You are on page 1of 89

Pile Design Report

FOR INTERNAL USE ONLY

Sample Design Calculations


For Micropiles in Kenny
Hill Formation
Generalized Subsoil Profile
-

Generally flat terrain

Subsoil profile:
0-3m, silty SAND, SPT=1- 5
3-6m, silty SAND, SPT= 15 - 50
6-20m, highly weathered sandstone

Schematic Detail

Soil becoming
weathered rock

Mild Steel Capping Plate


L
=
350mm
B
=
350mm
Thickness
=
10mm
Mild Steel Stiffeners
Thickness =
10mm
Pile Boring
Diameter = 200mm

L = 20.0m

API Pipe
O.D.
Thickness
fy (min)
Grade

=
=
=
=

127.0mm
9.2mm
552 Mpa
N-80

Cementitious Grout
W/c
=
0.45
Fcu
=
25 Mpa
Safe Working Load
Pa
=
80 tonnes
Lsocket
=
20m

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 1

Pile Design Report

FOR INTERNAL USE ONLY

Subject : Micropile Design


1.0

Material Properties

1.1

Basic Dimensions and Properties

1.1.1
1.1.2
1.1.3

Micropile Diameter, D
Pile Composite Modulus Ep
Moment of Inertia, Ip

1.2

Cementitious Grout

1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.2.6

Max. water/cement ratio


Anti-shrink / Additives
Grout Area. Ac
28 day Comp. Strength, Fcu'
Density
Elastic Modulus. Ec

1.3

API Pipe Reinforcement

1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
1.3.7
1.3.8
1.3.9

Source
Outer Diameter, OD
Wall Thickness. t
Inner Diameter. ID
Cross Sectional Area, As
API Specification
Grade Designation
Mm. Yield Strength, fy
Elastic Modulus. Es

1.4

Compliance with British Standards Designed

1.4.1
1.4.2
1.4.3
1.4.4

Working Grout/API Pipe Bond (MPa)


0.8
12
Grout Characteristic Strength, fcu (MPa)
25
20
Cement content (kg/m"3)
400
00
Grout working compressive stress,0.4fcu/FoS 0.2 x fcu 0.25 x fcu

1.5

Minimum Factors of Safety

1.5.1
1.5.2
1.5.3
1.5.4

Against Structural Failure


Against Buckling Failure
Against Geotech. Failure
Against Geotech. Failure

2.0

Structural Design
Assuming that the applied vertical load is carried by the API Pipe alone.
Ultimate Load Capacity Pu
= 0.87 x fy x As
= 1633450 N
= 1633.5 kN
= 163.3 tonnes
Use the Factor of Safety prescribed in Section 1.5 on Plate 2
Allowable Load Capacity Pa
= 82 tonnes

2.1

2.2

Cawangan Jalan, Ibu Pejabat JKR, K.L

= 200mm
= 41
GPa
= 7.85E+07 mm^4

=
=
=
=
=
=

0.45
Adogroud 100g 150kg bag
45686
mm"2
25
MPa
2000
kg /M^3
28
GPa

=
=
=
=
=
=
=
=
=

127
9.19
108.62
3401
5A-80
N-80
552
210

=
=
=
=

2.00
1.60
2.00
2.50

mm
mm
mm
mm^2

MPa
GPa
Req. Min.
(Max)

Source

BS8110
BS8004
BS8004
BS8004

Skin Friction
End Bearing

Page 2

Pile Design Report

FOR INTERNAL USE ONLY

2.3

Design Safe Working Load SWL

= 80 tonnes

3.0

Geotechnical Design
Refer Piler Analysis for derivation of Geotechnical Safe Working Load -Appendix ......

3.1

Design Length

3.1.1
3.1.2
3.1.3

Safe Working Load per Pile


Nominal Diameter
Embedment

3.2

Grout l API Pipe Bond

3.2.1
3.2.2
3.2.3
3.2.4

Ultimate Grout Pipe - Bond Stress, t (u)


Factor of Safety
Working Bond Stress, t (w)
Req'd API Pipe Embedment in Grout

P
D
Ls

Therefore, adopted socket length is

= 800
= 200
= 20.0 m

kN
mm

= 2.0
= 2.5
= 0.8
= 2.5
< 20.0 m
OK

MPa
MPa
m

4.0

Buckling (Pile Slenderness)

4.1

Pile End Conditions (Unfilled Cavities)

4.1.1
4.1.2
4.1.3
4.1.4

Pile Top (at Pilecap Level)


Pile Base (at Rock Head Level)
Ass. length in unfilled cavity L assumed
Effective Length - 0.7 x L L eff.

4.2

Eucler's Buckling Load (Unfilled Cavities)

4.2.1
4.2.2

Effective radius
Euler Critical Load

4.3

Elastic Buckling Load of Pile embedded in Overburden (ie Winkler Medium)

4.3.1
4.3.2
4.3.3
4.3.4

Average SPT in Overburden soils, N


Est. Und. Cohesion Overburden soils, Cu
Modulus of Horiz. Subgrade Reaction, kh'c
20100 kPa
Elastic Buckling Load, Pcr

4.3.5

FOS available

5.0

Rate of Corrosion of Reinforcement

5.1

Ex Oil Drill API Pipe Reinforcement

5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
5.1.7

Outer Diameter
Wall Thickness
Internal Diameter
Cross sectional Area
API Specification
Grade Designation
Min Yield Strength

Cawangan Jalan, Ibu Pejabat JKR, K.L

Analysis not appropriate


for Kenny Hill Formation

r
Pe
FOS available

O.D.
t
I.D.
As

fy

=
=
=
=

Fixed
Fixed
1m
0.7 m

=41.8
=@pi^2 - Ep l(Lelr)^2 = 1428 kN
=9.78
OK

=
=
=
=
=
=
=

50
6 ' N kPa 300 kPa
67*Cu
20.1 MPa
2 x @sgrt (Ep x Ip x kh x d)
16014 kN
20.02 OK

=
=
=
=
=
=
=

127.0
9.2
108.6
3401
5A-80
N-80
552

mm
mm
mm
mm^2

MPa
Page 3

Pile Design Report

FOR INTERNAL USE ONLY

5.1.8
5.1.9

Elastic Modulus Es
=
210
GPa
Allowable Axial Working Stress (Clause 7.4.6.3.1 BS8004)
Fa
=
50% of Yield Strength
=
276 MPa

5.2

Design for allowable corrosion as for sheetpiles w/o grout/


concrete protection

5.2.1
5.2.2
5.2.3
5.2.4
5.2.5

Allowable corrosion rate


Max. pile axial load Pa
Req'd Steel Area
Min. OD of API Pipe
Allowable Corrosion Period

=
=
=
=
=

Asc
O.D.
Tc

0.01
800
2899
124.5
255

mm/year
kN
mm^2
mm
years

Summary

No additional reinforcement required, Tc > Design Life of 50 years.


6.0

Pilehead Capping Details


Safe Working Load

800

kN

=
=
=
x

25
6.85
116800
350

MPa
MPa
mm^2
OK

155

MPa

6.1

Capping Plate Size

6.1.1
6.1.2
6.1 3

Assume characteristic strength of pileca f cu


Permissible direct compressive stress fcu13.65
Req'd bearing area of capping plate
Adopt plate of dimmensions (mm)
350

6.2

Thickness of Stiffners

6.2.1

Allowable Axial Compressive Stress


=
(Table 17 (a). BS449 : Part 2: 1969)
Contact Area of API Pipe on Capping Plate
=
Stiffener projection beyond API pipe OD
=
Required thickness of MS Stiffeners
t(s) =
Adopt

6.2.2
6.2.3
6.2.4

6.3

Thickness of Capping Plate

6.3.1
6.3.2

Allow Shear Stress on Capping Plate


(Table 10. BS449:Part 2:1969)
Effect. Punching Shear Shear Perimeter

6.3.3

Required Thickness of Capping Plate

125

OD of API Pipe + Perimeter


- 8 x thickness of stiffeners
1599 mm
4.0
mm
10
mm

=
=
Adopt

6.4

Allowable Bearing Stress on Capping Plate

6.4.1

Allow. Bearing Stress on Capping Plate


(Table 9. BS449:Part 2:1969)
Proj. Bearing Area (API + Stiffeners)
Actual Bearing Stress

6.4.2
6.4.3

Cawangan Jalan, Ibu Pejabat JKR, K.L

3401 mm^2
184
mm
2.4
mm
10
mm
(4No. MS Stiffeners)

MPa

210

MPa

=
=

10761 mm^2
74
MPa
< All. Bearing Stress, OK
Page 4

Pile Design Report

FOR INTERNAL USE ONLY

6.5

Check Stiffeners for Buckling

6.5.1
6.5.2

Bearing Area of API Pile


=
3401 mm^2
Bearing Area of 4No. Stiffeners
=
7359 mm^2
Assume uniform distribution of Pile Axial Load,
Compressive Load per Stiffener
=
136.8 kN
Pile head Embedment into Pilecap
=
150
mm
Assume Stiffener Depth, d
=
140
mm
(Conservative Estimate)
Slenderness Ratio of Stiffener
d ' @sgrt(3)1 thickness of stiffener
=
24.2
Allow. Compressive Stress
=
146
MPa
(Table 17(a). BS449)
Allow. Buckling Load on Stiffener
=
268.6 kN '
> Compressive Load of Stiffener, OK

6.5.3
6.5.4
6.5.5
6.5.6
6.5.7
6.5.8

6.6

Check Bearing on API Pipe

6.6.1
6.6.2
6.6.3
6.6.4

Moment equilibrium about intersection of Capping Plate and API Pipe,


Bearing Force on API Pipe
=
180
kN
Assume material for API Pipe to be equivalent to G55 steel,
Allow. Bearing Stress
=
320
MPa
Allow Bearing Load
=
448
kN
> Actual Bearing Force, OK

6.7

Fillet Weld Design (Stiffener to API Pipe)

6.7.1

Weld Length per Stiffener

6.7.2

Req'd Shear Load Capacity for weld

Cawangan Jalan, Ibu Pejabat JKR, K.L

=
=
=
Adopt

2xd
280
0.49
7

mm per stiffener
kN/mm
mm Fillet Weld

Page 5

Pile Design Report

FOR INTERNAL USE ONLY

Design Report
1.

Introduction
This report presents the design criteria and design calculations for pile foundation for
Interchange 3 of Project B 15 Road Upgrading Works.
Interchange 3 is a cloverleaf interchange with arch shaped R.C bridge as shown below

From structural analysis the compression load coming over the piles from one half of the
bridge is 12600 ton while the other half is 2800 ton in tension.
2.

Site Condition
The topograph of the site is rolling to undulating. The subsoil condition is generalized as
shown above.
The top 12m to 16m from the OGL of the residual soil is clayey silt with SPT 6-39 (aver
age SPT=20): This is underlain by hard clayey silt sith SPT exceeding 50 up to 28m bgi.

3.

4.

Analysis
Shallow foundation is not suitable because part of the formation is on filled ground and also
part of the foundation is in tension or high compression.
Driven spun piles cannot or not practical to provide adequate tension required. Large diam
eter bored piles are suitable for high compression and tension required.
Design Calculations
4.1

Compression piles

The allowable compression load carrying capacity of the single pile has been cal
culated based on the SPT 'N" values, using the following formula.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 6

Pile Design Report

FOR INTERNAL USE ONLY

Allowable load

Ab

Ab, af + As,fs
3
2
2
base area (m )

qf

=
=

unit base resistance


400 Nb (in SI-unit), Meyerhof's Empirical Formula

Nb

average 'N' over 5m above and 3m below depth


being considered (< 50)

As

Pile circumference area (m2)

fs

=
=

unit skin friction


2 Nave (in SI-unit)

Nave

= Average SPT value with depth

Factor of safety of base resistance


= 3 to control settlement
Factor of safety of friction resistance = 2
The detailed pile calculations are given in Appendix B.
4.2

Tension piles

The allowable tension load carrying capacity of single pile has been calculated
based on SPT 'N' values, using following formula
Allowable load
=
As . fs 2
As

Pile circumference area

fs

=
=

Unit skin friction


2 Nave (in SI-unit)

Nave

Average SPT 'N' value with depth

Factory of safety against friction resistance = 2


The detailed pile calculations are given in Appendix B.
5.

Design Calculations

5.1

General

Diameter of Compression pile : 1500 mm with design load of 900 ton


Diameter of Tension piles : 1200m with design load of 400 ton
Estimated pile length = 19m socketing 3 times diameter into hard stratum of SPT> 50

5.2

Preliminary Load Tests Analysis

Compression load tests and pull out tests were carried out at the Interchange bridge site to
assess the performance of the piles installed to the design lengths.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 7

Pile Design Report

FOR INTERNAL USE ONLY

(a)

West Abutment

The tension Test Piles (No.81) located on the west abutments satisfied the per
formance criteria. Based on Prof Chin's Stability Plot:
Ultimate load
: 1141 tonne
Average Unit Shaft Friction

16 tonne/m2

The compression Test Pile No. 15 located ont the west abutments satisfied crite
ria at work load and 2 x work load but just failed to satisfy the recovery criteria.
Based on stability plot.
Ultimate capacity
: 2,490 tonne
Ultimate Shaft capacity

1,945 tonne

Mobilised Toe capacity

548 tonne

Ultimate Unit Shaft Resistance

39 tonne/m2

Mobilised Unit Toe Resistance

310 tonne/m2

Based on these assessment, piles were constructed to following toe elevations:


Compression Piles
: RL 33.00
(5m longer than Test Piles)
Tension Piles
(same length as Test Pile)
(b)

RL 31.00

East Abutment

Tension Pile No. 71 was tested. Pile satisfy the deflection criteria at working load
but however failed to attain the 2 x working load without excessive movement.
Based on Stability Plot, the following capacitities can be estimated:
Ultimate Shaft capacity

624 tonne

Unit Shaft Resistance

9 tonne/m2

This is much less than the 16.0 tonne/m2 value of tension pile No. 81. Based on
the evaluated value of 9.0 tonne/m2, all remaining working tension
piles are installed to RL 21.00 toe level, l O.Om longer than the test pile.
Compression pile No. 65 was first tested. It failed to satisfy the performance cri
teria. Estimated capacities are:
Ultimate capacity
: 1600 tonne
Ultimate Shaft capacity

625 tonne

Ultimate Toe capacity

1041 tonne

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 8

Pile Design Report

FOR INTERNAL USE ONLY

Unit Shaft Resistance

12 tonne/m2

Mobilised Unit Toe Resistance589 tonne/m2 Based on above results, Test Pile
No. 2 (Pile No.66) located 4.50m from P65 was installed to toe level RL 33.00
(5.Om longer). Theoretical ultimate capacity should be of the order of 1,900
tonnes. The test showed the following:
Ultimate capacity
: 1520 tonne
Ultimate Shaft capacity

730 tonne

Mobilised Toe capacity

790 tonne

Ultimate Unit Shaft Resistance

10 tonne/m2

Mobilised Unit Shaft Resistance

447 tonne/m2

These are less than values obtained from P65, indicating significant variation in the sub
soil strength. Concreting procedures are satisfactory and concrete batch records
and test indicate supplied concrete complied with the requirements of the specification.
Concreting volume of pile does not indicate occurrence of collapse of borehole or neck
ing. Since the pile was concrete immediately after boring, strength relaxation due to
aging should not occured.
Based on above, all remaining piles are to be installed to toe levels 23. Pile No. P52 will
be test to assess amount of pile head movement at working load and 2 x working load.
Estimated ultimate capacity of piles to toe level RL 23.00 is order 2,100 tonnes.
(c)

Results of loads tests carried out at Interchange No. 3 are shown in Figure T1 to
T.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 9

Road B -15

= 2*Nave (SI-Unit s)

fs

Cawangan Jalan, Ibu Pejabat JKR, K.L

62

61

60

59

58

57

26

27

28

29

30

39

38

37

36

35

50

50

50

50

50

50

50

50

50

50

50

50

50

47

47

32

32

28

28

31

31

29

29

23

23

17

17

16

16

16

75

75

75

75

75

75

75

75

75

32.5

32.5

32.5

32.5

31

31

23.5

23.5

21.5

21.5

23

23

22

22

19

19

16

16

15.5

15.5

15.5

C o r r ect ed

37.53

36.28

34.95

33.52

31.98

30.33

28.54

26.6

24.5

22.2

21.71

21.18

20.58

19.92

19.26

18.53

18.2

17.82

17.54

17.21

16.68

16.05

15.39

14.56

13.93

13.08

12.5

11.63

10.33

7.75

N ave

A ver ag e

75.06

72.57

69.9

67.04

63.96

60.65

57.08

53.21

49

44.41

43.43

42.35

41.16

39.83

38.53

37.06

36.4

35.64

35.08

34.42

33.36

32.1

30.78

29.13

27.86

26.17

25

23.25

20.67

15.5

f s=2 N

141.37

136.66

131.95

127.23

122.52

117.81

113.1

108.38

103.67

98.96

94.25

89.54

84.82

80.11

75.4

70.69

65.97

61.26

58.55

51.84

47.12

42.41

37.7

32.99

28.27

23.56

18.85

14.14

9.42

4.71

As

10612

9917

9223

8529

7837

7146

8456

5767

5080

4395

4093

3792

3491

3191

2905

2620

2401

2184

1984

1784

1572

1361

1160

961

788

817

471

329

195

73

Qs

U LT I M A T E S HA F T R E S I S T A N C E

1. Correct ed N = 15 + 0.5 (N-15), f or N up t o and equal t o 4 t imes N=50

25

Not e:

24

20

45

41

19

40

18

47

46

23

17

48

42

16

49

21

15

51

50

22

14

52

43

13

53

44

11

12

54

63

10

64

55

65

56

D ep t h

Level ( m)

