You are on page 1of 240

ENVIRONMENTAL IMPACT STATEMENT

FOR THE PROPOSED CONSTRUCTION OF A


SHOPPING MALL IN NDOLA BY KAFUBU MALL
LIMITED
NOVEMBER 2012

TABLE OF CONTENTS
ABBREVIATIONS AND TERMINOLOGY .....................................................................................10
EXECUTIVE SUMMARY ..................................................................................................................11
INTRODUCTION ................................................................. ERROR! BOOKMARK NOT DEFINED.
PROJECT BACKGROUND ......................................................................................................................21
THE PROCESS OF CONSTRUCTING A SHOPPING MALL .........................................................................22
1.1.1.

Preparatory Works ..........................................................................................................22

1.1.2.

Tendering Process...........................................................................................................22

1.1.3.

Organizing Implementation of a Project .........................................................................22

1.1.4.

Approval and Awarding of Contracts .............................................................................23

1.1.5.

Supervision of Physical Work .........................................................................................23

OBJECTIVES OF THE EIA .....................................................................................................................27


SCOPE OF THE EIA .............................................................................................................................. 28
STUDY APPROACH AND METHODOLOGY ............................................................................................28
ENVIRONMENTAL IMPACT ASSESSMENT TEAM ..................................................................................31
POLICY, LEGAL AND INSTITUTIONAL FRAMEWORK ..........................................................32
ENVIRONMENTAL POLICY FRAMEWORK AND STRATEGY ...................................................................32
1.1.6.

National Conservation Strategy ......................................................................................32

ENVIRONMENTAL LEGISLATIVE FRAMEWORK ....................................................................................32


1.1.7.

Environmental Protection and Pollution Control Act, Chapter 204 ............................... 32

1.1.8.

EIA Legislative Requirements .........................................................................................32

OTHER ACTS REVIEWED RELEVANT TO THE CONSTRUCTION OF A SHOPPING MALL ..........................34


1.1.9.

National Council for construction Act ............................................................................34

1.1.10.

Town and Country Planning Act, Chapter 283 ..........................................................35

1.1.11.

Forest Act, Chapter 199 .............................................................................................35

1.1.12.

Water Resources Management Act No 21 of 2011 .....................................................36

1.1.13.

National Heritage Conservation Commission Act .....................................................36

1.1.14.

The Land Act of 1995 .................................................................................................37

1.1.15.

The Lands Acquisition Act No. 2 of 1970 ...................................................................37

1.1.16.

Mines and Minerals Act, Chapter 32 .........................................................................38

1.1.17.

Road and Traffic Control Act, Chapter 464 ............................................................... 38

1.1.18.

Local Government Act, Chapter 281 ..........................................................................38

1.1.19.

Public Health Act, Chapter 295 .................................................................................39

1.1.20.

Factories Act, Chapter 441 ........................................................................................39

1.1.21.

Petroleum Act, Chapter 439 .......................................................................................39

1.1.22.

Energy Regulation Act, Chapter 436..........................................................................40

INTERNATIONAL AND REGIONAL CONVENTIONS ................................................................................40

PROJECT DESCRIPTION .................................................................................................................41


PROJECT LOCATION ............................................................................................................................41
PROJECT ACTIVITIES ...........................................................................................................................43
1.1.23.

Phases in Shopping mall construction .......................................................................43

DECOMMISSIONING AND CLOSURE.....................................................................................................50


1.1.24.

Sources of Raw materials for shopping Mall .............................................................51

1.1.25.

Raw materials During Construction ..........................................................................51

1.1.26.

Waste Products during Construction Phase ............................................................... 54

1.1.27.

Waste Products during Operational Phase ................................................................ 55

ANALYSIS OF ALTERNATIVE SHOPPING MALL CONSTRUCTION ..........................................................56


1.1.28.

Option A: Do Nothing; ............................................................................................... 56

PHYSICAL ENVIRONMENT OF PROJECT SITE & ITS SURROUNDINGS .............................1


1.1TOPOGRAPHY ...................................................................................................................................1
1.2 SOILS AND GEOLOGY ......................................................................................................................1
1.3 CLIMATE .........................................................................................................................................2
1.4 HYDROLOGY AND DRAINAGE .........................................................................................................5
1.5 WATER AND SANITATION ...............................................................................................................6
FLORA AND FAUNA ...............................................................................................................................8
1.1.29.

Flora and Vegetation ...................................................................................................8

1.1.30.

Fauna around the project area area ............................................................................9

SOCIO-ECONOMIC ENVIRONMENT ............................................................................................10


DEMOGRAPHIC PROFILE .....................................................................................................................10
1.1.31.

Major Demographic Characteristics .........................................................................10

1.1.32.

Economic Profile Around the project area ................................................................ 10

LAND-USE ...........................................................................................................................................11
1.1.33.

Land Tenure Systems ..................................................................................................11

1.1.34.

Settlements..................................................................................................................12

CULTURAL ENVIRONMENT ..........................................................................................................13


CULTURAL RESOURCES ......................................................................................................................13
1.1.35.

Archaeological, Cultural and Historical Sites ...........................................................13

PUBLIC MEETINGS/ CONSULTATIONS ......................................................................................14


APPROACH AND METHODOLOGY ........................................................................................................14
COMMUNITY CONCERNS .....................................................................................................................15
POTENTIAL ENVIRONMENTAL IMPACTS ................................................................................19
IMPACTS ON LAND AND SOIL ..............................................................................................................19
1.1.36.

Construction Phase ....................................................................................................19

1.1.37.

Operational Phase......................................................................................................19

IMPACTS ON VEGETATION ..................................................................................................................20


1.1.38.

Construction Phase ....................................................................................................20

1.1.39.

Operational Phase......................................................................................................20

IMPACTS ON WILDLIFE AND WILDLIFE HABITATS ..............................................................................21


1.1.40.

Construction Phase ....................................................................................................21

1.1.41.

Operational Phase......................................................................................................21

IMPACTS ON WATER QUALITY ............................................................................................................21


1.1.42.

Construction Phase ....................................................................................................21

1.1.43.

Operational Phase......................................................................................................21

IMPACTS ON AIR QUALITY ..................................................................................................................22


1.1.44.

Construction Phase ....................................................................................................22

1.1.45.

Operational Phase......................................................................................................22

IMPACTS OF NOISE .............................................................................................................................. 22


1.1.46.

Construction Phase ....................................................................................................22

1.1.47.

Operational Phase......................................................................................................23

IMPACTS ON LANDSCAPE AND AESTHETICS ........................................................................................23


1.1.48.

Construction Phase ....................................................................................................23

1.1.49.

Operational Phase......................................................................................................23

IMPACTS ON LAND-USE AND SURROUNDING ENVIRONMENT .............................................................. 24


1.1.50.

Construction Phase ....................................................................................................24

1.1.51.

Operational Phase......................................................................................................24

IMPACTS ON SOCIO-ECONOMIC ENVIRONMENT ..................................................................................24


1.1.52.

Construction Phase ....................................................................................................24

1.1.53.

Operational Phase......................................................................................................24

IMPACTS ON CULTURAL AND HISTORIC SITES ....................................................................................25


1.1.54.

Construction Phase ....................................................................................................25

1.1.55.

Operational Phase......................................................................................................25

IMPACTS ON HUMAN SETTLEMENTS ...................................................................................................25


1.1.56.

Construction Phase ....................................................................................................25

1.1.57.

Operational Phase......................................................................................................25

IMPACTS OF QUARRIES AND BORROW PITS .........................................................................................25


1.1.58.

Construction Phase ....................................................................................................25

1.1.59.

Operational Phase......................................................................................................26

IMPACTS OF ROAD TRAFFIC ................................................................................................................26


1.1.60.

Construction Phase ....................................................................................................26

1.1.61.

Operational Phase......................................................................................................26

IMPACTS OF WORK ACCIDENTS ..........................................................................................................27


1.1.62.

Construction Phase ....................................................................................................27

1.1.63.

Operational Phase......................................................................................................27

IMPACTS OF CONSTRUCTION CAMPS ...................................................................................................27


1.1.64.

Construction Phase ....................................................................................................27

1.1.65.

Operational Phase......................................................................................................28

EVALUATION OF ENVIRONMENTAL IMPACTS ......................................................................29


NATURE OF IMPACT ............................................................................................................................29
DIRECT IMPACT ..................................................................................................................................29
INDIRECT IMPACT ............................................................................................................................... 29
SPATIAL EXTENT ................................................................................................................................ 29
DURATION ..........................................................................................................................................30
INTENSITY...........................................................................................................................................30
PROBABILITY ......................................................................................................................................31
DETERMINATION OF SIGNIFICANCE ....................................................................................................32
MITIGATION MEASURES................................................................................................................45
PROPOSED MEASURES TO ADDRESS CONCERNS OF THE COMMUNITIES AROUND THE PROJECT AREA 59
1.1.66.

Shopping Mall Site & its Surroundings ......................................................................59

1.1.67.

Quarries & Borrow Pits .............................................................................................59

1.1.68.

Sitting of Construction Camps ...................................................................................59

1.1.69.

Abstraction of Water from Local Sources ..................................................................59

1.1.70.

Drainage Design/Culverts ..........................................................................................59

1.1.71.

Accidents & Black-Spots ............................................................................................59

1.1.72.

Project Benefits to the Local Community ...................................................................60

1.1.73.

Detour, By-pass, Lay-bys and Access Roads .............................................................. 60

1.1.74.

District/Community Role in the Project .....................................................................60

ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN ...........................................61


INTRODUCTION ...................................................................................................................................61
ENVIRONMENTAL MANAGEMENT PLAN .............................................................................................61
1.1.75.

Impact Mitigation Plan .............................................................................................. 62

IMPACT MITIGATION PLAN .................................................................................................................68


ENVIRONMENTAL MONITORING PLAN .............................................................................................. 127
MONITORING ACTIVITIES AND INDICATORS .....................................................................................128
INSTITUTIONAL FRAMEWORK FOR MONITORING, REPORTING & SUPERVISION ................................ 152
1.1.76.

Establishment of Collaborating Network .................................................................152

1.1.77.

Monitoring Arrangements ........................................................................................152

1.1.78.

Reporting Procedure and Flow of Information ........................................................153

1.1.79.

Construction Phase ..................................................................................................153

1.1.80.

Operational Phase....................................................................................................156

SCHEDULING OF MITIGATION MEASURES AND MONITORING OF PERFORMANCE .............................. 157


1.1.81.

Table for Implementation Schedule of Mitigation Measures ...................................157

1.1.82.

Table for Implementation Schedule of Monitoring ...................................................162

CONCLUSIONS AND RECOMMENDATIONS ............................................................................167


CONCLUSIONS ...................................................................................................................................167
RECOMMENDATIONS .........................................................................................................................167

LIST OF FIGURES

Figure 1: Map showing the location of the project


Figure 2: Fauna around the project area

LIST OF TABLES
Table 1: List of EIA team
Table 2: Showing raw material during construction
Table 3: Average precipitation for 84 years old period
Table4: Average relative temperature
Table 5: Average relative humidity
Table 6: Population distribution in the project planning area
Table 7: Community Concerns
Table 8: Table of evaluation of impacts
Table 9: Mitigation measures
Table 10: Monitoring activities and indicators
Table 11: Monitoring and reporting Responsibilities
Table 12: implementation schedule of mitigation measures

LIST OF APPENDICES

Copy of approved Terms of Reference


Maps and satellite images
Certificate of incorporation
Investment License
Proof of public consultation
Land ownership
Geotechnical studies
Water physiological and Bacteriological Analysis
Bill of Quantities

ABBREVIATIONS AND TERMINOLOGY

CBO

Community Based Organization

CNEL

Community Noise Equivalent Level

DDCC

District Development Coordinating Committee

dB

Decibel (Noise Measure)

ZEMA

Zambia Environmental Management Agency

EIA

Environmental Impact Assessment

EPB

Environmental Project Brief

EIS

Environmental Impact Statement

EMMP

Environmental Management and Monitoring Plan

EPPCA

Environmental Protection and Pollution Control Act

m2

Square Meter

m3

Cubic Meter

NCS

National Conservation Strategy

NGO

Non-governmental Organization

NHCC

National Heritage Conservation Commission

ZAWA

Zambia Wildlife Authority


10

ZESCO

Zambia Electricity Supply Corporation

SIGNATURE PAGE
11

We the undersigned hereby declare that the information contained in this report is true and
correct to the best of our knowledge:

1) Cuthbert Makondo - Environmental and Natural Resource specialist.


2) Mwimba Nkosha - Soci-Econimist..
3) Kennedy Chileshe-

Civil Engineer and Hydrology

4) Habena Habenzu -

Structural Engineer and Material Testing..

5) Dillon Rothman-

Developer................................................................

EXECUTIVE SUMMARY
1.1 The Project
The Management of Kafubu Mall Limited wants to construct a shopping mall in Ndola that will
be of international standards. Once build this will provide access to goods and services to
12

tourist resort facilities as well as the residents of Ndola and other surrounding towns .Ndola is
endowed with a lot of minerals and has got the potential for economic growth.
Kafubu Mall Limited, propose to establish a shopping mall in Ndola .Kafubu Mall Limited are
a private property holding company, which was registered on the 16th of May 2012. Kafubu
Mall Limited shareholders have a diversified portfolio throughout South Africa which includes
offices, warehouses and shopping centers. In this regard, they have identified a piece of land in
Ndola of about 2.5 hectares as a possible site upon which to build a 1163m2 shopping mall. The
proposed development introduces an iconic retail-centric mixed-use development with an
international flavour, where people will experience an exclusive shopping environment, dine
and socialize in an up market setting.
The concept revolves around the construction of a multi-million dollar Shopping Mall
Development facility with a final build-out of approximately 1163m2 in Ndola. These premises
lie at the junction of T-3 and president Avenue and can be accessed through the T-3 and
President Avenue, and are directly opposite Kundalila Flats. The projected total cost of the
whole development will be US $7 million. (US Dollar Seven million). The construction of the
shopping mall will be done at once and is scheduled to commence in March 2013 with
completion set for June 2015

This anticipated project falls under the Second Schedule of the Environmental Impact
Assessment (EIA) Regulations of the Environmental Protection and Pollution Control Act
(EPPCA), and its various Instruments. Provided for under this Act is the requirement that an
Environmental Impact Assessment (EIA) study be carried out for this and similar projects. The
Environmental Impact Statement (EIS) of which this report is the main part, presents the
findings of the EIA study to identify both positive and negative impacts together with
recommendations to mitigate potential negative impacts and to enhance benefits

Kafubu Mall Limited has appointed the consultant to undertake an EIA to comply with the
Environmental Protection and Pollution Act of the Laws of Zambia and subsequent Statutory
Instrument No. 28 of 1997 (Environmental Impact Assessment) regulations
Project Objectives
The key objectives of this project are as follows:

13

To increase shareholders wealth and value through profit generation by operating on a


sound commercial basis.
To offer a one stop shopping and entertainment experience for the people of Ndola and
surrounding areas.
To provide a modern shopping and entertainment experience for international visitors to
the city of Ndola.
To contribute towards the modernization of the city of Ndola and support the increased
affluence and spending resulting from the booming mining industry and its support
sectors.
To contribute in a limited way towards improving the quality of life for the people of
Ndola and surrounding areas by offering quality and international class shopping and
entertainment facilities, and employment.

We are convinced that this project will meet the above objectives once implemented and
fully operational.
Location
The shopping mall will be situated in the central commercial business area; it will cover
23683m2 and the floor of about 11623m2..The shopping mall will be accessed from the
president Avenue opposite Kundalila flats.
Arc 1950 coordinates
EASTINGS

NORTHINGS

67795.104

8564499.761

677948.972

8564621.367

678035.833

8564527.061

677891.892

8564410.419

The Proponent
Kafubu Mall Limited is a private property holding company, which was registered on 16

May 2012. Kafubu Mall Limited shareholders have a diversified portfolio throughout
South Africa, which includes offices, warehouses and shopping centers. Kafubu mall

14

shareholders have been managing a number of properties in Melrose, Johannesburg


South Africa.
Position

Name

Residential Postal

Percentage shares

Address
Director

Rajarathnam Ravi

Flat 1,2 Dolphin

Sankar

court,Kanini,p.o box
70998,Ndola

Director

Steven Bernard Herring

Suite 9A-1st
Floor,3Melrose
Boulevard,Melros
ARCH
Johannesburg,216 RSA

Director

Musonda Mulenga

ZAMTEL Complex

Kambikambi

Northrise, P.O Box


70998 Ndola

Particulars of shareholders:

15

Secretaries

Moores Rowland Ndola

4th Floor Compensation

Corporate Services

House Broad way P.O

Limited

Box 70998 Ndola

Total proposed project investment: US$ 7 Million

Proposed Project Implementation Date: March, 2013

CONTACT DETAILS

Name of Developer

Kafubu Mall Limited

4th Floor Compensension House


Address of Developer

Broadway Ndola
Zambia

Telephone Number of Developer

Tel +260 212 610297


FAX 260 212 617776

Person Responsible for the project


Project coordinator

Steven Bernard Herring


Mwimba Nkosha
Mansansa Close
Plot #224/A Rhodespark
P.o Box 32379
Lusaka

Phone 0976926817/0978811345
16

Relevant Legislation

National Conservation Strategy


EIA Legislative Requirements
According to the EMA of 2011, Section 3 (1) of the Environmental Impact Assessment
(EIA) Regulations, states that, a developer shall not implement a project for which a
project brief or environmental impact statement is required under these Regulations,
unless the project brief or the environmental impact statement has been concluded in
accordance with these regulations and the Zambia Environmental Management Agency
(ZEMA) has issued a decision letter.
Kafubu mall limited has commissioned this study as part of its corporate responsibility
to comply with the prevailing environmental laws in Zambia so that key environmental
issues associated with the project are identified and suitable measures that can mitigate
the potential adverse impacts are put in place.The following legislation were reviewed

17

The Environmental Management Act of 2011 (EMA)

National Council for construction Act


Town and Country Planning Act, Chapter 283
Forest Act, Chapter 199
Water Resources Management Act No 21 of 2011
National Heritage Conservation Commission Act
The Land Act of 1995
The Lands Acquisition Act No. 2 of 1970
Mines and Minerals Act, Chapter 32
Road and Traffic Control Act, Chapter 464
Local Government Act, Chapter 281
Public Health Act, Chapter 295
Factories Act, Chapter 441
Petroleum Act, Chapter 439
.

Energy Regulation Act, Chapter 436


International and Regional Conventions
Project Description
The mall will have two landscaped courtyard spaces, which can be used for meetings,
performances, or open market space hence enhancing social interaction. The courtyard
also breaks the monotony of built up space and provide leisurely atmosphere. Surface
parking of approximately 275 vehicles plus 43 taxis near the road will cater for vehicles.
This wide separation of parking will provide convenient flow of vehicles.
18

Subject to approval of this EIS by the ZEMA, project implementation is schedule to


commence in the first quarter of 2013. Construction of the Shopping Mall will take
approximately 3 years.
Decommissioning and closure will depend on future economic and technological
conditions over the life of the Project.
Potential Impacts and Mitigating Measures
The construction of the mall will be done on the virgin land. The Construction of the
shopping mall is likely to cause an increase in a number of people as well as vehicular
traffic. The major negative environmental impacts have been indentified as:

Biophysical Impacts
Disfigurement to the project area due to construction activities
Increased air pollution from increased vehicular traffic.
Increased noise nuisance both during construction and operation phases
Irreversible environmental destruction from construction activities such as
deforestation, borrow pit digging and camping site for construction workers
Disfigurement to the landscape from construction wastes and borrow pits
River siltation from eroded soil and silt from incresed run-off due to disturbance of
sub-soil structure
Oil and gasoline spills from construction equipment and plant maintenance activities
Littering domestic refuse and sewarage waste from construction camps
Increased particulate matter (diesel) and dust.
Socio-economic Impacts:
Increased access to tourist facilities
General improvement in local livelihoods due to synergistic impacts of positive
effects of the project
Increase in revenue to local authorities and institutions from communications, land
rates, licences and personal levy
Changed human settlement patterns due to increased population who may be
attracted to the area
Creation of employement opportunities during the construction and opreation phase
Increased trade opportunities in the community due to increased population
Environmental Management and Monitoring Plan
19

An Environmental Management and Monitoring Plan covering the construction and


operational phases will be elaborated. The plan will comprises elements to be
incorporated in the detailed design of the project. The responsibilities of the Kafubu
Mall, the Contractor and of the various public authorities will be clearly defined.
Environmental monitoring and enforcement will be stated along with the output from
such monitoring activities. Monitoring responsibilities will be specified for the
responsible authorities, ZEMA, the developer and the Contractor.

The KML EIS TEAM


The EIA team comprises the following experts:
NAME

POSITION

Cuthbert Makondo

Environmental and
Natural Resource
specialist

Mwimba Nkosha

Social Economist

Kennedy Chileshe

Civil Engineering and


Hydrology

Habene Habenzu

Structural Engineering
and Material Testing

SIGN

Conclusions and Recommendations


The findings from the study indicate that the socio-economic benefits of the
construction of a shopping mall to the communities in the project area of influence
outweigh the no-development scenario. The project is therefore being recommended
for implementation provided that the recommended mitigating measures with the
implementation of the Impact Mitigation Plan and Environmental Monitoring Plan are
undertaken.

20

1.1 Project Background


Zambia has vast potential for sustainable economic development through effective
exploitation of its natural resources. One of these areas is through the exploitation of its
vast land resources through property development. The other is the naturally occurring
Tourism potential. Both have greatly contributed to the creation of employment, foreign
exchange, local economic growth, and improving of the aesthetics of the nation at large.
With the growth of its fund and coupled with lack of assets in the market which could
yield real rates of returns, Kafubu Mall Limited has decided to enhance its investments
in property development for Commercial use on the Copperbelt Ndola to be specific. As
21

a consequence, Kafubu Mall Limited is intending to construct a shopping mall that will
be called Kafubu Mall of 32 shops covering about 11623m2. Therefore these EIS is
prepared by the Consultants on behalf of the client Kafubu Mall.

