk alternatif oleh
pentender boleh diterima.
3.0
Dimaklumkan juga bahawa seperti perbincangan yang telah diadakan dengan pegawai tuan
Ir. Lam Yok Lon pada 15/06/1989, pusat ini bersetuju bahawa kos anggaran asas bagi pro
jek ini ditambah lebih kurang 15% atas sebab desakan untuk melaksanakan projek ini
secepat mungkin. Pertambahan ini adalah untuk menyesuaikan perkara yang mungkin be
rlaku semasa pembinaan atas langkah-langkah yang dibuat semasa perancangan untuk
menyingkatkan tempoh masa perancangan dan rekabentuk seperti berikut:a)
Penyiasatan tapak telah dilakukan secara 'appointed - contractor' dan dengan ini kos
kontrak tidak boleh melebihi $50,000.00. Ini telah menghadkan skop penyiasatan
tapak yang perlu dijalankan.
b)
Lokasi-lokasi bangunan telah diubah daripada lokasi cadangan asal yang mengaki
batkan ada beberapa bangunan tidak terdapat ujian gerekan dalam dijalankan.
c)
Ketidak seragaman keadaan tanah bawahan ditapak projek ini yang mana masalah
(a) telah menyulitkan lagi keadaan ini. 4.0 Perlu dimaklumkan bahawa pusat ini
mendapati bahawa tidak terdapat apa-apa sistem perparitan yang telah disediakan
bagi projek ini. pleh yang demikian pihak tuan perlulah mengkaji akan hal ini dan
membuat pengesyoran yang sewajarnya.
Sekian, harap maklum
'BERKHIDMAT UNTUK HEGARA'
'CINTAILAH BAHASA KITA'
Saya yang menurut perintah,
Page 75
Institut Latihan & Penyelidikan JKR, Jalan Serdang,43000 KAJANG, Selangor DarulEhsan.
Projek :
1.0
Tujuan
Laporan ini adalah bertujuan untuk menyampaikan keputusan penyiasatan tapak dan syorsyor asas yang sesuai bagi projek di atas.
2.0
Skop Projek
Perlaksanaan projek ini akan melibatkan pembinaan blok-blok bangunan seperti yang tert
era di dalam lukisan pelan tatatur BKP 187/89/1 (PRE) A dan penyediaan tapak akan
melibatkan kerja-kerja pemotongan sedalam di antara 0.0 hingga b.Om dan penimbusan di
antara 0.0 hingga 5.0m.
3.0
4.0
Syor-syor Asas
Keupayaan galas
yg. Dibenarkan
(kN/cerucuk)
Beban Ujian
(kN/cerucuk)
305 x 305
@ 21.0
450.0
900.0
Keupayaan
tanggung yg.
Dibenarkan
(kN/m 2)
-
"
305 x 305
@ 18.0
"
"
Penapak
Konkrit
Tetulang
95.0(2000 psf)
@ 1.5m b.F.L.
(JKR probes >
40 blows/foot).
(A)
"
"
(B)
"
"
Jenis
Bangunan
Jenis
Asas
Saiz &
Panjang
Cerucuk
Konkrit
Tetulang
Page 76
(A)
Cerucuk
Kayu
Berubat
152 x 152
@ 9.0
100.0
200.0
(B)
Penapak
Konkrit
Tetulang
"
Cerucuk
Konkrit
Tetulang
305 x 305
@ 18.0
500.0
1000.0
"
"
"
"
Penapak
Konkrit
Tetulang
Cerucuk
Konkrit
Tetulang
305 x 305
@ 15.0
430.0
860.0
Penapak
Konkrit
Tetulang
Cerucuk
Konkrit
Tetulang
254 x 254
@ 6.0
160.0
320.0
"
305 x 305
@ 15.0
500.0
1000.0
Penapak
Konkrit
Tetulang
"
"
"
"
Page 77
U1
U2
(A)
Cerucuk
Konkrit
Tetulang
381 x 381
@ 18.0
650.0
1300.0
(C)
"
381 x 381
@ 18.0
650.0
1300.0
atau
"
305 x 305
@ 18.0
450.0
900.0
(B)
Penapak
Konkrit
Tetulang
(A)
"
(B)
Cerucuk
Konkrit
Tetulang
381 x 381
@ 15.0
650.0
1300.0
atau
"
305 x 305
@ 18.0
381 x 381
450.0
900.0
650.0
1300.0
305 x 305
450.0
900.0
254 x 254
@ 15.0
300.0
600.0
"
atau
atau
"
381 x 381
@ 18.0
900.0
1800.0
Penapak
Konkrit
Tetulang
Page 78
Syor-syor Tambahan
a)
Kerja-kerja penimbusan dan pemotongan hendaklah dijalankan pada perinakat
permu laan kerja-kerja pembinaan dan tanah yang ditimbus hendaklah di dalam
lapisan tidak melebihi 300mm dan setiap lapisan dipadat ke tahap 95% mengikut
Piawaian Kepadatan British dengan penentuan JKR.