SPT

B ored pile diamet er

Db

2.00

1.20 met ers

FS f or f rict ional res

FS f or base resist ain 3.00

A llowable load = A b*qf / 3 + A s*f s/ 2

A llowable load = Ult imat e load along base/ 3.0 + Ult imat e load along shaf t / 2.0

Nave = average spt value wit h dept h

= SPT value at base

= pile circumf erence (m^2)

As

= 400*Nb(SI-Unit s)

qf

Nb

= base area (m^2)

Ab

R ed uced

where

(WEST SIDE OF THE CENTRE LINE OF THE ROA D)

P ILE LE N G T H E S T IM A T IO N A LO N G T H E IN T E R C H A N G E # 3

75

75

75

75

70

64

59

54

48

43

36

30

29

27

26

25

24

23

22

21

21

20

19

18

17

15

14

13

13

12

10

Nb

30000

30000

30000

30000

27875

25750

23625

21500

19300

17100

14525

11950

11400

10850

10375

9900

9450

9000

8775

8550

8275

8000

7625

7250

6925

5825

5571

5233

5000

4650

4133

q f =4 0 0 N b

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

1.767

Ab

53014

53014

53014

53014

49259

45504

41749

37994

34106

30218

25668

21117

20145

19174

18334

17495

16700

15904

15507

15109

14623

14137

13474

12812

12237

10294

9846

9248

8836

8217

7304

Qb

U LT I M A T E E N D B E A R I N G R E S I S T A N C E

17671

17671

17671

17671

16420

15168

13916

12665

11369

10073

8556

7039

6715

6391

6111

5832

5567

5301

5169

5036

4874

4712

4491

4271

4079

3431

3282

3083

2945

2739

2435

B ase

5306

4958

4611

4265

3918

3573

3228

2883

2540

2197

2047

1896

1746

1596

1453

1310

1201

1092

992

892

786

681

580

480

394

308

236

164

97

37

S haf t

22977

22630

22283

21936

20338

18741

17144

15548

13909

12270

10602

8935

8461

7987

7564

7141

6767

6393

6161

5928

5660

5393

5072

4751

4473

3739

3517

3247

3043

2776

2435

T o t al ( kN )

A LLO W A B LE LO A D

B oring B H-11(West side)

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 47

V .Sof t clayey silt SPT 2

V .Sof t clayey silt SPT 2

V .Sof t clayey silt SPT 2

St if f clayey silt SPT 29

St if f clayey silt SPT 23

M ed clayey silt SPT 17

M ed clayey silt SPT 16

B oring

B H-13(Eest side)

24
26

2
0

22

20

16

14

12

10

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

V .St if f clayey silt SPT

V .St if f clayey silt SPT

V .St if f clayey silt SPT

St if f clayey silt SPT 11

St if f clayey silt SPT 7

M ed clayey silt SPT 9

M ed clayey silt SPT 6

Dept h(m) RD Level 25.75m

6
4

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

V .St if f clayey silt SPT 39

V .St if f clayey silt SPT 39

St if f clayey silt SPT 12

M ed clayey silt SPT 11

M ed clayey silt SPT 10

Soil Invest igat ion Ph:l

28

26

24

22

20

18

16

14

12

10

RD Level 66.50m

B H-13(West side)
Dept h(m)

B oring

18

Soil Invest igat ion Ph:ll

28

26

24

22

20

18

16

14

12

10

Dept h(m) RD Level 64.89m

10

12

14

16

18

20

22

24

26

28

30

32

34

36

38

40

42

44

46

48

50

52

54

56

58

60

62

64

66

68

Level(m)

Reduced

S UB S O IL P R O F ILE A LO N G T H E B R ID G E LO C A T IO N

A ppe ndix B

FOR INTERNAL USE ONLY

Pile Design Report

Page 10

Road B -15

= 2*Nave (SI-Unit s)

fs

Cawangan Jalan, Ibu Pejabat JKR, K.L

26

27

28

29

30

-1

-2

-3

-4

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

38

38

32

31

21

21

11

11

11

75

75

75

75

75

75

75

75

75

75

75

75

32.5

32.5

32.5

32.5

26.5

26.5

23.5

23

18

18

11

11

11

C o r r ect ed

39.82

38.65

37.4

36.05

34.61

33.06

31.38

29.56

27.59

25.43

23.07

20.48

17.61

16.78

15.85

14.81

13.63

12.71

11.65

10.67

9.55

8.7

7.67

7.25

6.71

5.4

4.5

N ave

A ver ag e

79.65

77.3

74.79

72.11

69.22

66.12

62.76

59.13

55.17

50.86

46.14

40.95

35.21

33.56

31.71

29.63

27.27

25.43

23.31

21.33

19.09

17.4

15.33

14.5

13.43

12

10.8

f s=2 N

113.1

109.33

105.56

101.79

98.02

94.25

90.48

86.71

82.94

79.17

75.4

71.63

67.86

64.09

60.32

58.55

52.78

49.01

45.24

41.47

37.7

33.93

30.16

26.39

22.62

18.85

15.08

11.31

7.54

3.77

As

9008

8451

7895

7340

6785

6231

5678

5127

4576

4027

3479

2933

2389

2151

1912

1675

1439

1246

1054

885

720

590

462

383

304

226

163

102

60

23

Qs

U LT I M A T E S HA F T R E S I S T A N C E

1. Correct ed N = 15 + 0.5 (N-15), f or N up t o and equal t o 4 t imes N=50

25

Not e:

24

20

19

18

23

17

16

10

21

15

11

22

14

12

13

13

11

12

15

14

10

17

18

16

22

19

23

24

25

21

26

20

D ep t h

Level ( m)

SPT

B ored pile diamet er

Db

2.00

1.20 met ers

FS f or f rict ional res

FS f or base resist ain 3.00

A llowable load = A b*qf / 3 + A s*f s/ 2

A llowable load = Ult imat e load along base/ 3.0 + Ult imat e load along shaf t / 2.0

Nave = average spt value wit h dept h

= SPT value at base

= pile circumf erence (m^2)

As

= 400*Nb(SI-Unit s)

qf

Nb

= base area (m^2)

Ab

R ed uced

where

(WEST SIDE OF THE CENTRE LINE OF THE ROA D)

P ILE LE N G T H E S T IM A T IO N A LO N G T H E IN T E R C H A N G E # 3

75

75

75

75

75

75

75

70

64

59

54

48

42

35

29

27

25

22

20

18

16

14

12

10

Nb

30000

30000

30000

30000

30000

30000

30000

27875

25750

23625

21500

19075

16650

14075

11475

10750

10025

8950

7875

7100

6225

5500

4650

4050

3450

2900

2686

2400

2160

1800

1600

q f =4 0 0 N b

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

Ab

33929

33929

33929

33929

33929

33929

33929

31528

29123

26719

24316

21573

18831

15918

12978

12158

11338

10122

8906

8030

7040

6220

5259

4580

3902

3280

3037

2714

2443

2036

1810

Qb

U LT I M A T E E N D B E A R I N G R E S I S T A N C E

11310

11310

11310

11310

11310

11310

11310

10509

9708

8906

8105

7191

6277

5306

4326

4053

3779

3374

2969

2677

2347

2073

1753

1527

1301

1093

1012

905

814

679

603

B ase

4504

4226

3947

3670

3393

3116

2839

2563

2288

2013

1740

1467

1195

1075

956

838

720

623

527

442

360

295

231

191

152

113

81

51

30

11

S haf t

15814

15535

15257

14980

14702

14425

14149

13072

11996

10920

9845

8658

7472

6381

5282

4890

4499

3997

3496

3119

2707

2369

1984

1718

1452

1206

1094

956

844

690

603

T o t al ( kN )

A LLO W A B LE LO A D

B oring B H-11(West side)

M ed clayey silt SPT 16

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 47

V .Sof t clayey silt SPT 2

V .Sof t clayey silt SPT 2

V .Sof t clayey silt SPT 2

St if f clayey silt SPT 29

St if f clayey silt SPT 23

M ed clayey silt SPT 17

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

V .St if f clayey silt SPT 39

V .St if f clayey silt SPT 39

St if f clayey silt SPT 12

B oring

B H-13(Eest side)

24
26

2
0

22

18

16

14

12

10

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

V .St if f clayey silt SPT

V .St if f clayey silt SPT

V .St if f clayey silt SPT

St if f clayey silt SPT 11

St if f clayey silt SPT 7

M ed clayey silt SPT 9

M ed clayey silt SPT 6

Dept h(m) RD Level 25.75m

20
4

M ed clayey silt SPT 10


M ed clayey silt SPT 11

Soil Invest igat ion Ph:l

28

26

24

22

20

18

16

14

12

10

RD Level 66.50m

B H-13(West side)
Dept h(m)

B oring

Soil Invest igat ion Ph:ll

28

26

24

22

20

18

16

14

12

10

Dept h(m) RD Level 64.89m

10

12

14

16

18

20

22

24

26

28

30

32

34

36

38

40

42

44

46

48

50

52

54

56

58

60

62

64

66

68

Level(m)

Reduced

S UB S O IL P R O F ILE A LO N G T H E B R ID G E LO C A T IO N

A ppe ndix B

FOR INTERNAL USE ONLY

Pile Design Report

Page 11

Road B -15

= 2*Nave (SI-Unit s)

fs

Cawangan Jalan, Ibu Pejabat JKR, K.L

29

30

19

18

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

32.5

32.5

32.5

32.5

32.5

C o r r ect ed

68.15

67.92

67.67

67.41

67.13

66.83

66.5

66.15

65.76

65.34

64.88

64.38

6..82

63.19

62.5

61.72

60.83

59.82

58.65

57.29

55.68

53.75

51.39

48.44

44.64

39.58

32.5

32.5

32.5

32.5

32.5

N ave

A ver ag e

136.29

135.83

135.34

134.82

134.26

133.65

133

132.29

131.52

130.68

129.76

128.75

127.63

126.39

125

123.44

121.67

119.64

117.31

114.58

111.36

107.5

102.78

96.88

89.29

79.17

65

65

65

65

65

f s=2 N

113.1

109.33

105.56

101.79

98.02

94.25

90.48

86.71

82.94

79.17

75.4

71.63

67.86

64.09

60.32

56.55

52.78

49.01

45.24

41.47

37.7

33.93

30.16

26.39

22.62

18.85

15.08

11.31

7.54

3.77

As

15414

14850

14287

13723

13160

12597

12034

11471

10908

10346

9784

9222

8661

8100

7540

6980

6421

5864

5307

4752

4198

3647

3100

2558

2020

1492

980

735

490

245

Qs

U LT I M A T E S HA F T R E S I S T A N C E

1. Correct ed N = 15 + 0.5 (N-15), f or N up t o and equal t o 4 t imes N=50

28

20

Not e:

26

27

21

25

22

24

23

20

28

24

19

29

23

18

30

25

17

31

21

16

32

22

15

33

27

14

34

26

12

13

35

11

37

36

10

38

40

39

41

45

44

46

47

42

48

43

D ep t h

Level ( m)

SPT

B ored pile diamet er

Db

2.00

1.20 met ers

FS f or f rict ional res

FS f or base resist ain 3.00

A llowable load = A b*qf / 3 + A s*f s/ 2

A llowable load = Ult imat e load along base/ 3.0 + Ult imat e load along shaf t / 2.0

Nave = average spt value wit h dept h

= SPT value at base

= pile circumf erence (m^2)

As

= 400*Nb(SI-Unit s)

qf

Nb

= base area (m^2)

Ab

R ed uced

where

(WEST SIDE OF THE CENTRE LINE OF THE ROA D)

P ILE LE N G T H E S T IM A T IO N A LO N G T H E IN T E R C H A N G E # 3

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

70

64

59

54

48

45

40

33

33

33

Nb

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

30000

27875

25750

23625

21500

19375

17857

15833

13000

13000

13000

q f =4 0 0 N b

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

1.131

Ab

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

33929

31526

29123

26719

24316

21913

20196

17907

14703

14703

14703

Qb

U LT I M A T E E N D B E A R I N G R E S I S T A N C E

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

11310

10509

9708

8906

8105

7304

6732

5969

4901

4901

4901

B ase

7707

7425

7143

6662

6580

6298

6017

5735

5454

5173

4892

4611

4330

4050

3770

3490

3211

2932

2653

2376

2099

1824

1550

1278

1010

746

490

368

245

123

S haf t

19017

18735

18453

18171

17890

17608

17327

17045

16764

16483

16202

15921

15640

15360

15080

14800

14520

14242

13963

13686

13409

12332

11257

10185

9115

8050

7222

6337

5146

5023

4901

T o t al ( kN )

A LLO W A B LE LO A D

M ed clayey silt SPT 16

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 47

V .Sof t clayey silt SPT 2

V .Sof t clayey silt SPT 2

V .Sof t clayey silt SPT 2

St if f clayey silt SPT 29

St if f clayey silt SPT 23

M ed clayey silt SPT 17

B oring

B H-13(Eest side)

24
26

2
0

22

18

16

14

12

10

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

V .St if f clayey silt SPT

V .St if f clayey silt SPT

V .St if f clayey silt SPT

St if f clayey silt SPT 11

St if f clayey silt SPT 7

M ed clayey silt SPT 9

M ed clayey silt SPT 6

Dept h(m) RD Level 25.75m

20
4

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

Hard clayey silt SPT 50

V .St if f clayey silt SPT 39

V .St if f clayey silt SPT 39

St if f clayey silt SPT 12

M ed clayey silt SPT 11

M ed clayey silt SPT 10

RD Level 66.50m

Soil Invest igat ion Ph:l

28

26

24

22

20

18

16

14

12

10

Soil Invest igat ion Ph:ll

28

26

24

22

20

18

16

14

12

10

Dept h(m)

B H-13(West side)
B oring

B oring B H-11(West side)


Dept h(m) RD Level 64.89m

10

12

14

16

18

20

22

24

26

28

30

32

34

36

38

40

42

44

46

48

50

52

54

56

58

60

62

64

66

68

Level(m)

Reduced

S UB S O IL P R O F ILE A LO N G T H E B R ID G E LO C A T IO N

A ppe ndix B

FOR INTERNAL USE ONLY

Pile Design Report

Page 12

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 13

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 14

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 15

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 16

Pile Design Report

FOR INTERNAL USE ONLY

5)

Check for buckling load


Qub

Where

Qub

Allowable Qb

Cu El

CU

=
=

10
15 kPa

210 kN/mm2
1/64 B (d14 - d24)

15 x 210 x

B (101.64 - 85.444)
64
106

10

907 kN

907
___
2

454 kN > 300 kN


OK

6) Check for elastic compression


e

PL

P
L

=
=

300 kN
10m

EP

31416 mm2

Ep

= 35.3 kN/mm2

300 x10 x103


31416 x 35.3

3 mm

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 17

Pile Design Report

FOR INTERNAL USE ONLY

Sample Pile Design Calculations


1.

Project :

KKS Road Project


Piled Embankment for the approaches to Sg. Likas
Bridge.

2.

Generalized subsoil profile.

Piled embankment

Sand Lenses

C
L
Bridge

V.soft to soft clay

Stiff to hard
Sandstone/shale

3.

Flat alluvial formation

Top 24m consists of soft to very soft alluvium with few localized sandy lenses (Cu =
10-20 kPa with an average of about 15 kPa except at lenses of sand). Stiff to hard
strata of about 2 - 4m thick overlying on highly to moderately weathered
sandstone/shale bedrock. WT is near the ground surface.

Analysis
Stability and settlement analysis have concluded that simple ground treatments by partial
sand replacement with high strength woven polyester geotextile reinforcement or vertical
drains are not possible to achieve FOS = 1.5 and or post construction settlement to be less
than 200mm for the first 5 years of service if height of embankment exceeds 4.2m.
Piled raft embankment is adopted in preference to EPS, elevated structure and stone column
treatment because:
a)
EPS embankment is technically not acceptable because the site is subject to flooding
& the cost is high.

4.

b)

Elevated structure is about 30% more expensive (separate analysis)

c)

Though treatment by stone columns is cheaper, it requires longer time to consolidate


and technically less superior

Design calculation

Analysis has shown that driven R.C piles will be the most cost effective.
The site has no vibration or noise or ground heave constraints. Pile capacity of about
600 kN is chosen to get optimum pile spacing of 2 to 3m and raft thickness of 350 450mm for pile depth of about 30m.

Use 250X250 R.C piles at spacing "x" bothways Max design capacity - 625 kN.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 18

Pile Design Report

FOR INTERNAL USE ONLY

Load on each pile = x2.d.h, where

625

= x2.20.h

x
For h
For h
For h
For h
For h

=
=
=
=
=
=

x
d

=
=

=
=

spacing
soil density
20kN/m3 h
embankment height

(31.25/h)1/2
6.5m, x = 2.19m, say 2.0m
6.0m, x = 2.2m, say 2.0m
5.5m, x = 2.38m, say 2.25m
5.0m, x = 2.50m, say 2.25m
4.5m, x = 2.64m, say 2.25m (allow some traffic load of 10 kPa)

Conclusion:

Use 250x250 R.C x 30m long at 2.0m spacing for h=6.5 - 6.0m & 2.25m spacing for h = 4-6m
(Pile capacity calculations enclosed).
R.C piles (MS 1314, Class 1) are designed as end bearing piles driven to set.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 19

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 20

Pile Design Report

FOR INTERNAL USE ONLY

Design of Micropile
a) Design load per pile
b) Diameter of micropile
c) Main reinforcement

= 800kN
= 200mm
= 3 Nos of 50mm diam. deformed bars of yield
stress fy = 410N/mm2.

d) Factor of safety

= 2.5 (min)
= 20N/mm2.

e) Grout characteristic strength, fcu


Check Structural Capacity

= B/4 x 502 x 3
= 5892mm2
= 20N/mm2

Area of reinf, Asc


fcu

= B /4 x 2002
= 31,416mm2
= 31,416 - 5892
= 25,524mm2

Area of grout, Ag
..Area of net grout

According to BS 8110, clause 3.8. 4.3


Ultimate axial load, Pu = 0.4 fcu Ac + 0.75Asc fy
= 0.4x20x25,524 + 0.75x5892x410
= 2,016kN.
.. Factor of safety
= Pu/800
= 2.53
> 2.5 O.K.
Check Bond Length Required
- Depth of micropile = 20m
At least l0m will be embedded in very hard decomposed granite SPT, N > 50.
-

Bond between grout & hard formation = 0.4N/mm2

..

