You are on page 1of 9

PROJECT TITLE:

LOCATION:

ITEM NO.
I

DESCRIPTION
TEMPORARY STRUCTURE

A.

1
1

II

PLUMBING WORKS

1
1
1

III

PAINTING WORKS

A.

TOTAL COST OF THE PROJECT =

Proposed Rain Collecting Piping


Toyota Zamboanga Boalan Branch

DESCRIPTION

UNIT

MPORARY STRUCTURE
QUANTITY = 1.00 LOT
SCOPE OF WORK:
Includes:
1. Fabrication and Installation of Steel Ladders and Safety Barriers
Materials:
12mm x 6.0 m Def. Bars
2mm x 2" x 6" C-Purlins
2" dia. G.I. Pipe Sch. 20
Welding Rod
Safety Harness

pcs.
pcs.
pcs.
kgs.
pcs.

Welding Machine
Angle Grinder w/ Cutting Disk

days
days

B. Equipment Rental:

C. Labor
Manpower

days

DIRECT COST:
INDIRECT COST:
a. OCM
b. CONTRACTOR'S PRO
c. CONTRACTOR'S TAX
TOTAL COST:
Unit cost:

UMBING WORKS
QUANTITY = 42.36 LN.M.
SCOPE OF WORK:
Includes: Supply and Installation of
1. Downspout
2. Sanitary System
A. Materials:
4" dia. x 3m PVC Pipe (S-1000)
4" dia. PVC Coupling
4" dia. x 90 deg. PVC Elbow

pcs.
pcs.
pcs.

4" dia. x 4" dia. PVC Tee


5mm x 25mm x 25mm Angle Bar
10mm x 6.0m Def. Bars
Welding Rod
2 1/2" Tekscrew
Hacksaw Blade
Solvent Cement

pcs.
pcs.
pcs.
kgs.
pcs.
pcs.
qrts.

B. Equipment Rental:
Welding Machine
Unit Hand Drill
Angle Grinder w/ Cutting Disk

days
days
days

Manpower

days

C. Labor

DIRECT COST:
INDIRECT COST:
a. OCM
b. CONTRACTOR'S PRO
c. CONTRACTOR'S TAX
TOTAL COST:
Unit cost:

NTING WORKS
(Note: Apply Two (2) Coatings)
QUANTITY = 13.30 SQ.M.
SCOPE OF WORK:
Includes: Painting Works for:
1. Steel Frames
Materials:
Epoxy Enamel
Red Oxide Primer Paint
Easy Tite
Paint Thinner
Paint Roller w/ Tray
Paint Brush

gals
gals
gals
gals
sets
pcs.

Manpower

days

B. Labor

DIRECT COST:
INDIRECT COST:
a. OCM

b. CONTRACTOR'S PR
c. CONTRACTOR'S TA
TOTAL CO
Unit cost:

TOTAL COST OF THE PROJECT =

QTY.

UNIT COST

AMOUNT

9
6
4
3
3

350.00
995.00
1275.00
150.00
250.00

3150.00
5970.00
5100.00
450.00
750.00
15420.00

2
2

1,500.00
300.00

3,000.00
600.00
3,600.00

281.00

1686.00
1686.00

IRECT COST:
NDIRECT COST:
OCM
CONTRACTOR'S PROFIT
CONTRACTOR'S TAX
OTAL COST:
nit cost:

18
10
8

20706.00
2070.60
2070.60
2981.66
27828.86
27828.86

55.00
47.00
113.00

990.00
470.00
904.00

10%
10%
12%

3
3
3
5
100
4
3

110.00
275.00
116.00
150.00
2.50
55.00
320.00

330.00
825.00
348.00
750.00
250.00
220.00
960.00
6047.00

1
2
2

1500.00
300.00
300.00

1500.00
600.00
600.00
2700.00

3.00

281.00

3372.00
3372.00

IRECT COST:
NDIRECT COST:
OCM
CONTRACTOR'S PROFIT
CONTRACTOR'S TAX
OTAL COST:
nit cost:

12119.00
1211.90
1211.90
1745.14
16287.94
670.00

1.00
1.00
1.00
1.00
4.00
4.00

840.00
350.00
497.00
325.00
54.00
50.00

840.00
350.00
497.00
325.00
216.00
200.00
2428.00

2.00

281.00

1686.00
1686.00

IRECT COST:
NDIRECT COST:
a. OCM

10%
10%
12%

4114.00
411.40

10%

b. CONTRACTOR'S PROFIT
c. CONTRACTOR'S TAX
TOTAL COST:
Unit cost:

411.40
592.42
5529.22
415.73

49646.02

10%
12%

You might also like