Professional Documents
Culture Documents
EIS For Kafubu Mall PDF
EIS For Kafubu Mall PDF
TABLE OF CONTENTS
ABBREVIATIONS AND TERMINOLOGY .....................................................................................10
EXECUTIVE SUMMARY ..................................................................................................................11
INTRODUCTION ................................................................. ERROR! BOOKMARK NOT DEFINED.
PROJECT BACKGROUND ......................................................................................................................21
THE PROCESS OF CONSTRUCTING A SHOPPING MALL .........................................................................22
1.1.1.
1.1.2.
Tendering Process...........................................................................................................22
1.1.3.
1.1.4.
1.1.5.
1.1.8.
1.1.10.
1.1.11.
1.1.12.
1.1.13.
1.1.14.
1.1.15.
1.1.16.
1.1.17.
1.1.18.
1.1.19.
1.1.20.
1.1.21.
1.1.22.
1.1.25.
1.1.26.
1.1.27.
1.1.30.
1.1.32.
LAND-USE ...........................................................................................................................................11
1.1.33.
1.1.34.
Settlements..................................................................................................................12
1.1.37.
Operational Phase......................................................................................................19
1.1.39.
Operational Phase......................................................................................................20
1.1.41.
Operational Phase......................................................................................................21
1.1.43.
Operational Phase......................................................................................................21
1.1.45.
Operational Phase......................................................................................................22
1.1.47.
Operational Phase......................................................................................................23
1.1.49.
Operational Phase......................................................................................................23
1.1.51.
Operational Phase......................................................................................................24
1.1.53.
Operational Phase......................................................................................................24
1.1.55.
Operational Phase......................................................................................................25
1.1.57.
Operational Phase......................................................................................................25
1.1.59.
Operational Phase......................................................................................................26
1.1.61.
Operational Phase......................................................................................................26
1.1.63.
Operational Phase......................................................................................................27
1.1.65.
Operational Phase......................................................................................................28
1.1.67.
1.1.68.
1.1.69.
1.1.70.
1.1.71.
1.1.72.
1.1.73.
1.1.74.
1.1.77.
1.1.78.
1.1.79.
1.1.80.
Operational Phase....................................................................................................156
1.1.82.
LIST OF FIGURES
LIST OF TABLES
Table 1: List of EIA team
Table 2: Showing raw material during construction
Table 3: Average precipitation for 84 years old period
Table4: Average relative temperature
Table 5: Average relative humidity
Table 6: Population distribution in the project planning area
Table 7: Community Concerns
Table 8: Table of evaluation of impacts
Table 9: Mitigation measures
Table 10: Monitoring activities and indicators
Table 11: Monitoring and reporting Responsibilities
Table 12: implementation schedule of mitigation measures
LIST OF APPENDICES
CBO
CNEL
DDCC
dB
ZEMA
EIA
EPB
EIS
EMMP
EPPCA
m2
Square Meter
m3
Cubic Meter
NCS
NGO
Non-governmental Organization
NHCC
ZAWA
ZESCO
SIGNATURE PAGE
11
We the undersigned hereby declare that the information contained in this report is true and
correct to the best of our knowledge:
4) Habena Habenzu -
5) Dillon Rothman-
Developer................................................................
EXECUTIVE SUMMARY
1.1 The Project
The Management of Kafubu Mall Limited wants to construct a shopping mall in Ndola that will
be of international standards. Once build this will provide access to goods and services to
12
tourist resort facilities as well as the residents of Ndola and other surrounding towns .Ndola is
endowed with a lot of minerals and has got the potential for economic growth.
Kafubu Mall Limited, propose to establish a shopping mall in Ndola .Kafubu Mall Limited are
a private property holding company, which was registered on the 16th of May 2012. Kafubu
Mall Limited shareholders have a diversified portfolio throughout South Africa which includes
offices, warehouses and shopping centers. In this regard, they have identified a piece of land in
Ndola of about 2.5 hectares as a possible site upon which to build a 1163m2 shopping mall. The
proposed development introduces an iconic retail-centric mixed-use development with an
international flavour, where people will experience an exclusive shopping environment, dine
and socialize in an up market setting.
The concept revolves around the construction of a multi-million dollar Shopping Mall
Development facility with a final build-out of approximately 1163m2 in Ndola. These premises
lie at the junction of T-3 and president Avenue and can be accessed through the T-3 and
President Avenue, and are directly opposite Kundalila Flats. The projected total cost of the
whole development will be US $7 million. (US Dollar Seven million). The construction of the
shopping mall will be done at once and is scheduled to commence in March 2013 with
completion set for June 2015
This anticipated project falls under the Second Schedule of the Environmental Impact
Assessment (EIA) Regulations of the Environmental Protection and Pollution Control Act
(EPPCA), and its various Instruments. Provided for under this Act is the requirement that an
Environmental Impact Assessment (EIA) study be carried out for this and similar projects. The
Environmental Impact Statement (EIS) of which this report is the main part, presents the
findings of the EIA study to identify both positive and negative impacts together with
recommendations to mitigate potential negative impacts and to enhance benefits
Kafubu Mall Limited has appointed the consultant to undertake an EIA to comply with the
Environmental Protection and Pollution Act of the Laws of Zambia and subsequent Statutory
Instrument No. 28 of 1997 (Environmental Impact Assessment) regulations
Project Objectives
The key objectives of this project are as follows:
13
We are convinced that this project will meet the above objectives once implemented and
fully operational.
Location
The shopping mall will be situated in the central commercial business area; it will cover
23683m2 and the floor of about 11623m2..The shopping mall will be accessed from the
president Avenue opposite Kundalila flats.
Arc 1950 coordinates
EASTINGS
NORTHINGS
67795.104
8564499.761
677948.972
8564621.367
678035.833
8564527.061
677891.892
8564410.419
The Proponent
Kafubu Mall Limited is a private property holding company, which was registered on 16
May 2012. Kafubu Mall Limited shareholders have a diversified portfolio throughout
South Africa, which includes offices, warehouses and shopping centers. Kafubu mall
14
Name
Residential Postal
Percentage shares
Address
Director
Rajarathnam Ravi
Sankar
court,Kanini,p.o box
70998,Ndola
Director
Suite 9A-1st
Floor,3Melrose
Boulevard,Melros
ARCH
Johannesburg,216 RSA
Director
Musonda Mulenga
ZAMTEL Complex
Kambikambi
Particulars of shareholders:
15
Secretaries
Corporate Services
Limited
CONTACT DETAILS
Name of Developer
Broadway Ndola
Zambia
Phone 0976926817/0978811345
16
Relevant Legislation
17
Biophysical Impacts
Disfigurement to the project area due to construction activities
Increased air pollution from increased vehicular traffic.
Increased noise nuisance both during construction and operation phases
Irreversible environmental destruction from construction activities such as
deforestation, borrow pit digging and camping site for construction workers
Disfigurement to the landscape from construction wastes and borrow pits
River siltation from eroded soil and silt from incresed run-off due to disturbance of
sub-soil structure
Oil and gasoline spills from construction equipment and plant maintenance activities
Littering domestic refuse and sewarage waste from construction camps
Increased particulate matter (diesel) and dust.
Socio-economic Impacts:
Increased access to tourist facilities
General improvement in local livelihoods due to synergistic impacts of positive
effects of the project
Increase in revenue to local authorities and institutions from communications, land
rates, licences and personal levy
Changed human settlement patterns due to increased population who may be
attracted to the area
Creation of employement opportunities during the construction and opreation phase
Increased trade opportunities in the community due to increased population
Environmental Management and Monitoring Plan
19
POSITION
Cuthbert Makondo
Environmental and
Natural Resource
specialist
Mwimba Nkosha
Social Economist
Kennedy Chileshe
Habene Habenzu
Structural Engineering
and Material Testing
SIGN
20
a consequence, Kafubu Mall Limited is intending to construct a shopping mall that will
be called Kafubu Mall of 32 shops covering about 11623m2. Therefore these EIS is
prepared by the Consultants on behalf of the client Kafubu Mall.
The Management of Kafubu Mall are the executing agency while the contractor will be
responsible for the implementation of this project. The main objective of the
construction of the shopping mall is to secure access to goods and services that are
efficient in answering to peoples needs, thereby making a significant contribution to
realizing and developing Zambia's economic potential. In addition to investment and
wealth creation, was to add beauty to the city of Ndola and bring vibrancy to the new
and up and coming part of Ndola destined to be a high end area.
1.1.1.
Preparatory Works
1.1.2.
Tendering Process
This process involves invitation to tender, making tender documents available to prequalified or registered contractors, organizing pre-tender site visits, issuing tender
notices, receipt and opening of tenders, tender evaluation, and contract negotiations and
awarding of tenders.
1.1.3.
This process involves giving notices to the contractor to commence work, liaising and
reporting to the employer/ client and liaising with contractors on the work programme
and mobilization of staff, workers and equipment.
22
1.1.4.
This process entails obtaining performance bond, insurance of work and workers, giving
notice to contractor to take possession of site, obtaining contractors work programme
and mobilization of staff, workers and equipment.
1.1.5.
This involves day to day monitoring of physical progress of the workers, application of
conditions of contract, enforcement of specifications, measuring of works with
contractors' representatives, quality control in form of materials testing at laboratory and
on site, certification of work done, preparation of interim payment certificates, control
of material and equipment on site, issuing of site instructions and variation orders and
settlement of disputes (arbitration, conciliation, etc).
THE PROPONENT
Kafubu Mall Limited is a private property holding company, which was registered on 16
May 2012. Kafubu Mall Limited shareholders have a diversified portfolio throughout
South Africa, which includes offices, warehouses and shopping centers. Kafubu mall
shareholders have been managing a number of properties in Melrose, Johannesburg
South Africa.
Particulars of shareholders:
Position
Name
Residential Postal
Address
Director
Rajarathnam Ravi
Sankar
court,Kanini,p.o box
70998,Ndola
Director
Suite 9A-1st
Floor,3Melrose
Boulevard,Melros
ARCH
Johannesburg,216 RSA
Director
Musonda Mulenga
ZAMTEL Complex
Kambikambi
70998 Ndola
Secretaries
Corporate Services
Limited
Broadway Ndola
Zambia
Project coordinator
Mwimba Nkosha
Mansansa Close
Plot #224/A Rhodespark
P.o Box 32379
Lusaka
Phone 0976926817/0978811345
Project Rationale
Zambia is experiencing a growing economy as reflected by the GDP rated at 5.4% in
2011 and is expected to grow in the coming years, and comparing favorably with
general economic growth in the region. With a population currently estimated at
455.194, Ndola has experienced rapid urbanization in recent years, which has
resulted in demand for more modern infrastructure. The city is thus facing a number of
challenges,
which
include
inadequate
parking,
lack
of
appropriate
and the need to service expanding areas and new development nodes. These areas
include:
Northrise
Kansenshi
Itawa
Mushili
Lubuto
There is an urgent need to address the inadequacies of existing infrastructure and to
meet a growing demand for modern facilities in the office and retail market, the
residential market and the hotel and hospitality industry as well as leisure
market.The current situation obtaining in the property market in include
25
The shopping mall will be situated in the central commercial business area; it will cover
23683m2 and the floor of about 11623m2..The shopping mall will be accessed from the
president Avenue opposite Kundalila flats.
Table 2: Arc 1950 coordinates
EASTINGS
NORTHINGS
67795.104
8564499.761
677948.972
8564621.367
678035.833
8564527.061
677891.892
8564410.419
26
We are convinced that this project will meet the above objectives once implemented and
fully operational.
We have provided mitigation measures to mitigate the negative impacts. We have also
recommended enhancement plans to enhance positive impacts of the project. An
environmental Management Plan has been presented in this report to provide clear
steps designed to ensure focused implementation of the recommended mitigation
and enhancement measures.
27
Council
of
Zambia
and
warrants
them
to
authorize
the
Kafubu mall limited has identified a pieace of land for the construction of the shopping
mall, which also encompasses an environmental impact assessment. The EIA will assess
the impacts from the construction and evaluate the alternatives. The existing pieace of
land has been included with a "zero-alternative", in case the construction on the
proposed land does not take place.
The EIA will determine whether the Construction of the shopping mall will have
significant adverse or beneficial impacts on the environment during the construction
phase and operational life of the mall, and it will also recommend measures for
mitigation of negative environmental effects through the preparation of an
environmental management and monitoring plan.
The scope of the study is outlined in the Scoping Report and Terms of Reference
(November 2012) as reviewed, commented and approved by the Environmental Council
of Zambia. The output from the EIA is this Environmental Impact Statement (EIS)
comprising of an Environmental Management and Monitoring Plan (EMP).
Study Approach and Methodology
The EIA process took place from October 2012 to November 2012, and involved the
following steps:
28
This included review of the Environmental Protection and Pollution Control Act and its
subsidiary legislation and other relevant Acts and international conventions.
This task involved collecting data around the project areas and identifying areas
requiring detailed investigations, which include sensitive areas.
Scoping
The scoping exercise included consultative meetings and discussions with relevant
government institutions at national, provincial and district level, local communities,
representatives from NGOs and community based organizations and residents from
communities around the project area. Letters stating the objectives of the project and
requesting local participation and consultation in the process were also distributed.
Responses from the consultations and discussions provided the relevant background
information and helped identify major environmental concerns of the communities
around the proposed shopping mall for the detailed EIA process.
Impacts will be evaluated in terms of magnitude and significance. There are four
groupings of impacts on the environment, which will be evaluated for the duration of
the project namely;
Physical environment
Biological environment
Socio-economic environment
Cultural environment
29
These impacts may be positive (beneficial) or negative (adverse) and will be classified
as low, moderate or high to the extent their effects will be described quantitatively in
terms of environmental costs and benefits. Effects may be direct or indirect, short term,
intermediate or long term.
The impacts will be assessed during the following stages of the project:
Pre-Construction (Design) Phase
Construction Phase
Operational Phase
It will be important that the likely impacts are defined and evaluated at an early stage of
the planning process. This was done through scoping the specific impacts and their
implications which are pertinent to the shopping mall project so that alternatives can
then be investigated and changes can be incorporated at the design stage. Other
measures will also be identified which can be taken into account during design and
construction phases that would enhance the environmental quality of the shopping mall.
The mitigation measures will be considered to reduce the effect of the development on
the surrounding environment. Wherever possible recommendations will be made to
mitigate against impacts on the physical, biological, socio-economic environment and
cultural environment.
The report will include a plan for monitoring and implementation of mitigation
measures during construction and operation. Mitigation plans should be included in the
tender document to form part of the overall construction contract.