Min required bond length in hard


formation, Ib = 800 x 2.5 x l 000N
B x 200 x 0.4
= 7958mm
= 8.0m.
< 10m provided O.K.

Design of M.S. Plate for Pile Head


Use 250mm x 250mm x 20mm M.S. plate
Stress on plate
= 800 x l03N
250 x 250
= 12.8N/mm2
< 155N/mm2 O.K.
(allowable stress BS449)
Details of Micropiles & works specification are encl

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 21

FOR INTERNAL USE ONLY

Pile Design Report

Works Specification for Design and Installation of


200mm Diameter Micropiles
1.
Scope of work shall include design & installation of 200mm diam micropiles of 20m provi
sional length. The micropiles shall be reinforced with 3 Nos. of 50mm diam deformed bars
(fy = 410N/mm2) The working load of the micropile is 800KN.
2.

Drilling

Initial drilling involves installation of 242mm diam conductor casing through loose soil
(about 1.5m) by means of rotary boring or equivalent. Upon reaching hard/stiff formation
down the hole hammer will be used to advance the borehole till a minimum penetration of
10m in very hard decomposed granite. The drilled hole will be flush clean by compressed
air before the reinforcement bars are inserted into the hole. Suitable coupling device will be
used. During drilling, a complete record of soil strata will, be taken for Engineer's inspec
tion.
3.

Grout Mix

Ordinary Postland cement with water cement ratio of 0.5 will be used Non-shrink cement
admixture will be added to improve bonding.
4.

Grouting Procedure

A high speed Koken grout mixer is used for the mixing of the cement grout. The capacity
of the grout mixer is about 25-0 litres.
For grout mixing, 100 litres of water with some non shrink admixture is poured into the
mixer follow by 4 bags of 50 kg. ordinary Portland cement then allow to mix throughly,
normally a few minutes. After mixing, the cement grout, a pressure hose is connected to the
grouting pipe which acts as tremie pipe for grouting. The other end of the pressure hose is
connected to a diesel engine high pressure pump.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 22

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 23

Pile Design Report

FOR INTERNAL USE ONLY

Micropile Design Calculations


Micropile design for underpinning works for an old building is shown as follows. The subsoil consists of about 3m of very soft clay, 5m to 8m of stiff to hard sandy clay with gravels (SPT = 11 to
42). The bedrock generally consists of highly weathered and fractured sandstone/shale (RQD = 0 25%, UCS = 7.5 Mpa).
1)

Micropile details
Diameter of micropile
Design load of micropile
Pipe diameter
Pipe wall thickness
Steel grade (API pipe)

=
=
=
=
=

Yield strength

= 500 N/mm2

(a)

200 mm
300 kN
101.6 mm
8.08 mm
N80

Check for structural capacity


Ultimate structural capacity
PU = B (101.62 -85.44 2) X 500 kN
4
1000
= 1187 kN
Applying factor of safety of 2.5.
Allowable structural capacity.
PA

= 1187
2.5
= 475 kN > 300 kN
OK

(b)

Check for geotechnical capacity


Based on boreholes BH1 and BI-12, the depth of bedrock (sandstone/shale) varies
from 8.7 m to 11.0 m b.g.l. Since the overburden soil consists of about 3.0 m of very
soft soil, the shaft friction on the remaining overburden soil (5 to 8 m) with N value
of 11 to 42 should be ignored and the micropiles are designed to be socketed into the
bedrock.
The socketing length in rock, L, is worked out as follows:
FS Qa

0.05 qa B D x L + 0.5qa B D2
4

where FS is the factor of safety


=
2.5
Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 24

Pile Design Report

FOR INTERNAL USE ONLY

Qa
qa

= Allowable geotechnical capacity


= Unconfined compressive strength of rock
= 7.5 Mpa for sandstone/shale

Bond stress
D
2.5 x 300

= 5% of UCS of rock
= Diameter of micropile hole
= 0.05 x 7.5 x 103 x B x0.2 L +
0.5 x 7.5 x 103 x B x 0.22
4

750
L

= 235.6 L + 117.8
= 2.68 m

Designed socketing length of pile = 3.0 m


2)

Check overall underpinning pile support


Estimated total load of the whole building (3 storey).
=
2,000 tons
No. of micropile points
Load on each pile

= 95
= 2,000
95
= 21 tons

Working load for each micropile provided = 30 tons


OK
3)

Check for anchorage bond between underpinning pile and the existing foundatic
Since epoxy grout is used to fill the hole formed by the micropile in the existir foundation
and the strength of epoxy grout is much higher than the concrete strength, it can be consid
ered as monolithic for the whole foundation.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 25

Pile Design Report

FOR INTERNAL USE ONLY

Critical section
for shear check
Existing
Column
Stump
650mm

Proposed 200mm
micropile
100
mm

1900mm

4)

Check for shear failure of existing foundation.


Perimeter for shear check, p

= 1900 mm

Effective depth of foundation, d = 1050-50-10


= 990 mm
Maximum reaction load,
Shear stress, V

= 300 kN
= V
Pd
= 300 x 103
1900 x 990
= 0.16 N/mm2

From Table 3.9, BS 8110 for d > 400 mm and


100As/bd = 0.25 (nominal reinforcement), allowable shear stress Vc = 0.40 N/mm2
V<Vc

OK

In grouting operation, the cement grout is pumped into the borehole through the pipe by
tremie method. All loose material, cuttings and water in the borehole are displaced by the
cement grout. Pressure applied should be just adequate to displace the cutting and water
from the borehole. Temporary casings should be withdrawn where cement grout overflow
from the casing and top up cement grout if necessary.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 26

Pile Design Report

FOR INTERNAL USE ONLY

Item
No.
A.

Description

Quantity Unit

Rate

Design and install cast in-situ 800kN working


capacity micropiles complete with
reinforcement as shown on the drawings in
provisional lengths 20.0m and pressuregrouted with and including approved grouting
material, drilling in all types of soils and
rock and all coring casings, linings, plugs,
etc. and disposal of all excavated material
and debris from site.
Design information:a)
b)
c)
d)

Diameter of piles: 200mm


Main bars: 3Y50
Links: R05 helical link @ 100mm c/c
Steel casings: 292mm O.D x 9mm thick

e) Grout: Cement grout, w/c = 0.5, fcu = 20N/m2


f) Grout additives: Non shrink admixture
g) Factor of safety : 2.5
h) Bond strength: 0.9N/mm2
i) Bond length: 10m
j) Ultimate load: 2016kN
k) Capacity: 800kN
l) Working load: 800kN
m) etc
Design and install all capping plates and
starter bars
Design information:-

B.

Plate size: 250 x 250mm


Plate thickness: 25mm
Starter bar size: 3Y50 or 8Y25

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 27

Pile Design Report

FOR INTERNAL USE ONLY

Projek :

Cadangan Blok Tambahan pada Hospital


Bersalin di Hospital Besar, K.Lumpur.

1.0

Tujuan
Laporan ini bertujuan untuk menyampaikan laporan penyiasatan tanah dan syor-syor
asas yang sesuai bagi:Projek blok tambahan pada hospital bersalin, Kuala Lumpur.

2.0

Skop Projek
Perlaksanaan projek ini melibatkan pembinaan blok tambahan 2 tingkat di Hospital
Bersalin. Blok yang dicadangkan ini dikelilingi oleh bangunan sedia ada.

3.0

Keadaan Tanah
3.1 Sebanyak 3 ujian gerekan dalam telah dijalankan. Hasil ujian menunjukkan
keadaan lapisan tanah seperti berikut :Jenis Tanah
SPT (blows/ft.)
Ukurdalam(m)
0 - 4.5
Very soft CLAY
0-4
4.5 - 9/10.5
Loose SAND
1-7
9/10.5-13.5/16.0
Stiff silt or CLAY
1-9
13.5/16.0
Limestone
RQD = 73 - 100%.
>16.0
Limestone
3.2

4.0

Kedudukan aras air bawah tanah ialah 1.45m.

syor-syor Asas
4.1 Penapak konkrit tetulang adalah tidak sesuai kerana keupayaan galas yang rendah
dan jugs paras air bawah-tanah adalah tinggi.
"Driven R.C. or steel piles" adalah juga tidak sesuai kerana masalah "noise &
vibration" dikawasan Hospital sukar diterima. "Inclined bedrock" juga mungkin
mengakibat "excessive pile deviations".
Syor-syor asas yang dicadangkan adalah seperti berikut :-

Jenis Bangunan

Jenis Asas

Saiz Panjang Keupayaan


(mm)
(m) galas yg
dibenarkan

Blok Tambahan Cerucuk


200
16.5-19 200kN mikro
with 102
(micropile) API paip
(4)

Geseran
Kulit
negatif

Beba
Ujian

400kN

4.2

Cerucuk mikro hendaklah digerudi sehingga ke paras batukapur dan dikunci


(key) minima 3m ke dalam batukapur.

4.3

Sekurang-kurangnya 2 bilangan cerucuk digunakan untuk setiap tiang.

4.4

Jack pile (200x200xl5m) juga boleh diterima sebagai cerucuk gantian.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 28

FOR INTERNAL USE ONLY

5.0

Syor-syor Tambahan
5.1 Jika rongga (cavity) ditemui, cerucuk hendaklah dipanjangkan
melebihi rongga dan dikunci (keyed) minima 3m ke dalam batukapur
tanpa rongga. (rujuk Fig. 1).
5.2

6.0

Pile Design Report

Untuk mengatasi masalah penanaman micropile dirongga, penender mestilah


diarah mengemukakan cadangan sistem 'micropile installation' dan teknik-teknik
'grouting' dirongga semasa tawaran dibuat.

Hal-hal lain
Satu set rekod penanaman cerucuk-cerucuk yang diuji berserta ujian beban hendaklah
dihantar ke Unit Makmal bagi tujuan dokumentasi.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 29

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran A

Micropile Specfication
1.

General
The work involves the construction of 200mm (8") diameter micropile. The micropile shall
be fabricated using steel tube and the bond length of micropile shall be 16m or directed
by the S.O. The working load of micropile is 200 kN and factor of safety used in design is
2.0. The whole of work and materials shall be in, accordance with curreht Malaysian or
British Standard or other National Standards approved by the S.O.

2.

Reinforcement
Steel grade - HFS 16 (BS: 1775 - 1964)
External diameter 139mm (51/2)
Thickness - 9.5mm (3/8") 2
Yield strength - 250 N/mm (16 Tsi)

3.

Grout
The grout shall be thcFoughly mixed with Ordinary Portland Cement (MS522) and water
(MS28). The grout shall be Antishrink cement grout. The water cement ratio shall be 0245 0.50. The 28 days. Strength for cement grout shall be 25N/mm (3570 psi). The representa
tive cubes shall be collected on each day of grouting works for testing on the 28th days.
Details of admixture shall be submitted to the S.O. for approval before commencement of
works. The use of the admixture shall comply with instruction by the manufacturer & MS
922. The grout shall be free from segregation, slumping, & bleeding of water and fine
materials during and after placing.

4.

Installation
a)

Drilling

The drilling for installation of micropile shall guarantee the absence of Vibration
which may cause damage to the existing building. Adequate precaution must be
taken to ensure boreholes for micropile do not collapse during drilling.
If necessary, temporary casing shall be used. During drilling of borehole, the con
tractor shall maintain complete record of soil profile. The logging shall include
depth of soil and water table. This drilled hole Viand! soil bore log shall be
signed by contractor's site representative and a copy of which shall be deposited
with the S.O. The contractor shall be required to keep representative sample of
soil for each soil profil in plastic bag for inspection by.the S.O. Sample may only
be disposed after the S.O. is satisfied that the logging has been properly done.
The type-of drilling equipment shall be approved by the S.O. The drilled hole
shall be flushed ckean.with air or water.
b)

Fabrication of micro pile

Method of splicing of bars or pipes shall be approved by the S.O. Centralisers at


about 3m centre must be used to ensure a minimum cover of 25mm or directed
by the S.O.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 30

FOR INTERNAL USE ONLY

c)

Pile Design Report

Grouting

The contractor shall also provide details on method and equipment used in grout
mixing. Further information such as grouting pressure, grouting procedure, grout
ing equipment and techniques employed in grouting under water shall also be
furnished and approved by the S.O.
'To prevent deterioration of strength of soil, soil coring, installation of reinforce
ment and cement grouting shall be carried out in one continous operation.
5.

Load Testing
Micro-pile shall be load tested to 2 times design load using the Maintain Load Test.
Minimum of one (1) load test shall be carried out. The contractor shall also specify and pro
vide details of the method of load testing. Micropile shall be constructed only after the pre
liminary pile pass the load test requirements of JKR standard specification for building
Works.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 31

Pile Design Report

FOR INTERNAL USE ONLY

Contoh Jadual Sebut Harga


Bil.
1

Description

Unit

Quantity

Rate

MICROPILES
(ALL PROVISIONAL)

A.
B.

Allow for Preliminaries

Item

Provide all necessary piling


equipment on site, maintain on site,
dismantle and remove from site on
completion, allow for all standing
or idling time and cost of operation
for the whole of piling works.

C.

Item

Installation of 200mm diameter


Micropiles in soil, including coring,
4" diameter pipe, steel plate head,
jointing and extension and grouting

MR

in cement, all as specified (50


positions)
D.

Provide all necessary pile testing


equipment on site, dismantle and
remove from site on completion.
T est 200mm diameter Micropiles in soil
as specified.

Cawangan Jalan, Ibu Pejabat JKR, K.L

NO

Page 32

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran E1

Pile Design
for
SMK (Perempuan Raja Zarina)
Kelang
1.

This project consists of construction of one additional 3-storey school block.

2.

Max column load = 57 ton

3.

This is a typical coastal alluvium site where first 60ft to 100 ft consists of very soft clay

4.

Deep Sounding is very suitable and 4 nos of D/S results give consistent results as shown in
Lampiran E-1

5.

The site is a flat land and the first 4 ft is imported fill (about 5 years ago) Negative friction
has to be checked.

6.

Selection of piles (Refer to Fig. 1)


6.1 Non displacement piles not suitable because of low column load and very soft clay
near the first 100 ft.

7.

6.2

Timber pile also not suitable bacause its max length is about 40 ft. only.

6.3

Use 12" x 12" x 100 ft R.C. piles Design load = 30 Ton/pile (max)

Check Pile Capacity (Refer to Lampiran E-1)


From D/S results
Qu

= Qs + Qp

where Qu

= ultimate capacity

Qs

= skin friction

Qp

= end resistance

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 33

Pile Design Report

FOR INTERNAL USE ONLY

7.1

Skin friction, Qs
Based on total friction (remoulded)
At 30m (100ft), total friction = 3,000 kg.
Qs

= tube friction x-pile perimeter


tube perimeter
= 3,000 x (12" x 2.54 x 4)
11.3
= 32,300 kg
= 30 Ton.

Based on local friction (undisturbed)


Qs

= (8.5 x 0.05 + 7.5 x 0.13 + 13 x 0.27 + 0.9) x 3.28 x 4 x 0.92


= 70 Ton

Sensitivity = Qs (undisturbed)
Qs (remoulded)
= 70
30
= 2.3, within usual range
Q's = " Qs, where " = 0.7 (Bjerrum)
= 0.7 x 70
= 49 Ton
7.2

End Resistance, Qp,


Qp = 80 (kg/cm2) x 1 ft2 x 0.92
= 73.6 Ton
Qu = 49 + 73.6
= 122.6 Ton

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 34

Pile Design Report

FOR INTERNAL USE ONLY

7.3

Negative friction
Negative friction for piles at spacing more than 3 x diameters is
fn

0.2 Po (Bjerrum)
where Po

= effective overburden
= h
= 100' (100psf - 62.4 psf)
= 3760 psf

Max. fn

= 0.2 Po
= 0.2 x 3760
= 752 psf

Average fn

= (0 + 752)/2
= 376 psf

Total negative friction

7.4

=
=
=
=

fn x As
376 x (100 x 4)
150,400 lb
67 Ton

Allowable load, Qs
The negative skin friction, QN should only considered in combination with dead
load because QN acts mainly at the lower portion of the pile and would only affect
the settlement.
2.5 QD.L = Qu - QN
QD.L = 70% Qa
2.5 x 0.7Qa = Qu - QN
Qa
= (Qu - QN) /1.75
= (122.6 - 67)/1.75
= 31 Ton
say 30 Ton/pile
Notes :

The filling is done about 5 years ago. At least 60 - 70% consolidation com
pleted.
fn used is about the same as the undrained shear strength. Hence QN estimated is on the
light side.
To prevent tensile stress and buckling during driving, free drop hammers is preferred.
8.

Recommendation
Use 12" x 12" x 100 ft R.C. piles
Friction piles, driven to the required pene:,tration and load test to verify the capacity. (No
"set" required).# Load tests after 4 weeks of driving.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 35

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 36

Pile Design Report

FOR INTERNAL USE ONLY

Memo
Daripada:

Penolong Pengarah Makmal,Caw. Rekabentuk & Penyelidikan, IP. JKR

Kepada:

Penolong Pengarah(Binaan), Ibu Pejabat JKR, K.L.

Bil surat:

(X) dlm. PKR.RB 4112

Tarikh :

26.3.1983

Per: Cadangan Masjid Baru di Batu 31/2, Jalan Cheras, K.L.


Berhubung dengan perkara yang tersebut di atas, sukacita dimaklumkan bahawa cadan
gan asas yang disyorkan adalah seperti berikut:1.