The Management of Kafubu Mall are the executing agency while the contractor will be
responsible for the implementation of this project. The main objective of the
construction of the shopping mall is to secure access to goods and services that are
efficient in answering to peoples needs, thereby making a significant contribution to
realizing and developing Zambia's economic potential. In addition to investment and
wealth creation, was to add beauty to the city of Ndola and bring vibrancy to the new
and up and coming part of Ndola destined to be a high end area.

The Process of Constructing a shopping Mall


The process leading to final construction of the shopping mall works is organized under
four main areas namely; preparatory works, organizing project implementation,
approval and awarding of contracts and supervision of physical works.

1.1.1.

Preparatory Works

This include selection of the Mall, field assessment (Construction interventions,


surveys, collection of data, etc), preparing improvements plans (preparing of technical
specification, local maps and standard cross sections for works to be carried out and
calculations of bill of quantities) preparation of EIA contract clauses.

1.1.2.

Tendering Process

This process involves invitation to tender, making tender documents available to prequalified or registered contractors, organizing pre-tender site visits, issuing tender
notices, receipt and opening of tenders, tender evaluation, and contract negotiations and
awarding of tenders.

1.1.3.

Organizing Implementation of a Project

This process involves giving notices to the contractor to commence work, liaising and
reporting to the employer/ client and liaising with contractors on the work programme
and mobilization of staff, workers and equipment.
22

1.1.4.

Approval and Awarding of Contracts

This process entails obtaining performance bond, insurance of work and workers, giving
notice to contractor to take possession of site, obtaining contractors work programme
and mobilization of staff, workers and equipment.

1.1.5.

Supervision of Physical Work

This involves day to day monitoring of physical progress of the workers, application of
conditions of contract, enforcement of specifications, measuring of works with
contractors' representatives, quality control in form of materials testing at laboratory and
on site, certification of work done, preparation of interim payment certificates, control
of material and equipment on site, issuing of site instructions and variation orders and
settlement of disputes (arbitration, conciliation, etc).
THE PROPONENT
Kafubu Mall Limited is a private property holding company, which was registered on 16
May 2012. Kafubu Mall Limited shareholders have a diversified portfolio throughout
South Africa, which includes offices, warehouses and shopping centers. Kafubu mall
shareholders have been managing a number of properties in Melrose, Johannesburg
South Africa.

Particulars of shareholders:
Position

Name

Residential Postal
Address

Director

Rajarathnam Ravi

Flat 1,2 Dolphin

Sankar

court,Kanini,p.o box
70998,Ndola

Director

Steven Bernard Herring

Suite 9A-1st
Floor,3Melrose
Boulevard,Melros
ARCH
Johannesburg,216 RSA

Director

Musonda Mulenga

ZAMTEL Complex

Kambikambi

Northrise, P.O Box


23

70998 Ndola
Secretaries

Moores Rowland Ndola

4th Floor Compensation

Corporate Services

House Broad way P.O

Limited

Box 70998 Ndola

Total proposed project investment: US$ 7 Million


Proposed Project Implementation Date: March, 2013
CONTACT DETAILS
Name of Developer

Kafubu Mall Limited

4th Floor Compensension House


Address of Developer

Broadway Ndola
Zambia

Telephone Number of Developer

Tel +260 212 610297


FAX 260 212 617776

Person Responsible for the project

Steven Bernard Herring

Project coordinator

Mwimba Nkosha
Mansansa Close
Plot #224/A Rhodespark
P.o Box 32379
Lusaka
Phone 0976926817/0978811345

Project Rationale
Zambia is experiencing a growing economy as reflected by the GDP rated at 5.4% in
2011 and is expected to grow in the coming years, and comparing favorably with
general economic growth in the region. With a population currently estimated at
455.194, Ndola has experienced rapid urbanization in recent years, which has
resulted in demand for more modern infrastructure. The city is thus facing a number of
challenges,

which

include

inadequate

parking,

lack

of

appropriate

accommodation, traffic congestion due to the increasing number of vehicles and


overstretched designed traffic routes through the City Centre from north and south
24

and the need to service expanding areas and new development nodes. These areas
include:

Northrise
Kansenshi
Itawa
Mushili
Lubuto
There is an urgent need to address the inadequacies of existing infrastructure and to
meet a growing demand for modern facilities in the office and retail market, the
residential market and the hotel and hospitality industry as well as leisure
market.The current situation obtaining in the property market in include

25

1.4 Proposed location and site MAP


The location plan as prepared by Kafubu mall Limited for this project is provide below:

The shopping mall will be situated in the central commercial business area; it will cover
23683m2 and the floor of about 11623m2..The shopping mall will be accessed from the
president Avenue opposite Kundalila flats.
Table 2: Arc 1950 coordinates
EASTINGS

NORTHINGS

67795.104

8564499.761

677948.972

8564621.367

678035.833

8564527.061

677891.892

8564410.419

26

1.5 Project Objectives


The key objectives of this project are as follows:
To increase shareholders wealth and value through profit generation by operating on a
sound commercial basis.
To offer a one stop shopping and entertainment experience for the people of Ndola and
surrounding areas.
To provide a modern shopping and entertainment experience for international visitors to
the city of Ndola.
To contribute towards the modernization of the city of Ndola and support the increased
affluence and spending resulting from the booming mining industry and its support
sectors.
To contribute in a limited way towards improving the quality of life for the people of
Ndola and surrounding areas by offering quality and international class shopping and
entertainment facilities, and employment.

We are convinced that this project will meet the above objectives once implemented and
fully operational.

Objectives of the EIA


As earlier stated, the study was carried out in partial fulfillment of the
requirements of the EIA Regulations to identify potential negative and positive
impacts of the project and provide mitigation measures for negative impacts and
enhancement measures for positive impacts respectively.

We have provided mitigation measures to mitigate the negative impacts. We have also
recommended enhancement plans to enhance positive impacts of the project. An
environmental Management Plan has been presented in this report to provide clear
steps designed to ensure focused implementation of the recommended mitigation
and enhancement measures.

27

We trust the information contained herein meets the requirement of the


Environmental

Council

of

Zambia

and

warrants

them

to

authorize

the

implementation of the KML project.

Scope of the EIA


To determine the environmental implications of the construction of the shopping mall,
an EIA must be undertaken according to the Environmental Protection and Pollution
Control Act (Environmental Impact Assessment) Regulations of 2011.

Kafubu mall limited has identified a pieace of land for the construction of the shopping
mall, which also encompasses an environmental impact assessment. The EIA will assess
the impacts from the construction and evaluate the alternatives. The existing pieace of
land has been included with a "zero-alternative", in case the construction on the
proposed land does not take place.

The EIA will determine whether the Construction of the shopping mall will have
significant adverse or beneficial impacts on the environment during the construction
phase and operational life of the mall, and it will also recommend measures for
mitigation of negative environmental effects through the preparation of an
environmental management and monitoring plan.

The scope of the study is outlined in the Scoping Report and Terms of Reference
(November 2012) as reviewed, commented and approved by the Environmental Council
of Zambia. The output from the EIA is this Environmental Impact Statement (EIS)
comprising of an Environmental Management and Monitoring Plan (EMP).
Study Approach and Methodology
The EIA process took place from October 2012 to November 2012, and involved the
following steps:

28

Review of the existing environmental information and legislation

This included review of the Environmental Protection and Pollution Control Act and its
subsidiary legislation and other relevant Acts and international conventions.

Initial environmental survey at the proposed Shopping mall

This task involved collecting data around the project areas and identifying areas
requiring detailed investigations, which include sensitive areas.

Scoping

The scoping exercise included consultative meetings and discussions with relevant
government institutions at national, provincial and district level, local communities,
representatives from NGOs and community based organizations and residents from
communities around the project area. Letters stating the objectives of the project and
requesting local participation and consultation in the process were also distributed.
Responses from the consultations and discussions provided the relevant background
information and helped identify major environmental concerns of the communities
around the proposed shopping mall for the detailed EIA process.

Identification of the magnitude and significance of the principal impacts

Impacts will be evaluated in terms of magnitude and significance. There are four
groupings of impacts on the environment, which will be evaluated for the duration of
the project namely;

Physical environment
Biological environment
Socio-economic environment
Cultural environment

29

These impacts may be positive (beneficial) or negative (adverse) and will be classified
as low, moderate or high to the extent their effects will be described quantitatively in
terms of environmental costs and benefits. Effects may be direct or indirect, short term,
intermediate or long term.

The impacts will be assessed during the following stages of the project:
Pre-Construction (Design) Phase
Construction Phase
Operational Phase

It will be important that the likely impacts are defined and evaluated at an early stage of
the planning process. This was done through scoping the specific impacts and their
implications which are pertinent to the shopping mall project so that alternatives can
then be investigated and changes can be incorporated at the design stage. Other
measures will also be identified which can be taken into account during design and
construction phases that would enhance the environmental quality of the shopping mall.

Identification of appropriate mitigation measures and/or design changes to


eliminate or reduce the identified impacts

The mitigation measures will be considered to reduce the effect of the development on
the surrounding environment. Wherever possible recommendations will be made to
mitigate against impacts on the physical, biological, socio-economic environment and
cultural environment.

Formulation of an environmental management and monitoring plan

The report will include a plan for monitoring and implementation of mitigation
measures during construction and operation. Mitigation plans should be included in the
tender document to form part of the overall construction contract.

30

Environmental Impact Assessment Team

Table 1: The EIA team comprises the following experts:


NAME

POSITION

Cuthbert Makondo

Environmental and

SIGN

Natural Resource
specialist
Mwimba Nkosha

Social Economist

Kennedy Chileshe

Civil Engineering and


Hydrology

Habene Habenzu

Structural Engineering
and Material Testing

31

POLICY, LEGAL AND INSTITUTIONAL FRAMEWORK


Environmental Policy Framework and Strategy

1.1.6.

National Conservation Strategy

The National Conservation Strategy (NCS) is the forerunner to environmental


legislation in Zambia. The NCS was adopted by the Government of Zambia in 1985 and
led to the enactment of the Environmental Protection and Pollution Control Act in 1990
and provided for the establishment of the Environmental Council of Zambia
(ZEMA)which became operational in 1991. The NCS provided guidance for the
sustainable development of Zambia through the use and conservation of natural
resources within a centrally planned and controlled economy. However, in 1992, the
National Environmental Action Plan process was established to update the NCS, to meet
the demands of an economy undergoing liberalization and to update technical
information.
Environmental Legislative Framework

1.1.7.

Environmental Protection and Pollution Control Act, Chapter 204

The Environmental Protection and Pollution Control Act (EPPCA), Cap 204, Part IV to
VII sets the role of ZEMA in setting environmental quality standards for waste, water,
air, pesticides and toxic substances, noise, ionising radiation and natural resources
conservation. In 1997 an amendment to the EPPCA established the Environmental
Impact Assessment Regulations, Statutory Instrument No. 28 of 1997 for conducting
and review of Environmental Impact Assessment of certain projects such as this one .

The Zambia Environmental Management Agency being a Statutory body is mandated to


enforce the provisions of the EPPCA on natural resource management and pollution
control for the protection of the environment.

1.1.8.

EIA Legislative Requirements

According to the EMA of 2011, Section 3 (1) of the Environmental Impact Assessment
(EIA) Regulations, states that, a developer shall not implement a project for which a
project brief or environmental impact statement is required under these Regulations,
unless the project brief or the environmental impact statement has been concluded in
32

accordance with these regulations and the Zambia Environmental Management Agency
(ZEMA) has issued a decision letter.
Kafubu mall limited has commissioned this study as part of its corporate responsibility
to comply with the prevailing environmental laws in Zambia so that key environmental
issues associated with the project are identified and suitable measures that can mitigate
the potential adverse impacts are put in place.
The Environmental Management Act of 2011 (EMA)
This Act was passed in the year 2011 and its the Principal Act governing, managing
and regulating environmental issues in Zambia. Its main functions include the protection
of the environment and control of pollution, in particular to provide for the health and
welfare of people, animals, plants and the environment.
Specifically, Section 3(1) of the EIA Regulations states that, a developer shall not
implement a project for which a project brief (EPB) or environmental impact statement
(EIS) is required under these Regulations, unless the project brief or the environmental
impact statement has been concluded in accordance with these regulations and the
Environmental Council of Zambia has issued a decision letter.
Prescribes the conducting of an environmental impact assessment and the development
of impact mitigation measures. The Complianc is that the developer needs to Prepare
an impact assessment and submission of an EMP thereafter.
The contents of an Environmental Impact Statement shall be prepared to include the
following elements:
A description of the project;
A description of the site;
A description of the raw material inputs, technology, processes, products and byproducts;
A description of the site surrounding environment;
A description of the environmental effects;
A description of the socio-economic impacts;
Impact management Plan

33

EIA Legislative Requirement for Construction of a shopping Mall

This anticipated project falls under the Second Schedule of the Environmental Impact
Assessment (EIA) Regulations of the Environmental Protection and Pollution Control
Act

(EPPCA), and its various Instruments. Provided for under this Act is the

requirement that an Environmental Impact Assessment (EIA) study be carried out for
this and similar projects. The Environmental Impact Statement (EIS) of which this
report is the main part, presents the findings of the EIA study to identify both positive
and negative impacts together with recommendations to mitigate potential negative
impacts and to enhance benefits.
Therefore the EIA process was conducted in line with the provisions of these EIA
Regulations.
Other Acts Reviewed Relevant to the Construction of a shopping Mall

The Acts below have also been reviewed in order to ensure that the project complies
with other relevant existing laws that have a bearing on environmental management.

1.1.9.

National Council for construction Act

This is an act to provide for the establishement of the national Council for construction
and to define its function; to provide for the promotion and development of the
construction industrial in Zambia; to provide for the registration of the contractors to
provide for the affiliation to the council of professional bodies or organisation whose
members are engaged in activities related to the construction industry; to provide for the
regulation of the construction industry; to provide for the regulation of the construction
industrial; to provide for the establishement for the construction school; to provide for
the training of persons engaged in construction or in activities related to the
construction; and provide for matters connected with or incidental to the fore-going.

The construction of the shopping mall will be undertaken in accordance with the
National Council for Construction Act that will aim to promote the construction
industry, it will also use trained and qualified persons as well as registered contractors.

34

1.1.10. Town and Country Planning Act, Chapter 283


The Town and Country Planning Act, came into force in 1962 and provides for the
control, use and change of land use zones and reservations for various purposes, eg.
siting of work sites. It also provides for the compensation of those affected by planning
decisions and regulated development subdivisions.

The construction of the shopping mall project will be undertaken in accordance with the
approved land use plans as provided for under the Town and Country Planning Act.

1.1.11. Forest Act, Chapter 199


The Forest Act, passed in 1974, provides for the establishment and management of
National and Local forests, conservation and protection of forest and trees, and licensing
and sale of forest products. The Act prohibits the felling, collecting or injuring of forest
products in protected forest areas or forest reserves, unless a license has been obtained
to do so. It also prohibits excavation, construction, and operation of machinery within
the forest reserves or protected areas.

Forest reserves currently cover approximately 10% of the country and are intended for
the conservation and development of forest resources, as well as providing protection to
watersheds.

The Act also provides for the protection of 6 tree species nationally whether in a
protected area or outside it. These are as follows:

Entandrophragma caudatum

Mountain Mahogany

Khaya nyasica

Red Mahogany

Pterocarpus angolensis

African Teak

Afzelia quanzensis

Pod Mahogany

Faurea saligna

Beechwood

Baikiaea plurijuga

Teak

35

During biological/ecological investigations protected tree species have not been found
around the project area.. During the construction of the mall, these species would have
been addressed.

1.1.12. Water Resources Management Act No 21 of 2011


An Act to establish the Water Resources Management Authority and define its functions
and powers; provide for the management, development, conservation, protection and
preservation of the water resource and its ecosystems; provide for the equitable,
reasonable and sustainable utilisation of the water resource; ensure the right to draw or
take water for domestic and noncommercial purposes, and that the poor and vulnerable
members of the society have an adequate and sustainable source of water free from any
charges; create an enabling environment for adaptation to climate change; provide for
the constitution, functions and composition of catchment councils, sub-catchment
councils and water users associations; provide for international and regional cooperation
in, and equitable and sustainable utilisation of, shared water resources; provide for the
domestication and implementation of the basic principles and rules of international law
relating to the environment and shared water resources as specified in the treaties,
conventions and agreements to which Zambia is a State Party; repeal and replace the
Water Act, 1949; and provide for matters connected with, or incidental to, the
foregoing. The Act also establishes the pollution of public water as an offence, although
the Water Pollution Control Regulations are established by the EPPCA.

The project will comply with the provisions of the Act by ensuring that storm water
disposal structures intended to control runoffs from the mall into the aquatic
environment (both surface and groundwater) are part of the overall detailed designs for
construction of the shopping mall.

1.1.13. National Heritage Conservation Commission Act


The National Heritage and Conservation Act established the National Heritage
Conservation Commission (NHCC), which is responsible for the conservation of
ancient, cultural and natural heritage, relics and objects of aesthetic, historical,
prehistoric, archaeological

or scientific interest

by preservation, restoration,

rehabilitation, reconstruction, adaptive use and good management. The Commission


also provides regulations for archaeological excavation and export of relics.
36

If a development is unable to proceed without affecting an item of heritage, permission


must be sought from the NHCC as outlined in Sections 35 and 36 of the National
Heritage Conservation Commission Act.
During the surveys and detailed EIA investigations items of heritage were not found
near the project area, but if fund will be addressed in accordance with the mitigation
measures provided in the management plan in this report.

1.1.14. The Land Act of 1995


The Land Act of 1995 was enacted to guarantee peoples' right to land while enhancing
development. The Act recognizes the holding of land under customary tenure and the
Chiefs role has been legally recognized, such that land cannot be converted or alienated
without approval of the chief.

The developer worked closely with the local community and has obtained consent from
Area Councillors and local authorities of Ndola Communities during the EIA process
and will continue to do so during final shopping mal construction works.

1.1.15. The Lands Acquisition Act No. 2 of 1970


Land acquisition is governed by the Lands Acquisition Act No. 2 of 1970. The Act sets
out regulations for compulsory acquisition of land and property and compensation for
such acquisition. The president (his designated and authorized person) may acquire any
property in the interest of the Republic. Notice shall be given in person not less than two
months in advance and shall be gazetted. Compensation for acquired property, losses
and damages shall be paid as may be agreed or, finally determined by the National
Assembly in case agreement on compensation is not reached within six weeks after
publication in the Gazette. Any disputes except for disputes related to the amount of
compensation may be instituted for court proceedings. The Act also provides for
compensation to be granted by allocation of new land to the property owner.

The Act instituted a Compensation Advisory Board to advise the Minister of Lands in
assessment of compensation payable under the Act. The functions of the Board have
been delegated to various committees. Various forms to be used in proceedings of
property acquisition are prescribed in the statutory Instrument No. 60 of 1970.
37

The developer will confine the construction works within the proposed project reserve
area to minimize impacts in the immediate environment.

1.1.16. Mines and Minerals Act, Chapter 32


The Mines and Minerals Act Cap 32 of 1976 regulates activities relating to mines and
minerals operations including quarrying and provides for regulations for environmental
protection during prospecting and mining activities and rehabilitation of the areas
mined. Further, the Ministry of Transport and Communications, Environmental
guidelines Section 7.6 (2) states that:
Contractors shall obtain licenses from the Ministry of Mines to operate borrow pit
areas and 7.10 (6) states that Contractors shall obtain mining licenses for quarrying.

In this project quarrying for gravel material will be carried out and rehabilitation of the
quarries created in the process will be carried out based on the mitigation measures
outlined in this document and in the subsequent Environmental Project Brief for a new
borrow pit.

1.1.17. Road and Traffic Control Act, Chapter 464


The Road and Traffic Control Act, provides for the control of traffic, and for the
regulation of storm water disposal structures.

In this shopping mall construction project, requirements for storm water disposal
structures along the access road as provided for under this Act are part of the overall
designs for the shopping mall.

1.1.18. Local Government Act, Chapter 281


The Local Government Act allows the Council to implement environmental protection
and natural resources management functions, which include prevention of pollution of
water supplies and undertaking of mining operations.

38

For instance, the Act would support the location and restorations of borrow pit sites,
subject to approval by the relevant Government Departments and Local Communities in
the areas in which they are located.

Location and sitting of camps and borrow pits will be undertaken with consultations
and consent from the local community and approval from relevant Government
Departments. In the case of opening a new borrow pit this will require approval from
the Zambia Environmental Management Agency by way of undertaking an
Environmental Project Brief.

1.1.19. Public Health Act, Chapter 295


The Public Health Act empowers a Council to prevent diseases and pollution dangerous
to human health and to any water supply for domestic use.

The project will ensure that measures to prevent diseases and pollution dangerous to
human health and to any water supply are taken into account through the provision of a
drainage control system.

1.1.20. Factories Act, Chapter 441


The Factories Act provides a framework for the setting of regulations to ensure the
safety, health and welfare of persons employed on construction work sites and in
factories. The Act is applicable during the shopping mall construction.

The project will ensure that the safety, health and welfare measures and facilities of
workers during the construction of the mall will be in accordance with the provisions of
the Factories Act.

1.1.21. Petroleum Act, Chapter 439


The areas of the Petroleum Act of relevance to this project are regulations for the
conveyance and storage of petroleum, inflammable oil and liquids e. g. jet A fuel,
paraffin and diesel.