30
POSITION
Cuthbert Makondo
Environmental and
SIGN
Natural Resource
specialist
Mwimba Nkosha
Social Economist
Kennedy Chileshe
Habene Habenzu
Structural Engineering
and Material Testing
31
1.1.6.
1.1.7.
The Environmental Protection and Pollution Control Act (EPPCA), Cap 204, Part IV to
VII sets the role of ZEMA in setting environmental quality standards for waste, water,
air, pesticides and toxic substances, noise, ionising radiation and natural resources
conservation. In 1997 an amendment to the EPPCA established the Environmental
Impact Assessment Regulations, Statutory Instrument No. 28 of 1997 for conducting
and review of Environmental Impact Assessment of certain projects such as this one .
1.1.8.
According to the EMA of 2011, Section 3 (1) of the Environmental Impact Assessment
(EIA) Regulations, states that, a developer shall not implement a project for which a
project brief or environmental impact statement is required under these Regulations,
unless the project brief or the environmental impact statement has been concluded in
32
accordance with these regulations and the Zambia Environmental Management Agency
(ZEMA) has issued a decision letter.
Kafubu mall limited has commissioned this study as part of its corporate responsibility
to comply with the prevailing environmental laws in Zambia so that key environmental
issues associated with the project are identified and suitable measures that can mitigate
the potential adverse impacts are put in place.
The Environmental Management Act of 2011 (EMA)
This Act was passed in the year 2011 and its the Principal Act governing, managing
and regulating environmental issues in Zambia. Its main functions include the protection
of the environment and control of pollution, in particular to provide for the health and
welfare of people, animals, plants and the environment.
Specifically, Section 3(1) of the EIA Regulations states that, a developer shall not
implement a project for which a project brief (EPB) or environmental impact statement
(EIS) is required under these Regulations, unless the project brief or the environmental
impact statement has been concluded in accordance with these regulations and the
Environmental Council of Zambia has issued a decision letter.
Prescribes the conducting of an environmental impact assessment and the development
of impact mitigation measures. The Complianc is that the developer needs to Prepare
an impact assessment and submission of an EMP thereafter.
The contents of an Environmental Impact Statement shall be prepared to include the
following elements:
A description of the project;
A description of the site;
A description of the raw material inputs, technology, processes, products and byproducts;
A description of the site surrounding environment;
A description of the environmental effects;
A description of the socio-economic impacts;
Impact management Plan
33
This anticipated project falls under the Second Schedule of the Environmental Impact
Assessment (EIA) Regulations of the Environmental Protection and Pollution Control
Act
(EPPCA), and its various Instruments. Provided for under this Act is the
requirement that an Environmental Impact Assessment (EIA) study be carried out for
this and similar projects. The Environmental Impact Statement (EIS) of which this
report is the main part, presents the findings of the EIA study to identify both positive
and negative impacts together with recommendations to mitigate potential negative
impacts and to enhance benefits.
Therefore the EIA process was conducted in line with the provisions of these EIA
Regulations.
Other Acts Reviewed Relevant to the Construction of a shopping Mall
The Acts below have also been reviewed in order to ensure that the project complies
with other relevant existing laws that have a bearing on environmental management.
1.1.9.
This is an act to provide for the establishement of the national Council for construction
and to define its function; to provide for the promotion and development of the
construction industrial in Zambia; to provide for the registration of the contractors to
provide for the affiliation to the council of professional bodies or organisation whose
members are engaged in activities related to the construction industry; to provide for the
regulation of the construction industry; to provide for the regulation of the construction
industrial; to provide for the establishement for the construction school; to provide for
the training of persons engaged in construction or in activities related to the
construction; and provide for matters connected with or incidental to the fore-going.
The construction of the shopping mall will be undertaken in accordance with the
National Council for Construction Act that will aim to promote the construction
industry, it will also use trained and qualified persons as well as registered contractors.
34
The construction of the shopping mall project will be undertaken in accordance with the
approved land use plans as provided for under the Town and Country Planning Act.
Forest reserves currently cover approximately 10% of the country and are intended for
the conservation and development of forest resources, as well as providing protection to
watersheds.
The Act also provides for the protection of 6 tree species nationally whether in a
protected area or outside it. These are as follows:
Entandrophragma caudatum
Mountain Mahogany
Khaya nyasica
Red Mahogany
Pterocarpus angolensis
African Teak
Afzelia quanzensis
Pod Mahogany
Faurea saligna
Beechwood
Baikiaea plurijuga
Teak
35
During biological/ecological investigations protected tree species have not been found
around the project area.. During the construction of the mall, these species would have
been addressed.
The project will comply with the provisions of the Act by ensuring that storm water
disposal structures intended to control runoffs from the mall into the aquatic
environment (both surface and groundwater) are part of the overall detailed designs for
construction of the shopping mall.
or scientific interest
by preservation, restoration,
The developer worked closely with the local community and has obtained consent from
Area Councillors and local authorities of Ndola Communities during the EIA process
and will continue to do so during final shopping mal construction works.
The Act instituted a Compensation Advisory Board to advise the Minister of Lands in
assessment of compensation payable under the Act. The functions of the Board have
been delegated to various committees. Various forms to be used in proceedings of
property acquisition are prescribed in the statutory Instrument No. 60 of 1970.
37
The developer will confine the construction works within the proposed project reserve
area to minimize impacts in the immediate environment.
In this project quarrying for gravel material will be carried out and rehabilitation of the
quarries created in the process will be carried out based on the mitigation measures
outlined in this document and in the subsequent Environmental Project Brief for a new
borrow pit.
In this shopping mall construction project, requirements for storm water disposal
structures along the access road as provided for under this Act are part of the overall
designs for the shopping mall.
38
For instance, the Act would support the location and restorations of borrow pit sites,
subject to approval by the relevant Government Departments and Local Communities in
the areas in which they are located.
Location and sitting of camps and borrow pits will be undertaken with consultations
and consent from the local community and approval from relevant Government
Departments. In the case of opening a new borrow pit this will require approval from
the Zambia Environmental Management Agency by way of undertaking an
Environmental Project Brief.
The project will ensure that measures to prevent diseases and pollution dangerous to
human health and to any water supply are taken into account through the provision of a
drainage control system.
The project will ensure that the safety, health and welfare measures and facilities of
workers during the construction of the mall will be in accordance with the provisions of
the Factories Act.
Where petroleum products shall be transported to or stored on site this shall be done in
compliance with the provisions of the Petroleum Act.
39
Where fuels shall be transported to, handled or stored on site this shall be done in
compliance with the provisions of the Energy Regulation Act.
International and Regional Conventions
Of the above, only the Convention on the Protection of World Cultural and Natural
Heritage has some relevance for the project in case such are fund on site during
excavation works. The site will be addressed by the project as proposed in this
Environmental Management Plan.
40
PROJECT DESCRIPTION
Project Location
The proposed project is located at the junction of T-3 and president Avenue in the
central business area of Ndola, a city on the Copperbelt Province of Zambia . The
province has ten districts.
NORTHINGS
67795.104
8564499.761
677948.972
8564621.367
678035.833
8564527.061
677891.892
8564410.419
41
The shopping complex will accommodate leisure, social and recreational facilities.
These will include shopping, entertainment and administration area of 23683m2. This
includes the parking space.
The mall will be inter-linked by covered walkways. The small retail-shopping units will
vary in size from 48m2 to 450m2. However, the areas can be adaptable to the required
minimums required by the tenant. This also allows for a wide range of tenant mix and
wide range of commodity.
The shopping mall will have adequate provision for full service restaurants and pubs in
the complex and provisions for coffee shops and business caf. A large super store of
about 800m2 as one of the key tenants will be run by a recommended franchise that will
allow for variety of commodities. This will be serviced from the back and fully house
with administration offices, staff canteen kitchens and storage spaces.
The mall will have two landscaped courtyard spaces, which can be used for meetings,
performances, or open market space hence enhancing social interaction. The courtyard
also breaks the monotony of built up space and provide leisurely atmosphere. Surface
parking of approximately 275 vehicles plus 43 taxis near the road will cater for vehicles.
This wide separation of parking will provide convenient flow of vehicles.
Subject to approval of this EIS by the ZEMA, project implementation is schedule to
commence in the first quarter of 2013. Construction of the Shopping Mall will take
approximately 3 years.
Decommissioning and closure will depend on future economic and technological
conditions over the life of the Project.
The project will consist of the following phases:Phase 1 Site Preparation (Year 1),
Phase 2 Construction (Year 1 Year 2),
Phase 3 Operations (Year 2 Year 30), and
Phase 4 Decommissioning and Closure (may not be done).
42
Project Activities.
This phase involves carrying out a survey of the proposed shopping mall. Survey in this
case refers to land investigations, drilling, measurements and pre-works examination of
the site. To facilitate the development of a conceptual design an environmental impact
assessment was undertaken and the key concerns from the study were taken into account
in the design phase. The output from this phase is an environmentally friendlyengineered design for the shopping mall, which has to be implemented in the
construction phase.
Construction Phase
The actual construction of the shopping mall will take place in the construction phase.
The estimated shopping mall works will cover the following activities:
The Site Establishment will include the initial construction of the following facilities:
There will be labour camp on the project site, although security personnel will be
accommodated on the site. Various plant and equipment to be used during the execution
of civil works will include
Graders
Cranes
Vibrators Rollers
Water Trucks
Bulldozers
Front End Loader
Generator Set 125 KVA
6m Containers
Concrete Mixers
Concrete Pokers Excavators
Water Pumps
Mechanical Tool Boxes
Compressors
Civil Plate Compactors x3
Pedestal Rollers
Tipper Trucks
10 Ton Trucks 4
Construction activities will be repeated as required over the two phased Construction
cycles. The main anticipated project construction activities that will have potential
impacts on the environment are:
will be constructed by-and large on the existing level requiring minimal basic
earthworks, which will minimise the need for filling of areas with laterite and
aggregates. Earthworks will for the most part involve the use of heavy
machinery such as bulldozers and graders.
Construction of the roads will involve earth moving and shaping of formation
shoulders, and stabilization of the base with the piling, spreading and
compaction of gravel and aggregate materials on the road.The entrance to the
mall will be opposite Kundalila flats on president avenue studies are underway
to find the best way to incoparate the nearby existing public road network, a
team of expertise from local authority and RATSA including RDA and the
developer are yet to develop the traffic strategy Construction of a bitumen
surface pavement will involve the spreading and compaction of aggregates and
tar materials on the road. Construction of drainage will involve excavation and
shaping of drains and soil compaction. Lined drains will require the preparing
and pouring of concrete.
c) Excavation and Foundations:
This will involve the excavation of trenches for foundation strips for buildings
and trenches for ground water storage tank water, and sewage reticulation
system. The geotechnical survey of the site is indicative that the bearing
capacities of soils are good and the foundation depth and design for the intended
structures will not be complicate.
45
46
g) Maintenance of Machinery
A temporary workshop facility will be constructed on site for the maintenance of
construction vehicles and machinery. This will be combined with the fuel storage
facility.
j) Water Abstraction
As mentioned earlier, water will be required for construction, workers domestic and
dust suppression measures. Water will be abstracted from on site water system
provided by Kafubu Water and Sewerage Company at a rate not exceeding 2.5 l/s.
47
k) Waste Management
Waste management during the construction phase will include:
Provision of temporary workers sanitation.
Collection and disposal of domestic waste at ZEMA approved disposal sites.
Transportation and disposal of building waste and rubble.
Collection and disposal of used oils / lubricants according to ZEMA
Requirements and ERB standards
Fencing
It is recommended that a perimeter fence be provided that secures the entire shopping
mall. The shopping more will be situated in a central business area near some residential
houses so it is necessary to fence off the mall.
The shopping mall will have to put in place furniture in the forms of signs, demarcations
and lining, safety barriers, culvert beacons, traffic lights. The Project proposes to
introduce all the above-mentioned furniture where appropriate.
48
Firefighting equipment and communication system for safety measures on mall will be
installed.
Operational Phase
The main activities that will exist during the operation stage will be those that will relate to the
specific different parts of the development. As indicated in the foregoing, the completion of
each development phase will result into the commencement of the respective operation of the
particular facilities. The completion of the Shopping Mall will open up new avenues to the
populace for consumer shopping, trading in the tenant lots to be provided, and participation in
the varied entertainment packages that will be available. Because of the availability of open
paved spaces, leisure related activities will be highly exploited.
During these operational phases, certain activities that are likely to have an impact on the
environment include:
1) Water Supply As mentioned the average and maximum water demand of the project is
estimated at 2,508 m /day and 4,238 m /day respectively to be sourced from KWSC water
supply. Water will be stored in tanks (Sub-surface, surface or Overhead) in case of water
shortfall.
2) Commuter Traffic The volume of traffic to and from the project area will increase
appreciably once the project is operational. This will especially apply at peak times during the
day with commuter traffic and during peak shopping periods such as weekends.
3) Commercial Activities These will include retail activities at the commercial node.
4). Leisure Activities This includes activities like the shopping, and other entertainment
facilities including restaurants.
5). Estate Management Post Construction Activities relating to estate management will
include:
49
Waste Management
Solid waste management from the commercial node will be the responsibility of the centre
management who will ensure that the area is at all times clean and tidy. The facilities
provided for the separation of waste for recycling and storage will be in enclosed and caged
skips to prevent materials from being blown away from the site. An approved contractor for
disposal in accordance with NCC and ZEMA regulations will collect waste regularly.
Sewer & Storm Water Management Sewer line maintenance will include routing and
flushing the sewer mains, service calls on potentially blocked mains, repair of damaged
mains, and flushing driveway culverts.
Electrical Maintenance & Management The electrical distribution system will be
monitored and maintained on a day-to-day basis. This will be up to the distribution
board at each facility. All internal electrical maintenance will be the tenants
responsibility and must be carried out by an approved electrical contractor.
Water Management The water reticulation system will be monitored and maintained on
a day-to-day basis in conjunction with the KWSC. All internal water supply
maintenance will be the responsibility of the owners and will be carried out by an
approved plumbing contractor.
Vector/Pest Control (mosquitoes and cockroaches) One of the most effective methods
of vector control is Indoor Residual Spraying (IRS). In this method, the inside walls of
mall are sprayed with residual insecticides. Contact with the walls by any of the pests
results in their death immediately or soon afterwards. The other effective method of
mosquito control is that a person sleeps under insecticide treated nets (ITNs). The ITN
works not only by creating a barrier between the mosquito and its intended victim, but
also by killing the mosquito if it gets into contact with the net. The Management will
contract for the annual spraying of public areas of the mall with appropriate pyrethroids
to control mosquitoes and bi- annually with approved pesticide for the control of
cockroaches.
Decommissioning And Closure
Decommissioning and closure is dependent on economic and technological conditions
after the 30-year Project life.