Keputusan penyiasatan tanah


Sebanyak 28 Nos. Proba JKR dan 5 Nos. Deep Boring telah dijalankan ditapak projek
itu. Keputusan - keputusan yang diterima menunjukkan bahawa kawasan projek ini
adalah terdiri daripada batu kapur. Paras batu kapur adalah daripada 2.5m hingga 14m
daripada paras permukaan tanah sedia ada. Oleh kerana keadaan batu dasar yang susah
untuk diramalkan, langkah-langkah pengawasan dan faktor keselamatan yang lebih
tinggi perlu diambil di dalam rekabentuk asas.

2.
2.1

Syor-syor asas
Jenis - jenis asas yang disyorkan adalah seperti dicatitkan di dalam Lampiran A.
Sebelum kerja - kerja piling dimulakan sekurang - kurangnya satu ujian Proba JKR
perlu dijalankan di setiap kedudukan tiang untuk menentukan paras batu dasar (>400
blows/kaki). Sekiranya paras batu dasar didapati kurang daripada 4.5m dibawah per
mukaan bumi, adalah dicadangkan supaya menggunakan R.C.cylinder foundation
(sila lihat Lampiran A & B)

2.2

Sekurang - kurangnya 2 cerucuk perlulah digunakan ditiap-tiap kedudukan tiang


kecuali jika R.C.cylinder foundation digunakan. Tiap - tiap tiang hendaklah diikat den
gan rasak bawah dikedua - dua arah. Ini adalah sebagai langkah awas oleh kerana terda
pat rongga - rongga dan kemungkinan masalah surutan.

2.3

Untuk memperolehi pengawasan yang lebih baik semasa memacu cerucuk tukul jatuh
bebas(free drop hammer) dicadangkan supaya digunakan. Ini ialah supaya cerucuk tidak
menerima hentaman dan menyimpang berlebihan (overdriving and excessive deviation)
oleh kerana keadaan batu dasar yang mencerun (inclined bedrock surfaces).

2.4

Hujung cerucuk keluli hendaklah dikelulikan dengan plat yang lebih. Ini adalah perlu
untuk menahan tegasan yang berlebihan (withstand overstressing) apabila cerucuk sam
pai ke paras batu dasar.

2.5

Sekurang - kurangnya 2 nos. kumpulan cerucuk (pile group, NCT single pile) perlulah
dipilih untuk ujian beban. Satu set driving records dan keputusan ujian beban hendak
lah dihantar kepada Unit Makmal ini untuk analisa dan sebagai rekod di Unit Makmal.

2.6

Perhatian hendaklah diberi kepada pengalaman yang lepas iaitu cerucuk - cerucuk tam
bahan mungkin diperlukan untuk menggantikan cerucuk - cerucuk yang menyimpang

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 37

FOR INTERNAL USE ONLY

Pile Design Report

berlebihan dan cerucuk - cerucuk yang masih tidak set diparas yang dalam (>10m).
Adalah dicadangan supaya tambahan sebanyak 25m disertakan didalam B.Q.
2.7

Oleh kerana keadaan tanah yang rumit (tricky) jurutera tapak bina hendaklah selalu
rujuk kepada keputusan penyelidikan tapak semasa menyelia kerja - kerja pembinaan
asas. Apabila cerucuk dijangka sampai paras batu dasar, kejatuhan pemukul (drop of
hammer) hendaklah dikurangkan. Tujuan langkah ini ialah untuk better keying & bed
ding effect on rock surface. Langkah ini juga akan mengurangkan cerucuk daripada
menyimpang berlebihan.

Sekian disampaikan ulasan kami untuk tindakan tuan selanjutnya.


Berkhidmat Untuk Negara

......................................................
(Ir. Neoh Cheng Aik),
Jurutera Kerja Kanan (R1),
bp. Penolong Pengarah (Makmal),
Ibu Pejabat JKR, K.L.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 38

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran A

Cadangan Asas Untuk Pro jek


Mas jid Batu 31/2, Jalan Cheras,K.L.

1.

Bangunan Masjid (13T - 105T)


Sila gunakan cerucul; keluli 203mm x 203mm x 45kg/m (Grade 43A9 BS 4360) den
gan beban keupayaan 210 0/eerucuk. Untuk tujuan tawaran, panjang cerucuk ialah 8.5m
(27ft) ATAU "R-C- cylinder foundation".Sila lihat Para 2.1

2.

Bangunan Quarters Kelas G(9T - 16T)


Sila gunakan eerucuk I-,yu berubat (treated timber pile) 125m x 125m dengan beban
keupayaan 5W/oerucuk. Untuk tujuan taviarany panjang cerucuk ialah 8.5m (27 ft).

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 39

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 40

FOR INTERNAL USE ONLY

Pile Design Report


Lampiran E 5

Extension of Terminal Building, Subang Airport


1.

General
The project consists of extension of International and Domestic Transper Corridor for
Subang International Airport. The proposed-site is situated approximately 13 miles west of
Kuala Lumpur.
Due to the close proximity of the proposed site to the existing terminal building v where the
Control Tower for the airport is located, severe vibration such as driving piles is unaccept
abldo Bored and Cast-in-situ piles were considered most suitable.

2.

Soil Condition
The site consists of residual soils of granite.
Lampiran E5-1 represents the generalised poil profile. The top layer of the soil consists of
brown firm sandy silty clay with some organic matters. The depth of this top soil varies
from 6" to 2ft. Beneath this top soil underlies the yellowish with patches of grey medium
sandy clayey silt with some gravelse This medium sandy clayey silt extend to a depth of 40
to 85 ft. below R.L. 86.00'. Between these layers of medium sandy clayey silt and the frac
tured or slightly weathered granite bedrocksq lies the greyish very stiff decomposed granite
residual soil. The thickness of this decomposed granite residual soil varies. Water table is
about Oft. b.g.l.

3.

Load Settlement Criteria


The system of piling to be designed shall meet the followings:a) Safety Factor

The factor of safety for the purpose of computing the working load shall be taken
as 2.5.
b) Working Load

The working load adopted for single pile shall not be greater than the ultimate
load divided by the safety factor of 2.5 and the ultimate load is defined as:
(i)
Load at which the gross settlement continues to increase without any further
increase in load.
(ii)

Load at which gross settlement is 10% of the pile diameter.

c) Settlement Criteria

(i)

Gross settlement of the pile at working load during the first cycle of load
ing, loading to one time working load, shall not exceed 0.5".

(ii)

The residual settlement of the pile at the end of the first cycle of loading
shall not exceed 0.10".

(iii)

The gross settlement of the pile at twice the working load shall not exceed
1.5"

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 41

Pile Design Report

FOR INTERNAL USE ONLY

d) Group Effect

Negligible because of small group (2 or 3 pile per group) & large spacing 2.5 .
4.

Structural Capacity of Piles


Since piles are not fully reinforced, the structural capacity of the piles will be solely depend
on the concrete section of the piles* In this case, the pile is reinforced for the top 40ft.
only for the dispersion of the possible slight bending moment elperienced at the pile top.
The piles will be designed as short columns. According to CP 2004, the structural carrying
capacity of Cast-in-situ concrete pile, that is, the safe working load per pile, W
W - 1/4 (Acc.Uw)

5.

Where Acc
Uw

=
=
=

Gross cross section of the area of concrete


Specified cube crushing strength at 28 days.
3000 psi.

For d
d
d

=
=
=

18, max. structural load =


24, max. structural load =
30, max structural load =

80 Ton.
150 Ton
230 Ton.

Check Pile Capacity


Use 18" bored piles x85 ft max. Meyerhofs formula (modified) is applicable for bored
piles in residual soil
Qu
Qs + Qp
=
=

fs As.+ Op Ap

N As + N. Ap
50

where N =

average SPT along pile shaft

average SPT near pile base (4 above pile base & 2 below pile base).

As

pile shaft area (ft2)

As

pile base area (ft2)

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 42

Pile Design Report

FOR INTERNAL USE ONLY

Based on DB12

18" x 75'
= 0.32 TSF

16

fs = N
50

50

qp = 50 TSB

Qs

=
=

fs As
0.32 x (1.5' x 3.1416 x 75) = 113 Ton

Qp

50 x (1/4 x 1.52 x 3.1416) = 88 Ton

Qa

=
Qs/20 + Qp/3.0
=
56.5 + 29.3
=
85.8 Ton
say 80 Ton

Based on DB 10

18" x 55ft
N

20

fs

= 0.4 TSF

=
=

80
qp
= 80 TSF
0-4 x (1o5 x 301416 x 55)

Qp

80 x (1/4 x 1o5 x 1o5 x 3o1416) = 141 Ton

Qa

Qs/2.0 + Op/3.0 = 52 + 47

=104 Ton

= 99 Ton
say 80 Ton.

Based on DB 13

18 x 80ft.
N

23

fs

= 0.46 TSF

35

qp

= 35 TSF

Qs

0.46 x (1.5 x 3.1416 x 80)

Qp

35 x (1/4 x 3o1416 x 1o5 x 145) =62 Ton

Qa

Qs / 2.0 + Qp / 3.0

Cawangan Jalan, Ibu Pejabat JKR, K.L

=173 Ton

=173/2 + 62/3.0
= 86 + 31
= 117 Ton
> 80 Ton.
Page 43

FOR INTERNAL USE ONLY

Pile Design Report

6.

Founding Level
Founding level should be determined by observing the soil type from the boring. Suitable
founding soil should be weathered granite bedrock or oompacted/cemented clayey silt with
gravels, or up to a max depth of eft'. In case of dou7gt, SPT should be carried in the bored
base.

7.

Recommendation
Use 18 bored pile Vrith max capacity 80 Ton per pile. Site engineer should use the DB
results to determine the founding level. Para 6 above can be used as a guide. 4 Nos load
tests should be carried out to verify the capacity.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 44

DB 13

DB 12

Cawangan Jalan, Ibu Pejabat JKR, K.L


DB 10
DB 9

Loose clayey, silty sand

Hard, Fractured, Weathered granite

Stiff sandy clayey silt with gravels


Compact clayey silty sand with gravels

Sandy silty clay

Hard surface tarmac

DB 11
DB 8

Scale: Horizontal 3/16 to 480

Fig. 1 Soil Profile

DB 7

DB 6
DB 5

DB 4

DB 3

DB 2

DB 1

FOR INTERNAL USE ONLY

Pile Design Report

Page 45

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran E 6

1.

Objective
To design the foundation system for the proposed Dewan Orang Ramai in Kampung
Cheras Baru

2.

Introduction
2.1 The proposed.structure is a one-storey assembly-hall'situated on Lot 405 in
Kampung Ceras Baru, M11rim Ampang, Daerah Hulu Langat
2.2

Column loads

Maximum
Minimum
3.

- 68T
- 30T

Site Condition
3.1

Surface Condition

The terrain is generally flat. It was formerly an old building site that has been
cleared. Springs of water are visible which suggest the ground water table is
very near the ground surface. The only visible form of undergrowth are bushes
and shrubs.
3.2

Subsurface Condition

3.2.1

Referring to the geological map of Kuala Lumpur District (after Ting


and Ooi 1972)2, Kampung Cheras Baru is located in the Granite
region. Hence the soil is residual Gradite soil.

3.2.2

Scope of Site Investigation.


Initially 6 Nos of JKR Probes were performed by the district office of
JKR Hulu Langat. Due to the inconsistency of the probe results, a
more elaborate method of sub-soil exploration in the form of 3 Nos.
Deep Boring was done by the Unit Makmal Ibu Pejabat JKR.
Borehole positions are as indicated in Appendix B. From the borelog
results (APPENDIX C) the soil profile is not consistent along the three
boreholes. Generally) though, the sub-soil eonsists of interlayer
between sand, clay and stilt. The first 9 metres Appears to be com
prised of loose to medium dense sand and very soft-to firm clays (the
variation occuring with depth). Below 9m the soil seems to improve
from medium dense to very dense silts and sands as well as stiff to
very hard clays. The groundwater is very near to the surface and the
subsoil is assumed to be fully saturated.

3.2.3

Other Relevant Information.


Near to the proposed site of the hall, in a north, easterly direction is sit
uated a quarry. There is an access-road leading to the intended site but
it is in a bad state.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 46

Pile Design Report

FOR INTERNAL USE ONLY

4.

Foundation Analysis and Recommendation


4.1

Selection of type of foundation

With reference-to the results obtained from the S.I. done the first 5 metres com
prises of compressible material which is of insufficient strength to sustain the
intended imposed loads. Hence an ordinary shallow foundation in the form of a
pad footing would not suffice. A piled foundation system is warranted here in
order to transfer the loads to the stronger material found below 15m of the
ground-level. In selecting the particular type of pile'to be used, particular consid
eration has been made to
(a)
Cost.
(b)

Driving lengths

(c)

Resistance to hard driving.

(d)

Strength mf pile as structural member

(e)

Effectiveness in mobilising friction and end-bearing

(see T able 1)

Table 1 : Selection of Pile Type


T ype

Max. length

Resistance

Structural

Merit as

Merit as

Cost

of

of

to Hard

Capacity

frictional

end

(per m run)

pile

Driving possible

Driving

pile

bearing

(18m)
R.C.
Steel

pile

T imber X

Figures in box represents order of choise


e.g. 3 third choice

From Table 1, the most apparent' choice would be to use steel piles. However,
based on the soil variation (profile) and the intended loading system which is rel
atively small, the .use of steel' piles is overly conservative. Furthermore hard
driving is not expected.RC piles would be more appropriate in this case because;
(a)
it is more economical
(b)

RC piles would be able to mobilise sufficient safe end-bearing resistance


at a much shallower depth than would be necessary fdv its steel counter
part.

(c)

Due to its rougher surface texture RC piles can mobilise frictional resist
ance better than steel piles

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 47

Pile Design Report

FOR INTERNAL USE ONLY

Hence RC Piles would serve better and cheaper than-steel piles as both a friction
al and end-bearing pile in this particular sub-soil condition.
4.2

Estimation of Ultimate Loads

4.2.1 Design Assumptions


(a)
The soil is fully saturated. In calculating the effective overburden pressure,
Pd, the values of X sat for the various soil categories are obtained from
Appendix B in Ref. 1 (Pg. 397).
(b)

For an SPT value of N 11p the undrained cohesion Cu, is assumed


approximately to be 125 lbs/ft ,

(c)

Due to the inconsistency in the soil variation for the three boreholes, the
piles were designed based on each individual borehole result and the worst
(or lowest)' calculated working load per pile was adopted for use.

(d)

The criteria for design was only to consider both frictional and end-bear
ing piles. Totally frictional or totally end-bearing-piles were not consid
ered.

(e)

Assumed that piles would achieve safe and bearing resistance in soil lay
ers with SPT values of N-~ 15 i.e. in medium dense coesionless soils or
stiff cohesive layers.

(f)

Factor of safety adopted is 2.5 (para 4.6 pg. 149 of. ref. 1)

(g)

Lower values of were assumed for silts as compared to sands.Generally,

(h)

Type of Silts

V.loose to loose

0 - 10

27 - 29

Medium Dense

10 - 30

29 - 34

Dense to V.Dense

30

34 - 39

In obtaining the end-bearing resistance in cohesion soils, the bearing


capacity factor No is taken to be 9 (Para 2 Pg. 122 Ref. 1)

4.2.2 Formulae Used in the Estimation of the Ultimate Loads


4.2.2.1 In Cohesionless Soil.
For frictional resistance
*Qs Avg. uni akin friction = is (1.) Ref. 1 Pg. 137 Para 4)

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 48

Pile Design Report

FOR INTERNAL USE ONLY

where
Qs a Ultimate akin resistance
As = .Area, of shaft
.
Avg. unit skin friction is obtained from Fig. 4.19
Pg. 139 of Ref. 1)
*The foriaula (Ref. 1 Pg. 136 Eln. 4.13)

Qs = 1/2 K, Pd tan As is not applicable in this


particular case because it becomes invalid for
penetration depths/width ratios 10-20 for straight
sided piles (Ref. 1 Pg. 137)
For End-Bearing
Qb = Pd Nq Ab

(2) (Ref. 1 Pg. 135 Eqn.4.12)

where
Qs = Ultimate End,-Bearing Resistance.
Pd = Effective Overburden Pressure
Nq = Bearing Capacity Factor
(obtained from Berezantsevs' Curves in Ref. 1 Pg 134
Fig. 4.14 (b) )
Ab = Area of pile base
It should be noted that value of Qb at penetration depths of 20
diameters is taken as the peak value for ultimate end bearing
resistance but shall not exceed 100 tons/ft2.
4.2.2.2

In Cohesive Soil
For frictional resistance
Qs = Cu As

- (3) (Ref. 1 Pg. 123 Eqn. 4o5) ,

where
Qs = Ultimate skin resistance

= adhesion factor (taken - 1)

Cu = Average undisturbed undrained cohesion of


soil surrounding pile shaft
As = Area of shaft
For End-bearing resistance
Qs = No Cb Ab - (4)(Ref. 1 Pg. 122 Eqn. 4.2)

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 49

Pile Design Report

FOR INTERNAL USE ONLY

where
No = Bearing Capacity factor (taken = 9)
Cb = Undisturbed undrained cohesion of soil at pile
toe
Ab = Area of pile base
4.2.3 Recommendation
Scope of work done on S.I. were 6 Nos. JO -Probes and 3 Nos. Deep
Boring. On compilation of the results, the soil profile was generalized as
Table 2 : Generalized Soil Profile
Soil Type and Condition

Depth (m)
0-9

Loose sand and soft clay

9 - 13

M. Dense Silts and firm clay

> 13

Dense/V.Dense silts and


firm /stiff/v.stiff clays

follows:A piled foundation system was selected instead. of shallow foundation in


order to transfer the loads onto the stronger layers at the lower depths.
RC piles were chosen and- designed to be partly frictional and partly endr
bearing. Trids were done with 15" s 15", 12" z 12" and 10" = 10" RC
Pile size

Penetration

Working loads (Tons/pile)

Depth (m)

BH 1

BH 2

BH 3

15" x 15"

21.5

101

12" x 12"

20

69

37

42

21.5

70

40

52

16.5

32

28

31

19.5

42

26

31

10" x 10"

Table 3 : Summary of Analysis

piles. The results are summarised in the table below.