b)
Page 79
tanah timbus melebihi 2.50m kegunaan lantai gantung adalah diperakukan, dan
untuk bangunan-bangunan lain yang mana lantai-lantai tingkat bawah akan
dilekakan di atas tanah timbus tidak melebihi 2.50m lantai-lantai ini hendaklah
diperkuatakan dengan 2 lapisan BRC dan sambungan bebas disediakan di anatara
lanatai dan rasuk/dinding bangunan.
c)
Penyediaan penyambung bagi setiap jarak 6.0m adalah wajar bagi lantai-lantai
apron kesemua bangunan yang dicadangkan dan mana-mana lantai apron yang akan
diletakkan di atas timbus melebihi -1.0m lantai apron ini perlu dipisahkan daripada
tiang/rasuk/dinding bangunan dengan bitumen.
d)
Bagi blok-blok bangunan di mana pusat ini telah mengesyorkan lebih dari satu saiz
cerucuk, pihak tuan . bolehlah memilih mana-mana saiz.yang didapati lebih
ekonomik tetapi HANYA SATU SAIZ CERUCUK DIBENARKAN bagi satu ban
gunan.
e)
Pusat ini juga mengesyorkan agar. kecuraman cerun-cerun yang akan didirikan tidak
melebihi IM: 1(H) bagi cerun-cerun potong (cut slopes) dan, IM: 1.5(H) bagi cerungerun timbud (filled slopes).
6.0
Hal-hal Lain
Satu set rekod penanaman cerucuk-cerucuk yang diuji berserta dengan keputusan ujianujian bebannya hendaklah dikemukakan kepada pusat ini untuk tujuan dokumentasi.
7.0
Penutup
Dikemukakan syor-syor dan ulasan pusat ini untuk tindakan tuan selanjutnya.
Page 80
Lampiran 'E'
Hence for estimation of settlement of fill, fig. 1.0 below would be used.
From fig. 1.0 graph 5, cohesive material would settle around 11% of its thickness.
Suppose that construction period is 2 years and construction of ground floor would be carried out
after a period of 1.5 years after placement of fill..
Take case where height of fill = 2.50m
Therefore settlement of fill = 0.11 x 2.50 = .275m
Settlement (': of height of fill) = 0.08 x. 2.50 = 0.200m after period of 1.5 yrs.
Hence remaining settlement after = 0.275 - 0.200 = 0.075m period of 1.5 yrs.
Therefore for those buildings placed on fill ground of height >> 2.50m suspended floor is recommended and for the others . place on fill < 2.50m independent floor with 2 layers of BRC.
Cawangan Jalan, Ibu Pejabat JKR, K.L
Page 81
Projek :
Pakej :
1.0. Tujuan.
Lapuran ini adalah bertujuan untuk menyampaikan keputusan penyiasatan tapak dan syor
asas yang sesuai bagi.projek diatas.
2.0. Skop Kerja
Perlaksanaan projek ini akan melibatkan pembinaan 1 Blok, 2 Tingkat (6BD,) bangunan
sekolah seperti yang tertera didalam pelan tatatur JKR/SB:765/81A. Aras tanah sediada
adalah merupakan cadangan aras formasi tapakbina ini,dan tidak-melibatkan sebarang
penambunan.
3.0. Skop Kerja Penyiasatan Tapak
Sebanyak 8 bilangan ujian proba JKR telah dijalankan oleh JKR Sabak Bernam, dan-2
bilangan ujian gerekan dalam telah dijalankan oleh Unit Makmal dilokasi-lokasi yang
bertanda didalam pelan tatatur.
4.0. Syor-syor Asas
Berdasarkan kira-kira rekabentuk, syor asas adalah seperti berikut:Jenis Asas
Cerucuk Konkrit
Tetulang
4.1.
4.2.
4.3.
Saiz Asas
(mm)
Panjang Asas
(mm)
254 x 254
30.0
Keupayaan galas
Beban
yg. Dibenarkan
Ujian
(kN/cerucuk)
300
600
Page 82
NEGERI : SELANGOR
1. HISTORY OF SITES
*
NO
Is there a slope ?
NO
PILE
RC
305 x 305
-
When Constructed ?
80s
OK
SIGN OF
CRACKS
30
3. SOIL CONDITIONS
* What type of soils ?