Where petroleum products shall be transported to or stored on site this shall be done in
compliance with the provisions of the Petroleum Act.
39

1.1.22. Energy Regulation Act, Chapter 436


This Act allows for the establishment of procedures for the transportation, handling and
storage of fuels to minimize negative environmental impacts.

Where fuels shall be transported to, handled or stored on site this shall be done in
compliance with the provisions of the Energy Regulation Act.
International and Regional Conventions

Zambia is a signatory to a number of international and regional conventions, the ones


which are related to the environment are listed below:-

Convention on Wetlands of International Importance especially as a Waterfowl


Habitat
Convention on the Protection of World Cultural and Natural Heritage
Convention on International Trade in Endangered Species of Wild Flora and Fauna

United Nations Framework Convention on Climate Change


Convention on Biological Diversity United Nations Convention to Combat
Desertification

Of the above, only the Convention on the Protection of World Cultural and Natural
Heritage has some relevance for the project in case such are fund on site during
excavation works. The site will be addressed by the project as proposed in this
Environmental Management Plan.

40

PROJECT DESCRIPTION
Project Location
The proposed project is located at the junction of T-3 and president Avenue in the
central business area of Ndola, a city on the Copperbelt Province of Zambia . The
province has ten districts.

Figure 1: Map showing the location of the project site


Arc 1950 coordinates
EASTINGS

NORTHINGS

67795.104

8564499.761

677948.972

8564621.367

678035.833

8564527.061

677891.892

8564410.419

41

The shopping complex will accommodate leisure, social and recreational facilities.
These will include shopping, entertainment and administration area of 23683m2. This
includes the parking space.
The mall will be inter-linked by covered walkways. The small retail-shopping units will
vary in size from 48m2 to 450m2. However, the areas can be adaptable to the required
minimums required by the tenant. This also allows for a wide range of tenant mix and
wide range of commodity.
The shopping mall will have adequate provision for full service restaurants and pubs in
the complex and provisions for coffee shops and business caf. A large super store of
about 800m2 as one of the key tenants will be run by a recommended franchise that will
allow for variety of commodities. This will be serviced from the back and fully house
with administration offices, staff canteen kitchens and storage spaces.

The mall will have two landscaped courtyard spaces, which can be used for meetings,
performances, or open market space hence enhancing social interaction. The courtyard
also breaks the monotony of built up space and provide leisurely atmosphere. Surface
parking of approximately 275 vehicles plus 43 taxis near the road will cater for vehicles.
This wide separation of parking will provide convenient flow of vehicles.
Subject to approval of this EIS by the ZEMA, project implementation is schedule to
commence in the first quarter of 2013. Construction of the Shopping Mall will take
approximately 3 years.
Decommissioning and closure will depend on future economic and technological
conditions over the life of the Project.

The project will consist of the following phases:Phase 1 Site Preparation (Year 1),
Phase 2 Construction (Year 1 Year 2),
Phase 3 Operations (Year 2 Year 30), and
Phase 4 Decommissioning and Closure (may not be done).

42

Project Activities.

1.1.23. Phases in Shopping mall construction


The project is made up of four phases namely preparation, construction, operation and
decommissioning phase. Each of the phases comprises a series of activities contributing
to overall attainment of the project objectives. The activities involved in each phase are
elaborated in the sections below.

Pre-Construction (Design) Phase

This phase involves carrying out a survey of the proposed shopping mall. Survey in this
case refers to land investigations, drilling, measurements and pre-works examination of
the site. To facilitate the development of a conceptual design an environmental impact
assessment was undertaken and the key concerns from the study were taken into account
in the design phase. The output from this phase is an environmentally friendlyengineered design for the shopping mall, which has to be implemented in the
construction phase.

Construction Phase

The actual construction of the shopping mall will take place in the construction phase.
The estimated shopping mall works will cover the following activities:

Shopping mall construction


The initial activities during this phase relating to construction management will include:

Establishment of the construction Project Management Team (PMT).


Establishment of a professional Site Inspection Team.
Establish and agree management, inspection, and reporting procedure

The Site Establishment will include the initial construction of the following facilities:

Establishment of site management office and facilities.


43

Maintenance workshop sheds and stores.


Fuel depot / kerb site for the temporary fuel stocks for construction equipment
Establishment of temporary services and builders supply i.e. water supply
Establishment of temporary fencing around the site

There will be labour camp on the project site, although security personnel will be
accommodated on the site. Various plant and equipment to be used during the execution
of civil works will include

Graders
Cranes
Vibrators Rollers
Water Trucks
Bulldozers
Front End Loader
Generator Set 125 KVA
6m Containers
Concrete Mixers
Concrete Pokers Excavators
Water Pumps
Mechanical Tool Boxes
Compressors
Civil Plate Compactors x3
Pedestal Rollers
Tipper Trucks
10 Ton Trucks 4
Construction activities will be repeated as required over the two phased Construction
cycles. The main anticipated project construction activities that will have potential
impacts on the environment are:

a) Site Preparation and Leveling

Initial site preparation will entail removal of the existing infrastructure,


scarifying of topsoil and earthworks to establish the required levels. The project
44

will be constructed by-and large on the existing level requiring minimal basic
earthworks, which will minimise the need for filling of areas with laterite and
aggregates. Earthworks will for the most part involve the use of heavy
machinery such as bulldozers and graders.

b) Construction of Roads and Drainage System

Construction of the roads will involve earth moving and shaping of formation
shoulders, and stabilization of the base with the piling, spreading and
compaction of gravel and aggregate materials on the road.The entrance to the
mall will be opposite Kundalila flats on president avenue studies are underway
to find the best way to incoparate the nearby existing public road network, a
team of expertise from local authority and RATSA including RDA and the
developer are yet to develop the traffic strategy Construction of a bitumen
surface pavement will involve the spreading and compaction of aggregates and
tar materials on the road. Construction of drainage will involve excavation and
shaping of drains and soil compaction. Lined drains will require the preparing
and pouring of concrete.
c) Excavation and Foundations:

This will involve the excavation of trenches for foundation strips for buildings
and trenches for ground water storage tank water, and sewage reticulation
system. The geotechnical survey of the site is indicative that the bearing
capacities of soils are good and the foundation depth and design for the intended
structures will not be complicate.

This will be in accordance with local engineering standards.


Construction of foundations will involve the compaction of underside
of foundation trenches and
Pouring and mixing of concreate

45

d) Sub-structural works and Floor slabs


This will involve block work, mixing, pouring and compaction of
concrete, backfilling and compaction of material according to specifications.
This sub structural works will include the laying of water and sewage
reticulation pipes and underground electrical cables.
e) Construction of Superstructures (shopping mall)
This will involve:
The preparing of mortar and concrete.
Structural steel erection
The laying of concrete block walls.
Fixing of roofs.
Erection of roof trusses.
Installation of finishes and fixing electrical and plumbing fixtures
and fittings.
Landscaping

f) Materials Mobilization, Handling and Storage


This refers to the acquisition, delivery, and storage of materials required for
construction works. Gravel, laterite, and stone aggregates will be acquired and
transported to the site from ZEMA approved quarry sites within the Ndola area.
Provision will be made for bulk storage of materials such as sand, aggregate and
laterite. Petroleum products, such as fuels (petrol/diesel), lubricating oils, hydraulic
fluids and bitumen / asphalt mix will also be sourced. Only limited amounts of these
materials will be stored on site as reliable supply sources will be within close
proximity. A small fuel storage facility of capacity 1000 litres, will be established
on site. Other materials that will be transported and stored include sand, cement and
blocks,

46

g) Maintenance of Machinery
A temporary workshop facility will be constructed on site for the maintenance of
construction vehicles and machinery. This will be combined with the fuel storage
facility.

h) Movement of Construction Traffic and Heavy Machinery


Transportation of construction materials and waste to and from the site will involve
the movement of heavy vehicles on access roads to the project site as well as within the
site. Daily transportation of construction workers will also add to the volume of
construction traffic to the site. Construction activities such as clearing, excavation,
earth moving and mixing of concrete will involve the movement and operation of
heavy plant and equipment on and around the site.

i) Construction Workers Activities


Although no labour camp is planned in the project area, social interaction activities
will undoubtedly result between project workers and local communities. The
project will as much as is possible hire labour from within local communities. Local
market transactions will take place between construction workers and local
communities. Casual sexual relationships may also result from interactions between
workers and the community. A canteen will be established on site to cater for
construction workers. The presence of construction workers will require the provision
of water for food preparation and domestic purposes as well as the provision of
sanitation and health services.

j) Water Abstraction
As mentioned earlier, water will be required for construction, workers domestic and
dust suppression measures. Water will be abstracted from on site water system
provided by Kafubu Water and Sewerage Company at a rate not exceeding 2.5 l/s.

47

k) Waste Management
Waste management during the construction phase will include:
Provision of temporary workers sanitation.
Collection and disposal of domestic waste at ZEMA approved disposal sites.
Transportation and disposal of building waste and rubble.
Collection and disposal of used oils / lubricants according to ZEMA
Requirements and ERB standards

Shopping Mall Design Parameters


The mall will be a single level development covering 11623m2 of floor space catering
for about 32 shop spaces. It will be fully enclosed and air-conditioned. It will have
provision for four (4) anchor tenants. Central to the concept of the development will be
an extensive Food Court area with large enclosed clerestore-lit and landscaped common
seating area that will cater for five (5) sit-down restaurants. The knuckles of the mall
will have three (3) court areas. The shopping mall will also have 273 parking bays at
full capacity and in addition it will43taxis parking spaces the taxi drop off zone.

Fencing
It is recommended that a perimeter fence be provided that secures the entire shopping
mall. The shopping more will be situated in a central business area near some residential
houses so it is necessary to fence off the mall.

Installation of shopping mall furniture

The shopping mall will have to put in place furniture in the forms of signs, demarcations
and lining, safety barriers, culvert beacons, traffic lights. The Project proposes to
introduce all the above-mentioned furniture where appropriate.

48

Communication and Safety Measures

Firefighting equipment and communication system for safety measures on mall will be
installed.

Operational Phase

The main activities that will exist during the operation stage will be those that will relate to the
specific different parts of the development. As indicated in the foregoing, the completion of
each development phase will result into the commencement of the respective operation of the
particular facilities. The completion of the Shopping Mall will open up new avenues to the
populace for consumer shopping, trading in the tenant lots to be provided, and participation in
the varied entertainment packages that will be available. Because of the availability of open
paved spaces, leisure related activities will be highly exploited.

During these operational phases, certain activities that are likely to have an impact on the
environment include:

1) Water Supply As mentioned the average and maximum water demand of the project is
estimated at 2,508 m /day and 4,238 m /day respectively to be sourced from KWSC water
supply. Water will be stored in tanks (Sub-surface, surface or Overhead) in case of water
shortfall.

2) Commuter Traffic The volume of traffic to and from the project area will increase
appreciably once the project is operational. This will especially apply at peak times during the
day with commuter traffic and during peak shopping periods such as weekends.

3) Commercial Activities These will include retail activities at the commercial node.
4). Leisure Activities This includes activities like the shopping, and other entertainment
facilities including restaurants.

5). Estate Management Post Construction Activities relating to estate management will
include:
49

Waste Management
Solid waste management from the commercial node will be the responsibility of the centre
management who will ensure that the area is at all times clean and tidy. The facilities
provided for the separation of waste for recycling and storage will be in enclosed and caged
skips to prevent materials from being blown away from the site. An approved contractor for
disposal in accordance with NCC and ZEMA regulations will collect waste regularly.

Sewer & Storm Water Management Sewer line maintenance will include routing and
flushing the sewer mains, service calls on potentially blocked mains, repair of damaged
mains, and flushing driveway culverts.
Electrical Maintenance & Management The electrical distribution system will be
monitored and maintained on a day-to-day basis. This will be up to the distribution
board at each facility. All internal electrical maintenance will be the tenants
responsibility and must be carried out by an approved electrical contractor.
Water Management The water reticulation system will be monitored and maintained on
a day-to-day basis in conjunction with the KWSC. All internal water supply
maintenance will be the responsibility of the owners and will be carried out by an
approved plumbing contractor.

Vector/Pest Control (mosquitoes and cockroaches) One of the most effective methods
of vector control is Indoor Residual Spraying (IRS). In this method, the inside walls of
mall are sprayed with residual insecticides. Contact with the walls by any of the pests
results in their death immediately or soon afterwards. The other effective method of
mosquito control is that a person sleeps under insecticide treated nets (ITNs). The ITN
works not only by creating a barrier between the mosquito and its intended victim, but
also by killing the mosquito if it gets into contact with the net. The Management will
contract for the annual spraying of public areas of the mall with appropriate pyrethroids
to control mosquitoes and bi- annually with approved pesticide for the control of
cockroaches.
Decommissioning And Closure
Decommissioning and closure is dependent on economic and technological conditions
after the 30-year Project life.
50

Final rehabilitation will includei) Removal (or alternative use) of the redundant Mall infrastructure,
ii) Re-vegetation and re-profiling of the Mall area, and
iii) Post closure environmental monitoring and inspection.
The above-mentioned actions will effectively rehabilitate the Project site.

1.1.24. Sources of Raw materials for shopping Mall


1.1.25. Raw materials During Construction
No Raw Materials

Sources

Mode of
Delivery

Sand - River and Building

Local

Road truck

suppliers
(for concrete and
building mortar)

Laterite

Approved

Road truck

borrow pits
( for foundations and

and quarries

construction of road sub


base )

Aggregates

Local ZEMA

Road truck

approved
(for concrete and construction

suppliers (e.g.

of sub base and pavement of

Oriental and

internal road

Raube
Quarries.

Cement

Local approved

Road truck

supplier (Chilanga
51

(for concrete, mortar and road cement plc


works
5

Asphalt and bitumen

Local

Road truck

ERB

approved
supplier

clay brick

Registered

Road truck

foreign and
local clay brick
suppliers e.g.
Kalulushi
Bricks

Concrete blocks and

To be

Culverts

Road truck

manufacture
d on and off

(for in fills/ building)

Petroleum Products Diesel

site

Local

Road truck

suppliers
(for operation of plant

Local ERB
approved

and machinery)

supplier

Water

for

construction,

Serviced by KWS

Road truck

To be serviced by

To be supplied

dust

suppression and
domestic use

10

Electricity

52

ZESCO
11

General building materials

Local

by ZESCO
Road truck

ZEMA
(e.g. timber for

approved

shuttering, door and

suppliers

window frames
polythene sheeting,
brick force and mesh
for reinforcement,
timber, sewer pipes,
paint e.t.c)

12

Finished products and

Imported

equipment

ensuring

Road truck

compliance
steel

with Zambian

sections ,IBR roofing

standards and

sheets, gypsum board,

regulations

(e.g.

structural

uPVC

and

HDPE

piping,

light

fittings,

switches,

aluminum

fittings,

switches,

window frames, sanitary


ware, brass ware and
finishes, ceramic floor
tiles,

air

conditioners

geysers, sewer treatment


plant,

booster

pumps

etc)

Table2: showing raw materials during construction

53

Raw Material during the Operational Phase


The main raw materials inputs required for the operational phase of the project will include:
1) Water This will be used for both domestic and commercial use. The water supply
demand is as outlined above.

2) Electricity Provisional electricity demand for the project is estimated at 20 MVA.


The actual supply may be even less than this. ZESCO has indicated that this is
within its capacity to supply.

3) Raw Foodstuffs and Sundries This will be required during the

operation of

catering services of the Restaurants. This will also include cleaning chemicals and
products for tertiary treatment of sewerage

1.1.26. Waste Products during Construction Phase


The following waste and by-products are expected to be generated during the
project Construction cycle:
1. Topsoil
This Top soil will result from scarifying of the site.
2. Building rubble
This will include sub-soil removed and any rock rubble generated by blasting (or
other rock breaking activities) during excavation of trenches for foundation strips.
This will also occur during the laying of sewer / water reticulation pipes,
excavations for water features / ground storage tanks for water and fuel, etc. and
other spoil such as rejected concrete, broken blocks and tiles, etc.
3. Solid waste
The other solid construction waste will include material such as scrap timber and
various off cuts and refuse such as discarded packaging (e.g. cement bags),
workers garbage, and domestic waste from workers canteen etc.
4. Used oil
Used oil and lubricants will be generated from routine on-site maintenance of Plant
machinery and equipment.

5. Sewage
54

This will be Sanitary and Sewerage waste generated by the construction


workforce.
6. Runoff
This will be Storm water runoff from the site
7. Dust
Dust will be generated on the site from delivery of material and various
construction activities.
8. Exhaust emissions:
This will be from the operation of vehicles and machinery on site.

1.1.27. Waste Products during Operational Phase


The following by- and waste products are expected to be generated during
operation:
1. Sewage
Average and peak daily sewage flow estimates are based on 80 % return flows of
the volume of water supply. The estimated average sewage volume will be
approximately 1662 m3 /day.
2. Domestic / Commercial Solid Waste:
Shoppers, Tenants and Restaurants will generate domestic solid waste. Solid waste
from Restaurant will typically have a high organic content (e.g. vegetable matter
and rejected foodstuffs). The primary generator of solid waste from shops and offices
in the development will be waste packaging and delivery materials (e.g. card board
and plastics) and waste paper. Shoppers will also deposit some litter. Rewstaurants,
offices and shopping complexes generally do not give rise to hazardous or toxic
wastes.
3. Storm Water
An increase in storm water runoff will result from the site due to the
development of roofed and paved areas, which do not allow infiltration of rain water.
Storm water run off from the parking areas may contain some hydrocarbons from
minor oil or fuel leaks/spills. Storm water run-off typically also contains silt and
suspended solids.

4. Exhaust air:
55

Discharges to air from the kitchens of hotel, vehicles and mall restaurants
5. Vegetative Waste
This will include leaves and grass cuttings from maintenance of landscaped areas of
the estate.
Analysis of Alternative Shopping Mall Construction
It is very unlikely that a different type of scheme would achieve the same level of
infrastructural development as that of the proposed project in terms of surfaced road
network and the implementation of a regulated water supply network.

In addition, many other benefits of the proposed project, such as provision of


employment and numerous multiplier effects on the economy would not be realized if it
were not implemented. The proposed project is fully compatible with general
development in the area and is likely to increase the value of neighbouring properties
and ventures. General and specific environmental impacts, which are anticipated
because of the implementation of the project, are detailed in this report. On balance, is
considered that the proposed project will help to meet an urgent need for new
infrastructure and facilities in Ndola without significant net adverse impacts on the local
and general environment. This will be facilitated by the application of the appropriate
mitigation measures as discussed in this report.

Taking the effect of constructing a shopping mall project on the environment, other
alternatives were taken into consideration. The purpose was to assess the effects of these
alternatives on the environment against expected benefits. The alternatives considered
are:

1) Option A: Do Nothing;
2) Option B: Building on the same given site;
1.1.28.

Option A: Do Nothing;

Option A: Do Nothing;
Option A, Do Nothing Alternative

option, would

mean

that

the

current

environmental assessments and implementation being done on site are brought to a


halt, because the option entails not proceeding with construction of shopping mall
56

2) Option B: Building on the same given site;


Option B: Proceeding with the option of constructing the Kafubu mall on the proposed
site is the developers preferred option as the area has already been given to the
company and title deed issued.

Comparison of Alternatives
An objective assessment of the alternatives implies weighing the impacts of continuing
with the option and not continuing. The No option alternative would mean that the
Mall is not built on the proposed site and all the potential impacts on the environment,
i.e., biophysical, socio-economic and cultural would not occur. Option B would entail all
the foreseeable impacts on the bio-physical, socio-economic and cultural environment
would occur.
From the above, it can objectively be stated that considering the distance from the Ndola
and shortage of land in Ndola for such investments, the proposed site would be ideal for
construction of the mall. The main reason for preparing an Environmental Impact
Statement is to identify all the possible impacts associated with the investment and
formulate the best measures to mitigate them before implementation of the project.

57

PHYSICAL

ENVIRONMENT

OF

PROJECT

SITE

&

ITS

SURROUNDINGS
1.1Topography
The Copperbelt province lies on a plateau that slopes gently from 1,370m in
the north-west to 1,130m in the middle. The province has the Kafue River as
the main river basin that drains the Copperbelt in a wide arc from north to
south and is fed by many tributary rivers and streams principally, the
Lufwanyama, Luswishi, Kafubu and Mwambashi Rivers in the west and the
Kafulafuta River in the east.

Topographically, Ndola district lies on the gentle sloping Copperbelt pen plain
at altitudes ranging between 1,200m and 1,455m above sea level,
approximately 13 0 South and 280 35 East. Ndola has an average elevation of
approximately 1,300 m (1,200-1,450 m) above sea level. There are however
isolated hilly outcrops such as Dola, Nakaputa and Kaloko Hills. Higher
elevation is reached north-west of Ndola, where mountains form the border
with the Democratic Republic of Congo, whereas the elevation drops towards
river valleys in the East and South.
The district is characterised by undulating terrain of less than 100 slopes and
from the project area, the land gently slopes northwards towards the Kafubu
River with an average gradient of 2%. The average elevation is about 1200 m
above sea level.
1.2 Soils and Geology
The Copperbelt region of Zambia and Congo D.R. is a 500 million year old
mountain chain, the Lufilian Arc, which formed when two large pieces of
continental crust, the Kalahari Craton and the Congo Craton, collided. This
collision was one of the many that happened between 700 and 500 million
years ago to form the Gondwana supercontinent.

-1-

This collision is thought to have remobilised base metals, largely already


present in the sediments that had accumulated in the basin between the two
cratons. These brines then concentrated the base metals either along
stratigraphic boundaries, or along fractures, faults or within structurally
controlled 'traps' (such as the nose of afold). The collision also produced
crustal shortening, during which the stratigraphic sequence was techtonically
pushed northwards on top of the Congo Craton.