It should be noted that due. to the inconsistency of the soil variation of the
three boreholes done, the design was based on each individual borehole.
From the analysis done, it was decided to use a combined system of RC
piles driven to a depth of 2090m below formation level in order to opti
mise the cost of pile installation and prevent the problem of eccentricity
between columns and single pile foundation system during construction.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 50

Pile Design Report

FOR INTERNAL USE ONLY

Hence the recommended system is as follows:For the-loading range of


(a)
30T - 40T - Use 10" _ .10" RC pile with a working load of
20T/pile driven to a depth of 20m below forma
tion level.
(b)

4.3

40T - 70T

- Use a minimum of 2 Nose 12" = 12" piles with a


working load of 35T/pile driven to a depth of 20m
below formation level.

Settlement Analysis

In this particular project, the concern for settlement would be over


(a) settlement of the pile toe
(b) settlement of the sub-soil due 'to the surcharge weight of the fill material.
4-3.1

In the case of (a), settlement checks were not done as the piles are not totally fric
tional and generally the recommended foundation system would result in only 2
Nos* of piles to a . group. Furthermore, work done by X.Je Tomlinson have
shown that for piles of small to medium (up to 600mm) diameter the settlement
under the working load will not exceed 10mm or 3/8" if the safety factor is not
lower than 2.500..-00.00. (Ref- 1 Pg. 149)

4.3.2

Settlement. of tho sub-soil due to the surcharge weight of the fill material
4.3.2.1 Essumptions made
(a)
Soil layers with an SPT value of N48 were taken as compressible lay
ers
(b)

Depth of compressible layer = 12m,

(c)

Effective area of fill was approximated to be the same as the plan area
of the proposed Dewan Orang Ramai
i.e. B - 17m and L . 321x.

(d)

Depth of fill was not constant throughout the site. This is because the
original ground level is not the same over the intended site.
0.3m

Plane DB 2
qf2
DB 2

Plane DB 3

0.6m

qf3

Formation Level

DB 3

1m
O.G.L

qf1
DB 1

Fill Material
12m

Cawangan Jalan, Ibu Pejabat JKR, K.L

Compressible Layer

Page 51

Pile Design Report

FOR INTERNAL USE ONLY

Below is a schematic presentation of the fill depth and area.


(e)

The bulk density of the fill material was assumed to be 18 bulk

(f)

The borehole positions were taken as the points of consideration in


estimating the settlement of the soft layer due to the surcharge weight
of the fill, i.e. Points DB1,'DB2 and DB3

(g)

With regards to (e), the generalized surcharge weights over the'respeo


tive points in a plane orientation (see Fig. 1) areaPlane DB1; qf1 - 18 kN/m2
Plane DB2; qf2 - 6 kN,/m2
Plane DB3; qf3 - 12 kN/m2

(h)

The compressible soil was classified as type CL under the Casagrande


classification system

(i)

Liquid Limit of the soil was assumed to be 35%

(j)

Voids ratio assumed to be 0.7

(k)

The Compression Inde= Cc was obtained from the relationship cc o 0.009


(Lw - 10%)
where Lw = liquid limit-of the clay
(Eqn. 2.24 Ref. 3 Pg. 128)

4.3.2.2

Estimation of settlement
To obtain the average immediate _settlement the method of Janbu, Jerrum and
Kjaernsli was adopted where
Average settlement = p1 = U1 U1 of B ....(5)
E
U1 Uo are obtained from Refs 1 Pg. 180 Fig. 5.10
qf = net surcharge of the fill
B = width of fill area
E = Modulus of Elasticity of clay
Values of E were obtained from Ref. 1 Pg. 186 BU- 5 .17
For Consolidation Settlement, Terzaghils conventional 1-D consolidation theory
was used.
So = Co
1 t e,

Cawangan Jalan, Ibu Pejabat JKR, K.L

H. Log Po +z ......(6)
Po

Page 52

Pile Design Report

FOR INTERNAL USE ONLY

where,
Co = Compression Index
Eo = Initial voids ratio
H = Thickness of compressible layer (m)
Po = Effective overburden pressure (kN/m2)

z =

Value of vertical stress at depth considered (kN/m2)

Values of were obtained from

z = qfI o

.... (7) (Ref. 4 Pg. 223)

Where qf = surcharge of fill


Io = Influence factors obtained from Padumts Chart (Ref. 4 .Fgi 224 Fig.
7.2)
4.3.2.3

From the settlement analysis. done on the effect of the surcharge weight of the fill material, the following were obtained
settlement under plane DB1 - 92mm (3.6")
settlement under plane DB2 - 30am (1.2")
settlement under plane DB3 - 232 am (9")
(centre of fill)
Obviously, there is substantial total and differential settlement of the soft layer
due to the effect of the fill surcharge.
In the light. of this estimation, it is advisable to design a suspended floor for the
proposed structure and to use tie-beams (ground beams) for the foundation sys
tem (tied in two cUreotions) in order to have a more rigid structure.

4.4

Load Testing Requirement

4.4.1

2 nos. of load tests are recommended in accordance with JKt siandard


specificationsiUnit Malarial are to be advised of the date the loading
tests are to be done and copies of the results are to be cent to Unit
Makmal for purposes of monitoring and records.

4.4.2

The test loadings should be done at least 4 weeks after the test piles are
driven, to fully mobilise frictional resistance between soil and pile
interface.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 53

Pile Design Report

FOR INTERNAL USE ONLY

4.5

Associated Designs

4.5.1

Requirements of fill material and its commotion Soil should be of suit


able selected fill material. The H.S. 1377 s 1972 method shall be used
as the standard compaction test for determining the moisture density
relationship of the soil. The selected material should have liquid limit
values less than 35 (LL 35) and values of plasticity index less than 55
(Pole L 55)-The -field density after compaction shall be determined in
accordance with the "Band Replacement Method" or AASHO T205-64
(Rubber Balloon Method). The fill shall be compacted to a density of
not less than 95% of the ma3d!m,m dry density as determined by the
Standard Compaction Test.
The type of compacting equipment to be used shall be subject to the
approval of the Superintending Officer.

4.5.2

Structural Recommendations
In order to deal with the expected settlement of the soft sub-soil due to
the surcharge of the fill material, it is advisable to design a suspended
floor system for the structure.
Further precautions should be taken in the form of tying the columns
in two-directions with ground beams so as to' haves. more rigid struc
ture.

5.

Conclusion
From the-analysis done based on assumptions laid down in Clause ~4.2.1, the recommen
dations are
i) For the load range of
30T - 40T Use 10'1 x 10" RC piles with a working load of 20T/pile
40T - 702'

Use a minimum of 2 Nos 12" x 12" piles with a working load of


35T/pile:

ii) The piles shall function as partly frictional and partly end-bearing.
iii) Piles are to be driven to set below the formation level
iv) Specify tender lengths to be 20m and an additional 10% should be added to the number
of piles specified in the BQ or summary of tender to cater for pile deviations during
driving.
v) Use suspended floor and tie beams are to be provided in two directions between the col
umn positions.
6.

Appendices
Appendix A : Location Plan
Appendix B :

Layout plan showing locations of site investigation

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 54

Pile Design Report

FOR INTERNAL USE ONLY

Appendix C :
7.

Generalized soil profile Borelog Results

Bibliography
Ref. 1
:

PILE DESIGN AND CONSTRUCTION PRACTICE M. J. TOAIIINSON


VIEWPOINT PUBLICATION

Ref. 2

MALAYSIAN SOILS AND ASSOCIATED PROBLEKS


- DR. 001 TECK AUN

Ref. 3

FOUNDATION RESIGN AND CONS'T'RUCTION


- M.J. TOMLINSON
PITMAN INTEMATIONAL TEXT 3rd Edition

Ref. 4

ELEMENT OF SOIL MECHANICS - G. N. SMITH


CROSBY LOW00D STAPLES 4th Edition
'

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 55

Cawangan Jalan, Ibu Pejabat JKR, K.L

33.05

28.5

22.5

13.5

9.0

6.0

4.0
5.0

Hard silty clayey


Basalt(Boulder)
Hard clayey silt
-32.1

-30.6

Hard clayey silt N=50

V.Stiff clayey silt N=35

Stiff clayey silt N=18

Firm silty clay N=8

Soft silty clay N=4

Med. dense silty sand N=21

Loose silty sand N=2

V.soft silty clay N=1

25.50

19.50

15.00

13.50

12.00

9.00

7.50

5.00
6.00

2.45
3.15

29.45

Med. dense to loose silty sand

Proposed Pile

Granite

V.dense silty sand N>50

Hard clayey silt N=40

Hard silty clay N=30

Stiff silty clay N=15

Firm silty clay N=7

Firm silty clay N=14

Firm silty clay N=5

Sofy sandy silt N=4

V.Loose silty sandy N=2

Loose silty sand N=2


V.soft silty clay N=2

V.soft silty clay N=0

V.Loose silty sandy N=2

-34.25

-21.6

28.70

27.00

18.00

18.00

4.50

2.00
3.00

Granite

Sandy silt N>50

Quartzite and decomposed granite

Hard clayey silt N>50

V.stiff clayey silt N=24

Stiff clayey silt N=15

Firm clayey silt N=4

V.loose silty sand N=1

Loose silty sand N=5

V.soft silty clay N=2

FOR INTERNAL USE ONLY

Pile Design Report

Page 56

FOR INTERNAL USE ONLY

Pile Design Report

Cadangan Syor asas untuk Projek Rumah


Kediaman Kelas 'G' Penjara Penor, Kuantan, Pahang.
1.

Introduction
The project site is located off the Pekan - Kuantan trunk road. From the site plan an earth
filling of 1' to 5' is proposed for the whole site. The project consists of construction of
6 Blocks of JKR Standard 5-storey Class G Quarters.

2.

Site Conditions
6 nos of boreholes were carried out to determine the subsoil conditions. The sub soil con
sists of soft silty clay with organic matters from ground level to 6m below ground level.
From 6m to 12m below ground level the soil consists of loose silty sand with decayed mat
ters and from 12m to 28m the soil is of loose to medium stiff sandy clay with SPT N aver
ages from 6 to 12. From 28m_to,36m the soil strata consists of dense sandy'silt with traces
of gravel. SPT N ranges from 18 to 50.

3.

Geotechnical Evaluation
Due to the 1' to 5' of fill, consolidation settlement may occur for the compressible layers of
soil. Hence negative skin friction on piles is to be accounted for.
12" x 12" r.c. piles are evaluated for the bearing capacities. It is found that the founding
depths of the piles varies from 28.5m to 36m.
The following table is abstracted from the calculations for which the estimated founding
depths Ultimate loads (Qu) and allowable loads (Qa) are tabulated. A factor of safety of 2.5
and negative skin friction of 16 tons are used in the calculations.
BH nos.
Estimated depths
Ultimate load
Allowable load
(m)
Qu (tons)
Qa = Qu/2.5 - Qn
1
33
197.54
65.59
2
31.5
178.65
55.03
3
28.5
166.84
50.31
4
28.5
183.87
57.12
5
36
208.56
67.00
6
35
204.62
65.42
From the above it is noted that the calculated bearing capacities of the 12" x 12" r.c. piles
ranges from 50.00 to 67 tons. Hence it is proposed that 12" x 12" JKR r.c: piles of Grade 40
concrete be used.
The allowable working load of the 12" x 12" JKR r.c. piles shall be 49 tons per pile.
Calculations for the geotechnical evaluations for the 6 boreholes are attached.

4.

Conclusion
12" x 12" JKR Standard R.C. piles grade 40 with tender length of 36m shall be used.
Allowable load per pile is 49 tons.The estimated negative friction load is 16 Ton per pile.
Hence the test load shall 2 x (49 + 16) = 130 Tons. At least 4 piles shall be selected for load
tests.
All piles are designed as end bearing piles. All piles shall be driven to set which can be
achieved at about 28.5m to 36m below ground level.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 57

Pile Design Report

FOR INTERNAL USE ONLY


Cadangan Kelas G, Penjara Penoh, Kuantan, Pahang.
Evaluation of 12 x 12 reinforced concrete pile.
Borehole 1
Depth
(m)

Soil Description

Top soi l, soft


clayey silt

1.5

Loose clayey silt

Ditto

4.5
6

S.P.T
(Na)

Fs

Ap
(ft)

Qs
(Tons)

Qs
(tons)

Fb

Ab
(sq ft)

Qb (tons)

Qu
(tons)

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Loose clayey silt

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

7.5

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

10.5

Soft silty clay,


traces of sand

0.00

0.00

0.00

0.00

0.00

0.00

12

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

13.5

Ditto

2.5

0.05

0.98

0.98

20

20.00

20.98

8.39

15

Stiff silty clay,


traces of sand

5.5

0.11

2.16

3.15

24

24.00

27.15

10.86

16.5

Ditto

0.14

2.76

5.90

32

32.00

37.90

15.16

Qa
(tons)

18

Ditto

7.5

0.15

2.95

8.86

28

28.00

36.86

14.74

19.5

Ditto

0.14

2.76

11.61

28

28.00

39.61

15.84

21

Ditto

6.5

0.13

2.56

14.17

24

24.00

38.17

15.27

22.5

Ditto

7.5

0.15

2.95

17.12

36

36.00

53.12

21.25

24

Ditto

18

13.5

0.27

5.31

22.44

72

72.00

94.44

37.77

25.5

Ditto

16

17

0.34

6.69

29.13

64

64.00

93.13

37.25

27

Ditto

30

23

0.46

9.05

38.18

120

120.00

158.18

63.27

28.5

Dense silty sandy


gravel

25

27.5

0.55

10.82

49.00

100

100.00

149.00

59.60

30

Ditto

24

24.5

0.49

9.64

58.65

96

96.00

154.65

61.86

31.5

Ditto

21

22.5

0.45

8.86

67.50

84

84.00

151.50

60.60

33***
*

Ditto

30

25.5

0.51

10.04

77.54

120

120.00

197.54

79.02

34.5

Ditto

50

40

0.80

15.74

93.28

200

200.00

293.28

117.31

36

Ditto

50

50

1.00

19.68

112.96

200

200.00

312.96

125.19

To calc. negative skin friction (Qn)


Qn = fn x As, where fn = 0.25 x Po /2
Po = (110 -62.5) x H x 3.28, where H = 12m =
Qn = 0.25 x Po /2 x As x H x 3.28/2240

1869.6

Allowable load Qa = (Qu/2.5 Qn) =

79.02

16.43

62.59

*** from borelog N = 50, use N = 3D only

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 58

Pile Design Report

FOR INTERNAL USE ONLY

Cadangan Kelas G, Penjara Penoh, Kuantan, Pahang.


Evaluation of 12 x 12 reinforced concrete pile.
Borehole 2
Fs

Ap
(ft)

Qs
(Tons)

Qs
(tons)

Fb

Ab
(sq ft)

Qb
(tons)

Qu
(tons)

Qa
(tons)

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Depth
(m)

Soil Description

Top soi l, soft


clayey silt

1.5

Loose clayey silt

S.P.T
(Na)

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

4.5

Loose clayey silt

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

7.5

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

10.5

Soft silty clay,


traces of sand

0.00

0.00

0.00

0.00

0.00

0.00

12

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

13.5

Ditto

0.04

0.79

0.79

16

16.00

16.79

6.71

15

Stiff silty clay,


traces of sand

11

7.5

0.15

2.95

3.74

44

44.00

47.74

19.10

16.5

Ditto

12

11.5

0.23

4.53

8.27

48

48.00

56.27

22.51

18

Ditto

9.5

0.19

3.74

12.00

28

28.00

40.00

16.00

19.5

Ditto

0.12

2.36

14.37

20

20.00

34.37

13.75

21

Ditto

4.5

0.09

1.77

16.14

16

16.00

32.14

12.86

22.5

Ditto

0.10

1.97

18.11

24

24.00

42.11

16.84

24

Ditto

0.12

2.36

20.47

24

24.00

44.47

17.79

25.5

Ditto

5.5

0.11

2.16

22.63

20

20.00

42.63

17.05

27

Ditto

24

14.5

0.29

5.71

28.34

96

96.00

124.34

49.74

28.5

Dense silty sandy


gravel

26

25

0.50

9.84

38.18

104

104.00

142.18

56.87

30

Ditto

24

25

0.50

9.84

48.02

96

96.00

144.02

57.61

31.5

Ditto

30

27

0.54

10.63

58.65

120

120.00

178.65

71.46

33****

Ditto

50

40

0.80

15.74

74.39

200

200.00

274.39

109.76

34.5

Ditto

50

50

1.00

19.68

94.07

200

200.00

294.07

117.63

36

Ditto

50

50

1.00

19.68

113.75

200

200.00

313.75

125.50

To calc. negative skin friction (Qn)


Qn = fn x As, where fn = 0.25 x Po /2
Po = (110 -62.5) x H x 3.28, where H = 12m = 1869.6
Qn = 0.25 x Po /2 x As x H x 3.28/2240
Allowable load Qa = (Qu/2.5 Qn) =

71.46

16.43

55.03

*** from borelog N = 50, use N = 3D only

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 59

Pile Design Report

FOR INTERNAL USE ONLY


Cadangan Kelas G, Penjara Penoh, Kuantan, Pahang.
Evaluation of 12 x 12 reinforced concrete pile.
Borehole 3
S.P.T

Depth
(m)

Soil Description

0
1.5

Fs

Ap
(ft
)

Qs
(Tons)

Qs
(tons)

Fb

Ab
(sq ft)

Qb
(tons)