50
Final rehabilitation will includei) Removal (or alternative use) of the redundant Mall infrastructure,
ii) Re-vegetation and re-profiling of the Mall area, and
iii) Post closure environmental monitoring and inspection.
The above-mentioned actions will effectively rehabilitate the Project site.
Sources
Mode of
Delivery
Local
Road truck
suppliers
(for concrete and
building mortar)
Laterite
Approved
Road truck
borrow pits
( for foundations and
and quarries
Aggregates
Local ZEMA
Road truck
approved
(for concrete and construction
suppliers (e.g.
Oriental and
internal road
Raube
Quarries.
Cement
Local approved
Road truck
supplier (Chilanga
51
Local
Road truck
ERB
approved
supplier
clay brick
Registered
Road truck
foreign and
local clay brick
suppliers e.g.
Kalulushi
Bricks
To be
Culverts
Road truck
manufacture
d on and off
site
Local
Road truck
suppliers
(for operation of plant
Local ERB
approved
and machinery)
supplier
Water
for
construction,
Serviced by KWS
Road truck
To be serviced by
To be supplied
dust
suppression and
domestic use
10
Electricity
52
ZESCO
11
Local
by ZESCO
Road truck
ZEMA
(e.g. timber for
approved
suppliers
window frames
polythene sheeting,
brick force and mesh
for reinforcement,
timber, sewer pipes,
paint e.t.c)
12
Imported
equipment
ensuring
Road truck
compliance
steel
with Zambian
standards and
regulations
(e.g.
structural
uPVC
and
HDPE
piping,
light
fittings,
switches,
aluminum
fittings,
switches,
air
conditioners
booster
pumps
etc)
53
operation of
catering services of the Restaurants. This will also include cleaning chemicals and
products for tertiary treatment of sewerage
5. Sewage
54
4. Exhaust air:
55
Discharges to air from the kitchens of hotel, vehicles and mall restaurants
5. Vegetative Waste
This will include leaves and grass cuttings from maintenance of landscaped areas of
the estate.
Analysis of Alternative Shopping Mall Construction
It is very unlikely that a different type of scheme would achieve the same level of
infrastructural development as that of the proposed project in terms of surfaced road
network and the implementation of a regulated water supply network.
Taking the effect of constructing a shopping mall project on the environment, other
alternatives were taken into consideration. The purpose was to assess the effects of these
alternatives on the environment against expected benefits. The alternatives considered
are:
1) Option A: Do Nothing;
2) Option B: Building on the same given site;
1.1.28.
Option A: Do Nothing;
Option A: Do Nothing;
Option A, Do Nothing Alternative
option, would
mean
that
the
current
Comparison of Alternatives
An objective assessment of the alternatives implies weighing the impacts of continuing
with the option and not continuing. The No option alternative would mean that the
Mall is not built on the proposed site and all the potential impacts on the environment,
i.e., biophysical, socio-economic and cultural would not occur. Option B would entail all
the foreseeable impacts on the bio-physical, socio-economic and cultural environment
would occur.
From the above, it can objectively be stated that considering the distance from the Ndola
and shortage of land in Ndola for such investments, the proposed site would be ideal for
construction of the mall. The main reason for preparing an Environmental Impact
Statement is to identify all the possible impacts associated with the investment and
formulate the best measures to mitigate them before implementation of the project.
57
PHYSICAL
ENVIRONMENT
OF
PROJECT
SITE
&
ITS
SURROUNDINGS
1.1Topography
The Copperbelt province lies on a plateau that slopes gently from 1,370m in
the north-west to 1,130m in the middle. The province has the Kafue River as
the main river basin that drains the Copperbelt in a wide arc from north to
south and is fed by many tributary rivers and streams principally, the
Lufwanyama, Luswishi, Kafubu and Mwambashi Rivers in the west and the
Kafulafuta River in the east.
Topographically, Ndola district lies on the gentle sloping Copperbelt pen plain
at altitudes ranging between 1,200m and 1,455m above sea level,
approximately 13 0 South and 280 35 East. Ndola has an average elevation of
approximately 1,300 m (1,200-1,450 m) above sea level. There are however
isolated hilly outcrops such as Dola, Nakaputa and Kaloko Hills. Higher
elevation is reached north-west of Ndola, where mountains form the border
with the Democratic Republic of Congo, whereas the elevation drops towards
river valleys in the East and South.
The district is characterised by undulating terrain of less than 100 slopes and
from the project area, the land gently slopes northwards towards the Kafubu
River with an average gradient of 2%. The average elevation is about 1200 m
above sea level.
1.2 Soils and Geology
The Copperbelt region of Zambia and Congo D.R. is a 500 million year old
mountain chain, the Lufilian Arc, which formed when two large pieces of
continental crust, the Kalahari Craton and the Congo Craton, collided. This
collision was one of the many that happened between 700 and 500 million
years ago to form the Gondwana supercontinent.
-1-
-2-
Jan
Feb
h
cm
Ma
Ap
Ma
Ju
Ju
Au
Se
Oc
No
3.7
0.4
0.2
2.5
13
28.
24.
17.
Dec
27.
8
(Source: www.weatherbase.com)
Recorded temperature for Ndola has ranged from as low as -20C to as high as
360C. Low temperatures have been recorded in the months of April to
September while average high temperatures are usually experienced from
October to March.
Table 4: Average relative temperature
Month
Average
Average
Temperature High
Average
Highest
Lowest
Lower
Recorded
Recorded
21
27
16
30
12
February
21
27
16
30
12
March
21
27
16
30
12
April
21
27
16
30
12
May
20
28
13
30
June
16
25
28
July
18
27
31
-2
August
21
31
12
33
September 21
32
15
36
October
24
32
15
36
November 23
30
16
34
12
December
28
17
31
11
22
(Source: www.weatherbase.com)
-3-
Average relative humidity rises from October to February and thereafter drops
to as low as 30% in September.
Ja
Fe
Ma
Ap
Ma
Ju
Ju
Au
Se
Oc
No
De
75
75
69
61
52
47
43
36
30
33
54
71
(Source: www.weatherbase.com)
Wind directions are dominated by winds from the northeast through to the
southwest with maximum gusts ranging from 30 m/s in summer to 22 m/s
during the inter months.
The average wind speed of Ndola is 3.3m/s. A high frequency of light winds
occurs at Ndola, with 40 % of all winds less than 3.4 m/s. The highest
frequency of winds is from the sector east-northeast to east-southeast, with
more than 20% of all winds from the east. The strongest winds occur in this
sector and reach 8.5 m/s on 5 % of occasions, mainly in August and
September. On rare occasions the winds exceed 8.5 m/s.
Ambient air quality data is not available for the project site. However,
observations made during visits showed that the air was generally good.
Visibility was not Impaired no foul smell was observed. Some individuals
working in the environs of the project site where interviewed whether they
have been affected by any form of air pollution. The answer was that they
-4-
have not been affected so much apart from occasional smoke emissions from
plant operations and burning activities.
They also have a feeling that the air quality was generally clean. Being an
industrial area air quality was expected to be compromised but the actual
situation is different due to low industrial activities taking place in the area.
The project site being located in the central business area is vulnerable to noise
pollution. Key sources observed included vehicular traffic, plant machinery
operations and occasional train movement. Occasional noise is also recorded
from neighbouring plant machinery and vehicles on the roads such as T-3,
President Avenue and Chisokone Avenue. However, noise levels are generally
low. Snap survey conducted during the day around the project site using a
Decimeter showed noise levels ranging 50- 85 dB. The main source of noise
peaks observed was vehicular movement.
1.4 Hydrology and Drainage
Surface Water
The Copperbelt province is mainly drained by the Kafue River. The River
flows through the province in a wide arc from north to south and is fed by
many tributary rivers and streams principally, the Luswishi,Lufwanyama,
Kafubu and Mwambashi Rivers in the west and the Kafulafuta River in the
east. The City of Ndola is drained by the Kafubu River, which passes through
most of the town with its tributary streams such as the Kandola stream. Other
tributaries include the Kabushi seasonal stream towards the west. Run off
water from the site drains into Kafubu. However, there are no streams on the
specific kafubu shopping mall plot and its immediate areas of influence.
There are no aquatic water quality standards established for Kafubu river.
However, a study conducted by African Mining Consultants to establish water
quality of the Kafubu River using water collected from Kafubu river about 120
metres away from the proposed site showed that the water was generally of
good quality except for feacal coliforms, lead, iron, chromium, cadmium and
manganese which were above the Zambian Drinking Water Standards of 0/100
-5-
ml, 0.05 mg/l, 1.0 mg/l, 0.05 mg/l, 0.005 mg/l and 0.05 mg/l respectively
check appendix for the results.
Ground Water
Borehole data from sites drilled by Department of water Affairs in the area and
its surrounding indicate that the average depths of boreholes range from 3560m, with the water often stuck at depths ranging from 4-25m. Average
borehole yield from a 165mm bore is in the range of 2.5-11 litres per second
with an average draw down of 30.8 meters. Water samples collected from a
borehole near the proposed site at the golf club about 30 meters away showed
that the water was of good quality and complied with drinking water quality
standards. Check the appendix for the results attached
1.5 Water and Sanitation
All water in Ndola is supplied through a company called Kafubu Water and
Sewerage Company. This campany is charged with the responsibility of
providing water supply and sewerage services to the urban and peri-urban
areas of Ndola. The population coverage to these areas is estimated at 80%
and 60% for water and sewerage services respectively.
The water supply in Ndola is presently derived from both surface and
underground sources, with surface sources accounting for approximately 60%
of the total supply. Surface supplies are derived from the Itawa and Kafubu
impoundment's both of which are situated at the Kafubu River while
underground supplies are derived from two well fields in the Misundu area
developed in the 1980s to augment existing surface supplies.
The City is serviced by three sewage collection systems within two sewage
catchment areas. The first system serves Pamodzi, Chifubu, Kawama,
Kansenshi and parts of Northrise in the northern catchment and conveys
sewage to New Kanini Sewage Treatment Plant. The second system caters for
the Central Town area, Kanini, Hillcrest and remainder of Northrise and
Kansenshi, with sewage being pumped to Old Kanini Sewage Treatment Plant
-6-
through Itawa and Dambo pumping stations. The third system caters for the
southern supply district, and conveys sewage by gravity to Lubuto Sewerage
Treatment Plant. It was noted that sewers in the high cost and central business
district are generally in good condition with only a few blockages being
reported or noticed and Kafubu Water and Sewerage Company usually fix
them. However, most of the sewers in the low-cost housing areas no longer
have the capacity to effectively convey the high sewage flows as they now
cater for populations far in excess of the design capacity, resulting in frequent
flooding. The affected areas in this regard are mainly Chifubu, Main Masala
and Kabushi.
-7-
BIOLOGICAL ENVIRONMENT
Flora and Fauna
Ndola has the Mansansa Forest Reserve, located westwards of the City, and
with the Chichele Plantation attached to it. The project site however, is a
brown field, designated as light industrial area whose anthropogenic activities
continue to impact on the floral species of the area. Vegetation at the project
site mostly comprise of ornamental plants with very limited natural vegetation.
Fruit trees include mango, guava and apple trees (see figures 1 and 2 below).
Grass mainly comprise of couch grass (cynodondactylon).
-8-
The project area is a brown field, designated as an industrial area that has been
affected by years of anthropogenic activities. However, the few faunal species
near the project area are bird species such as tits, crows, pigeons, owls, and
goshawks. Rodents are found around the butter and soap plants. Insect species
found in the general locality of the site include mosquitoes, wasps, bees,
cockroaches, grasshoppers, butterflies, houseflies, aphids and dragonflies.
-9-
SOCIO-ECONOMIC ENVIRONMENT
Demographic Profile
Households
Male
Female
Total
Kanseshi
2,514
6,586
6,369
12,955
Nkwazi
4,600
10,713
10,689
21,402
Yengwe
3,570
9,376
10,689
21,402
Chipulikusu
7,651
18,526
18,814
37,340
Kanini
2,683
6,410
6,708
13,118
Twapia
6,034
14,316
14,819
29,135
Dag
2,335
4,860
5,044
9,904
305
677
663
1,340
Hamarskjoerd
Kaniki
- 11 -
Ndola District has a varying range of industrial and economic activities that
form land use activities.
The majority of the population practice subsistence farming with maize being
the major crop grown. This is mainly for household consumption. Some
households are involved in the growing of vegetables such as rape, cabbage
and tomatoes. As referred to above, substantial acreage of land in Ndola is
reserved for the Mansansa Forest Reserve while another piece of land has the
Chichele Plantation on it.
The land use activity around the project area is predominantly light industrial
as well as residential and the area is designated as a central business centre
area by the local authority. They are no change in the land use and that no
impacts will be associated with this in line with the development .The project
will also not result in the damage to agriculture assets as well as fisheries. The
council has given a go ahead of the project meaning that land use and other
associated factors were considered check appendix for council approval.
1.1.34.
Settlements
- 12 -
CULTURAL ENVIRONMENT
Cultural Resources
1.1.35.
- 13 -
Letters stating the objectives of the project and requesting local participation
and consultation in the process were also distributed.
- 15 -
Concern as to whether the much-talked about shopping will not be just like other malls that have failed to be
complited.
Concern as to what will happen to settlements near the project area in terms of dust pollution.
Concern as to what will the developer do to the fencing during the construction phase .
Concern of illegal sand and stone mining activities.
Quarries & borrow pits
Abandoned borrow pits pose hazards to the nearby community and animals .
Lack of consultation between contractor and local community on the sites for excavation of laterite
Lack of consultation between contractor and local community on the sites for camp sites
Concern that over exploitation of local water sources for construction works might lead to water shortage to the
sources.
local community.
Investigate the role of the Labour Department in the recruitment of local people.
Employment opportunities
Concern that employment opportunity for local people should not be restricted to unskilled labour but also skilled
labour.
Local government under the community development should be involved in the HIV/AIDS programmes
- 16 -
pregnancies.
Sensitive Areas
Drainage design/Culverts
- 17 -
Community Concerns
Concern that the project benefits to the local people are not known.
community.
Concern that the roles of the District Council & the community at project implementation level are not known.
District/Community role in the
Concern that the duration and cost of investment are not known project and the cost of rehabilitation are not known.
project
- 18 -
Within the construction phase some activities involving site installation, stock
piles preparation, quarrying, construction of detours, access roads, plant park
sites and drainage excavation will cause soil destabilisation. Soil compaction
by plant machinery and vehicles movement will lead to reduced groundwater
yields.
Abandoned excess laterite and stone aggregate littered around stock pile areas
after construction is completed change the soil structure in the surrounding
- 19 -
areas. Similarly devegetated areas resulting from post excavation and grading
works including drainage channels enhance soil erosion on discharge areas.