The Lufilian Arc contains two diamictites, megaconglomerates of glacial


origin. One of those is correlated with the sturtian glaciation, while another
correlates with the Marinoan Glaciation, both global glaciation events that had
profound influence on the history of the planet.

Soil formation in Zambia is strongly influenced by rainfall patterns, as these


affect the degree of weathering and leaching. High rainfall patterns in the
Copperbelt combined with a low nutrient base rock have resulted in leached,
nutrient-poor soils. The soils are deeply weathered, typically lateritic, acidic
(with pH values ranging from 4.0-5.5), generally leached of silica and base
nutrients and enriched in iron and aluminium oxides. The sandy topsoil often
overlies a more loamy and clayey subsoil and the composition of the soils
makes them susceptible to erosion if soil conservation practices are not used.
The soils at the specific project site are mostly laterite on the southern side and
clayey on the northern side.
1.3 Climate
Data from the Ndola Weather Station, located 9km northwest of Bwana
Mkubwa are used to define the regional climate and local weather conditions.
The Ndola Station located at an altitude of 1270m and, because of similarities
in altitude and topography, is considered representative of conditions at the
project area.

Average annual rainfall is approximately 1250mm, with the majority falling


during the summer months of November to March.

-2-

As indicated in Table 1 and Figure11, the 84-year average precipitation for a


24- hour event has been recorded at 28.6cm in January with the lowest being
0.2 in September.(Ndola Met Station 1974-2002)

Table 3:Average precipitation for an 84-year old period


Mont

Jan

Feb

h
cm

Ma

Ap

Ma

Ju

Ju

Au

Se

Oc

No

3.7

0.4

0.2

2.5

13

28.

24.

17.

Dec

27.
8

(Source: www.weatherbase.com)
Recorded temperature for Ndola has ranged from as low as -20C to as high as
360C. Low temperatures have been recorded in the months of April to
September while average high temperatures are usually experienced from
October to March.
Table 4: Average relative temperature
Month

Average

Average

Temperature High

Average

Highest

Lowest

Lower

Recorded

Recorded

Temperature Temperature Temperature Temperature


January

21

27

16

30

12

February

21

27

16

30

12

March

21

27

16

30

12

April

21

27

16

30

12

May

20

28

13

30

June

16

25

28

July

18

27

31

-2

August

21

31

12

33

September 21

32

15

36

October

24

32

15

36

November 23

30

16

34

12

December

28

17

31

11

22

(Source: www.weatherbase.com)

-3-

Average relative humidity rises from October to February and thereafter drops
to as low as 30% in September.

Table 5: Average Relative Humidity for a 3-Year Period


Mont

Ja

Fe

Ma

Ap

Ma

Ju

Ju

Au

Se

Oc

No

De

75

75

69

61

52

47

43

36

30

33

54

71

(Source: www.weatherbase.com)

Wind directions are dominated by winds from the northeast through to the
southwest with maximum gusts ranging from 30 m/s in summer to 22 m/s
during the inter months.

Ambient air quality in Ndola area is generally influenced by a number of


different sources of air pollution. These include industrial sources, brick
ovens, domestic fuel burning and veld burning for agricultural purposes,
charcoal manufacturing and vehicle entrainment of dust on unpaved roads.
Motor vehicles emissions also have some impact on air quality. Biomass
burning from July to September on a regional scale elevates the ambient
concentrations from local sources.

The average wind speed of Ndola is 3.3m/s. A high frequency of light winds
occurs at Ndola, with 40 % of all winds less than 3.4 m/s. The highest
frequency of winds is from the sector east-northeast to east-southeast, with
more than 20% of all winds from the east. The strongest winds occur in this
sector and reach 8.5 m/s on 5 % of occasions, mainly in August and
September. On rare occasions the winds exceed 8.5 m/s.

Ambient air quality data is not available for the project site. However,
observations made during visits showed that the air was generally good.
Visibility was not Impaired no foul smell was observed. Some individuals
working in the environs of the project site where interviewed whether they
have been affected by any form of air pollution. The answer was that they
-4-

have not been affected so much apart from occasional smoke emissions from
plant operations and burning activities.

They also have a feeling that the air quality was generally clean. Being an
industrial area air quality was expected to be compromised but the actual
situation is different due to low industrial activities taking place in the area.

The project site being located in the central business area is vulnerable to noise
pollution. Key sources observed included vehicular traffic, plant machinery
operations and occasional train movement. Occasional noise is also recorded
from neighbouring plant machinery and vehicles on the roads such as T-3,
President Avenue and Chisokone Avenue. However, noise levels are generally
low. Snap survey conducted during the day around the project site using a
Decimeter showed noise levels ranging 50- 85 dB. The main source of noise
peaks observed was vehicular movement.
1.4 Hydrology and Drainage
Surface Water
The Copperbelt province is mainly drained by the Kafue River. The River
flows through the province in a wide arc from north to south and is fed by
many tributary rivers and streams principally, the Luswishi,Lufwanyama,
Kafubu and Mwambashi Rivers in the west and the Kafulafuta River in the
east. The City of Ndola is drained by the Kafubu River, which passes through
most of the town with its tributary streams such as the Kandola stream. Other
tributaries include the Kabushi seasonal stream towards the west. Run off
water from the site drains into Kafubu. However, there are no streams on the
specific kafubu shopping mall plot and its immediate areas of influence.

There are no aquatic water quality standards established for Kafubu river.
However, a study conducted by African Mining Consultants to establish water
quality of the Kafubu River using water collected from Kafubu river about 120
metres away from the proposed site showed that the water was generally of
good quality except for feacal coliforms, lead, iron, chromium, cadmium and
manganese which were above the Zambian Drinking Water Standards of 0/100
-5-

ml, 0.05 mg/l, 1.0 mg/l, 0.05 mg/l, 0.005 mg/l and 0.05 mg/l respectively
check appendix for the results.

Ground Water
Borehole data from sites drilled by Department of water Affairs in the area and
its surrounding indicate that the average depths of boreholes range from 3560m, with the water often stuck at depths ranging from 4-25m. Average
borehole yield from a 165mm bore is in the range of 2.5-11 litres per second
with an average draw down of 30.8 meters. Water samples collected from a
borehole near the proposed site at the golf club about 30 meters away showed
that the water was of good quality and complied with drinking water quality
standards. Check the appendix for the results attached
1.5 Water and Sanitation
All water in Ndola is supplied through a company called Kafubu Water and
Sewerage Company. This campany is charged with the responsibility of
providing water supply and sewerage services to the urban and peri-urban
areas of Ndola. The population coverage to these areas is estimated at 80%
and 60% for water and sewerage services respectively.

The water supply in Ndola is presently derived from both surface and
underground sources, with surface sources accounting for approximately 60%
of the total supply. Surface supplies are derived from the Itawa and Kafubu
impoundment's both of which are situated at the Kafubu River while
underground supplies are derived from two well fields in the Misundu area
developed in the 1980s to augment existing surface supplies.

The City is serviced by three sewage collection systems within two sewage
catchment areas. The first system serves Pamodzi, Chifubu, Kawama,
Kansenshi and parts of Northrise in the northern catchment and conveys
sewage to New Kanini Sewage Treatment Plant. The second system caters for
the Central Town area, Kanini, Hillcrest and remainder of Northrise and
Kansenshi, with sewage being pumped to Old Kanini Sewage Treatment Plant
-6-

through Itawa and Dambo pumping stations. The third system caters for the
southern supply district, and conveys sewage by gravity to Lubuto Sewerage
Treatment Plant. It was noted that sewers in the high cost and central business
district are generally in good condition with only a few blockages being
reported or noticed and Kafubu Water and Sewerage Company usually fix
them. However, most of the sewers in the low-cost housing areas no longer
have the capacity to effectively convey the high sewage flows as they now
cater for populations far in excess of the design capacity, resulting in frequent
flooding. The affected areas in this regard are mainly Chifubu, Main Masala
and Kabushi.

-7-

BIOLOGICAL ENVIRONMENT
Flora and Fauna

1.1.29. Flora and Vegetation


From the point of view of phytochorial classification, the whole of Zambia
belongs (together with Malawi, Zimbabwe, large parts of Angola, Tanzania
and Mozambique) to the so-called Zambezian Region. Most of the region is
covered by savanna-woodland (Kawalika, M, 2004).

The Ndola region belongs naturally to the savanna-woodland type with


significant areas being agriculturally and horticulturally cultivated. The
vegetation of the Copperbelt Province, is covered with 80% Miombo
Woodlands (Brachystegia- Julbernardia), which include Brachystegia
longifolia, Isoberlinia angolensis, Albizia adianthifolia, Ficus brachylepis and
Uapaca kirkiana as the key tree species. Grass mainly comprise of the
Hyperrhenia and Digitaria species which include Elephant Grass (Pennisetum
purpureum).

Ndola has the Mansansa Forest Reserve, located westwards of the City, and
with the Chichele Plantation attached to it. The project site however, is a
brown field, designated as light industrial area whose anthropogenic activities
continue to impact on the floral species of the area. Vegetation at the project
site mostly comprise of ornamental plants with very limited natural vegetation.
Fruit trees include mango, guava and apple trees (see figures 1 and 2 below).
Grass mainly comprise of couch grass (cynodondactylon).

-8-

Figure 2: Fauna around the project area


1.1.30.

Fauna around the project area

The project area is a brown field, designated as an industrial area that has been
affected by years of anthropogenic activities. However, the few faunal species
near the project area are bird species such as tits, crows, pigeons, owls, and
goshawks. Rodents are found around the butter and soap plants. Insect species
found in the general locality of the site include mosquitoes, wasps, bees,
cockroaches, grasshoppers, butterflies, houseflies, aphids and dragonflies.

-9-

SOCIO-ECONOMIC ENVIRONMENT
Demographic Profile

1.1.31. Major Demographic Characteristics


The 2010 Census of Housing and Population show that currently, Ndola has a
total population of 455, 194 of which, females constitute 51% and males
49%.The most densely populated area in Ndola is Ndola Central Constituency,
which includes high density residential areas such as Nkhwazi, Yengwe,
Chipulukusu and Twapia, in addition to the low density areas of Kansenshi
and Kanini. Unfortunately, the report does not categorise population by
residential area but by ward.

Table 6: Population distribution in the project planning area


Ward

Households

Male

Female

Total

Kanseshi

2,514

6,586

6,369

12,955

Nkwazi

4,600

10,713

10,689

21,402

Yengwe

3,570

9,376

10,689

21,402

Chipulikusu

7,651

18,526

18,814

37,340

Kanini

2,683

6,410

6,708

13,118

Twapia

6,034

14,316

14,819

29,135

Dag

2,335

4,860

5,044

9,904

305

677

663

1,340

Hamarskjoerd
Kaniki

1.1.32. Economic Profile Around the project area


Ndola used to be the largest industrial centre of Zambia but has been
decimated over the years and scores of closed factories and plants can be seen
- 10 -

in the town. A number of former industries such as clothing and vehicle


assembly have gone completely.
Although copper is still Zambias largest foreign exchange earner and the
mainstay of the national economy, the city of Ndola has established itself as a
commercial and light industrial centre of considerable importance, as well as
being the junction and distribution centre for the Copperbelt. Modern
factories, offices and shops line the Central Business District. A big attraction
in Ndola is the annual Zambia International Trade Fair in July.

There are no mines in Ndola itself but a metallurgical plant by Bwana


Mkubwa is only 10 km south-east of the city centre. Copper and precious
metals used to be brought from elsewhere in the Copperbelt for processing at
the Ndola Copper Refinery and Precious Metals Refinery.
Ndola is host to the countrys only refinery, the Indeni Oil Refinery that
supplies petroleum products from Ndola to the whole country. The main
source of employment and livelihood in Ndola is a combination of formal and
informal employment. Formal employment is in the above named industrial
sector covering mining (copper, lime and cement), agriculture (mostly crop
production), food processing, beverages, textiles, saw milling, chemical
industries together with the service industry comprising government service
provision in health, education, sanitation as well as the private sectors
services in the hospitality industry, trade and transport. Agriculture, trade and
crafts dominate the informal sector.
Land-use

1.1.33. Land Tenure Systems


Zambia is divided into three types of land tenure systems namely Native
Reserves (Traditional Land), State Land and Trust Land. The proposed project
site falls under state land with a 99-year title leasehold

- 11 -

Ndola District has a varying range of industrial and economic activities that
form land use activities.

The majority of the population practice subsistence farming with maize being
the major crop grown. This is mainly for household consumption. Some
households are involved in the growing of vegetables such as rape, cabbage
and tomatoes. As referred to above, substantial acreage of land in Ndola is
reserved for the Mansansa Forest Reserve while another piece of land has the
Chichele Plantation on it.

Mining activities in Ndola are not as extensive as in other Copperbelt towns


even though this was the initial centre of mining. However, Lafarge and Ndola
Lime have quarry pits for their cement and lime production respectively while
Bwana Mkubwa mine processes copper ore from Lonshi Mine in the
Democratic Republic of Congo.

The land use activity around the project area is predominantly light industrial
as well as residential and the area is designated as a central business centre
area by the local authority. They are no change in the land use and that no
impacts will be associated with this in line with the development .The project
will also not result in the damage to agriculture assets as well as fisheries. The
council has given a go ahead of the project meaning that land use and other
associated factors were considered check appendix for council approval.

1.1.34.

Settlements

Zambia has five types of human settlements namely cities, municipalities,


district centres, rural centres and villages. Ndola falls under the city status type
of settlements. However, it also has settlements which reflect rural and village
set ups. The proposed project site is an urban setting.

- 12 -

CULTURAL ENVIRONMENT
Cultural Resources
1.1.35.

Archaeological, Cultural and Historical Sites

Sites of historical and archeological importance in Ndola include the original


mine on the copperbelt located at Bwanamkubwa, the grave site for Polish
settlers running away from war also located in Bwanamkubwa area, the Slave
tree and the Dag hamasjoeld memorial site located in the outskirts of the
Central District of Ndola.

There are no archaeological, cultural and historical sites on the proposed


project area. However, if fund during the construction the developer will
report to the National Heritage and Conservation Committee for action as
outlined by law

- 13 -

PUBLIC MEETINGS/ CONSULTATIONS


Approach and Methodology
The method adopted for community consultations was open discussions with
the relevant local institutions at provincial and district level, representatives
from NGOs and community based organisations and residents from
communities living around the proposed site.

Letters stating the objectives of the project and requesting local participation
and consultation in the process were also distributed.

Responses from the consultations and interviews provided the relevant


background information and helped identify major environmental concerns of
the communities around the airport for preparation of this environmental
impact statement.
Key Presentations, Questions and Concerns from the Community
Consultative Meetings
During public consultative meetings with the local communities, the
environmental team gave presentations on the project and also received the
questions/concerns from the community on issues that should be considered
and investigated in the detailed EIA. The key questions/ concerns are
contained in the Scoping Report (October 2012) reviewed, commented and
approved by the Environmental Council of Zambia.

These discussions were centered on:

The airport runway and its surroundings (land-use, natural resources,


water, etc.)
The most important features (market places, gathering sites, schools,
clinics, quarries, borrow pits, access and feeder roads, etc.)
Sensitive areas (protected areas, graveyards, historical sites, etc.)
Where should construction materials be taken from/or not taken from?
Employment opportunities
- 14 -

Benefits (increased trade and transport) and inconveniences (illegal trade,


increased traffic)
Positive or negative experiences with other contractors
Community Concerns
The key community concerns from the public consultative meetings are
summarised below and proposed mitigation measures are elaborated in the
chapters on mitigation measures and environmental management plan.

- 15 -

Table 7: Community Concerns


CONCERNS
Community Concerns

Project site & its surroundings

Concern as to whether the much-talked about shopping will not be just like other malls that have failed to be
complited.

Concern as to what will happen to settlements near the project area in terms of dust pollution.
Concern as to what will the developer do to the fencing during the construction phase .
Concern of illegal sand and stone mining activities.
Quarries & borrow pits

Abandoned borrow pits pose hazards to the nearby community and animals .
Lack of consultation between contractor and local community on the sites for excavation of laterite

Siting of construction camps

Lack of consultation between contractor and local community on the sites for camp sites

Abstraction of water from local

Concern that over exploitation of local water sources for construction works might lead to water shortage to the

sources.

local community.
Investigate the role of the Labour Department in the recruitment of local people.

Employment opportunities

Concern that employment opportunity for local people should not be restricted to unskilled labour but also skilled
labour.
Local government under the community development should be involved in the HIV/AIDS programmes

HIV/AIDS, other diseases and

- 16 -

pregnancies.

Sensitive Areas

Concern that Culture site if fund should be reported to the NHCC


Investigate the flooding at the site area, which occur during heavy rainfall.

Drainage design/Culverts

- 17 -

Table of Community Concerns (Cont'd)

Community Concerns

Project benefits to the local

Concern that the project benefits to the local people are not known.

community.
Concern that the roles of the District Council & the community at project implementation level are not known.
District/Community role in the

Concern that the duration and cost of investment are not known project and the cost of rehabilitation are not known.

project

- 18 -

POTENTIAL ENVIRONMENTAL IMPACTS


Construction of the shopping mall will adversely affect the environment and
the communities in the immediate surroundings of the construction site. Many
of these impacts will arise not only at the construction site but also at quarries,
borrow pits and materials storage areas serving the project. In addition,
adverse environmental and socio-cultural impacts will occur during
construction as a result of air and soil pollution from machinery, dust, noise
from construction equipment and blasting; fuel and oil spills, trash and
garbage; and the presence of non-resident labour forces.
Impacts on Land and Soil

1.1.36. Construction Phase


In this phase dust raised from gravel access roads by haulage trucks while
transporting laterite, stone aggregate, cement, lime, petroleum products and
other chemicals may change the soil structure. This impact is considered
insignificant.

Soil contamination will be caused by leakages from the machines operations,


poor handling of petroleum products such as oil and fuel spillage during
dispensing as well as improper disposal of used oils, hydraulic fluids, toxic
and empty oil containers.

Within the construction phase some activities involving site installation, stock
piles preparation, quarrying, construction of detours, access roads, plant park
sites and drainage excavation will cause soil destabilisation. Soil compaction
by plant machinery and vehicles movement will lead to reduced groundwater
yields.

1.1.37. Operational Phase

Abandoned excess laterite and stone aggregate littered around stock pile areas
after construction is completed change the soil structure in the surrounding
- 19 -

areas. Similarly devegetated areas resulting from post excavation and grading
works including drainage channels enhance soil erosion on discharge areas.
Impacts on Vegetation

1.1.38. Construction Phase


The vegetation to be affected most is that which is confined to the shopping
mall reserve and where gravel pits will be established. Plant most likely to be
affected are those found in the five vegetation types outlined in Section 5.1
above.

The ecological value of the inundated forests and woodlands to the riverine
ecosystem cannot be ignored in that such vegetation stands contain several
niches for diversity of animal species. Should the design of the shopping mall
confine the extent of land clearing to the limits of the shopping mall reserve,
then this will not affect vegetation in the outlying areas. However, trees within
the shopping reserve should be preserved for ecological and aesthetic reasons

Dust raised from gravel access roads by haulage trucks during the
transportation of laterite, stone aggregate, cement, lime, petroleum products
and other chemicals including emissions from plant machinery and vehicles
hamper normal growth of vegetation. Similarly Poor disposal of toxic waste
and petroleum products hampers normal growth of vegetation.

Loss of vegetation in this phase is caused by activities related to clearing of


sites for installation of works, clearing of the quarry site, preparation of stock
pile area, construction of detours, access roads and park sites and the demand
for fuelwood by labour force.

1.1.39. Operational Phase


Laterite dust and littered stone aggregate from the excess construction material
left after shopping mall construction works will hinder normal vegetation
growth around the stockpile areas.

- 20 -

Impacts on Wildlife and Wildlife Habitats

1.1.40. Construction Phase


The impacts on wildlife around the project area are considered not significant
since the shopping mall is in the middle of the commercial business area.

1.1.41. Operational Phase


Impacts on wildlife are not considered significant, as the shopping mall
runway is located in the commercial business centre. This will not have any
disruption of animal movements during the operation of the mall.
Impacts on Water Quality

1.1.42. Construction Phase


During construction phase, the bridges, side drains, mitre drains and culverts
will require cleaning, de-silting, reshaping and repair. Some of the drains and
culverts might be prone to soil erosion, which will result in siltation of nearby
watercourses. Also impacts on water quality may be caused by contaminated
run-off of petroleum product spillages, leakages from storage areas and heavy
vehicles, improper disposal of used oils and from hydraulic fluids which enters
the nearby surface water sources. Similarly, easily eroded destabilised soils
may be washed into surface water sources and cause siltation and
sedimentation which will reduce the water quality and impact on aquatic life.
Activities that will give rise to this impact include construction of detours,
access roads, drainage channels, excavation and grading works.

At the project site, the Contractor will set up temporary camp for its labour
force and will require sanitation facilities such as pit latrines. Construction of
sub-standard pit latrines for campsite labour force may contaminate
groundwater due to seepage to the groundwater.

1.1.43. Operational Phase


Excess construction material left after construction works may be washed into
the water sources and lead to sedimentation of water sources and lowering of
the water quality. Erosion of bare areas resulting from excavation and grading
- 21 -

works and construction of drainage channels may increase runoff which will
lead to sedimentation and increased turbidity in surface water as well as
reduced groundwater infiltration.

Further hazardous materials spilled from haulage vehicles and washed into
water sources will result in water pollution.
Impacts on Air Quality

1.1.44. Construction Phase


During construction phase large amounts of soil will be excavated and
transported. The machinery used for excavation will generate dust, which can
be dispersed by the wind affecting a zone of up to 100m around the
excavation.

Emissions to the air in form of exhaust fumes and dust from vehicles and
machines may cause nuisance to the closest surroundings. Dust raised from
gravel access roads by haulage trucks during transportation of materials will
also pollute the air of the immediate local environment.