Qu
(tons)

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

(Na)

Top soil , soft clayey


silt

Loose clayey silt

Qa
(tons)

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

4.5

Loose clayey s and

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

7.5

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

10.5

Soft silty clay, traces


of sand

0.00

0.00

0.00

0.00

0.00

0.00

12

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

13.5

Ditto

0.08

1.57

1.57

32

32.00

33.57

13.43

15

Stiff silty clay, traces


of sand

8.5

0.17

3.35

4.92

36

36.00

40.92

16.37

16.5

Ditto

12

10.5

0.21

4.13

9.05

48

48.00

57.05

22.82

18

Ditto

10.5

0.21

4.13

13.19

36

36.00

49.19

19.67

19.5

Ditto

11

10

0.20

3.94

17.12

44

44.00

61.12

24.45

21

Ditto

9.5

0.19

3.74

20.86

32

32.00

52.86

21.14

22.5

Ditto

0.14

2.76

23.62

24

24.00

47.62

19.05

24

Ditto

5.5

0.11

2.16

25.78

20

20.00

45.78

18.31

25.5

Ditto

5.5

0.11

2.16

27.95

24

24.00

51.95

20.78

27

Ditto

30

18

0.36

7.08

35.03

120

120.00

155.03

62.01

28.5

Dense silty sandy


gravel

30

30

0.60

11.81

46.84

120

120.00

166.84

66.74

30

Ditto

50

40

0.80

15.74

62.58

200

200.00

262.58

105.03

31.5

Ditto

50

50

1.00

19.68

82.26

200

200.00

282.26

112.90

33

Ditto

50

50

1.00

19.68

101.94

200

200.00

301.94

120.78

34.5

Ditto

50

50

1.00

19.68

121.62

200

200.00

321.62

128.65

36

Ditto

50

50

1.00

19.68

141.30

200

200.00

341.3 0

136.52

To calc. negative skin friction (Qn)


Qn = fn x As, where fn = 0.25 x Po /2
Po = (110 -62.5) x H x 3.28, where H = 12m = 1869.6
Qn = 0.25 x Po /2 x As x H x 3.28/2240
Allowable load Qa = (Qu/2.5 Qn) =

66.74

16.43

50.31

*** from borelog N = 50, use N = 3D only ddedit

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 60

Pile Design Report

FOR INTERNAL USE ONLY


Cadangan Kelas G, Penjara Penoh, Kuantan, Pahang.
Evaluation of 12 x 12 reinforced concrete pile.
Borehole 4
Depth
(m)

Soil Description

Top soil , soft


clayey silt

1.5

Loose clayey silt

S.P.T
(Na)

Fs

Ap
(ft)

Qs
(Tons)

Qs
(tons)

Fb

Ab
(sq ft)

Qb
(tons)

Qu
(tons)

Qa
(tons)

4.5

0.08

1.51

1.51

36

36.00

37.51

15.00

Ditto

15

12

0.20

4.01

5.52

60

60.00

65.52

26.21

4.5

Loose clayey
sand

11

0.19

3.68

9.20

28

28.00

37.20

14.88

Ditto

0.09

1.67

10.87

12

12.00

22.87

9.15

7.5

Ditto

3.5

0.06

1.17

12.04

16

16.00

28.04

11.22

Ditto

0.00

0.67

12.71

0.00

12.71

5.09

10.5

Soft silty clay,


traces of sand

0.03

0.00

12.71

0.00

12.71

5.09

12

Ditto

2.5

0.00

0.84

13.55

20

20.00

33.55

13.42

13.5

Ditto

5.5

0.04

1.84

15.39

24

24.00

39.39

15.76

15

Stiff silty clay,


traces of sand

0.09

2.01

17.40

24

24.00

41.40

16.56

16.5

Ditto

0.10

2.34

19.74

32

32.00

51.74

20.70

18

Ditto

0.12

2.34

22.08

24

24.00

46.08

18.43

19.5

Ditto

10

0.12

2.68

24.76

40

40.00

64.76

25.90

21

Ditto

11

10.5

0.14

3.51

28.27

44

44.00

72.27

28.91

22.5

Ditto

10

10.5

0.18

3.51

31.78

40

40.00

71.78

28.71

24

Ditto

0.18

3.01

34.79

32

32.00

66.79

26.72

25.5

Ditto

0.15

2.68

37.47

32

32.00

69.47

27.79

27

Ditto

35

21.5

0.14

7.19

44.66

140

140.00

184.66

73.87

28.5

Dense silty sandy


gravel

32

33.5

0.37

11.21

55.87

128

128.00

183.87

73.55

30

Ditto

50

41

0.57

13.72

69.59

200

200.00

269.59

107.84

31.5

Ditto

50

50

0.70

16.73

86.32

200

200.00

286.32

114.53

33

Ditto

50

50

0.85

16.73

103.04

200

200.00

303.04

121.22

34.5

Ditto

50

50

0.85

16.73

119.77

200

200.00

319.77

127.91

36

Ditto

50

50

0.85

16.73

136.50

200

200.00

336.50

134.60

To calc. negative skin friction (Qn)


Qn = fn x As, where fn = 0.25 x Po /2
Po = (110 -62.5) x H x 3.28, where H = 12m = 1869.6
Qn = 0.25 x Po /2 x As x H x 3.28/2240
Allowable load Qa = (Qu/2.5 Qn) =

73.55

16.43

57.12

*** from borelog N = 50, use N = 3D only

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 61

Pile Design Report

FOR INTERNAL USE ONLY


Cadangan Kelas G, Penjara Penoh, Kuantan, Pahang.
Evaluation of 12 x 12 reinforced concrete pile.
Borehole 5
Depth
(m)

Soil Description

Top soil , soft


clayey silt

1.5

Loose clayey silt

S.P.T
(Na)

Fs

Ap
(ft)

Qs
(Tons)

Qs
(tons)

Fb

Ab
(sq ft)

Qb
(tons)

Qu
(tons)

Qa
(tons)

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

4.5

Loose clayey
sand

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

7.5

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

10.5

Soft silty clay,


traces of sand

0.00

0.00

0.00

0.00

0.00

0.00

12

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

13.5

Ditto

0.08

1.57

1.57

32

32.00

33.57

13.43

15

Stiff silty clay,


traces of sand

7.5

0.15

2.95

4.53

28

28.00

32.53

13.01

16.5

Ditto

6.5

0.13

2.56

7.08

24

24.00

31.08

12.43

18

Ditto

0.12

2.36

9.45

24

24.00

33.45

13.38

19.5

Ditto

6.5

0.13

2.56

12.00

28

28.00

40.00

16.00

21

Ditto

6.5

0.13

2.56

14.56

24

24.00

38.56

15.43

22.5

Ditto

0.12

2.36

16.92

24

24.00

40.92

16.37

24

Ditto

10

0.16

3.15

20.07

40

40.00

60.07

24.03

25.5

Ditto

13

11.5

0.23

4.53

24.60

52

52.00

76.60

30.64

27

Ditto

28

20.5

0.41

8.07

32.67

112

112.00

144.67

57.87

28.5

Dense silty sandy


gravel

32

30

0.60

11.81

44.48

128

128.00

172.48

68.99

30

Ditto

18

25

0.50

9.84

54.32

72

72.00

126.32

50.53

31.5

Ditto

22

20

0.40

7.87

62.19

88

88.00

150.19

60.08

33

Ditto

20

21

0.42

8.27

70.45

80

80.00

150.45

60.18

34.5

Ditto

21

20.5

0.41

8.07

78.52

84

84.00

162.52

65.01

36

Ditto

30

25.5

0.51

10.04

88.56

120

120.00

208.56

83.42

To calc. negative skin friction (Qn )


Qn = fn x As, where fn = 0.25 x Po /2
Po = (110 -62.5) x H x 3.28, where H = 12m = 1869.6
Qn = 0.25 x Po /2 x As x H x 3.28/2240
Allowable load Qa = (Qu/2.5 Qn) =

83.42

16.43

67 .00

*** from borelog N = 50, use N = 3D on ly

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 62

Pile Design Report

FOR INTERNAL USE ONLY


Cadangan Kelas G, Penjara Penoh, Kuantan, Pahang.
Evaluation of 12 x 12 reinforced concrete pile.
Borehole 6
Depth
(m)

Soil Description

Top soi l, soft


clayey silt

1.5

Loose clayey silt

S.P.T
(Na)

Fs

Ap
(ft)

Qs
(Tons)

Qs
(tons)

Fb

Ab
(sq ft)

Qb
(tons)

Qu
(tons)

Qa
(tons)

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

4.5

Loose clayey
sand

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

7.5

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

10.5

Soft silty clay,


traces of sand

0.00

0.00

0.00

0.00

0.00

0.00

12

Ditto

0.00

0.00

0.00

0.00

0.00

0.00

13.5

Ditto

10

0.10

1.97

1.97

40

40.00

41.97

16.79

15

Stiff silty clay,


traces of sand

8.5

0.17

3.35

5.31

28

28.00

33.31

13.33

16.5

Ditto

6.5

0.13

2.56

7.87

24

24.00

31.87

12.75

18

Ditto

6.5

0.13

2.56

10.43

28

28.00

38.43

15.37

19.5

Ditto

0.12

2.36

12.79

20

20.00

32.79

13.12

21

Ditto

4.5

0.09

1.77

14.56

16

16.00

30.56

12.23

22.5

Ditto

4.5

0.09

1.77

16.33

20

20.00

36.33

14.53

24

Ditto

11

0.16

3.15

19.48

44

44.00

63.48

25.39

25.5

Ditto

15

13

0.26

5.12

24.60

60

60.00

84.60

33.84

27

Ditto

27

21

0.42

8.27

32.87

108

108.00

140.87

56.35

28.5

Dense silty sandy


gravel

26

26.5

0.53

10.43

43.30

104

104.00

147.30

58.92

30

Ditto

16

21

0.42

8.27

51.56

64

64.00

115.56

46.22

31.5

Ditto

20

18

0.36

7.08

58.65

80

80.00

138.65

55.46

33

Ditto

18

19

0.38

7.48

66.12

72

72.00

138.12

55.25

34.5

Ditto

23

20.5

0.41

8.07

74.19

92

92.00

166.19

66.48

36

Ditto

30

26.5

0.53

10.43

84.62

120

120.00

204.62

81.85

To calc. negative skin friction (Qn)


Qn = fn x As, where fn = 0.25 x Po /2
Po = (110 -62.5) x H x 3.28, where H = 12m = 1869.6
Qn = 0.25 x Po /2 x As x H x 3.28/2240
Allowable load Qa = (Qu/2.5 Qn) =

81.85

16.43

65.42

*** from borelog N = 50, use N = 3D only

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 63

Pile Design Report

FOR INTERNAL USE ONLY

Design Calculations of Bored Piles


& Pile Caps for Proposed SK
Taman Segar Cheras
1.

Introduction
The project consists of construction of 2 blocks. of 4-storey JKR Std. School buildings. The
site is generally flat with about 2m fill some 5 years ago. The generalized subsoil proper
ties are as follows:0 - 12m
:
loose clayey sand with localized very dense layer. Average SPT, N = 5.
12m - 17m :

medium to dense silty clayey sand, N = 16

17m - 27m :

very dense grey spotted yellowish fine to coarse silty sand with gravel
(N = 40 - 50). Water table 15m bgl.

No of colums per block is 44 and the columnload is about 78 Ton (max.)


Due to presence of localized very. dense cemented clayey sand with gravels at shallow
depth, very hard driving will encountered at shallow depth if driven piles are used.
Bored piles are considered more cost effective piling system in this case when compared
with other suitable piling system such as H piles (R.C. piles are Not suitable). Though the
site consists of sandy soil, the bored piles are considered suitable because water.table is low
and the residual soil is usually quite impermeable.
2.

Design Calculations
460mm diameter bored piles are proposed.
2.1

Design Criteria

2.2

Concrete Grade 25 for piles & caps


Design compressive stress = 4.8N/mm sq.
< fcu/4.
Longitudinal reinf provided is 1.0% for full bored shaft, i.e. 6Y20 & R9
@ 300mm c/c as helical reinforcement.
Installation procedure according to JKR spec (KPKR 6/1989).
max design load = 80 Ton.
max test load = 2 X design load.

Geotechnical Capacity

Use modified Meyerhof s equation:


Ultimate capacity, Qu = N1 As + K2 Ab
K1
K2
Where

N1
K1
K2
N2
As
Ab

Cawangan Jalan, Ibu Pejabat JKR, K.L

=
=
=
=

average SPT value for shaft


50
1
average SPT valug at base
= surface area(ft2)
= base area (ft2)
Page 64

Pile Design Report

FOR INTERNAL USE ONLY

Generalised Design SPT

0 - 17m, average SPT = 8


17m - 24m,average SPT = 40
Average SPT @ 24M = 50
.'. Total ultimate frictional resistance
Qs- Spx52x1.5xi1 +540 0 x22 x1.5xi1
= 39.2 + 82.9
= 122.1 Ton
Total ultimate end bearing
Qb = 50 x 1.52 x 11 /4 = 88.3 Ton
:. Qu =12.2.1+88.3 = 210.4 Ton
.'. Safe load Qa = 210.4/2.5 = 84.1 Ton
Say 80 Ton per bored pile (18" diam x 24m)
3.

Pilecap Design
Single Pilecap for Pile Diameter 460mm (18" Diam x 24m Bored Pile)

No. of Pile
Pile Diameter

=
1
= 460mm

Size of Pilecap

= 660 x 660 x 900mm

Steel Reinforcement

Main Bars
= 0.15% x b x d = 792mm2
.. Provide 4 Y 16 Bothways
Horizontal Links
.: Provide 3 Y 10

= 0.25% OF Main Steel Area = 100mm2

Quantities Per Cap

Excavation
Volume of Concrete

= 0.41 m3
= 0.39 m3

WT. of Reinforcement = 26.6 kg. (Y 16)


= 4.8 kg. (Y 10)
Lean Concrete
= .44 m2
Formwork
= 2.38 m2
Steel Content

= 134 lb/yd3

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 65

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 66

FOR INTERNAL USE ONLY

Pile Design Report

LAPORAN GEOTEKNIK
MAKTAB PER GUR UAN SRI PIN ANG ,
BUKIT MIER TAJAM,
SEBERANG PERA1,
PULAU PIN ANG

DISEDIAKAH OLEH :
IR. ANNIES MD. ARIFF
EH. AHMAD AZLAN AHMAD
(INSTITUT LATIHAN & PENYELIDIKAN JKR)
Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 67

Pile Design Report

FOR INTERNAL USE ONLY

Pendahuluan
Laporan ini adalah 'bertujuan untuk menyampaikan keterangan ringkas sumbangan yang
telah diberi oleh Pusat ini di dalam menentukan
pemilihan asas-asas yang sesuai bagi bangunan-bangunan yang dicadangkan untuk projek
yang disebut di atas. Sumbangan ini. adalah
bersesuaian dengan peranan utama pusat ini
sebagai satu organisasi.sokongan kepada semua
cawangan di dalam JKR dalam hal- hal yang
bersangkut-paut dengan bidang geoteknikal.
Laporan ini akan' ketengahkan juga masalahmasalah parancangan yang dihadapi semasa
pusat ini menjalankan kerja penyiasatan -tapak
dan kerja merekabentuk asas yang sesuai bagi
bangunan bangunan yang terlibat
Bagi 'projek ini permintaan untuk menjalankan
penyiasatan tapak dan seterusnya'pen gesyoran
syor-syor asas telah dikemukakan oleh
Cawangan Kerja Pendidikan melalui surat
PKR(KP)MP/PP/87/17(102) bertarikh
27/02/1989.
Skop Projek
Pelaksanaan projek ini melibatkan pembinaan
32 bush bangunan dengan ketinggian bangunan-bangunan di antara 1-tingkat hingga 4tingkat. Lingkungan beban-beban tiang pula
adalah dari serendah-rendah 50.0 kN sehingga
setinggi 1800.0 kN. Penyediaan tapak melibatkan kerja-kerja pemotongan se dalam di
antara 0.0 hingga 6.Om dan penimbusan setinggi di antara 0.0 hingga 6.0m.
Butiran bangunan mengikut bilangan tingkat
adalah seperti berikut:1-tingkat
- 16 unit
2-tingkat
- 7 unit
4-tingkat
- 8 unit
Tangki Air - 1 unit
Skop Penyiasatan Tapak/Tanah
Berpandukan lukisan punca tatatur yang dikemukakan, satu skop kerja penyiasatan tapak,
berupa 33 bil. ujian gerekan dalam, 3 bil. ujian
gerimit tangan dan 89 bil. ujian proba
Mckintosh, telah dirancangkan. Perancangan

Cawangan Jalan, Ibu Pejabat JKR, K.L

skop kerja penyiasatan tersebut dibuat


mengambilkira faktor-faktor berikut:i) Jenis bangunan serta beban-beban tiang yang
terlibat,
ii) Kegunaan bangunan,
iii) Ciri-ciri geology kawasan,
iv) Keadaan kawasan tapak,
v) Kerja-kerja tanah - potongan dan penimbu
san.
Selain dari perancangan skop kerja penyiasatan
kedudukan lokasi ujian-ujian juga dibuat dengan mengambilkira faktor-faktor yang disebutkan di atas.
Adalah dimaklumkan bahawa perkara (v) di
atas hanya dapat dibuat andaian sahaja semasa
perancangan skop penyiasatan tapak kerana
paras formasi tidak dinyatakan di dalam lukisan tatatur tersebut.
Oleh kerana projek ini telah dikelaskan sebagai
projek SEGERA dan memandangkan beban
kerja semasa unit penyiasatan tapak pusat ini
pada masa itu adalah terlalu banyak maka
keputusan telah dibuat supaya kerja-kerja
penyiasatan tapak ini dijalankan secara kontrak.
Juga bagi menjimatkan masa telah dipersetujui
bahawa tender kerja ini dilakukan secara lantikan terus. Kontraktor yang telah dilantik'
untuk menjalankan kerja-kerja ini adalah
Sekata Bina Sdn. Bhd. dengan kos kontrak
kerja terhad tidak melebihi $50,000-00.
Oleh yang demikian, kawalan kos yang ketat
telah dilakukan semasa kerja-.kerja penyiasatan
sedan& dijalankan bagi memastikan kos
keseluruhan kontrak ini tidak melebihi
$50,000-00.
Keputusan Penyiasatan Tapak
Berpandukan kepada peta Hydrogeologi
Semenanjung Malaysia tapak projek ini, iaitu
daerah Bukit Mertajam, adalah terletak di atas
formasi batu GRANIT yang diselubungi oleh
tanah jenis KELODAK/BERLIAT. Ini adalah
Page 68