Impacts on Vegetation
The ecological value of the inundated forests and woodlands to the riverine
ecosystem cannot be ignored in that such vegetation stands contain several
niches for diversity of animal species. Should the design of the shopping mall
confine the extent of land clearing to the limits of the shopping mall reserve,
then this will not affect vegetation in the outlying areas. However, trees within
the shopping reserve should be preserved for ecological and aesthetic reasons
Dust raised from gravel access roads by haulage trucks during the
transportation of laterite, stone aggregate, cement, lime, petroleum products
and other chemicals including emissions from plant machinery and vehicles
hamper normal growth of vegetation. Similarly Poor disposal of toxic waste
and petroleum products hampers normal growth of vegetation.
- 20 -
At the project site, the Contractor will set up temporary camp for its labour
force and will require sanitation facilities such as pit latrines. Construction of
sub-standard pit latrines for campsite labour force may contaminate
groundwater due to seepage to the groundwater.
works and construction of drainage channels may increase runoff which will
lead to sedimentation and increased turbidity in surface water as well as
reduced groundwater infiltration.
Further hazardous materials spilled from haulage vehicles and washed into
water sources will result in water pollution.
Impacts on Air Quality
Emissions to the air in form of exhaust fumes and dust from vehicles and
machines may cause nuisance to the closest surroundings. Dust raised from
gravel access roads by haulage trucks during transportation of materials will
also pollute the air of the immediate local environment.
The noise levels of machines and vehicles vary widely and depend on the type
of noise generated and level of activity. A front end loader has for instance a
- 22 -
power level of 100dB(A) while a truck will have a power level of 85 dB(A). In
the worst case a combined power level of 115 dB(A) will be in place during
construction which will result in the 50 dB(A) contour being located at a
maximum 250m from the construction site. However since the equipment will
never work at exactly the same location the 50 dB(A) contour will be confined
to the construction site and within the airport reserve area.
- 23 -
- 24 -
Quarries and borrow pits impact on the visual and aesthetic view. The
excavated areas become prone to soil erosion during rain season and can
contaminate nearby surface water.
However, improved sight lines and replacement of road furniture will reduce
some accidents. Overall, the potential impact of an increase in accidents is
considered significant and negative.
Impacts of Work Accidents
During construction phase, the construction teams will interact with the nearby
communities and can cause social upheaval and transmit diseases (STDs,
HIV/AIDS) to the communities living along the route. However since the road
has been in existence for a number of years, it is likely that the community has
- 27 -
- 28 -
Site, the impact could affect the whole or measurable portion of the site.
Whether it is limited to the immediate area of the proposed project;
- 29 -
Local, the impact could affect the extended area adjacent to the site
perhaps a neighborhood or small town. Whether it would affect environs
up to 15km outside the immediate environment;
Regional, that impact could affect the area including the outlying areas of
the city, the transport routes and the adjoining towns.
Short term, the impact will either disappear with mitigation or will be
mitigated through natural process in a span shorter than the construction
phase.
Medium term, the impact will last for the period of the construction
phase, thereafter it will be entirely negated.
Long term, the impact will continue or last for the entire operational life
of the development, but will be mitigated by direct human action or by
natural processes thereafter.
- 30 -
impacted environment, alter its functioning, or slightly alter it? These are rated
as follows:
Low, where the impact will not have significant influence on the
environment, and this will not be required to be significantly
accommodated in the project design or implementation; the impact alters
the affected environment in such a way that natural processes of functions
are not affected in any significant way.
This will be a relative evaluation within the context of all the activities and
the other impacts within the framework of the project. Note that some
impacts have a high intensity and a short duration with no permanent audio
effects.
Probability
This describes the likelihood of the impacts actually occurring. The impact
may occur for any length of time during the life cycle of the activity, and not
at any given time. The classes are rated as follows:
Unlikely, the probability of the impact occurring is very low, due to either
the circumstances, design or experience.
- 31 -
Probable, it is most likely that the impact will occur at some or other stage
of the development. Plans must be drawn up before the undertaking of the
activity.
Definite, the impact will take place regardless of any prevention plans, and
only mitigatory actions or contingency plans can be relied on to contain
the effect.
Determination of Significance
Significance is determined through a synthesis of impact characteristics or
combination of effects. Significance is an indication of the importance of the
impact in terms of physical extent, intensity and time scale, and therefore
indicates the level of mitigation required.
Negligible, the impact is not substantial and does not require any
mitigatory action.
Low, the impact is of little importance, but may require limited mitigation.
From the baseline information assembled in the previous chapter coupled with
the information gained during the consultation stage, the expected
environmental impacts can be categorised into positive and negative impacts.
The indirect impacts are primarily socio-economic and extend beyond the
project implementation. The indirect impacts include changes in economic
activities and long-term changes, such as increased land degradation due to
increased settlement and development near the runway.
Unlike the direct impacts, which occur in the immediate environment, the
indirect impacts would be felt in the adjacent regions.
- 33 -
Impact
Type of
Spatial
Impact
Extent
Duration
Intensity
Probability
Determination
of Significance
Impacts on Soil
Design
None
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Medium
Low
Unlikely
Negligible
term
Medium
Direct
Site
term
Moderate
Probable
Moderate
Direct
Site
Medium
Moderate
Probable
Moderate
Moderate
Probable
Moderate
Moderate
Probable
Moderate
methods.
Exposed soil is prone to erosion by water or wind.
term
Stripping and stockpiling of topsoil could lead to
Direct
Site
compaction
could
result
term
following
Direct
Site
construction activities.
Soil erosion near runway culverts and drainage
Operational
Medium
Medium
term
Indirect
Local
Long term
Moderate
Possible
Moderate
Indirect
Local
Long term
Moderate
Possible
Moderate
Impacts on Vegetation
- 34 -
Design
Construction
None
Retardation
n/a
of
vegetation
growth
due
n/a
to
n/a
n/a
n/a
n/a
Low
Unlikely
Moderate
Moderate
Probable
High
Medium
Direct
Local
term
emissions.
Loss of vegetation due to site clearing which will
lead to loss of habitat and displacement of fauna
Medium
Direct
Local
- 35 -
term
Impact
Type of
Spatial
Impact
Extent
Duration
Intensity
Probability
Determination
of Significance
Indirect
Site
Long term
None
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Long term
Moderate
Possible
Moderate
Indirect
Site
Long term
Moderate
Possible
Moderate
Direct
Local
Long term
Moderate
Possible
Moderate
Indirect
Site
Long term
Moderate
Possible
Moderate
None
n/a
n/a
n/a
n/a
n/a
n/a
Indirect
Local
Long term
Moderate
Probable
Moderate
the mall
Low
Possible
Moderate
habitat.
Operational
- 36 -
Indirect
Site
Long term
Moderate
Probable
Moderate
Indirect
Local
Long term
Moderate
Possible
Moderate
- 37 -
Impact
Type of
Spatial
Impact
Extent
Duration
Intensity
Probability
Determination
of Significance
None
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Local
Short term
Moderate
Probable
Moderate
Direct
Site
Short term
Moderate
Probable
Moderate
Indirect
Site
Long term
Moderate
Possible
Moderate
None
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Short term
Moderate
Probable
Moderate
Indirect
Site
Long term
Low
Possible
Low
n/a
n/a
n/a
n/a
n/a
n/a
Operational
Impacts on Noise
Design
Construction
- 38 -
Construction
Direct
Local
Moderate
Moderate
Definite
Moderate
Direct
Site
Moderate
Low
Probable
Moderate
construction
structures,
excess
- 39 -
Impact
Type of
Spatial
Impact
Extent
Duration
Intensity
Probability
Determination
of Significance
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Local
Short term
Moderate
Possible
Moderate
Indirect
Local
Short term
Moderate
Probable
Moderate
Indirect
Site
Long term
Low
Possible
Low
n/a
n/a
n/a
n/a
n/a
n/a
Indirect
Local
Short term
Moderate
Probable
Moderate
surrounding environment.
If labour is not recruited from local areas people
who reside far may start to settle near the project
site.
Operational
more
chances
of
transmission
of
sexually
- 40 -
Operational
Indirect
Site
Long term
Moderate
Possible
Moderate
n/a
n/a
n/a
n/a
n/a
n/a
Indirect
Site
Short term
Moderate
Probable
Moderate
Direct
Site
Long term
Moderate
Probable
Moderate
Direct
Site
Long term
Moderate
Probable
Moderate
Construction
Operational
- 41 -
Impact
Type of
Spatial
Impact
Extent
Duration
Intensity
Probability
Determination
of Significance
None
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Long term
Moderate
Probable
Moderate
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Medium
Moderate
Probable
Moderate
Moderate
Definite
Moderate
Operational
None
Construction
term
Direct
Local
Medium
term
Indirect
Local
Long term
Moderate
Possible
Moderate
Direct
Local
Short term
Low
Possible
Moderate
- 42 -
Indirect
Local
Medium
Moderate
Probable
Moderate
term
Direct
Site
Short term
Low
Probable
Moderate
Indirect
Site
Long term
Moderate
Possible
Low
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Medium
High
Low
Moderate
n/a
n/a
n/a
n/a
n/a
n/a
Construction
Operational
None
- 43 -
Impact
Type of
Spatial
Impact
Extent
Duration
Intensity
Probability
Determination
of Significance
Construction
n/a
n/a
n/a
n/a
n/a
n/a
Direct
Site
Short term
Moderate
Probable
Low
Indirect
Site
Short term
Low
Probable
Moderate
Indirect
Site
Short term
Moderate
Probable
Moderate
n/a
n/a
n/a
n/a
n/a
n/a
Operational
None
- 44 -
MITIGATION MEASURES
This section proposes mitigation measures for identified potential impacts as
discussed in earlier chapters. Mitigation measures are actions that are intended
to avoid, alleviate or reduce environmental impacts on the environment.
Mitigation measures form a basis on which an Environmental Management
Plan has been formulated. The mitigation measures are set forth to maximize
positive impacts and minimize negative impacts as a result of the proposed
development.
Mitigation Measure
Impact
storage
of
oil
disposal
methods.
products
dispensing
enough
to
contain
any
spillage.
Construction
Phase
periods;
Protection
of
susceptible
soil
- 45 -
soil quality.
be
preferred
for
stock
piles.
compaction
result
could
following
the
construction activities.
Only
heavy
equipment
with
Operational
Phase
especially
and
drainage
channels
near
culverts
by
culverts;
increase.
- 46 -
Regulation
of
waste
Mitigation Measure
Impact
Operational Phase
un-maintained vehicles.
Retardation
Impacts on Vegetation
Construction Phase
of
vegetation
water;
Haulage
emissions.
trucks
shall
not
per hour.
Operational Phase
preferred;
fauna
species,
especially
avifauna.
Provision
conservation
programme
the site.
of
forest
awareness
to
communities
mall
Impacts on Wildlife and Wildlife Habitat
Construction Phase
Construction
should
be
reserve area;
Noisy
activities
scheduled
to
occur
prescribed
normal
to
be
within
working
hours.
Aadequate signs for warning
Operational Phase
be provided;
Install
bird
mall parameter
- 47 -
and
animal
vehicular traffic.
pitched;
and culverts.
scour checks;
Drainage
systems
discharge
into
shall
settlement
basins;
Silt traps shall be put along
drainage systems;
- 48 -
Mitigation Measure
Impact
Construction Phase
(Cont'd)
community
over
the mall.
local
due
to
authority
consent
from
and
with
the
local
community.
Ground water contamination
for workers.
proper
maintenance
of
pit
latrines.
Operational Phase
turbidity
for
in
surface
water
other
works
such
as
shoulder building;
stone pitched;
construction works.
Construction Phase
pollution
caused
by
Regular
maintenance
of
construction
also
site;
disturb
habitats
for
vehicles
and
Cleaning
waste management.
unpleasant odours.
and
Waste should be
regular
carefully
- 49 -
Operational Phase
un-maintained equipment.
Impacts on Noise
Construction Phase
construction
light only;
machinery,
by
the
Factories
Operating
traffic movement.
hours
will
be
- 50 -
Mitigation Measure
Impact
Design Phase
Development
compatible
with
surrounding environment.
angles
the
of
the
slope
of
the
mall
surrounding
environment.
Construction Phase
Abandoned
Operational Phase
construction
materials
demolished
of
laterite,
stone
people
with
the
necessary
skills
employed
for
works;
Resettlement of communities
advance.
shall
the
with
be
runway
host
or
existing community.
Construction
detours
of
will
environment
Construction Phase
immediate
temporary
disturb
access
roads
and
the
the
surrounding
within
and
Detours,
environment.
- 51 -
Local
people
with
the
necessary
Resettlement of communities
project. area
skills
consultation
shall
with
be
host
or
on
air
existing community.
ZEMA
Operational Phase
Exhaust
fumes
to
the
Regulation
pollution;
Adherence
to increased traffic.
maintenance
standards
to
engine
schedules
and
reduce
air
to
pollution.
Impacts on Socio-economic Environment
Construction Phase
chances of transmission of
community
workers
etc.
with
local
communities.
- 52 -
on
STDs
and
Mitigation Measure
Impact
Operational Phase
speed retarders
Ndola Council to push for
improvement of major roads to
the project area.
access
roads
and
Poorly
mall
developed
design
could
shopping
impact
National
Heritage
Conservation
Commission
shall apply.
Detours,
access
roads
and
may
disfigure
the
Historic site
the
National
Conservation
Heritage
Commission
shall apply.
Detours,
access
roads
and
heritage site.
Heritage
Commission
shall apply.
Impacts on Human Settlements
Construction Phase
Rehabilitation
on
human
foreseen
settlements
since
are
construction
- 53 -
area;
shall
be
Detour,
shopping
however,
mall
reserve
construction
of
access
roads
and
areas
sites
and
conflicts.
residential
areas
shall
be
done
in
area
The
Operational Phase
construction
of
the
accessibility,
mobility
and
- 54 -
Mitigation Measure
Impact
Operational Phase
(Cont'd)
and
commercial
around
shopping mall.
traffic
volumes
improved
using
runway
communities
the
disturbs
around
the
runway.
the
constructed
Construction Phase
Quarries
and
borrow
pit
nearby communities.
communities.
Operational Phase
settlements.
- 55 -
Design Phase
Failure
to
use
established
routes
might
result
in
on
the
environment.
- 56 -
surrounding
Mitigation Measure
Impact
traffic
could
reduce
undisturbed areas.
impacting
Construction
on
vehicles
must
that
should
be
dust
construction
could
from
disturb
Control
of
dust
through
nearby communities.
Operational Phase
Design Phase
Development
requirements
procedures
of
and
safety
operational
manual.