1.1.45. Operational Phase


Impact on air quality in the operational phase is likely to come from increased
vehicles and vehicular traffic flows which proportionately discharge emissions
to the air. Also loose soils on cleared areas may be blown off during strong
winds and raise dust particulate matter, which may affect the quality of the air.
Impacts of Noise

1.1.46. Construction Phase


During construction phase heavy machinery will be used for the excavation of
soil. The machines are noisy and will cause a certain degree of nuisance to the
surrounding environment.

The noise levels of machines and vehicles vary widely and depend on the type
of noise generated and level of activity. A front end loader has for instance a
- 22 -

power level of 100dB(A) while a truck will have a power level of 85 dB(A). In
the worst case a combined power level of 115 dB(A) will be in place during
construction which will result in the 50 dB(A) contour being located at a
maximum 250m from the construction site. However since the equipment will
never work at exactly the same location the 50 dB(A) contour will be confined
to the construction site and within the airport reserve area.

Some common impacts of noise nuisance include annoyance, sleep


disturbance and interference with communication. Acceptable levels of noise
are regarded to be 40 dB(A) during the night and 50 dB(A) during the day.
Since construction will take place during the day only the 50 dB(A) level is of
importance.

1.1.47. Operational Phase


During operational phase the source of noise is expected to come from
increased a vehicular traffic. The current noise level at the proposed site is
42.6 dB. The normal acceptable noise level for such activities is 65dB or
CNEL (Community Noise Equivalent Level)
Impacts on Landscape and Aesthetics

1.1.48. Construction Phase


Generation of dust during quarrying, equipment movement including land
clearing for stockpiles as well as reshaping during the shopping mall
construction distorts the natural landscape and may degrade areas of scenic
beauty. Further extensive excavations and dumping of stripped top soils in
scenic area spoils the beauty of the areas.

1.1.49. Operational Phase


Abandoned structures, which are left near areas of scenic beauty after
construction works, excess construction materials of laterite, stone aggregate
and concrete slabs left in areas of scenic beauty reduces the quality scenery.

- 23 -

Impacts on Land-use and Surrounding Environment

1.1.50. Construction Phase


The land-use around the project site is characterised by residential and lodge
activity and commercial business areas. Since there are plans to develop the
shopping mall, major impacts are anticipated to the surrounding environment.
The major source of impact expected is generation of dust by construction
vehicles. However, this activity will be confined to the mall reserve areas and
therefore the impact can be minimised through a programme, which ensures
dust control such as regular watering down the dust areas.

1.1.51. Operational Phase


Increased vehicular traffic will entail a proportionate increase in exhaust
fumes and will have an impact to the immediate surrounding environment.
Impacts on Socio-economic Environment

1.1.52. Construction Phase


During this phase skilled and unskilled labour will be required. Project areas
are characterised by high level of unemployment and low level of skills and
employment opportunities will therefore increase the positive benefits for the
local people who are in dire need of income for sustenance. Furthermore,
indirect opportunities for employment will arise from the provision of services
to the construction teams, such as sale of food and beverages. In this sense the
construction of the shopping mall may have a positive impact on the
employment situation in the nearby communities. This impact is considered to
be positive.

1.1.53. Operational Phase


Socio-economic benefits provided by the construction of the shopping mall
will include all-weather services and goods provision and reliability, reduced
transportation costs, increased access to Banks, food, groceries farm products,
better access to health care and other social services.

- 24 -

Impacts on Cultural and Historic Sites

1.1.54. Construction Phase


Within the project area we do not have any cultural and historic sites.But if
fund during the construction works they will be protected under the National
Heritage Conservation Commission Act. The impacts likely to affect the sites
are disturbance due to increased tourist visitations and dust generation from
vehicles during construction. The dust can settle on the site and can disfigure
its outlook. Other activities that may also lead to this impact include location
of stockpile. In addition construction of detours, access roads and campsites
can destroy the site and may lead to loss of cultural heritage.

1.1.55. Operational Phase


No additional negative impacts on cultural values are foreseen during
operational phase.
Impacts on Human Settlements

1.1.56. Construction Phase


There will be no possibilities of demolition; relocation of any settlement
.Moreover construction work will be confined to the shopping mall reserve
area. The potential impact is considered insignificant.

1.1.57. Operational Phase


No direct correlation was determined between migration and construction of
the shopping mall especially that the mall is located on the vergin land with no
settlement. No additional negative impacts on human settlements are foreseen
during the operational phase.
Impacts of Quarries and Borrow Pits

1.1.58. Construction Phase


During construction phase, a number of quarries and borrow pits will be
opened up. Potential impacts include vegetation clearance and landscape scars
resulting from the absence of re-vegetation programmes and poor excavation
- 25 -

techniques. Extraction of construction materials from quarries and borrow pits


could generate excessive noise caused by blasting, movement of machinery
and labourers and thus impact on the nearby communities. Also increased air
pollution due to diesel fumes and dust generation resulting from the presence
of construction machinery and site clearing activities.

Quarries and borrow pits impact on the visual and aesthetic view. The
excavated areas become prone to soil erosion during rain season and can
contaminate nearby surface water.

1.1.59. Operational Phase


Quarries and borrow pits left abandoned after construction works could be a
potential hazard to ecology and nearby communities and animal population.
Transmission of diseases, such as malaria and their vector can occur in
stagnant water collected in abandoned borrow pits. Malaria that is transmitted
by the anopheles mosquito and diarrhoea are both water-related diseases. Thus
the potential impact from poor extraction techniques and lack of re-vegetation
programmes is considered significant. Further if the quarries and borrow pits
are sited nearby communities the pits could become habitats for dangerous
creatures such as snakes, which can easily attack unsuspecting children
playing in these abandoned quarries and borrow pits.
Impacts of Road Traffic

1.1.60. Construction Phase


Construction traffic could negatively impact on undisturbed areas of the
project. The construction process could impede movement of people on the
usual route to livelihood activities.

1.1.61. Operational Phase


The vehicular traffic intensity to the mall is likely to increase once the
construction of a shopping mall is complete and the mall becomes operational.
The additional vehicular flow may cause an increased number of accidents on
the road. This additional flow could be because of people going for shopping
- 26 -

or traffic connecting to neighboring communities beyond the shopping mall.


This increase in traffic may cause an increase in the number of accidents. The
types of accidents include those involving vehicles, bicycles and pedestrians.

However, improved sight lines and replacement of road furniture will reduce
some accidents. Overall, the potential impact of an increase in accidents is
considered significant and negative.
Impacts of Work Accidents

1.1.62. Construction Phase


During the construction phase heavy machinery will be employed. Heavy
machines make a lot of noise, cause carbon dioxide emissions and generate
dust and may cause accidents among operators if not handled properly. This is
likely to have negative impact on health of the workers. To limit the risk of
accidents, safety procedures will be put in place and enforced by the foreman
to ensure that vehicles and machinery only drive in designated places by
authorised personnel.

1.1.63. Operational Phase


As the runway rehabilitation project would have completed there will be no
workers on site and there will be no more impact from this phase.
Impacts of Construction Camps

1.1.64. Construction Phase


Construction of camps will require clearance of vegetation and this will result
in loss of vegetation along the route. In addition waste will be produced at the
camps including sewage and petroleum product waste. The potential impacts
are significant and negative.

During construction phase, the construction teams will interact with the nearby
communities and can cause social upheaval and transmit diseases (STDs,
HIV/AIDS) to the communities living along the route. However since the road
has been in existence for a number of years, it is likely that the community has
- 27 -

been exposed to a social change. The impact is therefore considered moderate


and negative.

1.1.65. Operational Phase


At the end of the rehabilitation project, construction camps will either be
demolished or handed over to the nearby communities and therefore the
potential impact in this phase is considered insignificant.

- 28 -

EVALUATION OF ENVIRONMENTAL IMPACTS


A project such as construction of the shopping mall is likely to affect the
environment and community. The objective of this section is to predict and to
assess these potential impacts of the proposed project to international standard
and to recommend mitigating measures to be incorporated into the project
design.

The assessment of the issues has been conducted according to a synthesis of


criteria required by the integrated environmental management procedure
defined as follows:
Nature of Impact
This is an appraisal of the type of effect the proposed activity would have on
the affected environmental component. Its description should include what is
being affected and in what way.
Direct Impact
An impact that appears immediately as a result of an activity of the project.
For example, the loss of forest habitat is a direct impact of logging.
Indirect Impact
An impact that is related to the project but that arises from an activity of the
project at a secondary level. For example, building a new runway may cause
indirect impacts on the local economy of a village by increasing accessibility
to other markets.
Spatial Extent
The physical and spatial size of the impact. It is a description of whether the
impact would occur on a scale described as follows:

Site, the impact could affect the whole or measurable portion of the site.
Whether it is limited to the immediate area of the proposed project;

- 29 -

Local, the impact could affect the extended area adjacent to the site
perhaps a neighborhood or small town. Whether it would affect environs
up to 15km outside the immediate environment;

Regional, that impact could affect the area including the outlying areas of
the city, the transport routes and the adjoining towns.

National, the impact could be as far reaching international boundaries.


Duration
The lifetime of the impact; this is measured in the context of the life-time of
the proposed development.

Short term, the impact will either disappear with mitigation or will be
mitigated through natural process in a span shorter than the construction
phase.

Medium term, the impact will last for the period of the construction
phase, thereafter it will be entirely negated.

Long term, the impact will continue or last for the entire operational life
of the development, but will be mitigated by direct human action or by
natural processes thereafter.

Permanent, the only class of impact which will be non-transitory.


Mitigation either by man or natural process will not occur in such a way or
in such a time span that the impact can be considered transient.
Intensity
A description of whether or not the intensity (magnitude) of the impact would
be high, medium, low or negligible (no impact). An attempt will be made to
quantify the impacts on components of the affected environment will be
described as follows: Is the impact destructive, or benign? Does it destroy the

- 30 -

impacted environment, alter its functioning, or slightly alter it? These are rated
as follows:

Low, where the impact will not have significant influence on the
environment, and this will not be required to be significantly
accommodated in the project design or implementation; the impact alters
the affected environment in such a way that natural processes of functions
are not affected in any significant way.

Moderate, where it could have an adverse influence on the environment


which would require modification of the project design or alternative
implementation schedules; The affected environment is altered, however,
function and process continue, albeit in a modified way.

High, where it could have significant influence on the environment but


cannot be mitigated or be accommodated by the project environment by
introducing alternative mitigation measures such as realignment at a
particular stretch or adoption of different design measures. Function or
process of the environment is disturbed to the extent where it temporarily
or permanently ceases.

This will be a relative evaluation within the context of all the activities and
the other impacts within the framework of the project. Note that some
impacts have a high intensity and a short duration with no permanent audio
effects.
Probability
This describes the likelihood of the impacts actually occurring. The impact
may occur for any length of time during the life cycle of the activity, and not
at any given time. The classes are rated as follows:

Unlikely, the probability of the impact occurring is very low, due to either
the circumstances, design or experience.
- 31 -

Possible, the impact could possibly happen, and mitigation planning


should be undertaken.

Probable, it is most likely that the impact will occur at some or other stage
of the development. Plans must be drawn up before the undertaking of the
activity.

Definite, the impact will take place regardless of any prevention plans, and
only mitigatory actions or contingency plans can be relied on to contain
the effect.
Determination of Significance
Significance is determined through a synthesis of impact characteristics or
combination of effects. Significance is an indication of the importance of the
impact in terms of physical extent, intensity and time scale, and therefore
indicates the level of mitigation required.

The classes are rated as follows:

Negligible, the impact is not substantial and does not require any
mitigatory action.

Low, the impact is of little importance, but may require limited mitigation.

Moderate, the impact is of importance and therefore considered to have


mitigation. Mitigation is required to reduce the negative impacts to
acceptable levels or positive impacts maximised.

High, the impact is of great importance. Failure to mitigate, with the


objective of reducing the impact to acceptable levels, could render the
entire development option or entire project proposal unacceptable.
Mitigation is therefore essential. Positive impacts should be enhanced as a
priority.
- 32 -

From the baseline information assembled in the previous chapter coupled with
the information gained during the consultation stage, the expected
environmental impacts can be categorised into positive and negative impacts.

In addition, it is important to consider the duration of the impact and at what


phase of the project it occurs, i.e. impacts during the rehabilitation phase or
impacts over the life of the runway (operational phase) and whether the
impacts are direct (i.e. removal of vegetation) or indirect (increased
deforestation as a result of the improved runway).

The direct impacts would be experienced mainly during the rehabilitation


process, and include effects on the physical environment, health and safety of
the residents along the runway and the construction workers during the
rehabilitation phase.

The indirect impacts are primarily socio-economic and extend beyond the
project implementation. The indirect impacts include changes in economic
activities and long-term changes, such as increased land degradation due to
increased settlement and development near the runway.

Unlike the direct impacts, which occur in the immediate environment, the
indirect impacts would be felt in the adjacent regions.

- 33 -

Table 8: Table of Evaluated Impacts:


Phase

Impact

Type of

Spatial

Impact

Extent

Duration

Intensity

Probability

Determination
of Significance

Impacts on Soil
Design

None

n/a

n/a

n/a

n/a

n/a

n/a

Change in soil texture due to accumulation of

Direct

Site

Medium

Low

Unlikely

Negligible

foreign dust particles falling from haulage trucks.

term

Soil contamination due to improper storage of

Medium

materials, fuels and poor waste oil disposal


Construction

Direct

Site

term

Moderate

Probable

Moderate

Direct

Site

Medium

Moderate

Probable

Moderate

Moderate

Probable

Moderate

Moderate

Probable

Moderate

methods.
Exposed soil is prone to erosion by water or wind.

term
Stripping and stockpiling of topsoil could lead to

Direct

Site

erosion and degradation of soil quality.


Soil

compaction

could

result

term
following

Direct

Site

construction activities.
Soil erosion near runway culverts and drainage
Operational

Medium

Medium
term

Indirect

Local

Long term

Moderate

Possible

Moderate

Indirect

Local

Long term

Moderate

Possible

Moderate

channels where water velocity could increase.


Soil contamination by waste and spillages of
aircraft.

Impacts on Vegetation

- 34 -

Design
Construction

None
Retardation

n/a
of

vegetation

growth

due

n/a

to

contamination from dust particles and gas

n/a

n/a

n/a

n/a

Low

Unlikely

Moderate

Moderate

Probable

High

Medium
Direct

Local

term

emissions.
Loss of vegetation due to site clearing which will
lead to loss of habitat and displacement of fauna

Medium
Direct

Local

species, especially avifauna.

- 35 -

term

Table of Evaluated Impacts:


Phase

Impact

Type of

Spatial

Impact

Extent

Duration

Intensity

Probability

Determination
of Significance

Impacts on Vegetation (Cont'd)


Operational

Increased access as a result of the development of

Indirect

Site

Long term

None

n/a

n/a

n/a

n/a

n/a

n/a

Disturbance to birds and animals and loss of

Direct

Site

Long term

Moderate

Possible

Moderate

Indirect

Site

Long term

Moderate

Possible

Moderate

Direct

Local

Long term

Moderate

Possible

Moderate

Indirect

Site

Long term

Moderate

Possible

Moderate

None

n/a

n/a

n/a

n/a

n/a

n/a

Siltation of water courses due to soil erosion of

Indirect

Local

Long term

Moderate

Probable

Moderate

the mall

Low

Possible

Moderate

could lead to increased deforestation

around the mall.


Impacts on Wildlife and Wildlife Habitat
Design
Construction

habitat.
Operational

Wildlife loss due to accidental killings caused by


increased traffic to the shopping mall.
Disruption to wildlife routes due to quarries and
borrow pits left in wildlife areas without
rehabilitation.
Noise disturbance to wildlife due to increased
vehicular traffic.

Impacts on Water Quality


Design
Construction

nearby drains and culverts.

- 36 -

Ground water contamination due to construction

Indirect

Site

Long term

Moderate

Probable

Moderate

Indirect

Local

Long term

Moderate

Possible

Moderate

of sub-standard campsite pit latrines for workers.


Operational

Sedimentation and increased turbidity in surface


water caused by erosion of bare areas and runoffs
resulting from excavation and grading works and
drainage channels left after construction works.

- 37 -

Table of Evaluated Impacts:


Phase

Impact

Type of

Spatial

Impact

Extent

Duration

Intensity

Probability

Determination
of Significance

Impacts on Air Quality


Design

None

n/a

n/a

n/a

n/a

n/a

n/a

Direct

Local

Short term

Moderate

Probable

Moderate

Direct

Site

Short term

Moderate

Probable

Moderate

Indirect

Site

Long term

Moderate

Possible

Moderate

None

n/a

n/a

n/a

n/a

n/a

n/a

Noise and vibration caused by construction

Direct

Site

Short term

Moderate

Probable

Moderate

Indirect

Site

Long term

Low

Possible

Low

n/a

n/a

n/a

n/a

n/a

n/a

Air pollution caused by diesel fumes and dust


from excavators, bull dozers, graders and as well
Construction

as site clearing will affect human, vegetation and


also disturb habitats for birds, animals and insects.
Unpleasant odours due to un-maintained toilets
and poor waste management.

Operational

Excessive diesel fumes due to un-maintained


equipment fuel stockpiles.

Impacts on Noise
Design
Construction

machinery, equipment and drilling.


Operational

Noise from increased vehicular traffic.

Impacts on Landscape and Aesthetics


Visual impact of the shopping mall could be
Design

substantial if designs do not consider the slope of


the surrounding environment.

- 38 -

Construction

Disfigurement of the natural landscape and

Direct

Local

Moderate

Moderate

Definite

Moderate

Direct

Site

Moderate

Low

Probable

Moderate

aesthetic view due to reconstruction works.


Abandoned
Operational

construction

structures,

excess

construction materials of laterite, stone aggregate


and concrete slabs left in areas of scenic beauty
reduces the quality of scenery.

- 39 -

Table of Evaluated Impacts:


Phase

Impact

Type of

Spatial

Impact

Extent

Duration

Intensity

Probability

Determination
of Significance

Impacts on Land-use and surrounding environment


Design

The proposed shopping mall construction might


influence migration and settlement patterns if

n/a

n/a

n/a

n/a

n/a

n/a

Direct

Local

Short term

Moderate

Possible

Moderate

Indirect

Local

Short term

Moderate

Probable

Moderate

Indirect

Site

Long term

Low

Possible

Low

n/a

n/a

n/a

n/a

n/a

n/a

Indirect

Local

Short term

Moderate

Probable

Moderate

labour requirements are not planned in advance.


Construction of temporary structures will disturb
the environment within the immediate and
Construction

surrounding environment.
If labour is not recruited from local areas people
who reside far may start to settle near the project
site.

Operational

Exhaust fumes to the surrounding environment


due to increased traffic.

Impacts on Socio-economic Environment


Design
Temporary marriages, casual sex relationships and
Construction

more

chances

of

transmission

of

sexually

transmitted diseases due to interaction of project


workers with local communities.

- 40 -

Operational

Increased accidents due to increased traffic to and

Indirect

Site

Long term

Moderate

Possible

Moderate

n/a

n/a

n/a

n/a

n/a

n/a

Indirect

Site

Short term

Moderate

Probable

Moderate

Direct

Site

Long term

Moderate

Probable

Moderate

Direct

Site

Long term

Moderate

Probable

Moderate

from the shopping mall


Impacts on Cultural and Historic Sites
Design

Poorly developed airport site design could impact


negatively on heritage sites.
Dust may disfigure the appearance of the site

Construction

Construction of detour next to the site may lead to


loss of heritage site. The area has no cultural and
historic sites

Operational

Increased tourist visit may disturb the site

- 41 -

Table of Evaluated Impacts:


Phase

Impact

Type of

Spatial

Impact

Extent

Duration

Intensity

Probability

Determination
of Significance

Impacts on Human Settlements


Design
Construction

None

n/a

n/a

n/a

n/a

n/a

n/a

Direct

Site

Long term

Moderate

Probable

Moderate

n/a

n/a

n/a

n/a

n/a

n/a

Direct

Site

Medium

Moderate

Probable

Moderate

Moderate

Definite

Moderate

Negative impacts on human settlements are not


foreseen since construction works will not affect
any in the area.

Operational

None

Impacts of Quarries and Borrow Pits


Design

Quarries and borrow pit location may negatively


impact on important ecological units.

Construction

Excessive noise from blasting, machinery may

term
Direct

Local

disturb nearby communities.


Operational

Un-rehabilitated borrow pits could pose potential

Medium
term

Indirect

Local

Long term

Moderate

Possible

Moderate

Direct

Local

Short term

Low

Possible

Moderate

hazard to ecological units animal movements and


residents.
Impacts of Road Traffic
Failure to use established routes might result in
Design

surveyors' vehicles negatively impacting on the


environment.

- 42 -

Construction traffic could impact on undisturbed


Construction

Indirect

Local

areas adjacent to the proposed site.


Excessive dust from construction works could

Medium

Moderate

Probable

Moderate

term
Direct

Site

Short term

Low

Probable

Moderate

Indirect

Site

Long term

Moderate

Possible

Low

n/a

n/a

n/a

n/a

n/a

n/a

Direct

Site

Medium

High

Low

Moderate

n/a

n/a

n/a

n/a

n/a

n/a

disturb nearby communities.


Operational

Increased accidents due to increased traffic flow.

Impacts of Work Accidents


Design

Advanced planning of safety equipment may


prevent accidents

Construction

Lack of safety and health regulations could impact


negatively on construction workers.

Operational

None

- 43 -

Table of Evaluated Impacts:


Phase

Impact

Type of

Spatial

Impact

Extent

Duration

Intensity

Probability

Determination
of Significance

Impacts of Construction Camps


Design

Construction

Advanced planning of construction camp siting.

n/a

n/a

n/a

n/a

n/a

n/a

Loss of vegetation at construction site.