FOR INTERNAL USE ONLY

berpadanan dengan keputusan penyiasatan


tapak/tanah yang diperolehi di mana tanah
bawahan adalah jenis tanah LIAT/KELODAK
dan berpasir. Tanah adalah dalam keadaan
sederhana kental hingga sangat kental di antara
paras dalaman 0.0 hingga 35.0m, dan keras
sehingga sangat keras pada -dalaman lebih dari
18.0m.
Kedudukan paras air bawah tanah semasa kerja
penyiasatan dijalankan (bulan Mac, 1989)
adalah di antara 1.55m hingga kering.
Rekabentuk Syor Asas
Pada amnya pemilihan jenis sistem asas adalah
berdasarkan kepada faktor-faktor berikut:a) kemampuan tanah bawahan menanggung
beban yang akan ditanggung berdasarkan
keupayaan galas yang dibenarkan yang '
dikira bersesuaian dengan keadaan tanah
bawahan dan juga ciri-ciri geologi
kawasan.
b) beban tiang dan jarak antara tiang
c) faktor keselamatan terhadap kegagalan dan
enapan yang dapat diterima pada beban
kerja struktur bagi memenuhi kehendak
'servicibilty limit state'
d) Kawalan mutu semasa pembinaan

Pile Design Report


tusan ujian-ujian tanah yang dibuat ditempat
kedudukan atau berdekatan dengan bangunan
yang terlibat. Walaubagaimanapun disebabkan
pindaan ke atas pelan punca projek ini, di mana
lokasi kebanyakan bangunan telah dialihkan,
maka terdapat bebarap ujian gerekan dalam
berada diluar kawasan tapak bangunan, malahan terdapat juga beberapa bangunan yang
tidak ada sebarang ujian penyiasatan tapak
dijalankan. Dalam hal demikian, pusat ini telah
membuat ekstrapolasi kepada keputusan-keputusan ujian tanah yang paling berdekatan dengan bangunan yang tiada sebarang ujian tanah,
dan mengunakan maklumat tersebut berserta
pengetahuan geologi kawasan bagi membuat
penganalisa geoteknik.
Berpandukan faktor-faktor di atas dan juga
keputusan penyiasatan tapak yang telah dibuat,
dua (2) jenis sistem asas telah direkabentuk
bagi projek ini. Dua (2) jenis sistem asas yang
dimaksudkan itu ialah asas penapak konkrit
dan alas cerucuk. Bagi sistem asas cerucuk dua
jenis cerucuk telah direkabentuk iaitu cerucuk
konkrit tetulang dan cerucuk kayu berubat.
Bagi sistem asas cerucuk daya tanggung cerucuk-cerucuk yang direkabentuk adalah dari
separa geseran badan (frictional) dan separa
tangouno hujung (end bearing) dan faktor keselamatan yang telah digunakan di dalam perkiraan adalah.2.0 serta menggunakan kekuatan
tanah dalam lingkungan batasan rendah.

e) Jenis struktur
f) tapak timbusan atau potongan
g) ekonomik
Oleh yang demikian sebelum menentukan
sebarang sistem asas yang hendak digunakan,
faktor-faktor di atas perlu diteliti terlebih dahulu bagi setiap bangunan supaya satu sistem asas
yang sesuai dan ekonomik dapat ditentukan.
Perlu dinyatakan disini bahawa di dalam hal
membuat perkiraan rekabentuk geoteknik
adalah mustahak ciri-ciri jenis tanah serta butiran kekuatan tanah-tanah yang dipilih di dalam
perkiraan rekabentuk diperolehi daripada kepuCawangan Jalan, Ibu Pejabat JKR, K.L

Apa yang dimaksudkan dengan geseran badan


ialah beban yang ditanggung oleh cerucuk
berkenaan akan dipindahkan ke tanah melalui
rintangan geseran (frictional resistance) di
antara permukaan badan cerucuk dan tanah,
dan ini akan hanya terjadi sekiranya cerucul:
tersebut mengalami mendapan lebih dari mendapan tanah (relative settlement of pile is
greater than that of the soil). Maksud tanggung
hujung pula ialah beban yang ditanggung oleh
cerucuk akan dipindahkan ke tanah melalui
penghujung cerucuk (base of pile).
Contoh-contoh perkiraan rekabentuk kedua-dua
jenis sistem, asas ada seperti di dalam lampiran-lampiran 'A' dan 'B'.
Page 69

FOR INTERNAL USE ONLY

Pile Design Report

Bagi bangunan-bangunan yang mana telah


disyorkan lantai gantung keputusan-ini adalah
berdasarkan kepada beberapa faktor yang mana
adalah seperti di bawah:a) timbusan Yang akan dilakukan adalah ter
lalu tinggi,
b) Kegunaan bangunan.
Contoh perkiraan anggaran enapan tanah timbusan adalah seperti di dalam -Lampiran 'E'.
Senarai Lampiran

Lampiran 'A' - CONTOH PERKIRAAN


REKABENTUK GEOT
EKNIK BAGI CERU
CUK KONKRIT TETU
LANG
Lampiran 'B' - CONTOH PERKIRAAN
REKABENTUK GEOT
EKNIK BAGI PENAPAK
Lampiran 'C' -

SURAT SYOR ASAS


YANG TELAH DIKE
MUKAKAN KEPADA
CAW. KERJA PEN
DIDIKAN

Lampiran 'D'-

LAPURAN PENYIASA
TAN TAPAK YANG
TELAH DIJALANKAN

Lampiran 'E' - CONTOH PERKIRAAN


ANGGARAN ENAPAN
TANAH TIMBUSAN

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 70

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran 'A'

Pile Foundation Design for Administration Blocks (4-Storey)


Northern Block :

F.F.L. = 16.0m;

Fill = 0.5 to 1.0m

Central Block

F.F.L. = 17.5m;

Fill = 0.0 to 1.5m


Cut = 0.0 to 1.0m

Southern Block :

F.F.L. = 19.0m;

Fill = 0.0 to 2.0m


Cut = 0.0 to 1.5m

Column Load

755.OkN (83 numbers); 700.OkN (83 numbers)

Deep Boring

DB/3, DB/4 and DB/G (Refer sketch attached)

Shaft Resistance Formulae


a) CLAY

Q =

*Cu*A. where = adhesion factor


Cu = undisturbed undrained cohesion '
A. = surface area of pile

b) SILT

Q = N/60*A. where N = Standard Penetration Test

c) SAND

Q. = N/50*A.

Base Resistance Formulae:


a) CLAYQb, =
N*Ab where Ab = base area of pile
b) SILT

2. 5iN*Ab

c) SAND Qb,

4N*Ab

Design Analysis
Adopt DB/4 since worst case and assume.height of fill = 2.0m Try R.C. Pile of size B" x B"
Shaft Resistance
For depth 0 - 2.0m b. F. F. L. : FILL
For depth 2 - 5.0m ; CLAY ; assume N = 13
take Cu = 82.0 kN/m2 (Terzaghi)

adopt

= 1.0 (Tomlinson)
= 0.4 (McClalland)

= 0.7
Q = 0.7*82.0*4*B*3.0
39.37*9.81

= 1.783B tonnes

For depth 5 - 9.0m : SAND ; assume N = 7


Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 71

Pile Design Report

FOR INTERNAL USE ONLY

Q. = 7*4*B*4.0*3.281
50* 12

= 0.612B tonnes

For depth 9 - 11.0m: SILT ; assume N = 6


Q. = 6*4*B*2.0*3.281
60*12

= 0.219B tonnes

For depth 11 - 18.0m: CLAY ; assume N = 13


take = 82.0 kN/m2 a. = 0. 65
= 3.864B tonnes

Q = 0.65*82.0*4*B*7.0
39.37*9.81
Q

= 6.478B tonnes

Base Resistance
At depth 21.Om b.F.F.L. take N = 13 and since proportion of SAND is quite high (> 30%) adopt
Qb = 2.0*N*Ab (i.e. between CLAY & SILT).
Qb = 2.0*13*B*B = 0.130B2
144
Ultimate Resistance Qa

If B = 12 inches;

= Qp + Qb
= G.478B-+ 0.180B2

Q, = 77.7 + 26.0 = 103.7 tonnes

Take overall Factor of Safety = 2.0


Allowable Resistance Q11, = 103.7/2.0 = 51.8 tonnes (say 52.0)
To allow for erratic nature of underlying soil and also as per para 3.0 of report allow for '15%
increase.
Hence adopt 12" x 12" R.C.Piles @ 21.0m with Q~,s = 450.0 kH/pile
Although the bulk of the carrying capacity of pile is mainly frictional set might be achieved before
depth design.
Hence set readings to be taken during driving and if set not achieve drive to design depth.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 72

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 73

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran `B'

Shallow Foundation Design For Pre-School Block (1-Storey)


Proposed F.F.L. = 26.0m; Cut = 4.5 to 5.0m
Column Load

128.OkN (22 numbers); 167.OkN (23 numbers)

Deep Boring DB/14-(R.L. = 30.74m)


At depth 1.Om b. F. F. L. take N *= 9 ( lower bound) and at this depth soil is COHESIVE (silty
CLAY),
Try pad footing of size B (m) x L -(m) @ depth 1.0m b.F.F.L.
From NAVFAC DM-7.2;
q*No*(1+0.08/L) + (D

where c = undrained cohesion


Na = bearing capacity factor
D = depth of footing
below original grd. level.

= bulk density of soil

Take c = 55.0 kn/m2. Assume 0 = 0 and (=18..0 kN/m3


Consider case when ground water table is 1.0m b.F.F.L.
Therefore for square footing, B/L = 1, and for 0 = 0, Na = 5.53
55.0*5.53*1.3 + 18.0*5.74
= 395.4 + 103.3
= 498.7 kN/mz
Adopt Factor of Safety = 3.0
q~ " = 498.7/3.0 = 166.2 kN/mx (say 166.0)
If ignoring depth contribution i.e. XD,
q"lro = 395.4 kN/mz
Applying same F.o.S.; gall = 131.8 kN/mz
Therefore adopt square footing with gall = 94.0 kN/mo (2000 p.s.f.) 0 1.0m b.F.F.L. (i.e. to follow
standard drawing).

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 74

FOR INTERNAL USE ONLY

Pile Design Report

Lampiran C

( )dlm. PKR.RPM.
85/ 173/GO5/03
30hb. Jun. 1989
Pengarah,
Cawangan Kerja Pendidikan,
Ibu Pejabat JKR,
Jalan Sultan Salahuddin,
50582 KUALA LUMPUR.(u.p: Ir. Lam Yok Lon)
Tuan,
Perkara : CadanganMaktab Perguruan Sri Pinang, Bukit Mertajam, Pulau Pinang.
Merujuk perkara di atas dengan segala hormatnya disampaikan keputusan penyiasatan tapak dan
syor-syor asas untuk tindakan tuan selanjutnya.
2.0

Selaras dengan penguatkuasaan surat pekeliling KPKR 2/88, sistem cerucuk alternatif oleh
pentender boleh diterima.

3.0

Dimaklumkan juga bahawa seperti perbincangan yang telah diadakan dengan pegawai tuan
Ir. Lam Yok Lon pada 15/06/1989, pusat ini bersetuju bahawa kos anggaran asas bagi pro
jek ini ditambah lebih kurang 15% atas sebab desakan untuk melaksanakan projek ini
secepat mungkin. Pertambahan ini adalah untuk menyesuaikan perkara yang mungkin be
rlaku semasa pembinaan atas langkah-langkah yang dibuat semasa perancangan untuk
menyingkatkan tempoh masa perancangan dan rekabentuk seperti berikut:a)

Penyiasatan tapak telah dilakukan secara 'appointed - contractor' dan dengan ini kos
kontrak tidak boleh melebihi $50,000.00. Ini telah menghadkan skop penyiasatan
tapak yang perlu dijalankan.

b)

Lokasi-lokasi bangunan telah diubah daripada lokasi cadangan asal yang mengaki
batkan ada beberapa bangunan tidak terdapat ujian gerekan dalam dijalankan.

c)

Ketidak seragaman keadaan tanah bawahan ditapak projek ini yang mana masalah
(a) telah menyulitkan lagi keadaan ini. 4.0 Perlu dimaklumkan bahawa pusat ini
mendapati bahawa tidak terdapat apa-apa sistem perparitan yang telah disediakan
bagi projek ini. pleh yang demikian pihak tuan perlulah mengkaji akan hal ini dan
membuat pengesyoran yang sewajarnya.
Sekian, harap maklum
'BERKHIDMAT UNTUK HEGARA'
'CINTAILAH BAHASA KITA'
Saya yang menurut perintah,

( IR. NEON CHENG AIK )


Penolong Pengarah Kanan (Pusat Penyelidikan) b.p. Pengarah,
Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 75

Pile Design Report

FOR INTERNAL USE ONLY

Institut Latihan & Penyelidikan JKR, Jalan Serdang,43000 KAJANG, Selangor DarulEhsan.

Projek :

Cadangan Maktab Perguruan Sri Pinang,


Bukit Mertajam, Pulau Pinang.

1.0

Tujuan
Laporan ini adalah bertujuan untuk menyampaikan keputusan penyiasatan tapak dan syorsyor asas yang sesuai bagi projek di atas.

2.0

Skop Projek
Perlaksanaan projek ini akan melibatkan pembinaan blok-blok bangunan seperti yang tert
era di dalam lukisan pelan tatatur BKP 187/89/1 (PRE) A dan penyediaan tapak akan
melibatkan kerja-kerja pemotongan sedalam di antara 0.0 hingga b.Om dan penimbusan di
antara 0.0 hingga 5.0m.

3.0

Skop Kerja Penyiasatan


Dalam menialankan kerja-kerja penyiasatan, sebanyak 30 bil. ujian gerekan dalam, 85 bil.
ujian proba Mackintosh dan bil. ujian gerimit tangan telah dijalankan dan lot:asi-lokasi
ujian-ujian ini adalah berdasarkan kepada lukisan tatatur asal BKP 187/89/1(PRE). Kerjakerja penyiasatan tapat: ini telah dijalankan oleh Sekata Bina Sdn. Bhd. Disamping ujianujian di tapak, ujian-ujian makmal juga telah diIakukan ke atas contoh-contoh tanah yang
diperolehi bagi mengetahui jenis dan sifat-sifat tanah yang terdapat di tapak.

4.0

Syor-syor Asas

Keupayaan galas
yg. Dibenarkan
(kN/cerucuk)

Beban Ujian
(kN/cerucuk)

305 x 305
@ 21.0

450.0

900.0

Keupayaan
tanggung yg.
Dibenarkan
(kN/m 2)
-

"

305 x 305
@ 18.0

"

"

Penapak
Konkrit
Tetulang

95.0(2000 psf)
@ 1.5m b.F.L.
(JKR probes >
40 blows/foot).

(A)

"

"

(B)

"

71.0 (1500 psf)


@ 1.5m b.o.g.l.
(JKR probes >
40 blows/foot).

"

71.0 (1500 psf)


@ 1.5m b.F.L.
(JKR probes >
30 blows/foot) .

Jenis
Bangunan

Jenis
Asas

Saiz &
Panjang

Cerucuk
Konkrit
Tetulang

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 76

Pile Design Report

FOR INTERNAL USE ONLY

(A)

Cerucuk
Kayu
Berubat

152 x 152
@ 9.0

100.0

200.0

(B)

Penapak
Konkrit
Tetulang

71.0 (1500 psf)


@ 1.5m b.F.L.
(JKR probes >
30 blows/foot).

"

71.0 (1500 psf)


@ 1.5m b.o.g.l.
(JKR probes >
40 blows/foot).

Cerucuk
Konkrit
Tetulang

305 x 305
@ 18.0

500.0

1000.0

"

"

"

"

Penapak
Konkrit
Tetulang

Cerucuk
Konkrit
Tetulang

305 x 305
@ 15.0

430.0

860.0

71.0 (1500 psf)


@ 1.5m b.o.g.l.
(JKR probes >
40 blows/foot).
-

Penapak
Konkrit
Tetulang

Cerucuk
Konkrit
Tetulang

254 x 254
@ 6.0

160.0

320.0

95.0 (2000 psf)


@ 1.5m b.F.L.
(JKR probes >
40 blows/foot).
-

"

305 x 305
@ 15.0

500.0

1000.0

Penapak
Konkrit
Tetulang

95.0 (2000 psf)


@ 1.5m b.F.L.
(JKR probes >
40 blows/foot).

"

"

"

"

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 77

Pile Design Report

FOR INTERNAL USE ONLY

U1

U2

(A)

Cerucuk
Konkrit
Tetulang

381 x 381
@ 18.0

650.0

1300.0

(C)

"

381 x 381
@ 18.0

650.0

1300.0

atau

"

305 x 305
@ 18.0

450.0

900.0

(B)

Penapak
Konkrit
Tetulang

95.0 (2000 psf)


@ 1.5m b.o.g.l.
(JKR probes >
50 blows/foot).

(A)

"

95.0 (2000 psf)


@ 1.5m b.F.L.
(JKR probes >
40 blows/foot).