Construction Phase
impact
negatively
on
construction workers.
Impacts of Construction Camps
Advanced
Design Phase
planning
of
authority,
the
- 57 -
local
Loss
of
vegetation
at
construction site.
Construction Phase,
Interaction
workers
of
with
construction
the
communities
may
transmission
of
nearby
lead
to
sexually
transmitted diseases.
people
necessary
skills
with
shall
- 58 -
the
be
- 60 -
Management
Agency,
Government
agencies,
Local
Authorities, the affected Local Communities, the shopping mall users and to
some extent the Public.
- 61 -
appropriate, all surface runoff from areas of disturbance and areas with
elevated runoff coefficient will be directed by correctly designed drainage
system, to sediment traps with sufficient volume and retention time to
maximise settlement of suspended sediment prior to release.
The drains will be designed according to the characteristics of peak flows for
the pre-determined design storm, and the requirement to discharge flows
without causing erosion.
Construction Waste
Construction waste will be generated as a result of the shopping mall
construction. All construction waste that has been generated will be recycled
or placed in designated disposal sites and covered with soil.
Noise.
Noise management will be limited to standard sound retarding devices on all
operational vehicles as recommended by the manufacturer. Noise generated
from operations at the project site is not expected to impact on local
communities due to the distances between the operations area and areas of
habitation. However, Kafubu mall limited and ZEMA will investigate any
noise complaints received.
Rehabilitation
Rehabilitation will be ongoing and progressively throughout the life of the
project. Evidence to date indicates that the re-vegetation of disturbed areas
will be both natural and rapid. As the first principle of rehabilitation is long
term stability, practices that address this issue will be implemented as part of
long-term approaches.
- 64 -
Workforce Awareness
Work force awareness and culture is an important component in minimising
environmental and cultural impacts resulting from project operations.
Construction personnel will be made aware of the Environmental Policy.
The Mall will have fire extinguishers and hydrants for the purpose of putting
off fires. The mall will also have clearly marked assembly points in the
event of fire where people will be required too assemble. The managers
office will direct response to fire but only in the absence of fire men.
Announcements will be made through the public address system at the mall.
decontamination)
could
be
adapted
for
sustainable
use
Activity
Responsible Personnel
Cost (ZMK)
of
applicable
Environmental Officer
4) Removal of all the steel scrap, non-steel General Manager and 10,500,000
scrap for alternative uses or disposal.
Total Costs
- 66 -
Environmental Officer
- 67 -
Mitigation Measure
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Soil
due
contamination
to
improper
Petroleum
Petroleum
Concrete
products
products
Construction
dispensing points
dispensing points
Phase
KML
loading bay
storage of materials,
shall
have
drip
shall be inspected
Approx US$
pans
and
oil
and approved by
oil absorbents
200/m3
absorbents ;
DCA
put in place
Officers
of
To avoid direct
potential
contact
soil
Construction
placed
pollutants such as
chemicals shall be
Phase
concrete hard
fuel,
chemicals in case
inspected
Surfaces shall
standing.
of accident.
approved by KML
oil
and
chemicals should
of
and
KML/ZEMA
Tanks to be
be sealed
be done on sealed
Officers
from
Concrete @
surfaces
to
ZEMA
before
US$200/m3
prevent
soil
commissioning.
contamination;
- 68 -
on
Collection
and
To reduce on the
Containers
recycling of used
amounts
oil
collection of used
waste
generation
and storage.
available on site.
One drum @
of
for
Construction
Contractor
Metal drums
Phase
KML
for collection
US$20
- 69 -
Mitigation Measure
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Construction
Contractor
Reinforced
petroleum spillage
tanks
Phase
KML
concrete wall
from spreading in
inspected
storage of materials,
case
high
accident.
contain
Soil
due
Petroleum storage
To
improper
contamination
to
enough
to
contain
of
any
an
any
spillage.
Limitation
shall
be
and
Storage tanks
approved by KML
will
have
bottom.
Officers
from
bund
walls
ZEMA
before
US$55/m2
around them
commissioning.
of
To avoid erosion
Period
of
earth moving to
of soil by fast
construction shall
Construction
dry periods;
flowing rainwater.
be specified in the
Phase
Tender Document
Monitoring of
to erosion by water or
with
earth moving
wind.
contractor
the
machines
dry land
- 70 -
to
Contractor
US$6.50/m3
KML
of gravel
Protection
susceptible
of
To
control
the
Mitigation
soil
Construction
flowing rainwater.
impact shall be
Phase
provided in the in
Grass
the Document.
planting
Protection
of
drainage channels
contact
fast
grass planting in
Construction
by planting grass
flowing
surface
drainage systems
Phase
or stone pitching;
water
with
Planting grass
overall Document
or
as
pitching
susceptible soils.
means
mitigating
erosion.
- 71 -
of
soil
US$2/m2 for
KML
planting
turf/grass
To avoid direct
of
Contractor
Contractor
US$2/m2 for
KML
planting
turf/grass
stone
US$50/m2 for
stone pitching
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
of
To
trap
soil
Mitigation
sedimentation
measures
to erosion by water or
basins or planting
wind.
of
flowing water.
erodible
surfaces as soon
as possible.
Excavate
Construction
KML
common soils
impacts on soils
Phase
Consultant
@ US$3/m3
Installation of
Excavate
contract
sedimentation
rock
Document
for
with
and
soil
To prevent highly
Mitigation
stockpiling of topsoil
should be avoided
measures
by selective soil
getting exposed to
stripping;
erosion.
quality.
Exposed
basins
Construction
KML
impact is part of
Phase
Consultant
the
contract
Selective soil
with
stripping will
Document
the contractor.
- 72 -
be done
US$50/m
Contractor
this
in
3
the contractor.
Stripping
in
US$2/m3
Areas
requiring
To limit on the
Mitigation
measures
be preferred for
to erosion.
stock
piles.
Contractor
this
Construction
KML
impact is part of
Phase
Consultant
the
contract
Clearing will
with
only be done
Clearing shall be
Document
the contractor.
in
approved by the
US$1.50/m3
approved
areas
local authorities.
Soil compaction could
Only
result
following
construction activities.
heavy
Mitigation
Contractor
For
equipment
with
of area prone to
measures
Construction
KML
activities use
pneumatic
tyres
compaction.
impact is part of
Phase
Consultant
the
shall be used on
the
Pneumatic
access roads.
Document
this
contract
the contractor
with
tyres are to be
used on the
access roads
- 73 -
rolling
rate
US$30/hr
of
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
erosion
near
should
prevented
especially
velocity
increase.
could
erosion
be
near
To
control
soil
Programme
Shopping
for
mall
Operational
KML
Phase
headwalls,
drainage
Culvert
aprons, wing-
maintenance shall
construction
walls
culverts
by
requiring
be developed and
will be done
construction
of
attention.
made available.
to
design
culverts;
standard
To
prevent
Contractor
Linear
Construction
KML
maintenance
Consultant
of the culverts
maintenance
of
clogging of the
measures
culverts
&
culverts
impact is part of
Phase
drainage channels;
drainage
the
Regular
&
the
system
contract
by debris carried
Document
the contractor
with
@ US$50/m
maintenance
schedule will
be
place
- 74 -
US$200/m
and
Mitigation
this
@
3
specific
correctly designed
Regular
Concrete
put
in
Soil contamination by
Soil
To control waste
Enforcement
contamination by
disposal methods
ZEMA
Regulations
spillages of mall
users
of
Operational
Shopping mall
ZEMA
Phase
users
monitoring
Waste
ZEMA
activities
waste
management
KML
management .
system will be
on
put in place
- 75 -
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Impacts on Vegetation
Retardation
of
Dust
control
by
application of water;
To suppress dust
Mitigation
generation
measures
Construction
this
Phase
Water
KML
bowsers
to
to contamination from
impact is part of
The
ground
water
gravel
the
will
be
DCAs
emissions.
Document
contract
with
watered
U$50/hr
Construction
N/A
the contractor
Haulage trucks shall
To
amount
generation.
hour.
reduce
of
the
Mitigation
dust
measures
this
Phase
impact is part of
Speed limited
the
to 60km per
contract
Document
the contractor
- 76 -
with
hour
KML
Less
areas
preferred;
habitat
vegetated
shall
be
and
To
reduce
the
Mitigation
this
Construction
Contractor
US$1.50/m2
Phase
KML
to clear less
measures
without
impact is part of
vegetation.
the
will
be
cleared
of
contract
vegetated area
displacement of fauna
Document
species,
the contractor
vegetation
To sensitize the
Forest
Construction
Forestry Dept
US$15,000
conservation
Phase
KML
for awareness
especially
with
avifauna.
Increased access as a
Provision
result
conservation
communities
could
awareness programme
about
increased
to communities around
importance
forests.
of
the
construction
lead
to
deforestation
area.
in
mall
the
of
forest
the
of
programme
is
programme
Operational
Phase
its implementation
Forest
schedule
conservation
prepared.
is
will
be
encouraged
such as tree
planting
- 77 -
Mitigation Measure
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Construction
should
of habitat.
confined
to
To reduce on the
Mitigation
be
measures
the
to
impact is part of
Construction
gravel
the
will
be
outside game
restricted
to
area
proposed site
be
impacted
upon.
this
contract
Document
with
the contractor
Noisy activities to
To reduce sleep
Mitigation
be scheduled to
disturbance
measures
occur
Construction
Contractor
Haulage
Phase
KML
suitable
of
from
the proposed
US$0.35/m3.
site
km
Construction
Contractor
Haulage
Phase
KML
suitable
impact is part of
Construction
Consultant
gravel
prescribed normal
the
contract
will restricted
Local
outside game
working hours.
Document
with
to day time
Authority
area
within
to
this
the contractor
only
from
US$0.35/m3.
km
- 78 -
of
To warn motorists
Mitigation
accidental
of the presence of
measures
caused by speeding
have
wildlife in certain
construction traffic .
sections
users of wildlife
road
presence;
motorists
killings
adequate
of
so
Construction
Phase
KML
US$100/each
impact is part of
Operational
Local
on average
the
the
Phase
Authority
that
Document
drive
this
KML signs @
contract
the contractor
with caution.
with
Signs will be
used
as
warning
to
- 79 -
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
There
accidental
adherence
be
To control over-
Provision of speed
Operational
Police Traffic
Speed humps
to
speeding through
retarders
and
Phase
Patrol Unit
provision
Speed
Local
each
roads
will be used
authority
mounting of speed
Partial fencing of
control traps.
shopping mall
Control of noisy
To monitor and
Enforcement
Operational
Local
Working
Noise disturbance to
activities on site
control
local by-laws.
Phase
Authority
hours limited
wildlife
generation.
ZEMA
to day light
killings
caused by speeding
shall
speed
traffic
increased
due
to
vehicular
of
noise
of
Local
laws);
will
traffic
applied
- 80 -
limit
laws
be
only.
US$500/
ZEMA Regulation
To monitor and
Enforcement
on
control
ZEMA
Abatement;
Noise
generation.
noise
Regulations
noise
of
on
Operational
Local
Phase
Authority
Noise
generation
will be within
the law
- 81 -
N/A
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
of
of
the
To filter of the
Mitigation
Construction
Contractor
Grassing
water
drainage shall be
sediment particles
measures
impact is part of
Operational
erosion
or stone pitched;
the
Phase
Stone pitching
Document
Stone pitching
@ US$50/m2
avoid erosion of
the contractor
will be used
the
Mitigation
Construction
Contractor
Using
of
measures
Phase
KML
masonry
of
nearby
this
contract
with
Phase
KML
US$3/m
soil surfaces by
stone pitching.
Drainage systems
To
reduce
current
checks;
rainwater flow.
this
impact is part of
Operational
the
Phase
contract
Document
the contractor
with
The drainage
will
have
scour checks
- 82 -
stone
US$12 each
at
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Siltation
of
water
of
To protect surface
Mitigation
water
measures
systems;
through
nearby
pollution
filtering
this
Construction
Contractor
Approx
Phase
KML
US$10/m
US$15 each
impact is part of
Operational
finest particles in
the
Phase
water current.
Document
contract
with
the contractor
To
excessive
and
control
risks
erosion.
flow
of
Mitigation
Construction
Contractor
measures provided
Phase
KML
for
Operational
impacts
Water
on
Quality
Phase
Spoon drains
overall
will
Document
contract
be
provided with
scour checks
- 83 -
Exploitation
To avoid conflicts
Mitigation
and
measures
construction
impact is part of
Permit will be
when
construction works.
works
local community.
the
obtained
are
done
shall
of
be
with
approval by the
to
receive
this
contract
Document
the contractor
- 84 -
with
Construction
Contractor
Nominal
Phase
KML
exploitation
obstruction
rights
for
works
not
reconstruction
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
water
To filter pollutants
Mitigation
Construction
Contractor
VIP latrine @
contamination due to
measures provided
Phase
KML
US$600 each
construction of sub-
water
ground water.
for
on
Water logged
areas;
Quality
areas will be
logged
impacts
Water
avoided
overall
siting
contract
Document
for
with
contractor
Good
standards
hygienic
and
To
promote
cleanliness
proper
avoid
maintenance of pit
in
latrines.
camps.
and
epidemics
construction
Mitigation
Construction
Contractor
Cleaning
measures provided
Phase
KML
activities
for
Public health
US$150/
and
month
impacts
Water
on
Quality
health
overall
contract
practice
be used
contractor
- 85 -
good
will
Sedimentation
and
increased turbidity in
Excavated
soils
To make use of
Mitigation
Construction
Contractor
For
measures provided
Phase
KML
soil
reduce on creating
for
by erosion of bare
as backfilling
Water
areas
and
runoffs
resulting
from
impacts
U$6.50/m
soils will be
used
spreading and
overall
backfilling
Quality
contract
and
Document
grading
and
the contractor
@
3
Excavated
excavation
works
construction
works.
- 86 -
on
gravel
with
to
for
compacting
@ US$2/m2
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
To filter of the
Mitigation
Construction
Contractor
channels shall be
sediment particles
measures provided
Phase
KML
susceptible
for
Operational
soil, grassing
or stone pitched;
Water
Phase
@ US$3/m2
increased turbidity in
Stone pitching
avoid erosion of
overall
will be used
US$3/m3
by erosion of bare
soil surfaces by
Document
areas
stone pitching.
the contractor
Sedimentation
and
and
runoffs
resulting
from
Drainage systems
To
excavation
and
current
grading
and
checks.
rainwater flow.
works
reduce
the
of
impacts
on
Quality
contract
with
Mitigation
Construction
Contractor
US$12
measures provided
Phase
KML
stone masonry
for
Operational
impacts
on
Water
after
Scorching
overall
checks will be
construction
works.