Direct

Site

Short term

Moderate

Probable

Low

Improper disposal of waste.

Indirect

Site

Short term

Low

Probable

Moderate

Indirect

Site

Short term

Moderate

Probable

Moderate

n/a

n/a

n/a

n/a

n/a

n/a

Interaction of construction workers with the


nearby communities may lead to transmission of
sexually transmitted diseases.

Operational

None

- 44 -

MITIGATION MEASURES
This section proposes mitigation measures for identified potential impacts as
discussed in earlier chapters. Mitigation measures are actions that are intended
to avoid, alleviate or reduce environmental impacts on the environment.
Mitigation measures form a basis on which an Environmental Management
Plan has been formulated. The mitigation measures are set forth to maximize
positive impacts and minimize negative impacts as a result of the proposed
development.

Table 9: Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts on Land and Soil


Petroleum
Soil contamination due to
improper

storage

of

materials, fuels and poor


waste

oil

disposal

methods.

products

dispensing

points shall have drip pans;


Storage of potential pollutants such
as fuel, oil and chemicals should be
done on sealed surfaces to prevent
soil contamination;
Collection and recycling of used oil
& lubricants;
Petroleum storage tanks shall have
bund walls around and shall be
high

enough

to

contain

any

spillage.
Construction

Limitation of earth moving to dry

Phase

periods;
Protection

of

susceptible

soil

Exposed soil is prone to

surface with mulch;

erosion by water or wind.

Protection of drainage channels by


stone pitching;
Installation of sedimentation basins
or planting of erodible surfaces as
soon as possible.

Stripping and stockpiling

Exposed soil should be avoided by

of topsoil could lead to

selective soil stripping;

- 45 -

erosion and degradation of

Areas requiring less clearing shall

soil quality.

be

preferred

for

stock

piles.

Clearing shall be limited to the site


approved by the local authorities.
Soil

compaction

result

could

following

the

construction activities.

Only

heavy

equipment

with

pneumatic tyres shall be used on


site.
Soil erosion should be prevented

Operational
Phase

Soil erosion near culverts

especially

and

construction of correctly designed

drainage

channels

near

culverts

by

where water velocity could

culverts;

increase.

Regular maintenance of culverts &


drainage channels;
ZEMA
disposal;

- 46 -

Regulation

of

waste

Table of Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts on Soil (Cont'd)

Operational Phase

Soil contamination by waste

Law enforcement to ensure that

and spillages of mall users and

only road worthy cars that are

un-maintained vehicles.

maintained are allowed on site.

Retardation

Dust control by application of

Impacts on Vegetation

Construction Phase

of

vegetation

growth due to contamination

water;

from dust particles and gas

Haulage

emissions.

exceed the speed limit of 60km

trucks

shall

not

per hour.

Operational Phase

Loss of vegetation due to site

Less vegetated areas shall be

clearing which will lead to loss

preferred;

of habitat and displacement of

Careful site planning;

fauna

Implementation of the EIA-

species,

especially

avifauna.

EMP mitigation measures.

Increased access as a result of

Provision

the shopping mall could lead to

conservation

increased deforestation near

programme

the site.

along and near the shopping

of

forest

awareness
to

communities

mall
Impacts on Wildlife and Wildlife Habitat

Construction Phase

Disturbance to birds and small

Construction

animals and loss of habitat.

confined to the shopping mall

should

be

reserve area;
Noisy

activities

scheduled

to

occur

prescribed

normal

to

be
within

working

hours.
Aadequate signs for warning
Operational Phase

Wildlife loss due to accidental

users of wildlife presence will

killings caused by vehicular

be provided;

traffic as a result of the

Install

construction of the mall.

detacters along the shopping

bird

mall parameter

- 47 -

and

animal

Noise disturbance to wildlife

Control of noisy activities on

due to increased aircraft and

site (local by-laws);

vehicular traffic.

ZEMA Regulation of Noise;

Impacts on Water Quality


Sides of the drainage shall be
planted with grass or stone
Construction Phase

Siltation of water courses due

pitched;

to soil erosion of nearby drains

Drainage systems shall have

and culverts.

scour checks;
Drainage

systems

discharge

into

shall

settlement

basins;
Silt traps shall be put along
drainage systems;

- 48 -

Table of Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts on Water Quality (Cont'd)

Construction Phase
(Cont'd)

Water shortage to the local

Exploitation of water sources

community

over

for rehabilitation works shall

exploitation for construction of

be done with approval by the

the mall.

local

due

to

authority

consent

from

and

with

the

local

community.
Ground water contamination

Proper siting of pit latrines

due to construction of sub-

away from water logged areas;

standard campsite pit latrines

Good hygienic standards and

for workers.

proper

maintenance

of

pit

latrines.

Operational Phase

Sedimentation and increased

Excavated soils shall be used

turbidity

for

in

surface

water

other

works

such

as

caused by erosion of bare areas

shoulder building;

and runoffs resulting from

Sides of drainage channels

excavation and grading works

shall be planted with grass or

and drainage channels left after

stone pitched;

construction works.

Drainage systems shall have


scour checks.

Impacts on Air Quality


Air

Construction Phase

pollution

caused

by

Regular

maintenance

of

exhaust fumes and dust from

construction

excavators, bull dozers, graders

equipment in order to reduce

as well as site clearing will

emission of exhaust fumes;

affect human, vegetation and

Periodically water down on the

also

site;

disturb

habitats

for

vehicles

and

animals, birds and insects.


Unpleasant odours due to un-

Cleaning

maintained toilets and poor

maintenance of toilets to avoid

waste management.

unpleasant odours.

and

Waste should be

regular

carefully

managed to prevent unpleasant


odours.

- 49 -

Operational Phase

Excessive diesel fumes due to

Law enforcement to ensure that

un-maintained equipment.

only road worth cars that are


maintained are on the road.

Impacts on Noise

Construction Phase

Noise and vibration caused by

Working hours limited to day

construction

light only;

machinery,

equipment and drilling.

Enforcement of the Factories


Act

by

the

Factories

Inspectorate under the Ministry


of Labour.
ZEMA Regulation on noise;
Operational Phase

Noise from increased vehicular

Operating

traffic movement.

restricted within the reasonable

hours

will

be

time and not beyond 22.hours

- 50 -

Table of Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts on Landscape and Aesthetics

Design Phase

Visual impact of the mall

Development

rehabilitation works could be

designs must be compatible

substantial if designs are not

with the slope angles of the

compatible

with

surrounding environment.

angles

the

of

the

slope

of

the

mall

surrounding

environment.

Construction Phase

Disfigurement of the natural

Development designs which

landscape and aesthetic view

are compatible with the final

due to construction works.

slope angles of the surrounding


environment.

Abandoned
Operational Phase

construction

Abandoned structure in areas

structures, excess construction

of scenic beauty shall be

materials

demolished

of

laterite,

stone

aggregate and concrete slabs


left in areas of scenic beauty
reduces the quality of scenery.
Impacts on Land-use and Surrounding Environment
Local
Design Phase

people

with

the

The proposed shopping mall

necessary

skills

might influence migration and

employed

for

settlement patterns if labour

works;

requirements are not planned in

Resettlement of communities

advance.

in new areas shall be done in


consultation

shall
the

with

be

runway

host

or

existing community.
Construction
detours

of

will

environment
Construction Phase

immediate

temporary

disturb

access

roads

and

the

equipment park site location

the

shall be done in consultation

surrounding

with local authorities, local

within
and

Detours,

environment.

people and take into account


the existing land use in the
area.

- 51 -

Local

people

with

the

If labour is not recruited from

necessary

local areas people who reside

employed in the project;

far may start to settle near the

Resettlement of communities

project. area

in new areas shall be done in

skills

consultation

shall

with

be

host

or

on

air

existing community.
ZEMA
Operational Phase

Exhaust

fumes

to

the

Regulation

pollution;

surrounding environment due

Adherence

to increased traffic.

maintenance
standards

to

engine

schedules

and

reduce

air

to

pollution.
Impacts on Socio-economic Environment

Construction Phase

Temporary marriages, casual

There shall be provision of

sex relationships and more

education both to the local

chances of transmission of

community

sexually transmitted diseases

HIV/AIDS using aids such as

due to interaction of project

video shows, pamphlets, talks,

workers

etc.

with

local

communities.

- 52 -

on

STDs

and

Table of Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts on Socio-economic Environment (Cont'd)

Operational Phase

Increased accidents due to

Provision of adequate warning

increased vehicular traffic to

signs in black spot areas and

the project area

speed retarders
Ndola Council to push for
improvement of major roads to
the project area.

Impacts on Cultural and Historic Sites


Detours,

access

roads

and

equipment park sites shall not


Mitigation Measures
for impacts at the
Design Phase

Poorly
mall

developed
design

could

shopping

be constructed near cultural

impact

sites. The provisions of the

negatively on heritage sites.

National

Heritage

Conservation

Commission

shall apply.
Detours,

access

roads

and

equipment park sites shall not


Dust
Construction Phase

may

disfigure

the

be constructed near cultural

appearance of the Cultural and

sites sites. The provisions of

Historic site

the

National

Conservation

Heritage
Commission

shall apply.
Detours,

access

roads

and

Construction of detour next to

equipment park sites shall not

the site may lead to loss of

be constructed near cultural

heritage site.

sites.The provisions of the


National
Conservation

Heritage
Commission

shall apply.
Impacts on Human Settlements

Construction Phase

Although no negative impacts

Rehabilitation

on

confined to the runway reserve

human

foreseen

settlements

since

are

construction

- 53 -

area;

shall

be

works will be confined to the

Detour,

shopping

equipment park site location

however,

mall

reserve

construction

of

access

roads

and

outside shopping mall reserve

detours, access roads and park

areas

sites

and

consultation with RDA` and

commercial leads to land use

local people and take into

conflicts.

account existing land use in the

residential

areas

shall

be

done

in

area
The
Operational Phase

construction

of

the

There shall be no conversion of

shopping mall will enhances

communal land into state land

accessibility,

around the constructed mall.

mobility

and

economic activities for the


communities around the mall

- 54 -

Table of Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts on Human Settlements (Cont'd)


Construction of the shopping

There shall be no conversion of

Operational Phase

mall will lead to increased

communal land into state land

(Cont'd)

human settlements, changed

around the improved airport .

settlement patterns, increased


cultivation

and

commercial

activities around g the airport ;


Construction of the shopping

There shall be no conversion of

mall will lead to increased land

communal land into state land

values and land resource tenure

around

around the mall,

shopping mall.

Noise from increased vehicular

Trees shall be planted around

traffic

settled areas to minimize noise

volumes

improved

using

runway

communities

the

disturbs

around

the

runway.

the

constructed

and hazardous emissions.


Noise barriers shall be erected
in settled areas where traffic
noise may exceed 90 decibel.

Impacts of Quarries and Borrow Pits


Quarrying shall not be done
Design Phase

Construction Phase

Quarries

and

borrow

pit

near surface water sources.

location may negatively impact

There shall be no quarrying

on important ecological units.

near cultural sites

Excessive noise from blasting,

Quarrying shall not be done

machinery may disturb nearby

nearby communities.

communities.

Quarrying shall be done in


conformity to the Mine and
Minerals Act, No. 31 of 1995.

Operational Phase

Un-rehabilitated borrow pits

Quarrying shall not be done

could pose potential hazard to

near water sources and human

ecological units and residents.

settlements.

Impacts of DCA Traffic

- 55 -

Design Phase

Failure

to

use

established

Surveyors should not venture

routes

might

result

in

too far away from the proposed

surveyors' vehicles negatively

route in order to avoid impacts

impacting on the environment.

on

the

environment.

- 56 -

surrounding

Table of Mitigation Measures


Phase

Mitigation Measure

Impact

Impacts of Road Traffic (Cont'd)


Established routes should be
Construction
Construction Phase

traffic

could

used where possible in order to

impact on undisturbed areas

reduce

adjacent to the project area.

undisturbed areas.

impacting

Construction

on

vehicles

must

only use pre-determined access


roads

that

should

be

determined in the design phase.


Allowance should be made for
alternative routes for existing
road users during construction.
Excessive

dust

construction

could

from
disturb

Control

of

dust

through

watering of dust areas.

nearby communities.

Operational Phase

Increased accidents due to

Provision of adequate warning

increased traffic flow.

road signs in black spot areas


and speed retarders at animal
and pedestrian crossing site.

Impacts of Work Accidents

Design Phase

Advanced planning of safety

Development

requirements

procedures

of
and

safety

operational

manual.

Construction Phase

Lack of enforcement of safety

Enforcement of Public health

and health regulations could

and safety regulations.

impact

negatively

on

construction workers.
Impacts of Construction Camps
Advanced
Design Phase

planning

construction camp sitting.

of

Selection of camp siting must


be done in consultation with
Local

authority,

the

authority and local people.

- 57 -

local

Loss

of

vegetation

at

construction site.

Clearing for camp siting must


be limited to the actual site to

Construction Phase,

avoid vegetation loss on a


larger scale.
Waste generation at campsite.

Waste disposal to be done at


designated sites approved by
the local authority and ZEMA.

Interaction
workers

of
with

construction

There shall be provision of

the

education both to the local

communities

may

transmission

of

nearby
lead

to

community and camp workers

sexually

on STDs and HIV/AIDS using

transmitted diseases.

aids such as video shows,


pamphlets, talks, etc.
Local

people

necessary

skills

with
shall

employed in the project;

- 58 -

the
be

Proposed Measures to Address Concerns of the Communities around the


Project area

1.1.66. Shopping Mall Site & its Surroundings


Detours, access Roads and equipment park site location shall be done in
consultation with local authority and with local people and shall take into
account the existing land use in the areas.

1.1.67. Quarries & Borrow Pits


Quarries and borrow pits shall not be done near the communities. However,
construction waste may be reused for rehabilitation of the borrow pits.

1.1.68. Sitting of Construction Camps


Selection of camp sites shall be done in consultation with local authority and
the local community. This will help to deal with social upheavals such as
temporary marriages, casual sex relationships and more chances of
transmission of sexually transmitted diseases due interaction. There shall be
sensitization to both construction workers and the local community on STDs
and HIV/AIDS using aids such as video shows, pamphlets. Further waste
disposal from camp site shall be done at sites designated by the Local
Authority and ZEMA.

1.1.69. Abstraction of Water from Local Sources


Exploitation of water sources for rehabilitation works shall be done with
approval by the local authority and with consent from the local community.
This will avoid conflicts and also to receive support from the local community.

1.1.70. Drainage Design/Culverts


Drainage systems shall discharge into the nearby river basins where water may
collect which could then be available to other users.

1.1.71. Accidents & Black-Spots


Provision of adequate warning signs in black spot areas and speed retarders
will be used
- 59 -

1.1.72. Project Benefits to the Local Community


The Contractor shall ensure that the local people with the necessary skills are
employed in the construction and operation of the project.

1.1.73. Detour, By-pass, Lay-bys and Access Roads


Detours, access roads and equipment park site location shall be done in
consultation with RDA and local people and shall take into account the
existing land use in the areas.

1.1.74. District/Community Role in the Project


The District/local community shall participate in the project through their local
authority during the project implementation phase. The KML shall ensure that
the local authority becomes part of the project monitoring team during the
implementation of the mitigation measures by the Contractor in those areas
under the jurisdiction of the local authority. A report on the contractor's
performance prepared by the KML shall also be made available to the affected
in the respective local authorities. The major communities around project area,
which should be considered as part of the project monitoring team, are the
flats residential flats near the project.This will ensure that the community's
concerns expressed during the scoping report and stated in this report are not
overlooked.

- 60 -

ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN


Introduction
The EIA Regulations state that the developer must provide an Environmental
Management and Monitoring Plan. An EMP is a document where all the
measures that are required for environmental protection, which will include
the mitigation measures and the monitoring plan, will be found for easy
reference. The aim of an environmental management plan is to avoid,
minimise, or ameliorate effects or impacts resulting from project
implementation and where possible, enhance beneficial effects.

In reality, the environmental management plan seeks to limit the interaction of


disturbed with undisturbed lands and through the various process of shopping
mall construction, restore the disturbed land to a pre-determined form of landuse or to a productivity level similar to that occurring prior to disturbance.
Environmental Management Plan
Environmental management is carried out in all stages of the Project namely;
Pre-construction, Construction and Operational. The key stakeholders in the
environmental management activities are: KML, the contractor, Zambia
Environmental

Management

Agency,

Government

agencies,

Local

Authorities, the affected Local Communities, the shopping mall users and to
some extent the Public.

The Environmental Management Plan for the management of the identified


environmental impacts associated with this project consists of three main
components:

1. Implementing the Impact Mitigation Plan


2. Monitoring the implementation of the EMP
3. Institutional Framework for Monitoring, Reporting and Supervision of
EMP

- 61 -

1.1.75. Impact Mitigation Plan


The impact mitigation plan allocates the responsibilities for implementation
of the proposed mitigation measures to the various stakeholders and indicates
at what stage in the project they should be performed. The Plan is presented in
this chapter under Section 12.3 and it addresses the negative impacts generated
by the construction works and presents the associated cost estimates of
mitigating the adverse impacts. The key components of the proposed impact
mitigation plan are:

Land and Soil


Vegetation
Water Quality
Air Quality
Noise
Landscape and Aesthetics
Land-use and Surrounding Environment
Socio-economic issues
Cultural and Historic Sites
Human Settlements
Quarries and Borrow Pits
Work Accidents
Construction Camps
Road Traffic

Surface Water Management


Surface water is an important component of both ecological and human use of
the land. The aim of the surface water management programme is to ensure
that where practical, flows into and through the project site and the nearby
streams are maintained and that water quality to these systems is maintained.

Erosion Control and Sediment Retention


The highly flocculated nature of the soils in the project areas indicates that
they are prone to erosion in a disturbed state. According, and where
- 62 -

appropriate, all surface runoff from areas of disturbance and areas with
elevated runoff coefficient will be directed by correctly designed drainage
system, to sediment traps with sufficient volume and retention time to
maximise settlement of suspended sediment prior to release.

The drains will be designed according to the characteristics of peak flows for
the pre-determined design storm, and the requirement to discharge flows
without causing erosion.

Vegetation and Flora


A number of management initiatives will be implemented to reduce potential
impacts and disturbance to flora and vegetation. These include:

Raising awareness in the workforce about conservation issues and legal


obligations of construction workers by structuring the environmental
awareness programme to include issues relating specifically to project site.
Designing the project layout to reduce the area of clearing required.
Clearly marking and restricting access to areas of high conservation value.
Providing adequate drainage control systems around the runway and
access tracks constructed as part of the project.
Establishing an efficient dust suppression plan in all areas where the
generation of dust has been identified as an environmental management
issue.
Retaining topsoil, and vegetation wherever possible during clearing for use
during restoration.
Progressively rehabilitating disturbed areas as they become available and
are no longer required for project operations.
Fauna
Experience indicates that fauna adapt readily to the general effects of project
operations. However; it is most likely that the more mobile species will tend to
move away from the areas of greatest activity during construction but will
return during the operation of the airport runway. Potential impacts on fauna
will be reduced by:- 63 -

Restricting disturbance and clearing of habitats to the minimum required


for safe and efficient operations.
Progressively rehabilitating disturbed areas to re-establish habitats;
Declaring a 50m no-go buffer zone around the project area to prevent
disturbance.

Construction Waste
Construction waste will be generated as a result of the shopping mall
construction. All construction waste that has been generated will be recycled
or placed in designated disposal sites and covered with soil.

Noise.
Noise management will be limited to standard sound retarding devices on all
operational vehicles as recommended by the manufacturer. Noise generated
from operations at the project site is not expected to impact on local
communities due to the distances between the operations area and areas of
habitation. However, Kafubu mall limited and ZEMA will investigate any
noise complaints received.

Management of Air Quality


Throughout the construction of the shopping mall standard water trucks will
use water to suppress dust. The water trucks will continually apply water to
potential dust generation areas such as the main detours and borrow pit area.

Rehabilitation
Rehabilitation will be ongoing and progressively throughout the life of the
project. Evidence to date indicates that the re-vegetation of disturbed areas
will be both natural and rapid. As the first principle of rehabilitation is long
term stability, practices that address this issue will be implemented as part of
long-term approaches.

- 64 -

Community Consultation and Interaction


The developer will ensure that the shopping mall project will be very much a
part of the local community. The developer will establish a Community
Consultation Programme as a means of providing a forum for dialogue
between the local and the project. The framework for this plan will be set up
during the construction phase so that the aims and objectives of the shopping
mall construction are clearly understood by the community.

Workforce Awareness
Work force awareness and culture is an important component in minimising
environmental and cultural impacts resulting from project operations.
Construction personnel will be made aware of the Environmental Policy.

Construction personnel will be made aware of the heritage and cultural


sensitive site.

An environmental awareness induction plan will be implemented to ensure


that all construction workers are aware of their environmental responsibilities.

EMERGENCY RESPONSE PLAN


Fire hydrants will be installed in strategic locations in the Mall to fight fires
that may break out. If the fire will be insurmountable for the fire hydrants,
the Ndola City Council Fire Brigade will be contacted on 993 for back up.

The Mall will have fire extinguishers and hydrants for the purpose of putting
off fires. The mall will also have clearly marked assembly points in the
event of fire where people will be required too assemble. The managers
office will direct response to fire but only in the absence of fire men.
Announcements will be made through the public address system at the mall.