(B)

Cerucuk
Konkrit
Tetulang

381 x 381
@ 15.0

650.0

1300.0

atau

"

305 x 305
@ 18.0
381 x 381

450.0

900.0

650.0

1300.0

305 x 305

450.0

900.0

254 x 254
@ 15.0

300.0

600.0

"
atau
atau

"

381 x 381
@ 18.0

900.0

1800.0

Penapak
Konkrit
Tetulang

95.0 (2000 psf)


@ 1.5m b.F.L.
(JKR probes >
40 blows/foot).

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 78

FOR INTERNAL USE ONLY

Pile Design Report

Syor-syor asas adalah seperti berikut:Nota:

i) Cerucuk Konkrit Tetulang


a) Daya tanggung beban kebanyakan cerucuk-cerucuF: yang direkabentuk adalah dari
separa geseran badan dan separ.a tanggung huiung dan keupayaan galas yang disy
orkan adalah berdasarkan kekuatan tanah dalam lingi:ungan batasan rendah serta
menggunakan faktor keselamatan 2.0.
b) Sekurang-Wrangnya 5 bilangan cerucuk permulaan perlu ditanam bagi setiap bangu
nan yang dicadangi;an yang memerlukan asas cerucuk dan 1 bilangan cerucuk ini
perlu dijalankan ujian beban (ini bermakna bahawa sekurang-kurangnya satu ujian
beban dibuat bagi setiap bangunan yang melibatkan asas cerucuF:). Ujian beban ini
boleh dijalankan selepas 3 minggu cerucuk-cerucuk berkenaan ditanam.
ii) Penapak Konkrit Tetulang
a) Fenapak-penapak E:onkrit hendaklah ditanam ke paras dalaman yang telah ditetap
kan di dalam jadual di atas (b. F. L. - below formation, atau b.o.g.l. - below original
ground level), dan lobang-lobang asas yang dikorek hendaklah jangan dibiarkan ter
dedah terlalu lama. Kerja-kerja 'concrete sdreeding' dan konkriting hendaklah
dilakukan secepat mungkin selepas penggalian lobang asas.
b) Walaubagaimanapun ujian pengesahan proba-proba JKR perlu dijalankan terlebih
dahulu bagi setiap kedudukan tiang bangunan-bangunan yang-dicadangkan bagi
memastikan hentaman proba-proba ini tidak kurang dari apa yang dicatitkan di dal
am jadual di atas dari dasar lobang asas kebawah dan ujian-ujian ini hendaklah dibu
at sebelum kerja-kerja pergorekkan lobang-lobang asas.
iii)
Cerucuk Kayu Berubat
a) Daya tanggung cerucuk yang direkabentuh adalah separa geseran badan dan sep
ara tanggung hujung dan faktor keselamatan yang digunakan di dalam perkiraan
adalah 2.0 serta menggunakan kekuatan tanah- dalam lingkungan batasan rendah.
b) Cerucuk hendaklah ditanam sehingga mencapai set yang sesuai dan ini dijangka
akan ditemui di paras dalaman lebih dari 6.0m.
c) Cerucuk !:ayu KEMFAS Berubat yang diluluskan oleh SIRIM hendaklah digu
nakan dan perlu mematuhi keperluan-keperluan yang terkandung di dalam surat
pekeliling KF*:R 7/1984.
d) Sekurang-kurangnya 3 bil. cerucuk permulaan perlu ditanam terlebih dahulu dan
2 bil. cerucuk ini hendaklah dijalankan ujian beban. Ujian beban ini boleh
dilakukan selepas 3 minggu cerucuk-cerucul: berkenaan ditanam.
5.0

Syor-syor Tambahan
a)
Kerja-kerja penimbusan dan pemotongan hendaklah dijalankan pada perinakat
permu laan kerja-kerja pembinaan dan tanah yang ditimbus hendaklah di dalam
lapisan tidak melebihi 300mm dan setiap lapisan dipadat ke tahap 95% mengikut
Piawaian Kepadatan British dengan penentuan JKR.
b)

Bagi bangunan-bangunan di mana lantai-lantai tingkat bawah akan diletakkan di atas

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 79

FOR INTERNAL USE ONLY

Pile Design Report

tanah timbus melebihi 2.50m kegunaan lantai gantung adalah diperakukan, dan
untuk bangunan-bangunan lain yang mana lantai-lantai tingkat bawah akan
dilekakan di atas tanah timbus tidak melebihi 2.50m lantai-lantai ini hendaklah
diperkuatakan dengan 2 lapisan BRC dan sambungan bebas disediakan di anatara
lanatai dan rasuk/dinding bangunan.
c)

Penyediaan penyambung bagi setiap jarak 6.0m adalah wajar bagi lantai-lantai
apron kesemua bangunan yang dicadangkan dan mana-mana lantai apron yang akan
diletakkan di atas timbus melebihi -1.0m lantai apron ini perlu dipisahkan daripada
tiang/rasuk/dinding bangunan dengan bitumen.

d)

Bagi blok-blok bangunan di mana pusat ini telah mengesyorkan lebih dari satu saiz
cerucuk, pihak tuan . bolehlah memilih mana-mana saiz.yang didapati lebih
ekonomik tetapi HANYA SATU SAIZ CERUCUK DIBENARKAN bagi satu ban
gunan.

e)

Pusat ini juga mengesyorkan agar. kecuraman cerun-cerun yang akan didirikan tidak
melebihi IM: 1(H) bagi cerun-cerun potong (cut slopes) dan, IM: 1.5(H) bagi cerungerun timbud (filled slopes).

6.0

Hal-hal Lain
Satu set rekod penanaman cerucuk-cerucuk yang diuji berserta dengan keputusan ujianujian bebannya hendaklah dikemukakan kepada pusat ini untuk tujuan dokumentasi.

7.0

Penutup
Dikemukakan syor-syor dan ulasan pusat ini untuk tindakan tuan selanjutnya.

Pusat Penyelidikan,Institut Latihan & Penyelidikan JKR.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 80

Pile Design Report

FOR INTERNAL USE ONLY

Lampiran 'E'

Settlement Estimation of Fill


From classification results underlying soil is of the COHESIVE type with a fair proportion of
sandy materials. It is most probable that the fill material to be used would be obtained from the
cut-areas. Hence for settlement analysis it is assume that the fill material is of the cohesive type.
In the estimation of soil settlement it is assume that the - original underlying soil where the fill
would be place experience negligible settlement and whatever settlement that would occur is solely from consolidation of the fill under its own weight. It is also assume that the fill is uncompacted
since it is most common now that the control exercised in placing fill and compaction has frequently been insufficient to ensure an adequate and uniform support for structures immediately
after placement.

Hence for estimation of settlement of fill, fig. 1.0 below would be used.
From fig. 1.0 graph 5, cohesive material would settle around 11% of its thickness.
Suppose that construction period is 2 years and construction of ground floor would be carried out
after a period of 1.5 years after placement of fill..
Take case where height of fill = 2.50m
Therefore settlement of fill = 0.11 x 2.50 = .275m
Settlement (': of height of fill) = 0.08 x. 2.50 = 0.200m after period of 1.5 yrs.
Hence remaining settlement after = 0.275 - 0.200 = 0.075m period of 1.5 yrs.
Therefore for those buildings placed on fill ground of height >> 2.50m suspended floor is recommended and for the others . place on fill < 2.50m independent floor with 2 layers of BRC.
Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 81

Pile Design Report

FOR INTERNAL USE ONLY

Projek :
Pakej :

SM. Kebangsaan Sungai Besar,Sabak Bernam, Selangor.


KBSM.

1.0. Tujuan.
Lapuran ini adalah bertujuan untuk menyampaikan keputusan penyiasatan tapak dan syor
asas yang sesuai bagi.projek diatas.
2.0. Skop Kerja
Perlaksanaan projek ini akan melibatkan pembinaan 1 Blok, 2 Tingkat (6BD,) bangunan
sekolah seperti yang tertera didalam pelan tatatur JKR/SB:765/81A. Aras tanah sediada
adalah merupakan cadangan aras formasi tapakbina ini,dan tidak-melibatkan sebarang
penambunan.
3.0. Skop Kerja Penyiasatan Tapak
Sebanyak 8 bilangan ujian proba JKR telah dijalankan oleh JKR Sabak Bernam, dan-2
bilangan ujian gerekan dalam telah dijalankan oleh Unit Makmal dilokasi-lokasi yang
bertanda didalam pelan tatatur.
4.0. Syor-syor Asas
Berdasarkan kira-kira rekabentuk, syor asas adalah seperti berikut:Jenis Asas

Cerucuk Konkrit
Tetulang

4.1.

4.2.
4.3.

Saiz Asas
(mm)

Panjang Asas
(mm)

254 x 254

30.0

Keupayaan galas
Beban
yg. Dibenarkan
Ujian
(kN/cerucuk)
300

600

Daya tanggung beban cerucuk konkrit tetulang yang direkabentuk adalah


kebanyakannya dari geseran badang, Perkiraan adalah menggunakan kekuatan tanah
di dalam lingkungan batasan rendah. Ini bermakna hanya 1 cerucuk sahaja diper
lukan bagi setiap tiang.
Bacaan set tidaklah perlu semasa penanaman cerucuk, dan cerucuk bolihlah
ditanamkan diparas dalaman 30.0m.
Sekurang-kurangnya 6 (enam) bilangan cerucuk permulaan hendaklah ditanam dan 1
(satu) bilangan cerucuk yang berdekatan dengan.lokasi ujian gerekan dalam hendak
lah dijalankan ujian.beban selepas 4 (empat) minggu cerucuk. berkenaan ditanam.

5.0. Syor-syor Tambahan


Bagi mengelakkan keretakan lantai apron unit ini berpend.apat penyed.iaan penyambung
bagi setiap jarak 6.Om adalah wajar. Lantai apron juga perlulah dipisahkan daripada dind
ing dan tiang bangunan supaya pergerakan berlainan sekiranya berlaku akan tersekat.
6.0. Hal-hal Lain
Satu set rekod penanaman cerucuk-cerucuk berserta dengan' keputusan ujian-ujian beban
nya hendaklah dikemukakan kepada unit ini bagi tujuan kaiian lanjut dan rekod.
7.0. Penutup.
Dikemukakan syor-syor dan ulasan unit ini untuk tindakan tuan selanjutnya.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 82

Pile Design Report

FOR INTERNAL USE ONLY

DATAS OBTAINED FORM : EN. BAHARUDIN LOKMAN JKR(O) S B

PROJEK : SMK SUNGAI BESAR


DAERAH : SABAK BERNAM

NEGERI : SELANGOR

1. HISTORY OF SITES
*

Any Cut / Fill ?

NO

- If theres fill when ?


- What is the depth of fill?
*

Is there a slope ?

NO

- How far from the proposed building ?


- What is the height of the slope ?
2.

HISTORY OF EXISTING NEARBY BUILDINGS


*

What is the type of foundation ?


If Pile - What Type ?
- What Size ?
If Pad - What Depth ?

PILE
RC
305 x 305
-

- What Bearing Capacity ?


*

When Constructed ?

80s

How is the present conditions ?

OK

- Any apron / floor cracks ?

SIGN OF

- Other sign of distress ?

CRACKS

How far is the nearest building ?

30

3. SOIL CONDITIONS
* What type of soils ?

* What is the water level ?

SOFT CLAY

HIGH

HBB /hbb

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 83

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Pile Design Report

Page 84

Pile Design Report

FOR INTERNAL USE ONLY

UNIT MAKMAL

NO. HELAI 1

KIRA KIRA REKABENTUK


REKABENTUK OLEH .
CAWANGAN REKABENTUK DAN PENYELIDIKAN IBU PEJABAT, JKR.

NO. FAIL ...

PROJEK : SMK SUNGAI BESAR.


DAERAH : SABAK BERNAM.
PAKEJ
: KBSM

TARIKH 4.10.89

RUJUKAN

KIRA KIRA

CATATAN

Lukisan

1. Blok / 2 tct. (GBD) sekolah

RL : 29.54

JKR/SB: 765/81A

FL : 30.00
Column Loadings(T)

Lukisan

Frame
Front

Back

F1

20

18

F2

29

25

F3

25

21

Datas &
Assumptions

MAX 29T

No fitting included

Level

Geological
Section

SPT

(m)

(ft)

(N)

v/s

12

40

Cu
kN/m

x
2

v/s

(0.03)

v.soft

v/s 25

to

(0.23)

Cu

Stiff

1.0

0.9

Silty
Clay

Qu = Qs + Qb
Clay: Qs = As x Cu Qb = Ab 9 Cb
Sand : Qs = ASN
50

Qb = Ab 4 N

Qa = Qu
f.o.s.
E96

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 85

Pile Design Report

FOR INTERNAL USE ONLY

UNIT MAKMAL

NO. HELAI 2..

KIRA KIRA REKABENTUK


REKABENTUK OLEH ..
CAWANGAN REKABENTUK DAN PENYELIDIKAN IBU PEJABAT, JKR.

PROJEK : SMK SUNGAI BESAR.


DAERAH : SABAK BERNAM.
PAKEJ
: KBSM

NO. FAIL ....


TARIKH 4.10.89.

RUJUKAN

KIRA KIRA

CATATAN

Try RC Piles

Level
(m)

(ft)

30

100

BXB

Qs

Qb

Qa

Qa

(in)

(T)

(T)

(T)

(T)

61 B

3.5 B 2

10 x 10

51

2.4

35

27

12 x 12

61

3.5

42

32

15 x 15

76

5.5

53

41

67B

40B2

10 x 10

56

28

47

42

12 x 12

67

40

58

54

15 x 15

84

63

77

74

Remarks

* quite close

Cost comperison

F2

F1

F3

F2

F3

F3

F2

F3

F3

F3

F1

Frames

Front

Back

Col

F1

F2

F3

12

E96

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 86

Pile Design Report

FOR INTERNAL USE ONLY

UNIT MAKMAL

NO. HELAI 3...

KIRA KIRA REKABENTUK


REKABENTUK OLEH ..
CAWANGAN REKABENTUK DAN PENYELIDIKAN IBU PEJABAT, JKR.

PROJEK : SMK SUNGAI BESAR.


DAERAH : SABAK BERNAM.
PAKEJ
: KBSM
RUJUKAN
Frames

NO. FAIL ....


TARIKH 4.10.89.

KIRA KIRA
Column

CATATAN

No of Piles
10 x 10 @
30T(30m)

12 x 12 @
30T(30m)

15 x 15 @
30T(30m)

at 100

at 100

at 100

Total

22

22

22

Rate

$0.32/m 2

$0.30/m 2

$0.28/m 2

Per m

Per m

Per m

Materials

$960/-

$1296/-

$1890/-

10%

96/-

129.6/-

189/-

Total Cost

$23,232/-

$31,363/-

$45738/-

Loads(T)

F1

20
18

F2

29
25

F3

25
21

Recommended

R.C. Piles
Size : 10 x 10 (254 x 254)
Length : 1 00 (30m)
Qa : 30T/Pile (300kN Pile)
f.o.s. : 1.5 skin 3.0 bearing
Pile is of mainly friction

E96

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 87

Pile Design Report

FOR INTERNAL USE ONLY

Project :

SM.KEB.SUNGAI BESAR, SABAK BERNAM, SELANGOR.

BD
SC
BDS
SCS

Bangunan
:
2 tingkat
Jenis (BD/SC/BDS/SCS)
: BD
Pile dim.
:
254 mm sq. piles
Length
:
30 m
W.Load
:
30 Tonnes
No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////// //////
Frames

Column
Position
Front
Back
Front
Back
Front
Back

Column
Load
20.0
18.0
29.0
25.0
25.0
21.0

=
=
=
=

Piles/
Column
1
1
1
1
1
1
TOTAL :

$35.20 /m. length

Cost :

Bilik Da
Makmal S
Bilik D
Makmal

Piles Reqd.
2
2
3
3
6
6
22
$23,232.00

ALTERNATIVELY : -

Pile dim.
Length
W.Load

:
:
:

305 mm sq. piles


30 m
45 Tonnes

No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////////////
Frames

Column
Position
Front
Back
Front
Back
Front
Back

Column
Load
20.0
18.0
29.0
25.0
25.0
21.0

Piles/
Column
1
1
1
1
1
1
TOTAL :

$47.52 /m. length

Cawangan Jalan, Ibu Pejabat JKR, K.L

Cost :

Piles Reqd.
2
2
3
3
6
6
22
$31,363.20

Page 88

Pile Design Report

FOR INTERNAL USE ONLY

Project :

SM.KEB.SUNGAI BESAR, SABAK BERNAM, SELANGOR.

BD
SC
BDS
SCS

Bangunan
:
2 tingkat
Jenis (BD/SC/BDS/SCS)
: BD
Pile dim.
:
381 mm sq. piles
Length
:
30 m
W.Load
:
30 Tonnes
No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////// //////
Frames

Column
Position
Front
Back
Front
Back
Front
Back

Column
Load
20.0
18.0
29.0
25.0
25.0
21.0

=
=
=
=

Piles/
Column
1
1
1
1
1
1
TOTAL :

$69.30 /m. length

Cost :

Bilik Da
Makmal S
Bilik D
Makmal

Piles Reqd.
2
2
3
3
6
6
22
$45,738.00

ALTERNATIVELY : -

Pile dim.
Length
W.Load

:
:
:

305 mm sq. piles


30 m
45 Tonnes

No. of
Frames
F1
2
///////////////////////////////
F2
3
///////////////////////////////
F3
6
///////////////////////////////
Frames

Column
Position
Front
Back
Front
Back
Front
Back

Column
Load
20.0
18.0
29.0
25.0
25.0
21.0

Piles/
Column
1
1
1
1
1
1
TOTAL :

$47.52 /m. length

Cawangan Jalan, Ibu Pejabat JKR, K.L

Cost :

Piles Reqd.
2
2
3
3
6
6
22
$31,363.20

Page 89

You might also like