Quality
contract
- 87 -
Phase
used
each
Regular
maintenance
construction
vehicles
equipment
will
affect
vegetation
human,
and
also
disturb
habitats
for
animals,
birds
and
insects.
To
of
check
defects
for
Log
and
vehicle
book
on
Construction
Contractor
US$30,000/
&
Phase
KML
month
for
servicing of the
equipment
Regular
medium
vehicles
and
maintenance shall
maintenance
old equipment
in
equipment so that
of
order to reduce
inspection
construction
emission
operation
vehicles will
condition.
overall
be done
exhaust fumes;
and
of
and
contract
- 88 -
to
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
down
on
temporary roads;
To suppress dust.
Construction
Contractor
control
Phase
KML
times
Periodic water
shall be kept on
down on the
temporary
roads will be
of
done
Tender Document
will
affect
vegetation
watering
showing
human,
and
also
disturb
habitats
for
animals,
birds
and
insects.
- 89 -
the
overall
US$50/ hr
Cleaning
to poorly maintained
regular
maintenance
management.
toilets
to
and
of
avoid
unpleasant odours.
To maintain and
Public
promote a healthy
standards
as
environment
provided
under
campsites
at
Health
Construction
Contractor
US$150/
Phase
KML
month
Periodic
Local
Authority
and
cleaning will
be done and
of diseases.
be enforced shall
monitored
be part of the
overall
Document
- 90 -
Tender
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Waste should be
To maintain and
Public
to poorly maintained
carefully managed
promote a healthy
standards
to
environment
provided
management.
unpleasant odours.
prevent
campsites
at
Health
Construction
Contractor
US$100/
as
Phase
KML
month
under
Waste
Local
Authority
and
management
system will be
of diseases.
ZEMA
put in place
Regulations
on
Waste
Management shall
be enforced shall
be part of the
overall
contract
diesel
of
To monitor and
Enforcement
un-
roads
maintained equipment.
to be used on site.
fumes
due
to
Enforcement
- 91 -
and
of
road
Construction
ZEMA
Police Traffic
Phase
KML
Patrol Unit
Operational
Phase
on Air Pollution
Abatement.
The stipulated
laws will be
applied
maintained are on
site.
- 92 -
ZEMA
Mitigation Measure
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Impacts of Noise
Noise and vibration
Working
caused by construction
limited
machinery, equipment
light only;
hours
to
day
To
avoid
sleep
disturbance
at
night.
and drilling.
Enforcement
of
Construction
Contractor
Cost
Phase
KML
applicable as
on
Construction
ZEMA
programme is
will
Local
based on 9-
Authority
day
Noise
Abatement.
be
limited to day
Enforcement
caused by construction
occupational
machinery, equipment
Cap 441.
health
and drilling.
of
To
Construction
Contractor
Phase
KML
Cap 441.
Occupation
Ministry
working
health will be
Labour
conditions among
implemented
the
promote
and
safe
Enforcement
construction
workers.
- 93 -
of
working
hours.
time
Noise and vibration
not
US$3,000/yr
of
ZEMA Regulation
To monitor and
Enforcement
on
control
traffic.
Abatement;
Noise
noise
generation.
Operational
ZEMA
Police Traffic
Phase
Local
Patrol Unit
204
Noise
Authority
on
of
Noise
Abatement.
Abatement
law will be
applied
Control of noise
To monitor and
Enforcement
generating
control
generation.
by-laws).
noise
Operational
ZEMA
Police Traffic
Phase
Local
Patrol Unit
204
By laws will
Authority
on
Abatement.
of
Noise
be
implemented
- 94 -
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Development
construction
of
the
of
To maintain areas
Shopping
of scenic beauty.
design
mall
Design Phase
Design
Cut
be
Construction
Engineers
spoil
shall
designs must be
environmentally
Phase
could be substantial if
environmentally
All
designs
designs
compatible
will
be
compatible
the
followed
as
the
surrounding
environment.
are
not
with
surrounding
surrounding
environment.
environment.
- 95 -
with
KML
per standard
to
fill/
@
3
US$3.50/m
Disfigurement of the
Development
of
To maintain areas
Runway
of scenic beauty.
shall
designs
Design Phase
Design
Cut
be
Construction
Engineers
spoil
designs must be
environmentally
Phase
construction works.
environmentally
and
Scenic beauty
and
compatible
will
landscape of the
maintained as
surrounding
designed
surrounding
environment.
compatible
to
fill/
@
3
KML
US$3.50/m
KML
Construction
be
environment.
Abandoned
Abandoned
To
construction
structures in areas
vandalism
excess
of scenic beauty
ruining
construction materials
shall be brought
structures, which
contract
of
down
may become an
with
eye
contractor
of
Design Phase
and
structures to be
Construction
waste can be
the
determined
Phase
reused
Bringing
refill borrow
down
pits as part of
structures that
the
are
rehabilitation
beauty
required
surrounding
on
environment.
pits.
structures,
laterite,
stone
avoid
sore
of
and
Disposal
the
- 96 -
at
signing
the
not
to
programme
borrow
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Design Phase
Contractor
About
unplanned
Construction
KML
US$3000 per
be
settlements which
unskilled
Phase
Community
unity
shall
the
Local people
Representative
structure
works;
priority
as
will be given
Local
relocated
social upheavals?
the
Authority
contract document
before
advance.
with
other
The
proposed
construction
influence
mall
might
migration
To
the
necessary
skills
shall
avoid
Recruitment
be
contractor
- 97 -
labour
and
the
chance
any
of
Resettlement
of
To avoid conflicts
Design Phase
Contractor
US$3,000/
communities
in
of land ownership.
Construction
Community
unit
resettlement
of
Phase
Representative
structure
done
in
communities
as
In case this
Local
relocated.
consultation with
construction
happens
Authority
community
works
as
will
be
RAP will be
to
the
prepared
confined
welfare
project
reserved
area,
however
department
and
host or existing
should there be
community.
any
resettlement
then it shall be
done
accordance
in
with
Resettlement
Action
Framework
- 98 -
plan
of
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
of
roads
and
equipment
disturb
environment
the
immediate
the
within
and
access
To avoid conflicts
Mitigation
between
measures
the
for
Design Phase
Contractor
To
Construction
Community
detours
US$76/m
impacts on land-
Phase
Representative
local
Local
Local
be
and
of
Authorities
Authority
done
park
in
community
also
to
the
overall
consultation with
monitor land-use
contract document
will
be
surrounding
change.
involved
in
environment.
shall
into
planning
for
the
detours
take
account
- 99 -
construct
@
To
of
Design Phase
Contractor
Lump
the
necessary
unplanned
Construction
Community
US$2,500/
skills
shall
be
settlements which
unskilled
Phase
Representative
month
areas
employed in the
shall
Employing of
Local
construction
priority
local
Authority
settle
well operation of
social upheavals?
If
labour
is
people
near
proposed project.
not
who
the
the project
as
avoid
Recruitment
labour
be
and
the
as
contract document
with
contractor
- 100 -
the
people
will be done
Sum
Mitigation Measure
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
Resettlement
of
To avoid conflicts
Design Phase
Contractor
US$3,000/
communities
in
of land ownership
Construction
Community
unit
resettlement
of
Phase
Representative
structure
done
in
communities
as
Local
relocated.
consultation with
rehabilitation
works
host or existing
community.
Authority
will
be
confined
to
the
project
reserve,
however
there
should
be
any
resettlement then
it shall be done in
accordance
the
Resettlement
action
Framework
- 101 -
with
plan
KML
of
Emission of exhaust
fumes
to
the
ZEMA Regulation
To monitor and
Enforcement
on Air Pollution;
control
emission
of exhaust fumes
204
surrounding
to the surrounding
Pollution.
environment due to
environment.
increased traffic.
- 102 -
on
of
Air
Operational
ZEMA
ZEMA
Phase
Local
Monitoring
Authority
Costs
Impact
Objective
Actions to be taken
Period of
Authority
Cost of Mitigation
Implementation
Responsible
Construction
Contractor
US$15,000/
month
to
for
Development
of
engine
Phase
KML
maintenance
any
maintenance
Vehicle
ZEMA
malfunctioning
schedules
engine.
making
schedules
and
fumes
standards
to
surrounding
reduce
air
environment due to
pollution.
the
check
engine
Emission of exhaust
to
To
available
and
maintenance
them
will be done
for
inspection on site.
increased traffic.
Impacts on Socio-economic Environment
- 103 -
Temporary marriages,
There
casual
provision
sex
shall
be
To sensitize the
Mitigation
of
construction
measures
for
Construction
Contractor
Lump
Phase
KML
US$20,000
education both to
impacts of STDs
Operational
Community
for
chances
of
the
communities
and
Phase
Based
project
transmission
of
community
Organizations
overall
Local
local
and
HIV/AIDS
camp workers on
of
to
STDs
HIV/AIDS and to
interaction
of
and
STDs
HIV/AIDS using
protect
local communities.
themselves.
and
shows, pamphlets,
talks, etc.
- 104 -
contract
Authority
Sum
whole
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
indicators
road
Provision
of
To prevent fatal
Mitigation
accidents.
measures
Construction
Contractor
US$100
Phase
KML
sign
accidents
due
to
adequate warning
increased
vehicular
signs in human
impacts on socio-
Operational
Local
crossing
and
economic shall be
Phase
Authority
constructed shopping
speed
retarders
Road
mall
and/
or
contract
human
mechanisms
at
Document
crossing points .
contractor.
for
with
crossing
signs
and
speed
retarders will
be used
- 105 -
per
Detours,
access
Mitigation
and
is designed in the
measures
manner
which
roads
Poorly
developed
equipment
park
Construction
Contractor
One
NHCC
for
Phase
KML
staff
to
impacts
on
The
National
attached
and
provisions of
Heritage
project during
Conservation
construction
Commission
of areas near
be
to
Cultural
could
constructed
the provisions of
the
negatively on heritage
through
the
be part of the
Heritage
sites.
overall
contract
Conservation
heritage sites
Commission
if fund during
sites.
contractor
shall apply.
excavation @
impact
Cultural
The
National
Heritage Act.
National
provisions of the
US$500/
National Heritage
month
Conservation
Commission shall
apply.
- 106 -
Impact
Objective
Actions to be taken
for its implementation
Monitoring
frequency and
Authority
Cost of Mitigation
Responsible
Indicators
access
that
Mitigation
by
measures
construction
constructed
Cultural
reserve area.
roads
appearance
equipment
site.in
case
of
the
Same
Construction
Contractor
for
Phase
KML
dust
impacts
on
Provisions of
National
US$100/hr
Cultural
and
the
Heritage
hire charge of
near
Heritage
Conservation
compressor or
and
thereby
be part of the
Conservation
Commission
regularly
disfiguring it.
overall
Commission
water
the
shall apply.
gravel
or
and
park
other
heritage
sites.
Provisions
of
the
To
dust
ensure
caused
contract
National
National
at
construction
of temporary
Heritage
enclosure
Conservation
around
Commission shall
protect
apply.
sensitive site
from dust.
- 107 -
to
Impact
Objective
Actions to be taken
Monitoring
Authority
for its
frequency and
Responsible
implementation
Indicators
Cost of Mitigation
no
Construction
negative impacts on
shall
human
To
Mitigation
Construction
Contractor
Liaison
problems
measures
for
Phase
KML
allowances
confined to the
associated with
impacts
on
Construction
Local Authority
US$100/ month
shopping
resettlement
Human
will be restricted
Community
Relocation
construction
reserve area.
Settlements sites
to the shopping
Representatives
two
mall reserve
settlements
works
be
ensure
mall
issues
are
will be confined to
circumvented
shall be part of
the
during
the
however, extending
construction
contract
phase.
Document with
project
residential
site
overall
the contractor.
structures.
- 108 -
of
structures
US$ 10000
Impact
Objective
Actions to be taken
Monitoring
Authority
for its
frequency and
Responsible
implementation
Indicators
Cost of Mitigation
no
Detour,
access
To avoid land-
Mitigation
use
measures
Construction
Contractor
Liaison
for
Phase
KML
allowances
on
Consultation
Local Authority
US$100/ month
negative impacts on
roads
human
equipment park
impacts
site
communities.
Human
Community
construction
outside
the
Settlements sites
athourity as well
Representatives
will be confined to
construction site
shall be part of
as
the
shall be done in
the
community will,
consultation
document
with
the contractor
settlements
size
of
proposed
reserve
the
mall
however,
extending
construction
affect
works
the
the
may
nearby
and
location
ZEMA,
conflicts
contract
take
into
account existing
residential
structures.
areas.
- 109 -
with
the
be done before
any activity
Construction of the
There shall be
To avoid land
Mitigation
shopping
no conversion of
ownership
measures
enhances
communal land
impacts
accessibility,
local
around
communities.
mall
mobility
economic
and
activities
Construction
Contractor
Liaison
for
Phase
KML
allowances
on
Proper
Local Authority
US$100/ month
Human
documentation
Community
Settlement sites
will be obtained
Representatives
constructed
shall be part of
on
strucure.
the
before
the
overall
contract
document
issue
construction can
with
the contractor
- 110 -
land
begin
Mitigation Measure
Objective
Actions to be taken
Monitoring
Authority
for its
frequency and
Responsible
implementation
Indicators
Cost of Mitigation
There shall be
To avoid land
Mitigation
no conversion of
ownership
measures
to increased human
communal land
impacts
settlements, changed
local
settlement patterns,
around
communities.
and
constructed
shall be part of
shopping mall i
the
commercial
the
Construction
Contractor
Liaison
for
Phase
KML
allowances
on
Respected
Local Authority
US$100/ month
Human
settlements will
Community
Settlements sites
protected
Representatives
overall
- 111 -
Construction of the
There shall be
To avoid land
Mitigation
no conversion of
ownership
measures
to
land
communal land
impacts
land
local
Human
Zambia Police
around
communities.
