Learning outcomes :
At the end of this task students should be able to:
i) Analyze and justify suitable design calculation for the case studies.
(CO1:PO5, CO2:PO4)
ii) Diagnose the structural failure and propose execution plan to solve the
damage. (CO2:PO4)
iii) Complete a proper report with introduction, content, conclusion and
references. (CO2:PO4)
TASK 1
Propose the design calculation and problem solving for the given structural layout
plan as shown in Figure 1. Each group is assigned to design the beam and slab
based on the Table 1 below. Every group must provide the complete design of the
reinforced concrete structural elements which includes analysis, design and
detailing.
Marks:
CO1:PO5 (30 marks)
CO2:PO4 (20 marks)
Table 1 : Design Specification
Group
Concrete
Class
Reinforceme
nt (mm)
Size beam
(mm)
1
C25/3
0
H12
2
C30/37
6
C30/3
7
H16
7
C35/45
H25
5
C25/3
0
H12
H20
8
C40/5
0
H25
150 x
300
200 x
400
300 x
600
150 x
300
200 x
400
250 x
500
300 x
600
2/A-E
250
x
500
3/A-E
Beam
design
Slab panel
Slab
thickness
(mm)
Ceiling
height (mm)
Brickwall
thickness
(mm)
Brickwall
Type
Location
1/A-E
E/1-4
C/1-4
B/1-3
A/1-3
D/1-3
FS1
125
FS2
150
FS5
175
FS4
200
FS3
125
FS6
150
FS5
175
FS8
200
2750
2600
3000
3300
2700
2650
2900
3150
115
125
115
125
115
125
115
125
Sand
Clay
Sand
Clay
Sand
Clay
Sand
Clay
Sungai
Lembin
Kota
Samarah
Jengk
a
Kundasa
ng
Camer
on
Kuala
Lump
Georgeto
wn
Langka
wi
H16
3
C35/
45
H20
4
C40/50
2 | Page
CES522/OCT2015/MINI PROJECT
Fire
Resistance
Finishes
an
R30
R60
R90
R120
Cerami
c Tiles
Mosaic
Marbl
e
Cement
Randor
Highlan
d
R30
ur
Parque
R60
R90
R120
Concr
ete
Tiles
Pebble
Tiles
Cerami
c Tiles
500
500
525
500
FS1
(Dp 100)
FS2
FS3
FS4
FS5
FS6
FS7
FS8
1
475
2
500
3
FS9
475
4
Figure 1: Structural Layout Plan
Note: Dp 100 for slab FS1 only.
TASK 2
Based on the proposed slab that need to be designed in TASK 1, analyze the
possible optimum yield line pattern that produces the best resistance for the slab
3 | Page
CES522/OCT2015/MINI PROJECT
panel by providing acceptable reasons. In addition, describe the approach adopted
in yield line analysis to obtain the moment resistance for the slab panel. Students
are advised to use the action values from slab analysis in TASK 1.
Marks:
CO1:PO5 (20 marks)
CO2:PO4 (10 marks)
Table 2 : Moment Ratio Value
Group
Slab
panel
Mx/My
Mx/Mx
My/My
TASK 3
1
FS1
2
FS2
3
FS5
4
FS4
5
FS3
6
FS6
7
FS5
8
FS8
1.2
1.3
1.4
1.3
1.4
1.5
1.4
1.5
1.6
1.5
1.6
1.7
1.6
1.7
1.8
1.7
1.8
1.9
1.8
1.9
2.0
1.9
2.0
2.1
Comment and discuss on Figure 2 below. Identify the possible failure causes and
propose stable repairing techniques. Your report should consist of:
i) Introduction of case studies which stated the diagnostic of failure
ii) Possible causes of the failure with appropriate justification with supporting figures
and diagrams
iii) Repairing plan by considering action to be taken, time and type of cost that would
occur
iv) Conclusion
Marks:
4 | Page
CES522/OCT2015/MINI PROJECT
ASSESSMENT RUBRIC
TASK 1
Design
Parameter
Poor
1-3
Incorrect
identified the
design
parameter.
Average
4-7
Identified the
design
parameter with 2
incorrect
parameters.
Action Analysis
Incorrect
Correctly
Good
8-10
Correctly
identified the
design
parameter with
only 1 incorrect
parameter.
Correctly
Outcomes
CO1:PO5
CO1:PO5
5 | Page
CES522/OCT2015/MINI PROJECT
calculation of
action analysis.
Structural
Analysis
(ULS)
Incomplete
design.
Structural
Check
(SLS)
Incomplete
check 2 or more
serviceability
check.
Detailing
No provision of
reinforcement
detailing.
calculate action
analysis with
error at
permanent
action and
variable action.
Complete design
with inaccurate
provision of main
reinforcement.
Incorrect values
used in SLS
check with
complete
calculation.
Provide detailing
with minor
errors.
calculate action
analysis with
minor error on
action values.
Complete
design with
suitable
provision of
main
reinforcement.
Complete check
with correct
values.
CO1:PO5
Complete
detailing.
CO2:PO4
CO2:PO4
TASK 2
Analysis
Poor
1-3
Incomplete
analysis.
Design
Incomplete
design.
Detailing
No provision of
reinforcement
detailing.
Average
4-7
Complete
analysis with
incorrect answer.
Complete design
with major error.
Provision of
incorrect
reinforcement
detailing.
Good
8-10
Complete
analysis with
correct answer.
Complete
design with
correct answer
and minor error.
Complete
detailing with
minor error.
Outcomes
CO1:PO5
CO1:PO5
CO2:PO4
TASK 3
6 | Page
CES522/OCT2015/MINI PROJECT
Introduction
Design
calculation
Repairing
execution
plan
Conclusion
References
Poor
1-3
Acknowledge
the task given
Good
8-10
Initiate effort with
some evidence
relate with current
issues to discuss
the given task
Outcome
s
CO2:PO4
able to express
effort in design
with
diagrams/figures/s
ample
calculaations
Aware of
Able to propose
Able to
execution plan
at least 3
recommend
with minimum
execution plan
more that 3
effort
considering
execution plan
action to be
by considering
taken/time/cost
time, cost and
A good
suitable
elaboration of
procedures/acti
execution plan
on to be taken
Excellent
without
copying from
elaboration of
other sources
task and able
to relate with
current issues
without
copying from
other sources
Able to manage Able to manage
Able to manage
information
information with
information with
with poor
good conclusion
satisfactorily
conclusion
inference
Not able to find Able to find
Able to find
relevant
sources but not
sources relevant
sources (less
relevant to the
to the given task
than 2
given task (more (more than 3
references
than 2
references
excluding
references
excluding internet
internet
excluding
sources)
sources)
internet sources)
CO2:PO4
Aware of design
procedure
involved in
completing the
task
Average
4-7
Able to discuss
problems and
contribute
relevant
justification to
support the
given task
Able to conduct
proper design
process
CO2:PO4
CO2:PO4
CO2:PO4
7 | Page
CES522/OCT2015/MINI PROJECT
8 | Page