In case of no-fire environmental emergencies, the Mall Manager or his


designate will contact the ZEMA emergency response team2 for resources
and backup.
- 65 -

DECOMMISSIONING AND CLOSURE PLAN


At closure, the Kafubu Shopping Mall steel infrastructure, brick structures
and foundations will be dismantled to 500 mm below ground level. Saleable
items will be sold at market values. Redundant equipment will be sold as
scrap or disposed off-site at an approved waste disposal site.
Mobile equipment, pumps, motors, valves, pipes, transformers, electric
cables, containers will be dismantled and/or removed to a secure storage
area awaiting sale to the local community, businesses and scrap metal dealers.
Certain of the Project buildings and Mall structures (after removal of process
Mall and

decontamination)

could

be

adapted

for

sustainable

use

including small business enterprise, light industry and/or warehouse use.


The local community and businesses will be consulted in this regard
prior to closure. This Decommission and Closure Plan assumes that
the whole Project site will dismantled and removed. Finally, the Mall site
will be leveled, re-profiled and re-vegetated.
The proposed closure cost estimates were based on the current market prices
and costs of labour. These shall be updated with annual inflation and major
economic changes.
Decommissioning and Closures Cost Estimates

Activity

Responsible Personnel

Cost (ZMK)

1) Administrative expenses such as salaries General Manager and 10,500,000


and bills during the Decommissioning and Environmental Officer
Closures Phase
2) Acquisition

of

applicable

permits, General Manager and 15,500,000

preparation of necessary statutory reports Environmental Officer


and any consultancy services.
3) Demolition and Levelling/re-profiling the General Manager and 20,000,000
area.

Environmental Officer

4) Removal of all the steel scrap, non-steel General Manager and 10,500,000
scrap for alternative uses or disposal.
Total Costs

- 66 -

Environmental Officer

- 67 -

Impact Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impact on Land and Soil

Soil
due

contamination
to

improper

Petroleum

To trap any fuel or

Petroleum

Concrete

products

oil spillage from

products

Construction

dispensing points

getting to the soil.

dispensing points

Phase

KML

loading bay

storage of materials,

shall

have

drip

shall be inspected

Drip pans and

Approx US$

fuels and poor waste

pans

and

oil

and approved by

oil absorbents

200/m3

oil disposal methods.

absorbents ;

DCA

put in place

Officers

from MTC before


commissioning.
Storage

of

To avoid direct

Sites for storage

potential

contact

soil

of fuel, oil and

Construction

placed

pollutants such as

with oil, fuel and

chemicals shall be

Phase

concrete hard

fuel,

chemicals in case

inspected

Surfaces shall

standing.

of accident.

approved by KML

oil

and

chemicals should

of

and

KML/ZEMA

Tanks to be

be sealed

be done on sealed

Officers

from

Concrete @

surfaces

to

ZEMA

before

US$200/m3

prevent

soil

commissioning.

contamination;

- 68 -

on

Collection

and

To reduce on the

Containers

recycling of used

amounts

oil

collection of used

oil & lubricants;

waste

generation

oil shall be made

and storage.

available on site.

One drum @

of

and its disposal on


soil.

for

Construction

Contractor

Metal drums

Phase

KML

for collection

US$20

- 69 -

Impact Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impact on Land and Soil


Petroleum storage

Construction

Contractor

Reinforced

petroleum spillage

tanks

Phase

KML

concrete wall

bund walls around

from spreading in

inspected

storage of materials,

them and shall be

case

fuels and poor waste

high

accident.

oil disposal methods.

contain

Soil
due

Petroleum storage

To

tanks shall have

improper

contamination
to

enough

to

contain

of

any

an

any

spillage.
Limitation

shall

be
and

Storage tanks

and slab at the

approved by KML

will

have

bottom.

Officers

from

bund

walls

ZEMA

before

US$55/m2

around them

commissioning.
of

To avoid erosion

Period

of

earth moving to

of soil by fast

construction shall

Construction

dry periods;

flowing rainwater.

be specified in the

Phase

Exposed soil is prone

Tender Document

Monitoring of

to erosion by water or

with

earth moving

wind.

contractor

the

machines
dry land

- 70 -

to

Contractor

US$6.50/m3

KML

of gravel

Protection
susceptible

of

To

control

the

Mitigation

soil

current of the fast

measures for this

Construction

surface with grass;

flowing rainwater.

impact shall be

Phase

provided in the in

Grass

the Document.

planting

Protection

of

Stone pitching and

drainage channels

contact

fast

grass planting in

Construction

by planting grass

flowing

surface

drainage systems

Phase

or stone pitching;

water

with

shall be part of the

Planting grass

overall Document

or

as

pitching

susceptible soils.

means

mitigating
erosion.

- 71 -

of
soil

US$2/m2 for

KML

planting
turf/grass

To avoid direct
of

Contractor

Contractor

US$2/m2 for

KML

planting
turf/grass

stone

US$50/m2 for
stone pitching

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impact on Land and Soil


Installation

of

To

trap

soil

Mitigation

Exposed soil is prone

sedimentation

particles from the

measures

to erosion by water or

basins or planting

current of the fast

wind.

of

flowing water.

erodible

surfaces as soon
as possible.

Excavate
Construction

KML

common soils

impacts on soils

Phase

Consultant

@ US$3/m3

shall be part of the

Installation of

Excavate

contract

sedimentation

rock

Document

for

with

and

soil

To prevent highly

Mitigation

stockpiling of topsoil

should be avoided

prone soils from

measures

could lead to erosion

by selective soil

getting exposed to

and degradation of soil

stripping;

erosion.

quality.

Exposed

basins

Construction

KML

impact is part of

Phase

Consultant

the

contract

Selective soil

with

stripping will

Document

the contractor.

- 72 -

be done

US$50/m

Contractor
this

in
3

the contractor.
Stripping

in

US$2/m3

Areas

requiring

To limit on the

Mitigation

less clearing shall

size of area prone

measures

be preferred for

to erosion.

stock

piles.

Contractor
this

Construction

KML

impact is part of

Phase

Consultant

the

contract

Clearing will

with

only be done

Clearing shall be

Document

limited to the site

the contractor.

in

approved by the

US$1.50/m3

approved

areas

local authorities.
Soil compaction could

Only

result

following

construction activities.

heavy

To limit the size

Mitigation

Contractor

For

equipment

with

of area prone to

measures

Construction

KML

activities use

pneumatic

tyres

compaction.

impact is part of

Phase

Consultant

the

shall be used on

the

Pneumatic

access roads.

Document

this

contract

the contractor

with

tyres are to be
used on the
access roads

- 73 -

rolling

rate

US$30/hr

of

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impact on Land and Soil


Soil
Soil

erosion

near

should

culverts and drainage

prevented

channels where water

especially

velocity
increase.

could

erosion
be

near

To

control

soil

Programme

erosion and check

Shopping

for culverts and


drainage channels

for
mall

Operational

KML

Phase

headwalls,

drainage

Culvert

aprons, wing-

maintenance shall

construction

walls

culverts

by

requiring

be developed and

will be done

construction

of

attention.

made available.

to
design

culverts;

standard
To

prevent

Contractor

Linear

Construction

KML

maintenance

Consultant

of the culverts

maintenance

of

clogging of the

measures

culverts

&

culverts

impact is part of

Phase

drainage channels;

drainage

the

Regular

&

the

system

contract

by debris carried

Document

with water flow.

the contractor

with

@ US$50/m

maintenance
schedule will
be
place

- 74 -

US$200/m

and

Mitigation
this

@
3

specific

correctly designed

Regular

Concrete

put

in

Soil contamination by

Soil

To control waste

Enforcement

waste and spillages of

contamination by

disposal methods

ZEMA

shopping mall users.

poor waste and

Regulations

spillages of mall
users

of

Operational

Shopping mall

ZEMA

Phase

users

monitoring

Waste

ZEMA

activities

waste

management

KML

management .

system will be

on

put in place

- 75 -

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Vegetation
Retardation

of

vegetation growth due

Dust

control

by

application of water;

To suppress dust

Mitigation

generation

measures

Construction
this

Phase

Water
KML

bowsers

to

to contamination from

impact is part of

The

ground

water

gravel

dust particles and gas

the

will

be

DCAs

emissions.

Document

contract
with

watered

U$50/hr

Construction

N/A

the contractor
Haulage trucks shall

To

not exceed the speed

amount

limit of 60km per

generation.

hour.

reduce
of

the

Mitigation

dust

measures

this

Phase

impact is part of

Speed limited

the

to 60km per

contract

Document
the contractor

- 76 -

with

hour

KML

Loss of vegetation due

Less

to site clearing which

areas

will lead to loss of

preferred;

habitat

vegetated
shall

be

and

To

reduce

the

Mitigation
this

Construction

Contractor

US$1.50/m2

Phase

KML

to clear less

extent of the area

measures

without

impact is part of

Not all areas

vegetation.

the

will

be

cleared

of

contract

vegetated area

displacement of fauna

Document

species,

the contractor

vegetation

To sensitize the

Forest

Construction

Forestry Dept

US$15,000

conservation

Phase

KML

for awareness

especially

with

avifauna.
Increased access as a

Provision

result

conservation

communities

could

awareness programme

about

increased

to communities around

importance

the proposed site ;

forests.

of

the

construction
lead

to

deforestation
area.

in

mall

the

of

forest

the
of

programme

is

programme

Operational

budgeted for and

Phase

its implementation

Forest

schedule

conservation

prepared.

is

will

be

encouraged
such as tree
planting

- 77 -

Impact Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Wildlife and Wildlife Habitat


Disturbance to birds

Construction

and animals and loss

should

of habitat.

confined

to

To reduce on the

Mitigation

be

extent of the area

measures

the

to

impact is part of

Construction

gravel

the

will

be

outside game

restricted

to

area

proposed site

be

impacted

upon.

this

contract

Document

with

the contractor

Noisy activities to

To reduce sleep

Mitigation

be scheduled to

disturbance

measures

occur

birds and animals.

Construction

Contractor

Haulage

Phase

KML

suitable

of

from

the proposed

US$0.35/m3.

site

km

Construction

Contractor

Haulage

Phase

KML

suitable

impact is part of

Construction

Consultant

gravel

prescribed normal

the

contract

will restricted

Local

outside game

working hours.

Document

with

to day time

Authority

area

within

to

this

the contractor

only

from

US$0.35/m3.
km

- 78 -

of

Wildlife loss due to

The roads to the

To warn motorists

Mitigation

accidental

proposed site shall

of the presence of

measures

caused by speeding

have

wildlife in certain

construction traffic .

signs for warning

sections

users of wildlife

road

presence;

motorists

killings

adequate

of
so

Construction
Phase

KML

US$100/each

impact is part of

Operational

Local

on average

the

the

Phase

Authority

that

Document

drive

this

KML signs @

contract

the contractor

with caution.

with

Signs will be
used

as

warning

to

and from the


site

- 79 -

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Wildlife and Wildlife Habitat


Wildlife loss due to

There

accidental

adherence

be

To control over-

Provision of speed

Operational

Police Traffic

Speed humps

to

speeding through

retarders

and

Phase

Patrol Unit

provision

humps along the

Speed

Local

each

warning signs &

roads

will be used

authority

mounting of speed

Partial fencing of

control traps.

shopping mall

Control of noisy

To monitor and

Enforcement

Operational

Local

Working

Noise disturbance to

activities on site

control

local by-laws.

Phase

Authority

hours limited

wildlife

(through local by-

generation.

ZEMA

to day light

killings

caused by speeding

shall

speed

traffic

increased

due

to

vehicular

of

noise

of

Local

laws);

will

traffic

applied

- 80 -

limit

laws
be

only.

US$500/

ZEMA Regulation

To monitor and

Enforcement

on

control

ZEMA

Abatement;

Noise

generation.

noise

Regulations
noise

of

on

Operational

Local

Phase

Authority

Noise
generation
will be within
the law

- 81 -

N/A

Impacts Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Water Quality


Sides
Siltation

of

of

the

To filter of the

Mitigation

Construction

Contractor

Grassing

water

drainage shall be

sediment particles

measures

courses due to soil

planted with grass

in the fast flowing

impact is part of

Operational

erosion

or stone pitched;

rain water with

the

Phase

Stone pitching

grass and also to

Document

Stone pitching

@ US$50/m2

avoid erosion of

the contractor

will be used

the

Mitigation

Construction

Contractor

Using

of

measures

Phase

KML

masonry

of

nearby

drains and culverts.

this

contract
with

Phase

KML

US$3/m

soil surfaces by
stone pitching.
Drainage systems

To

reduce

shall have scour

current

checks;

rainwater flow.

this

impact is part of

Operational

the

Phase

contract

Document
the contractor

with

The drainage
will

have

scour checks

- 82 -

stone

US$12 each

at

Impact mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Water Quality (Cont'd)

Siltation

of

water

courses due to soil


erosion

of

Silt traps shall be

To protect surface

Mitigation

put along drainage

water

measures

systems;

through

nearby

drains and culverts.

pollution
filtering

this

Construction

Contractor

Approx

Phase

KML

US$10/m

US$15 each

impact is part of

Operational

finest particles in

the

Phase

water current.

Document

contract
with

the contractor

Silt traps will


be used along
the drainage

Spoon drains shall

To

have scour checks.

excessive
and

control

risks

erosion.

flow
of

Mitigation

Construction

Contractor

measures provided

Phase

KML

for

Operational

impacts

Water

on

Quality

Phase

shall be part of the

Spoon drains

overall

will

Document

contract

be

provided with
scour checks

- 83 -

Water shortage to the

Exploitation

local community due

To avoid conflicts

Mitigation

water sources for

and

measures

to over exploitation for

construction

support from the

impact is part of

Permit will be

when

construction works.

works

local community.

the

obtained

are

done

shall

of

be
with

approval by the

to

receive

this

contract

Document
the contractor

local authority and


consent from the
local community.

- 84 -

with

Construction

Contractor

Nominal

Phase

KML

exploitation

obstruction
rights

for

works
not

reconstruction

Impacts Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Water Quality (Cont'd)


Ground

water

Proper siting of pit

To filter pollutants

Mitigation

Construction

Contractor

VIP latrine @

contamination due to

latrines away from

from getting to the

measures provided

Phase

KML

US$600 each

construction of sub-

water

ground water.

for

on

Water logged

standard campsite pit

areas;

Quality

areas will be

logged

impacts

Water

latrines for workers.

shall be part of the

avoided

overall

siting

contract

Document

for

with

contractor
Good
standards

hygienic
and

To

promote

cleanliness

proper

avoid

maintenance of pit

in

latrines.

camps.

and

epidemics
construction

Mitigation

Construction

Contractor

Cleaning

measures provided

Phase

KML

activities

for

Public health

US$150/

and

month

impacts

Water

on

Quality

shall be part of the

health

overall

contract

practice

document with the

be used

contractor

- 85 -

good

will

Sedimentation

and

increased turbidity in

Excavated

soils

To make use of

Mitigation

Construction

Contractor

For

shall be used for

available soils and

measures provided

Phase

KML

soil

surface water caused

other works such

reduce on creating

for

by erosion of bare

as backfilling

more bare areas

Water

which are prone to


soil erosion.

areas

and

runoffs

resulting

from

impacts

U$6.50/m

soils will be

For top soil

shall be part of the

used

spreading and

overall

backfilling

Quality

contract

and

Document

grading

and

the contractor

drainage channels left


after

@
3

Excavated

excavation
works

construction

works.

- 86 -

on

gravel

with

to

for

compacting
@ US$2/m2

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Water Quality (Cont'd)


Sides of drainage

To filter of the

Mitigation

Construction

Contractor

For loose soil/

channels shall be

sediment particles

measures provided

Phase

KML

susceptible

planted with grass

in the fast flowing

for

Operational

soil, grassing

or stone pitched;

rain water with

Water

Phase

@ US$3/m2

increased turbidity in

grass and also to

shall be part of the

Stone pitching

For firm soil

surface water caused

avoid erosion of

overall

will be used

US$3/m3

by erosion of bare

soil surfaces by

Document

areas

stone pitching.

the contractor

(Cont'd from above)

Sedimentation

and

and

runoffs

resulting

from

Drainage systems

To

excavation

and

shall have scour

current

grading

and

checks.

rainwater flow.

works

reduce

the
of

impacts

on

Quality

contract
with

Mitigation

Construction

Contractor

US$12

measures provided

Phase

KML

stone masonry

for

Operational

impacts

on

drainage channels left

Water

after

shall be part of the

Scorching

overall

checks will be

construction

works.

Quality

contract

document with the


contractor
Impacts on Air Quality

- 87 -

Phase

used

each

Air pollution caused

Regular

by exhaust fumes and

maintenance

dust from excavators,

construction

bull dozers, graders as

vehicles

well as site clearing

equipment

will

affect

vegetation

human,
and

also

disturb

habitats

for

animals,

birds

and

insects.

To
of

check

defects

for

Log

and

vehicle

book

on

Construction

Contractor

US$30,000/

&

Phase

KML

month

for

servicing of the

equipment

Regular

medium

vehicles

and

maintenance shall

maintenance

old equipment

in

equipment so that

be kept on site for

of

order to reduce

they are in good

inspection

construction

emission

operation

shall be part of the

vehicles will

condition.

overall

be done

exhaust fumes;

and

of

and

contract

document with the


contractor
Document

- 88 -

to

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Air Quality (Cont'd)


Periodically water
(Cont'd from above)

down

on

temporary roads;

To suppress dust.

Log book on dust

Construction

Contractor

control

Phase

KML

times

Periodic water

Air pollution caused

shall be kept on

down on the

by exhaust fumes and

site for inspection

temporary

dust from excavators,

and shall be part

roads will be

bull dozers, graders as

of

done

well as site clearing

Tender Document

will

affect

vegetation

watering

showing

human,
and

also

disturb

habitats

for

animals,

birds

and

insects.

- 89 -

the

overall

US$50/ hr

Unpleasant odours due

Cleaning

to poorly maintained

regular

toilets and poor waste

maintenance

management.

toilets

to

and

of
avoid

unpleasant odours.

To maintain and

Public

promote a healthy

standards

as

environment

provided

under

campsites

at

Health

Construction

Contractor

US$150/

Phase

KML

month

Periodic

Local
Authority

and

the Public Health

cleaning will

prevent the spread

Act Cap 295 shall

be done and

of diseases.

be enforced shall

monitored

be part of the
overall
Document

- 90 -

Tender

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Air Quality (Cont'd)


Unpleasant odours due

Waste should be

To maintain and

Public

to poorly maintained

carefully managed

promote a healthy

standards

toilets and poor waste

to

environment

provided

management.

unpleasant odours.

prevent

campsites

at

Health

Construction

Contractor

US$100/

as

Phase

KML

month

under

Waste

Local
Authority

and

the Public Health

management

prevent the spread

Act Cap 295 and

system will be

of diseases.

ZEMA

put in place

Regulations

on

Waste
Management shall
be enforced shall
be part of the
overall

contract

document with the


contractor
Excessive

diesel

of

To monitor and

Enforcement

un-

the roads and road

control unfit cars

roads

maintained equipment.

Traffic Act, Cap

to be used on site.

Traffic Act, Cap

fumes

due

to

Enforcement

- 91 -

and

of
road

Construction

ZEMA

Police Traffic

Phase

KML

Patrol Unit

464 and ZEMA

464 and EPPCA,

Operational

EPPCA Cap 204

Cap 204 on Noise

Phase

on Air Pollution

Abatement.

The stipulated

so that only road

laws will be

worth cars that are

applied

maintained are on
site.

- 92 -

ZEMA

Impacts Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts of Noise
Noise and vibration

Working

caused by construction

limited

machinery, equipment

light only;

hours
to

day

To

avoid

sleep

disturbance

at

night.

and drilling.

Enforcement

of

Construction

Contractor

Cost

EPPCA, Cap 204

Phase

KML

applicable as

on

Construction

ZEMA

programme is

will

Local

based on 9-

Authority

day

Noise

Abatement.

be

limited to day

Enforcement

caused by construction

the Factories Act,

occupational

machinery, equipment

Cap 441.

health

and drilling.

of

To

Construction

Contractor

the Factories Act,

Phase

KML

Cap 441.

Occupation

Ministry

working

health will be

Labour

conditions among

implemented

the

promote

and

safe

Enforcement

construction

workers.

- 93 -

of

working

hours.

time
Noise and vibration

not

US$3,000/yr

of

ZEMA Regulation

To monitor and

Enforcement

Noise from increased

on

control

traffic.

Abatement;

Noise

noise

generation.

Operational

ZEMA

Police Traffic

EPPC Act, Cap

Phase

Local

Patrol Unit

204

Noise

Authority

on

of

Noise

Abatement.

Abatement
law will be
applied

Control of noise

To monitor and

Enforcement

generating

control

activities (by local

generation.

by-laws).

noise

Operational

ZEMA

Police Traffic

EPPC Act, Cap

Phase

Local

Patrol Unit

204

By laws will

Authority

on

Abatement.

of

Noise

be
implemented

- 94 -

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Landscape and Aesthetics


Visual impact of the

Development

construction

`the shopping mall

of

the

of

To maintain areas

Shopping

of scenic beauty.

design

mall

Design Phase

Design

Cut

be

Construction

Engineers

spoil

shall

shopping mall works

designs must be

environmentally

Phase

could be substantial if

environmentally

safe enough and

All

designs

designs

safe enough and

compatible

will

be

compatible with the

compatible

the

followed

as

slope angles of the

the

surrounding

environment.

are

not

with

surrounding

surrounding

environment.

environment.