Settlements sites
Safety Council
constructed
shall be part of
constructed mall
mall.
the
increased
values
and
resource
tenure
the
Operational
Contractor
Liaison
for
Phase
KML
allowances
on
No
Local Authority
US$100/ month
communal
overall
document
contract with the
contractor
The construction of
Speed limits of
To save lives of
Mitigation
pedestrians and
measures
will
increase risks
shall
of
road
observed
accidents
traffic
to
communities around
the
the
mall.
be
near
shopping
Operational
Contractor
Speed humps @
Phase
KML
US$500 each
impact is part of
Local Authority
the
human crossing
Zambia Police
Document with
including
Safety Council
the contractor
signs
this
contract
constructed
will
provided
shopping mall
- 112 -
road
be
Impact
Objective
Actions to be taken
Monitoring
Authority
for its
frequency and
Responsible
implementation
Indicators
Cost of Mitigation
Construction of the
Trees shall be
To
planted
near
hazardous
settled areas to
emissions
filter
off
Mitigation
Operational
Contractor
US$20/per tree
planted
measures
for
Phase
KML
and
impacts
on
Trees shall be
Local Authority
minimize
also to act as
Human
hazardous
barriers to traffic
Settlements sites
emissions.
shall be part of
communities around
the
the
cause
contract
health
to
increased
risks
mall
to
from
vehicle emissions.
accident
planted
overall
to nearby settled
document
areas.
the contractor
- 113 -
with
Noise
from
high
To
have
disturbance
hours
of
may
opperation
to
communities.
airport.
disturb
the
avoid
restricted
noise
disturbance.
avoid
communities.
to
Operational
Contractor
US$20/m2
Phase
KML
Local Authority
part
have
Mitigation
measures
for
of
the
restricted
overall contract
hours
document
opperation
with
the contractor
- 114 -
of
of
the settlements
Impact
Objective
Actions to be taken
Monitoring
Authority
for its
frequency and
Responsible
implementation
Indicators
Cost of Mitigation
Quarrying shall
To avoid water
Mitigation
pits
pollution which
measures
location
may
negatively impact on
surface
important ecological
sources.
water
units.
might
lead
to
Contractor
Haul of suitable
Phase
KML
gravel
to
impacts
of
Will
of
Quarries
and
the
Borrow
Pits
deprivation
water
for
Construction
local
shall be part of
community?
the
be
done
Local Authority
away
from
Local
surface
water
Community
@
3
US$0.35/m . km
sorces
overall
contract
document
with
the contractor
Quarries and borrow
There shall be
To preserve the
Mitigation
pits
no
Heritage sites.
measures
location
may
negatively impact on
near
important ecological
sites
units.
quarrying
Sensitive
this
Construction
Contractor
Haul of suitable
Phase
KML
gravel
impact is part of
Will be done in
Local Authority
the
National
sensitive
Heritage
contract
Document with
the contractor
Conservation
Commission
- 115 -
and
@
3
US$0.35/m . km
Excessive
noise
Quarrying shall
Mitigation
associated with
measures
machinery
disturb
communities.
may
nearby
communities.
for
Construction
Contractor
Haul of suitable
Phase
KML
gravel
flying
pebbles
No
quarrying
Local Authority
from
blasting
part
the
will
be
Mine
Tender
near
Department
of
communities
Ministry
of
operations
and
minimise
of
overall
Document.
disturbance from
done
Mines.
noise.
- 116 -
Safety
@
3
US$0.35/m . km
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
Indicators
Quarrying shall be
To
blasting
done
compliance
and
in
ensure
conformity to the
the
nearby communities.
Mines
quarrying.
and
Law
with
on
Mitigation
Construction
Contractor
License
Phase
KML
about
impact is part of
Shall conform
Local
US$1,000 per
the
contract
to the mines
Authority
quarry
with
and minerals
Mine
ACT
Department of
measures
this
Document
31 of 1995.
the contractor
fees
Safety
Ministry
of
Mines.
Abandoned
pits
borrow
To
pose
harbouring disease
measures
to
causing organisms
impacts of Borrow
could
potential
hazard
human
and
residents.
settlements.
avoid
other
Mitigation
for
Operational
Contractor
Haul
Phase
DCA
suitable
This will be
Local
gravel
done
dangerous animals
of
that
contract document
may
find
the
these as suitable
with
habitats.
contractor.
Impacts of Traffic
- 117 -
overall
the
of
@
3
Authority
US$0.35/m .
from
Mine
km
settlements
Department of
away
Safety
Ministry
Mines.
of
Failure
to
established
might
use
Surveyors should
To avoid off-site
Mitigation
routes
impacts associated
Measures
away
with surveying.
impacts
result
in
surveyors'
vehicles
negatively
impacting
on the environment.
from
proposed
the
for
of
Design Phase
Contractor
US$20,000 to
Construction
KML
survey
Phase
Local
stake
Authority
project
Surveying shall be
Surveyors
site in order to
will
be
avoid impacts on
contract document
restricted
to
the
with
project site
surrounding
environment.
contractor
- 118 -
the
and
Impact
Objective
Actions to be taken
for its implementation
Monitoring
Authority
frequency and
Cost of Mitigation
Responsible
Indicators
Construction
could
impact
undisturbed
traffic
Established routes
To maintain the
Mitigation
should
existing
measures
be
used
on
where possible in
environment
areas
order to reduce
impacting
in
on
Contractor
To
Phase
KML
existing
impact is part of
Established
Local
detours,
the
routes will be
Authority
maintenance
this
contract
Document
undisturbed areas.
with
use
@ US$5/m
used
the contractor
Construction
To
necessary
use
disturbance
pre-
Construction
avoid
un-
Mitigation
Construction
Contractor
Maintenance
Phase
KML
of
impact is part of
Pre-
Local
predetermined
determines
Authority
DCAs
measures
of
this
determined access
the
cause danger to
Document
be determined in
other users.
the contractor
contract
with
access
- 119 -
roads
to
be
existing/
US$55/m
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
Indicators
Control of dust
To
construction
through watering
respiratory
of dust areas.
visibility problems
impact is part of
Watering
the
of dust on other
Document
protected
the contractor.
disturb
could
nearby
communities.
avoid
and
areas
Mitigation
measures
this
contract
with
Construction
Contractor
Water bowser
Phase
KML
US$50/hr
of
Local
Authority
be done
and property.
Increased
accidents
Provision
of
To save human
Mitigation
adequate warning
Measures
flow.
retarders
accidents.
result
of
Operational
Contractor
US$100/
Phase
KML
DCA sign
impacts of traffic
Warning signs
Local
in black spot
Authority
overall
areas
Document.
for
Tender
and
speed
retarders will
be used
- 120 -
Advanced planning of
Development
safety
safety procedures
people
measures
and
equipment
requirements
of
operational
manual.
To
ensure
that
Operational
Contractor
US$800/
this
Phase
KML
month
undertaking these
impact is part of
Safety
Local
tasks
the
procedure and
Authority
know
Mitigation
contract
exactly what is to
Document
be done.
the contractor
with
operational
manual
will
be developed
- 121 -
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
Indicators
Enforcement
of
Mitigation
Measures
regulations
safety regulations.
of workers.
Operational
Contractor
US$3,000/
Phase
KML
month
impacts of work
Public health
Local
impact negatively on
accidents shall be
as well safety
Authority
construction workers.
regulations
contract
will
could
for
Document
with
be
enforced
the contractor.
Impacts of Construction Camps
Advanced planning of
Selection of camp
To ensure camp
Mitigation
construction
siting
be
siting
measures
in
considered at the
consultation with
ZEMA,
siting.
camp
must
done
local
Design Phase
Contractor
US$1,000 for
Construction
KML
siting
impact is part of
Phase
ZEMA
planning
the
Stakeholders
Local
communities
Document
will
Authority
is
are
consulted well in
community.
advance.
this
contract
the contractor
with
be
consultanted
Local
Community
- 122 -
and
Loss of vegetation at
To
construction site.
siting
conserve
Mitigation
Contractor
Site clearance
Phase
KML
ZEMA
US$0.99/m2
must
be
vegetation around
measures
to
the
impact is part of
Clearing
protect
the
the
vegetation
vegetation loss on
from
extensive
a larger scale.
loss of vegetation
limited
site
Document
this
Construction
contract
with
the contractor.
will
of
Local
be
limited to site
Authority
Local
Community
- 123 -
Mitigation Measure
Objective
Actions to be taken
for its implementation
Monitoring
Authority
frequency and
Cost of Mitigation
Responsible
Indicators
Waste disposal to
To control waste
Mitigation
campsite.
be
at
disposal practices
Measures
sites
impacts
dumping.
construction
done
designated
approved by the
local authority.
camps
for
of
shall
be
- 124 -
the
Construction
Contractor
Disposal
of
Phase
KML
waste
To be done at
Local
US$0.10/ton.
approved site
Authority
km
by
ZEMA
authority
local
Interaction
of
construction
with
the
workers
nearby
There
shall
provision
be
To
prevent
the
Mitigation
of
transmission
of
Measures
for
Contractor
US$15,000
Phase
KML
Lump Sum
HIV/AIDS
Local
campaigns
Authority
education both to
sexually
impacts
the
transmitted
construction
to
community
diseases between
camps
be
will be done
CBO
camp workers on
the
on site and
Health
STDs
community
contract
community
transmission
sexually
diseases.
of
transmitted
local
and
and
local
and
of
Construction
shall
HIV/AIDS using
construction
Document
workers.
the contractor
shows, pamphlets,
talks, etc.
- 125 -
with
on
Impact
Objective
Actions to be taken
Monitoring
Authority
frequency and
Responsible
Cost of Mitigation
Indicators
To
the
necessary
local
skills
shall
be
impacts
employed in the
construction
project.
avoid immigration
camps
Department of
to
in land disputes
contract
Ministry
and
Document
Interaction
of
construction
with
the
workers
nearby
transmission
sexually
diseases.
of
transmitted
ensure
the
community
upheavals.
social
Mitigation
Measures
for
of
shall
the contractor
Construction
Contractor
US$2,500 per
Phase
KML
month
Local
Authority
be
with
Labour
of
Labour
Community
representative
- 126 -
- 127 -
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Land and Soil
Site
Land and Soil
Engineer
to
Periodical
Inspection Report is
Contractor's
make inspections of
inspections through
available
Engineer
fuel
Kafubu
Phase
maintained through
spillage
fuels
and
ensure
out
they
have
sealed
Phase.
with
shopping
Site
KML
mall
Construction
surfaces.
Site
Engineer
inspect
the
to
waste
disposal sites.
Periodical
Inspection Report is
Contractor's
inspections through
disposed
available at KML
Engineer
Phase
in
the
of
in
KML
approved
method.
Site
Engineer
to
Periodical
Containers
for
Used
oil
inspections through
collection of used
serviced
recycling.
Phase
site.
collected
containers.
- 128 -
from
plant
in
Contractor
Site
Site
Engineer
to
Contractor
and
construction
KML
and
ensure
they
to use.
plan
has
will be constructed.
have
bund
walls
been
developed approved
and is available.
enough to contain
any spillage.
- 129 -
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Land and Soil (Cont'd)
Daily
make
through
and
heavy
inspections
ensure
that
inspections
out
the
Construction Phase.
construction
Absence
of
Complaints
from
Contractor
caterpillar trampling
ZEMA
local
KML
in residential area
community
on
and cropland
invasion
of
the
equipment
is
settlements
and
confined
to
croplands
by
operational
only
and
areas
construction
avoids
existent.
cropland
The Site Engineer to
Daily
inspections
undertake inspection
through
of earthworks and
Construction Phase.
out
the
graded
to
specifications.
- 130 -
Absence
gullies
of
rills,
Absence of erosion
Contractor
features.
KML
Each
earthworks
are
Engineer
completed
through
should
monitor
the
restoration measures
out
time
Construction
Phase
to be implemented
such
as
Presence
of
re-
Restoration
Contractor
vegetation in erosion
KML
prone areas.
vegetation
of
exposed
soils
is
available
and
is
being implemented.
re-
vegetation
- 131 -
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Vegetation
Site
Vegetation
Engineer
ensure
to
that
The
of
Contractor
of
vegetation cleared is
clearance is clearly
ZEMA
minimal
marked
and
is
confined
to
the
vegetation
is
excessive clearance
of
out
vegetation
is
area
Construction
Phase
designs.
be confined to the
project site.
Wildlife and Wildlife Habitat
The Site Engineer to
Periodical
Absence of animal
inspections through
damage to project
Habitat
out
site.
of wildlife intrusion
Phase
Construction
- 132 -
Inspection report
Contractor
KML
Site
Water Quality
Engineer
to
Periodical
Absence of water
Contractor
inspections through
maintained through
pollution incidents
KML
Phase.
Phase.
working well.
- 133 -
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Water Quality (Cont'd)
Site
Water Quality
(Cont'd)
Engineer
Periodical
Absence of water
Contractor
inspections through
maintained through
pollution incidents
KML
that
where
liquids
Phase.
Phase.
Periodical
Absence of water
Contractor
inspections through
maintained through
pollution incidents
KML
that
Phase.
Phase.
Periodical
Absence of water
Contractor
inspections through
maintained through
pollution incidents
KML
along
Phase.
Phase.
areas
hazardous
are
to
stored
are
bunded.
Site
Engineer
water
concrete
to
from
batching
plants is treated.
Site
Engineer
to
drainage
systems;
- 134 -
Site
Engineer
Periodical
Absence of water
Contractor
inspections through
maintained through
pollution incidents
KML
that
Phase.
Phase.
Before construction
Construction is done
Contractor
of pit latrines.
according to design
construction report
KML
spoon
to
drains
Engineer
to
is
done
from
water
specifications.
logged areas;
- 135 -
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Water Quality (Cont'd)
Site
Engineer
to
Immediately there is
Operational
Presence
a pollution incident
Operational Manual
Water Quality
during Construction
followed.
on site.
(Cont'd)
the procedures to be
Phase.
Regular inspections
Deposition of dust
Dust deposition on
Contractor
through
on surfaces such as
the
KML
dust
Construction Phase.
surroundings
during Construction.
controlled.
Watering
down
decrease
should be done if
watering.
followed
in
of
Contractor
KML
the
event of pollution
incident is given to
the Site Engineer By
the Contractor.
Air Quality
Site
Air Quality
dust
Engineer
to
generated
levels
out
the
are
unacceptable.
- 136 -
with
immediate
is
Site
Engineer
to
Regular inspections
Exhaust
through
emissions
that
Construction Phase.
construction
vehicles
and
equipment
are
out
the
maintained in order
to reduce emission
of exhaust fumes;
- 137 -
controlled.
fume
are
Maintenance
Contractor
logbook is available
KML
on site.
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Air Quality (Cont'd)
Site
Air Quality
Engineer
Regular inspections
Unpleasant
through
are controlled.
that
Construction Phase.
toilets
cleaned
to
are
out
the
odours
Clean
toilet
environment
from
and
free
Contractor
KML
unpleasant
odours.
maintained to avoid
unpleasant odours.
Site
Engineer
Regular inspections
Controlled
through
disposal method.
waste is carefully
Construction Phase.
managed
disposed
to
out
the
and
of
in
designated places to
prevent
unpleasant
odours.
Noise
- 138 -
waste
Waste is dumped in
Contractor
designated places.
KML
Site
Noise
Engineer
to
Regular inspections
Number
through
nearest
complaints of noise
vibrations on an ad-
Construction Phase.
out
the
minimised.
noise
receptors
should
receiver
not
exceed 90-decibels.