SOFT CLAY
HIGH
HBB /hbb
Page 83
Page 84
UNIT MAKMAL
NO. HELAI 1
TARIKH 4.10.89
RUJUKAN
KIRA KIRA
CATATAN
Lukisan
RL : 29.54
JKR/SB: 765/81A
FL : 30.00
Column Loadings(T)
Lukisan
Frame
Front
Back
F1
20
18
F2
29
25
F3
25
21
Datas &
Assumptions
MAX 29T
No fitting included
Level
Geological
Section
SPT
(m)
(ft)
(N)
v/s
12
40
Cu
kN/m
x
2
v/s
(0.03)
v.soft
v/s 25
to
(0.23)
Cu
Stiff
1.0
0.9
Silty
Clay
Qu = Qs + Qb
Clay: Qs = As x Cu Qb = Ab 9 Cb
Sand : Qs = ASN
50
Qb = Ab 4 N
Qa = Qu
f.o.s.
E96
Page 85
UNIT MAKMAL
RUJUKAN
KIRA KIRA
CATATAN
Try RC Piles
Level
(m)
(ft)
30
100
BXB
Qs
Qb
Qa
Qa
(in)
(T)
(T)
(T)
(T)
61 B
3.5 B 2
10 x 10
51
2.4
35
27
12 x 12
61
3.5
42
32
15 x 15
76
5.5
53
41
67B
40B2
10 x 10
56
28
47
42
12 x 12
67
40
58
54
15 x 15
84
63
77
74
Remarks
* quite close
Cost comperison
F2
F1
F3
F2
F3
F3
F2
F3
F3
F3
F1
Frames
Front
Back
Col
F1
F2
F3
12
E96
Page 86
UNIT MAKMAL
KIRA KIRA
Column
CATATAN
No of Piles
10 x 10 @
30T(30m)
12 x 12 @
30T(30m)
15 x 15 @
30T(30m)
at 100
at 100
at 100
Total
22
22
22
Rate
$0.32/m 2
$0.30/m 2
$0.28/m 2
Per m
Per m
Per m
Materials
$960/-
$1296/-
$1890/-
10%
96/-
129.6/-
189/-
Total Cost
$23,232/-
$31,363/-
$45738/-
Loads(T)
F1
20
18
F2
29
25
F3
25
21
Recommended
R.C. Piles
Size : 10 x 10 (254 x 254)
Length : 1 00 (30m)
Qa : 30T/Pile (300kN Pile)
f.o.s. : 1.5 skin 3.0 bearing
Pile is of mainly friction
E96
Page 87
Project :
BD
SC
BDS
SCS
Bangunan
:
2 tingkat
Jenis (BD/SC/BDS/SCS)
: BD
Pile dim.
:
254 mm sq. piles
Length
:
30 m
W.Load
:
30 Tonnes
No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////// //////
Frames
Column
Position
Front
Back
Front
Back
Front
Back
Column
Load
20.0
18.0
29.0
25.0
25.0
21.0
=
=
=
=
Piles/
Column
1
1
1
1
1
1
TOTAL :
Cost :
Bilik Da
Makmal S
Bilik D
Makmal
Piles Reqd.
2
2
3
3
6
6
22
$23,232.00
ALTERNATIVELY : -
Pile dim.
Length
W.Load
:
:
:
No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////////////
Frames
Column
Position
Front
Back
Front
Back
Front
Back
Column
Load
20.0
18.0
29.0
25.0
25.0
21.0
Piles/
Column
1
1
1
1
1
1
TOTAL :
Cost :
Piles Reqd.
2
2
3
3
6
6
22
$31,363.20
Page 88
Project :
BD
SC
BDS
SCS
Bangunan
:
2 tingkat
Jenis (BD/SC/BDS/SCS)
: BD
Pile dim.
:
381 mm sq. piles
Length
:
30 m
W.Load
:
30 Tonnes
No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////// //////
Frames
Column
Position
Front
Back
Front
Back
Front
Back
Column
Load
20.0
18.0
29.0
25.0
25.0
21.0
=
=
=
=
Piles/
Column
1
1
1
1
1
1
TOTAL :
Cost :
Bilik Da
Makmal S
Bilik D
Makmal
Piles Reqd.
2
2
3
3
6
6
22
$45,738.00
ALTERNATIVELY : -
Pile dim.
Length
W.Load
:
:
:
No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////////////
Frames
Column
Position
Front
Back
Front
Back
Front
Back
Column
Load
20.0
18.0
29.0
25.0
25.0
21.0
Piles/
Column
1
1
1
1
1
1
TOTAL :
Cost :
Piles Reqd.
2
2
3
3
6
6
22
$31,363.20
Page 89