- 139 -
sensitive
are
disturbance
controlled.
of
is
Contractor
KML
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Noise (Cont'd)
Site
Engineer
to
Daily
inspections
Noise
through
Cont'd)
Construction Phase.
out
the
Sleep disturbance is
Number
minimised.
complaints of sleep
disturbance
minimised.
light only;
Landscape and Aesthetics
- 140 -
of
is
Contractor
KML
Site
Landscape and
Aesthetics
Engineer
make
to
visual
inspection of earth
Daily
through
inspections
out
the
Construction Phase.
reduced
are
to
Contractor
aesthetic
KML
view
other
sites,
contractor's camp.
- 141 -
is
excavation
around
alterations
minimum.
excessive
borrow
Landscape
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Land-use and surrounding environment
Contractor
shall
Before
Land-use and
ensure
that
local
Surrounding
people
with
Potential
Construction
construction
workers
requirements
shall
Environment
local community
employed to work
Pre-Construction
identified.
on
Phase.
the
project
the
runway
to
migration
recruitment
avoid
and
by
construction
workers
who
are
- 142 -
Contractor
are
KML
Planning
for
detours,
into
implemented
the Pre-Construction
according
Phase.
settled areas
specifications.
access
- 143 -
Contractor
access
access
KML
roads
account
and
the
roads
and
to
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Socio-economic Environment
Contractor
Socio-economic
Situation
shall
Planning
for
Programme
for
Target
group
for
Contractor
education both to
education both to
receiving education
KML
that
the
the
on
Local Community
education
is
construction
construction
STDs
and
HIV/AIDS
construction
community on STDs
community on STDs
and HIV/AIDS is
programme is being
community on STDs
developed
implemented during
and
Pre-Construction
the Pre-Construction
the
Phase.
Phase.
Phase.
HIV/AIDS
shows,
pamphlets, talks is
disseminated.
- 144 -
during
is
Construction
CBO
Site
Engineer
to
Planning
for
Contractor
erection of warning
identified
for
speed retarders in
KML
that
erection of warning
Local Authority
areas
signs
pedestrian
warning
adequate
signs
in
and
speed
and
speed
retarders
at
retarders
and
are
speed retarders at
pedestrian crossing
included
in
the
overall
the Pre-Construction
designs
Phase.
- 145 -
airport
constructed.
are
Element to be
Frequency of
Indicator
Means of Verification
Authority Responsible
for
of
KML
protection of Cultural
NHCC
Monitoring
Monitored
Cultural and Historic Sites
Site Engineer to monitor
Planning
construction
Sites
developed.
Construction Phase.
detours,
access
sites.
Human Settlements
- 146 -
Construction Phase.
Contractor
Site
Human Settlements
Engineer
to
Planning
for
Exploitation
of
exploitation of water
water
that exploitation of
from
the
local
local
community
for
rehabilitation works
construction
is
the Pre-Construction
shopping
Phase
controlled.
the
local community.
done
with
local
community
in
community.
- 147 -
resources
of
mall
is
Water
to
local
community
is
available.
Contractor
KML
Local Authority
Local community
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Human Settlements (Cont'd)
Site
Human Settlements
(Cont'd)
Engineer
to
Planning
for
Contractor
erection of warning
identified
for
speed retarders in
KML
that
erection of warning
Local Authority
areas
signs
constructed.
adequate
warning
signs
in
and
speed
and
speed
retarders
at
retarders
and
are
speed retarders at
included
in
the
pedestrian crossing
overall
Construction Phase.
designs
Planning
Shopping
airport
settlement areas
Quarries and Borrow Pits
Site
Quarries and Borrow
Pits
Engineer
to
exploitation
that
construction
quarries
and
for
of
Contractor
areas
KML
into
account
outside
protection
of
resources catchment
located
the
water
materials
water resources is
areas
water sources.
developed.
Construction Phase.
the
Pre-
Construction Phase.
- 148 -
the
are
in
from
mall
during
the
Ministry of Mines
Planning
exploitation
construction
materials
Historic Sites.
for
Contractor
of
KML
conservation measures
Ministry of Mines
NHCC
Sites is developed.
Construction Phase.
from
the
Pre-
Construction Phase.
- 149 -
Element to be
Method of Monitoring
Frequency of
Indicator
Means of Verification
Authority Responsible
Monitoring
Monitored
Quarries and Borrow Pits
Site
Quarries and Borrow
Pits
(Cont'd)
Engineer
to
Planning
exploitation
that
construction
quarries
and
for
of
mall
Contractor
KML
into
account
Ministry of Mines
protection
of
community
Local Authority
materials
located
local community is
the
developed.
Phase.
Operational Manual
Operational Manual
Contractor
nearby
communities.
in
the
from
Shopping
the
during
Construction
Pre-
Construction Phase.
Work Accidents
Site
Work Accidents
Engineer
to
Periodical
inspection
through
on Safety, Health
on Safety, Health
KML
Local Authority
on Safety, Health
Phase.
construction
construction
workers
construction
developed
available on site.
is
and
workers
- 150 -
being
implemented during
the
Phase.
Construction Phase.
is
Construction
Construction Camps
Site
Construction Camps
Engineer
to
Periodically through
Designated
disposal
Phase.
identified
is
done
designated
approved
in
available.
sites
by
the
- 151 -
waste
site
is
and
Waste
is
being
dumped
designated sites.
in
Contractor
KML
Local Authority
ZEMA
During the construction phase, Kafubu Mall Limited will ensure that the
contractor implement the mitigation measures recommended in the EIS.
Further, the Kafubu mall limited will ensure that construction workers are
sensitized with regard to environmental problems and their obligation. In
addition, Kafubu mall limited will liaise with respective government agencies
such as local authorities in the affected areas and Zambia Environmental
Management Agenc on environmental issues, which may arise during the
construction of the shopping mall phase.
Traffic police, RDA, Forestry Department, health authorities and other public
authorities will automatically monitor some of the effects of the Project during
their daily work. This information should on a regular basis be collected and
- 153 -
PARAMETERS TO BE
ORGANISATION
MONITORED
ZEMA
Overall
OUTPUT
environmental
Discussions
with
Kafubu
shopping
mall/contractor
Regular
of EMP
environmental
Overall
environmental
Construction
Engineer
materials
Implementation
methods
reports
to
stakeholders
progress
and
Regular
environmental
of
mitigating
progress
reports
to
ZEMA
Environmental management of
when
worksites
(Pollution, accidents,
Environmental management of
etc.)
construction camps
shopping mall
Environmental management of
quarries and borrow pits
Contractors waste management
Rehabilitation
worksites
- 154 -
of
abandoned
required
by
Kafubu
PARAMETERS TO BE
ORGANISATION
MONITORED
Contractor/Site
Performance
Engineer
equipment
of
OUTPUT
Contractors
Regular
environmental
Accidents
(traffic,
pollution
progress
reports
to
spills, etc.)
ZEMA
Community relations
Negative
social
and
when
required
environmental impacts
(Pollution, accidents,
Contractor
Environmental performance of
Maintenance records
equipment
Accidents reports
Implementation
of
mitigating
measures
Mitigating actions
Log sheet records
Instructions
to
the
impacts
Contractor
and
the
on
vegetation
and
wildlife
Consultant/Site
Engineer
NHCC
Instructions
to
the
Sites
Contractor
and
the
Consultant/Site
Engineer
Forestry Department
Instructions
to
the
Contractor
and
the
Consultant/Site
Engineer
Traffic Police
Local authorities
Traffic accidents
Police
Traffic nuisances
instructions
Contractor
Negative
social
environmental impacts
and
reports
Complaints
Contractor
Consultant/Site
- 155 -
and
to
to
and
Engineer
- 156 -
YEAR 1
ACTIVITY
Q1
- 157 -
Q2
Q3
YEAR 2
Q4
Q1
Q2
Q3
YEAR 3
Q4
Q1
Q2
Q3
Q4
Plant sides of runway drainage with grass or stone pitch to prevent siltation of nearby water
courses
Construct scour checks on drainage system using stone masonry
- 158 -
YEAR 1
ACTIVITY
Q1
- 159 -
Q2
Q3
YEAR 2
Q4
Q1
Q2
Q3
YEAR 3
Q4
Q1
Q2
Q3
Q4
Engage one NHCC Officer to work with the project in identified areas of cultural & historic sites
- 160 -
YEAR 1
ACTIVITY
Q1
- 161 -
Q2
Q3
YEAR 2
Q4
Q1
Q2
Q3
YEAR 3
Q4
Q1
Q2
Q3
Q4
YEAR 1
ACTIVITY
Q1
Observe the Performance of Mitigation Measures for Impacts on Land and Soil
Assess the condition of land and soil at storage sites with respect to soil contamination
Check for availability of designated dumpsites for disposal of construction wastes
Check for availability of metal drums for collection and storage of used oil & lubricants on site
Check for presence of concrete bund walls & slab around petroleum storage tanks on site
Check if there exist caterpillar trampling in croplands at project site
Check if there exist hills and gullies around the project site
Check for existence of re-vegetation programme in erosion prone areas
Observe the Performance of Mitigation Measures for Impacts on Vegetation
Assess the extent of vegetation clearance in project areas
Check for existence of awareness program for communities on importance of forest conservation
Observe the Performance of Mitigation Measures for Impacts on Wildlife and Wildlife Habitats
Check if there exist animal damage to project site
Check if there exist animal accidents in identified wildlife areas
Observe the Performance of Mitigation Measures for Impacts on Water Quality
Assess the quality of drinking water sources likely to be contaminated by project activities
Observe the Performance of Mitigation Measures for Impacts on Air Quality
Check for condition of dust level emissions and deposition on surrounding areas
- 162 -
Q2
Q3
YEAR 2
Q4
Q1
Q2
Q3
YEAR 3
Q4
Q1
Q2
Q3
Q4
Check for exhaust fume emission levels from construction vehicles and equipment
Check for condition of pit latrines & solid waste disposal sites
- 163 -
YEAR 1
ACTIVITY
Q1
Q2
- 164 -
Q3
YEAR 2
Q4
Q1
Q2
Q3
YEAR 3
Q4
Q1
Q2
Q3
Q4
Check for existence of tree planting programs in human settled areas to control emissions
Check for existence of noise barriers in human settlement areas
- 165 -
YEAR 1
ACTIVITY
Q1
Observe the Performance of Mitigation Measures for Impacts of Quarries and Borrow Pits
Assess the location of quarry and borrow pit areas in relation to wildlife areas
Assess the location of quarry and borrow pit areas in relation to cultural and historic sites
Assess the location of quarry and borrow pit areas in relation to human settlements
Assess the location of quarry and borrow pit areas in relation to drinking water sources
Observe the Performance of Mitigation Measures for Impacts of Road Traffic
Check if exist traffic congestion at project site due to insufficient signs & alternative routes
Check for existence of traffic accidents due to high dust levels & lack of detour and access roads
Observe the Performance of Mitigation Measures for Impacts of Work Accidents
Check for existence of programs & adherence to procedures on Safety, Health and Environment
Check if there exist work accidents at project sites
Observe the Performance of Mitigation Measures for Impacts of Construction Camps
Check if the local community was consulted over workers camp siting
Check if the local community was consulted over waste disposal siting
Check for existence of programs to sensitize camp workers on dangers of STDs and HIV/AIDS.
- 166 -
Q2
Q3
YEAR 2
Q4
Q1
Q2
Q3
YEAR 3
Q4
Q1
Q2
Q3
Q4
- 167 -
- 168 -
- 169 -
Appendix 2: Checklist
MONITORING AND SUPERVISION CHECKLIST
PROJECT SITE/LOCATION :.. DISTRICT:
FORM A.
RESPONSIBILITY FOR
ACTIVITY TO BE PERFORMED
IMPLEMENTATION
1.1
1.2
1.3
etc
2. VEGETATION
2.1
2.2
2.3
etc
3. WILDLIFE & WILDLIFE HABITAT
3.1
- 170 -
>75%
75% - 55%
55% - 45%
<45%
Good
Average
Fair
Poor
3.2
3.3
etc
4. WATER QUALITY
4.1
4.2
etc
5. AIR QUALITY
5.1
5.2
etc
- 171 -
RESPONSIBILITY FOR
ACTIVITY TO BE PERFORMED
IMPLEMENTATION
6. NOISE
6.1
6.2
6.3
etc
7. LANDSCAPE & AESTHETICS
7.1
7.2
7.3
etc
8. LAND--USE & SURROUNDING ENVIRONMENT
8.1
8.2
8.3
- 172 -
>75%
75% - 50%
55% - 45%
< 45%
Good
Average
Fair
Poor
etc
9. SOCIO-ECONOMIC ENVIRONMENT
9.1
9.2
9.3
etc
10. CULTURAL & HISTORIC SITES
10.1
10.2
10.3
etc
- 173 -
RESPONSIBILITY FOR
ACTIVITY TO BE PERFORMED
IMPLEMENTATION
11.1
11.2
11.3
etc
12. QUARRIES & BORROW PITS
12.1
12.2
12.3
etc
13. ROAD TRAFFIC
13.1
13.2
13.3
- 174 -
>75%
75% - 50%
55% - 45%
< 45%
Good
Average
Fair
Poor
etc
14. WORK ACCIDENTS
14.1
14.2
14.3
etc
15. CONSTRUCTION CAMPS
15.1
15.2
15.3
etc
- 175 -
FORM B:
CONSTRAINTS/DIFFICULTIES OF
IMPLEMENTATION
GOOD
FAIR
POOR
- 176 -
etc
4. WATER QUALITY
4.1
4.2
4.3
etc
5. AIR QUALITY
5.1
5.2
5.3
etc
- 177 -
CONSTRAINTS/DIFFICULTIES OF
IMPLEMENTATION
GOOD
FAIR
POOR
6. NOISE
6.1
6.2
6.3
etc
7. LANDSCAPE & AESTHETICS
7.1
7.2
7.3
etc
8. LAND-USE & SURROUNDING ENVIRONMENT
8.1
8.2
8.3
- 178 -
etc
9. SOCIO-ECONOMIC ENVIRONMENT
9.1
9.2
9.3
etc
10. CULTURAL & HISTORIC SITES
10.1
10.2
10.3
etc
- 179 -
GOOD
FAIR
POOR
- 180 -
etc
14. WORK ACCIDENTS
14.1
14.2
14.3
etc
15. CONSTRUCTION CAMPS
15.1
15.2
15.3
etc
- 181 -
FORM C:
ENVIRONMENTAL ISSUES
PROPOSED ACTION
1.
2.
3.
4.
5.
6.
7.
8.
- 182 -
RESPONSIBILITY
9.
10.
etc
- 183 -