- 95 -

with

KML

per standard

to

fill/
@
3

US$3.50/m

Disfigurement of the

Development

natural landscape and

the shopping mall

of

To maintain areas

Runway

of scenic beauty.

shall

designs

Design Phase

Design

Cut

be

Construction

Engineers

spoil

aesthetic view due to

designs must be

environmentally

Phase

construction works.

environmentally

and

Scenic beauty

and

compatible

with the natural

will

with the natural

landscape of the

maintained as

landscape and the

surrounding

designed

surrounding

environment.

compatible

to

fill/
@
3

KML

US$3.50/m

KML

Construction

be

environment.
Abandoned

Abandoned

To

construction

structures in areas

vandalism

excess

of scenic beauty

ruining

construction materials

shall be brought

structures, which

contract

of

down

may become an

with

aggregate and concrete

eye

contractor

slabs left in areas of

of

Design Phase

and

structures to be

Construction

waste can be

the

determined

Phase

reused

Bringing

refill borrow

down

pits as part of

structures that

the

distort the scenic

are

rehabilitation

scenic beauty reduces

beauty

required

the quality of scenery.

surrounding

on

environment.

pits.

structures,

laterite,

stone

avoid

sore

of

and

Disposal

the

- 96 -

at
signing
the

not

to

programme
borrow

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Land-use and surrounding environment


of

Design Phase

Contractor

About

unplanned

local people for

Construction

KML

US$3000 per

be

settlements which

unskilled

Phase

Community

unity

employed for the

may lead to land-

shall

the

Local people

Representative

structure

works;

use change and

priority

as

will be given

Local

relocated

social upheavals?

part of the overall

the

Authority

are not planned in

contract document

before

advance.

with

other

The

proposed

construction
influence

mall
might

migration

and settlement patterns


if labour requirements

Local people with

To

the

necessary

skills

shall

avoid

Recruitment

be

contractor

- 97 -

labour

and

the

chance
any

of

Resettlement

of

To avoid conflicts

The project does

Design Phase

Contractor

US$3,000/

communities

in

of land ownership.

not foresee any

Construction

Community

unit

new areas shall be

resettlement

of

Phase

Representative

structure

done

in

communities

as

In case this

Local

relocated.

consultation with

construction

happens

Authority

community

works

as

will

be

RAP will be

to

the

prepared

well as the social

confined

welfare

project

reserved

area,

however

department

and

host or existing

should there be

community.

any

resettlement

then it shall be
done
accordance

in
with

Resettlement
Action
Framework

- 98 -

plan

of

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Land-use and surrounding environment (Cont'd)


Detours,
Construction

of

roads

and

temporary detours will

equipment

disturb
environment
the

immediate

the
within
and

access

To avoid conflicts

Mitigation

between

measures

the

for

Design Phase

Contractor

To

Construction

Community

detours
US$76/m

Contractor and the

impacts on land-

Phase

Representative

site location shall

local

use shall be part

Local

Local

be

and

of

Authorities

Authority

done

park

in

community
also

to

the

overall

consultation with

monitor land-use

contract document

will

be

surrounding

local people and

change.

with the developer

involved

in

environment.

shall

into

planning

for

the

detours

take

account

existing land use.

- 99 -

construct
@

Local people with

To

of

Design Phase

Contractor

Lump

the

necessary

unplanned

local people for

Construction

Community

US$2,500/

recruited from local

skills

shall

be

settlements which

unskilled

Phase

Representative

month

areas

employed in the

may lead to land-

shall

Employing of

Local

reside far may start to

construction

use change and

priority

local

Authority

settle

well operation of

social upheavals?

part of the overall

If

labour

is

people

near

proposed project.

not

who

the

the project

as

avoid

Recruitment

labour

be
and

the
as

contract document
with
contractor

- 100 -

the

people

will be done

Sum

Impact Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Land-use and surrounding environment (Cont'd)

Cont'd from above

Resettlement

of

To avoid conflicts

The project does

Design Phase

Contractor

US$3,000/

communities

in

of land ownership

not foresee any

Construction

Community

unit

new areas shall be

resettlement

of

Phase

Representative

structure

done

in

communities

as

Local

relocated.

consultation with

rehabilitation

local authority and

works

host or existing
community.

Authority

will

be

confined

to

the

project

reserve,

however
there

should
be

any

resettlement then
it shall be done in
accordance
the

Resettlement

action
Framework

- 101 -

with

plan

KML

of

Emission of exhaust
fumes

to

the

ZEMA Regulation

To monitor and

Enforcement

on Air Pollution;

control

EPPC Act, Cap

emission

of exhaust fumes

204

surrounding

to the surrounding

Pollution.

environment due to

environment.

increased traffic.

- 102 -

on

of

Air

Operational

ZEMA

ZEMA

Phase

Local

Monitoring

Authority

Costs

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Period of

Authority

Cost of Mitigation

for its implementation

Implementation

Responsible

Construction

Contractor

US$15,000/
month

Impacts on Land-use and surrounding environment (Cont'd)


Adherence
(Cont'd from above)

to

for

Development

of

defects and repair

engine

Phase

KML

maintenance

any

maintenance

Vehicle

ZEMA

malfunctioning

schedules

engine.

making

schedules

and

fumes

standards

to

surrounding

reduce

air

environment due to

pollution.

the

check

engine

Emission of exhaust
to

To

available

and

maintenance

them

will be done

for

inspection on site.

increased traffic.
Impacts on Socio-economic Environment

- 103 -

Temporary marriages,

There

casual

provision

sex

shall

be

To sensitize the

Mitigation

of

construction

measures

for

Construction

Contractor

Lump

Phase

KML

US$20,000

relationships and more

education both to

workers and local

impacts of STDs

Operational

Community

for

chances

of

the

communities

and

Phase

Based

project

transmission

of

community

about the dangers

shall be part of the

Organizations

overall

Local

local
and

HIV/AIDS

sexually diseases due

camp workers on

of

to

STDs

HIV/AIDS and to

document with the


developer.

interaction

of

and

STDs

project workers with

HIV/AIDS using

protect

local communities.

aids such as video

themselves.

and

shows, pamphlets,
talks, etc.

- 104 -

contract

Authority

Sum

whole

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

indicators

Impacts on Socio-economic Environment (Cont'd)


Increased

road

Provision

of

To prevent fatal

Mitigation

accidents.

measures

Construction

Contractor

US$100

Phase

KML

sign

accidents

due

to

adequate warning

increased

vehicular

signs in human

impacts on socio-

Operational

Local

traffic to and from the

crossing

and

economic shall be

Phase

Authority

constructed shopping

speed

retarders

part of the overall

Road

mall

and/

or

contract

human

mechanisms

at

Document

crossing points .

contractor.

for

with

crossing

signs

and

speed
retarders will
be used

Impacts on Cultural and Historic sites

- 105 -

per

Detours,

access

To ensure the mall

Mitigation

and

is designed in the

measures

manner

which

roads
Poorly

developed

equipment

park

Construction

Contractor

One

NHCC

for

Phase

KML

staff

to

impacts

on

The

National

attached

and

provisions of

Heritage

project during

Conservation

construction

Commission

of areas near

be
to

shopping mall design

sites shall not be

take into account

Cultural

could

constructed

the provisions of

Historic sites shall

the

negatively on heritage

through

the

be part of the

Heritage

sites.

and Historic sites

overall

contract

Conservation

heritage sites

and other heritage

document with the

Commission

if fund during

sites.

contractor

shall apply.

excavation @

impact

Cultural

The

National

Heritage Act.

National

provisions of the

US$500/

National Heritage

month

Conservation
Commission shall
apply.

- 106 -

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken
for its implementation

Monitoring
frequency and

Authority

Cost of Mitigation

Responsible

Indicators

Impacts on Cultural and Historic sites (Cont'd)


Detours,

access

that

Mitigation

by

measures

construction

sites shall not be

sensitive site are fund

constructed

within the construction

Cultural

reserve area.

Historic sites and

Dust may disfigure the

roads

appearance

equipment

site.in

case

of

the
Same

Construction

Contractor

Blow off the

for

Phase

KML

dust

impacts

on

Provisions of

National

US$100/hr

vehicles does not

Cultural

and

the

Heritage

hire charge of

near

settle on the site

Historic sites shall

Heritage

Conservation

compressor or

and

thereby

be part of the

Conservation

Commission

regularly

disfiguring it.

overall

Commission

water

the

shall apply.

gravel

or

and
park

other

heritage

sites.

Provisions

of

the

To
dust

ensure
caused

contract

document with the


contractor.

National

National

at

construction
of temporary

Heritage

enclosure

Conservation

around

Commission shall

protect

apply.

sensitive site
from dust.

- 107 -

to

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its

frequency and

Responsible

implementation

Indicators

Cost of Mitigation

Impacts on Human Settlements


Although

no

Construction

negative impacts on

shall

human

To

Mitigation

Construction

Contractor

Liaison

problems

measures

for

Phase

KML

allowances

confined to the

associated with

impacts

on

Construction

Local Authority

US$100/ month

are foreseen since

shopping

resettlement

Human

will be restricted

Community

Relocation

construction

reserve area.

Settlements sites

to the shopping

Representatives

two

mall reserve

settlements

works

be

ensure

mall

issues

are

will be confined to

circumvented

shall be part of

the

during

the

however, extending

construction

contract

the works may affect

phase.

Document with

project

residential

site

overall

the contractor.

structures.

- 108 -

of

structures

US$ 10000

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its

frequency and

Responsible

implementation

Indicators

Cost of Mitigation

Impacts on Human Settlements


Although

no

Detour,

access

To avoid land-

Mitigation

use

measures

Construction

Contractor

Liaison

for

Phase

KML

allowances

on

Consultation

Local Authority

US$100/ month

negative impacts on

roads

human

equipment park

with the local

impacts

are foreseen since

site

communities.

Human

with the local

Community

construction

outside

the

Settlements sites

athourity as well

Representatives

will be confined to

construction site

shall be part of

as

the

shall be done in

the

community will,

consultation

document

with

the contractor

settlements

size

of

proposed
reserve

the
mall

however,

extending
construction
affect

works

the

the
may
nearby

and

location

ZEMA,

conflicts

contract

local people and


will

take

into

account existing

residential

land use in the

structures.

areas.

- 109 -

with

the

be done before
any activity

Construction of the

There shall be

To avoid land

Mitigation

shopping

no conversion of

ownership

measures

enhances

communal land

disputes with the

impacts

accessibility,

into state land

local

around

communities.

mall

mobility
economic

and
activities

for the communities


around the area.

Construction

Contractor

Liaison

for

Phase

KML

allowances

on

Proper

Local Authority

US$100/ month

Human

documentation

Community

Settlement sites

will be obtained

Representatives

constructed

shall be part of

on

strucure.

the

before

the

overall

contract
document

issue

construction can
with

the contractor

- 110 -

land

begin

Impact Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken

Monitoring

Authority

for its

frequency and

Responsible

implementation

Indicators

Cost of Mitigation

Impacts on Human Settlements (Cont'd)


Construction of the

There shall be

To avoid land

Mitigation

shopping mall lead

no conversion of

ownership

measures

to increased human

communal land

disputes with the

impacts

settlements, changed

into state land

local

settlement patterns,

around

communities.

and

constructed

shall be part of

shopping mall i

the

commercial

activities around the


shopping mall

the

Construction

Contractor

Liaison

for

Phase

KML

allowances

on

Respected

Local Authority

US$100/ month

Human

settlements will

Community

Settlements sites

protected

Representatives

overall

contract with the


contractor

- 111 -

Construction of the

There shall be

To avoid land

Mitigation

shopping mall lead

no conversion of

ownership

measures

to

land

communal land

disputes with the

impacts

land

into state land

local

Human

land into state

Zambia Police

around

communities.

Settlements sites

land around the

Safety Council

constructed

shall be part of

constructed mall

mall.

the

increased

values

and

resource

tenure

around the mall

the

Operational

Contractor

Liaison

for

Phase

KML

allowances

on

No

Local Authority

US$100/ month

communal

overall

document
contract with the
contractor
The construction of

Speed limits of

To save lives of

Mitigation

the shopping mall

40km per hour

pedestrians and

measures

will

increase risks

shall

of

road

observed

accidents

traffic
to

communities around
the

the
mall.

be
near

shopping

Operational

Contractor

Speed humps @

Phase

KML

US$500 each

impact is part of

Speed limits and

Local Authority

the

human crossing

Zambia Police

Document with

including

Safety Council

the contractor

signs

this

contract

constructed

will

provided

shopping mall

- 112 -

road
be

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its

frequency and

Responsible

implementation

Indicators

Cost of Mitigation

Impacts on Human Settlements (Cont'd)

Construction of the

Trees shall be

To

shopping mall may

planted

near

hazardous

lead to high traffic

settled areas to

emissions

volume which may


lead

filter

off

Mitigation

Operational

Contractor

US$20/per tree
planted

measures

for

Phase

KML

and

impacts

on

Trees shall be

Local Authority

minimize

also to act as

Human

hazardous

barriers to traffic

Settlements sites

emissions.

that may career

shall be part of

communities around

of the road and

the

the

cause

contract

health

to

increased
risks

mall

to

from

vehicle emissions.

accident

planted

overall

to nearby settled

document

areas.

the contractor

- 113 -

with

Noise

from

high

The mall will

To

traffic volumes using

have

disturbance

the shopping mall

hours

of

may

opperation

to

communities.
airport.

disturb
the

avoid

restricted

noise

disturbance.

avoid

communities.

to

Operational

Contractor

US$20/m2

Phase

KML

wall built to bar

this impact are

The mall will

Local Authority

the noise from

part

have

Mitigation
measures

for

of

the

restricted

overall contract

hours

document

opperation

with

the contractor

- 114 -

of

of

the settlements

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its

frequency and

Responsible

implementation

Indicators

Cost of Mitigation

Impacts of Quarries and Borrow Pits


Quarries and borrow

Quarrying shall

To avoid water

Mitigation

pits

not be done near

pollution which

measures

location

may

negatively impact on

surface

important ecological

sources.

water

units.

might

lead

to

Contractor

Haul of suitable

Phase

KML

gravel

to

impacts

of

Will

of

Quarries

and

the

Borrow

Pits

deprivation
water

for

Construction

local

shall be part of

community?

the

be

done

Local Authority

away

from

Local

surface

water

Community

@
3

US$0.35/m . km

sorces

overall

contract
document

with

the contractor
Quarries and borrow

There shall be

To preserve the

Mitigation

pits

no

Heritage sites.

measures

location

may

negatively impact on

near

important ecological

sites

units.

quarrying
Sensitive

this

Construction

Contractor

Haul of suitable

Phase

KML

gravel

impact is part of

Will be done in

Local Authority

the

areas that are not

National

sensitive

Heritage

contract

Document with
the contractor

Conservation
Commission

- 115 -

and

@
3

US$0.35/m . km

Excessive

noise

Quarrying shall

To avoid the risk

Mitigation

from blasting and

not be done near

associated with

measures

machinery
disturb
communities.

may
nearby

communities.

for

Construction

Contractor

Haul of suitable

Phase

KML

gravel

flying

pebbles

this impact are

No

quarrying

Local Authority

from

blasting

part

the

will

be

Mine

Tender

near

Department

of

communities

Ministry

of

operations

and

minimise

of

overall

Document.

disturbance from

done

Mines.

noise.

- 116 -

Safety

@
3

US$0.35/m . km

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

Indicators

Impacts of Quarries and Borrow Pits


Excessive noise from

Quarrying shall be

To

blasting

done

compliance

and

in

ensure

machinery may disturb

conformity to the

the

nearby communities.

Mines

quarrying.

and

Law

with
on

Mitigation

Construction

Contractor

License

Phase

KML

about

impact is part of

Shall conform

Local

US$1,000 per

the

contract

to the mines

Authority

quarry

with

and minerals

Mine

ACT

Department of

measures

this

Minerals Act, No.

Document

31 of 1995.

the contractor

fees

Safety

Ministry

of

Mines.
Abandoned
pits

borrow

Borrow Pits shall

To

pose

not be done near

harbouring disease

measures

to

water sources and

causing organisms

impacts of Borrow

could

potential

hazard

ecological units and

human

and

residents.

settlements.

avoid

other

Mitigation
for

Operational

Contractor

Haul

Phase

DCA

suitable

This will be

Local

gravel

Pits shall be part

done

dangerous animals

of

that

contract document

may

find

the

these as suitable

with

habitats.

contractor.

Impacts of Traffic

- 117 -

overall

the

of

@
3

Authority

US$0.35/m .

from

Mine

km

settlements

Department of

away

Safety

Ministry
Mines.

of

Failure

to

established
might

use

Surveyors should

To avoid off-site

Mitigation

routes

not venture too far

impacts associated

Measures

away

with surveying.

impacts

result

in

surveyors'

vehicles

negatively

impacting

on the environment.

from

proposed

the

for
of

Design Phase

Contractor

US$20,000 to

Construction

KML

survey

Phase

Local

stake

Authority

project

Surveying shall be

Surveyors

site in order to

part of the overall

will

be

avoid impacts on

contract document

restricted

to

the

with

project site

surrounding

environment.

contractor

- 118 -

the

and

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken
for its implementation

Monitoring

Authority

frequency and

Cost of Mitigation

Responsible

Indicators

Impacts of Traffic (Cont'd)

Construction
could

impact

undisturbed

traffic

Established routes

To maintain the

Mitigation

should

existing

measures

be

used

on

where possible in

environment

areas

order to reduce

the adjacent areas.

adjacent to the project.

impacting

in

on

Contractor

To

Phase

KML

existing

impact is part of

Established

Local

detours,

the

routes will be

Authority

maintenance

this

contract

Document

undisturbed areas.

with

use

@ US$5/m

used

the contractor

Construction

To

vehicles must only

necessary

use

disturbance

pre-

Construction

avoid

un-

Mitigation

Construction

Contractor

Maintenance

Phase

KML

of

impact is part of

Pre-

Local

predetermined

determines

Authority

DCAs

measures
of

this

determined access

traffic flow and

the

roads that should

cause danger to

Document

be determined in

other users.

the contractor

the design phase.

contract
with

access

are the only


ones
used

- 119 -

roads

to

be

existing/

US$55/m

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

Indicators

Impacts of Traffic (Cont'd)


Excessive dust from

Control of dust

To

construction

through watering

respiratory

of dust areas.

visibility problems

impact is part of

Watering

and the gathering

the

dust areas will

of dust on other

Document

protected

the contractor.

disturb

could
nearby

communities.

avoid
and

areas

Mitigation
measures

this

contract
with

Construction

Contractor

Water bowser

Phase

KML

US$50/hr

of

Local
Authority

be done

and property.
Increased

accidents

Provision

of

To save human

Mitigation

due to increased traffic

adequate warning

lives and injury

Measures

flow.

signs in black spot

that could arise as

areas and speed

retarders

accidents.

result

of

Operational

Contractor

US$100/

Phase

KML

DCA sign

impacts of traffic

Warning signs

Local

shall be part of the

in black spot

Authority

overall

areas

Document.

for

Tender

and

speed
retarders will
be used

Impacts of Work Accidents

- 120 -

Advanced planning of

Development

safety

safety procedures

people

measures

and

equipment

requirements

of

operational

manual.

To

ensure

that

Operational

Contractor

US$800/

this

Phase

KML

month

undertaking these

impact is part of

Safety

Local

tasks

the

procedure and

Authority

know

Mitigation

contract

exactly what is to

Document

be done.

the contractor

with

operational
manual

will

be developed

- 121 -

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

Indicators

Impacts of Work Accidents (Cont'd)


Lack of enforcement

Enforcement

of

To safe guard the

Mitigation

of safety and health

Public health and

health and safety

Measures

regulations

safety regulations.

of workers.

Operational

Contractor

US$3,000/

Phase

KML

month

impacts of work

Public health

Local

impact negatively on

accidents shall be

as well safety

Authority

construction workers.

part of the overall

regulations

contract

will

could

for

Document

with

be

enforced

the contractor.
Impacts of Construction Camps
Advanced planning of

Selection of camp

To ensure camp

Mitigation

construction

siting

be

siting

measures

in

considered at the

consultation with
ZEMA,

siting.

camp

must

done

local

Design Phase

Contractor

US$1,000 for

Construction

KML

siting

impact is part of

Phase

ZEMA

planning

design phase and

the

Stakeholders

Local

communities

Document

will

Authority

is

are

authority and local

consulted well in

community.

advance.

this

contract

the contractor

with

be

consultanted

Local
Community

- 122 -

and

Loss of vegetation at

Clearing for camp

To

construction site.

siting

conserve

Mitigation

Contractor

Site clearance

Phase

KML

ZEMA

US$0.99/m2

must

be

vegetation around

measures

to

the

the camp site and

impact is part of

Clearing

actual site to avoid

protect

the

the

vegetation

vegetation loss on

from

extensive

a larger scale.

loss of vegetation

limited

site

Document

this

Construction

contract
with

the contractor.

will

of

Local
be

limited to site

Authority
Local
Community

- 123 -

Impact Mitigation Plan


Impact

Mitigation Measure

Objective

Actions to be taken
for its implementation

Monitoring

Authority

frequency and

Cost of Mitigation

Responsible

Indicators

Impacts of Construction Camps (Cont'd)


Waste generation at

Waste disposal to

To control waste

Mitigation

campsite.

be

at

disposal practices

Measures

sites

and avoid illegal

impacts

dumping.

construction

done

designated

approved by the
local authority.

camps

for
of

shall

be

part of the overall


contract document
with
contractor

- 124 -

the

Construction

Contractor

Disposal

of

Phase

KML

waste

To be done at

Local

US$0.10/ton.

approved site

Authority

km

by

ZEMA

authority

local

Interaction

of

construction
with

the

workers
nearby

There

shall

provision

be

To

prevent

the

Mitigation

of

transmission

of

Measures

for

Contractor

US$15,000

Phase

KML

Lump Sum

HIV/AIDS

Local

campaigns

Authority

education both to

sexually

impacts

communities may lead

the

transmitted

construction

to

community

diseases between

camps

be

will be done

CBO

camp workers on

the

part of the overall

on site and

Health

STDs

community

contract

community

transmission

sexually
diseases.

of

transmitted

local
and

and

local
and

of

Construction

shall

HIV/AIDS using

construction

Document

aids such as video

workers.

the contractor

shows, pamphlets,
talks, etc.

- 125 -

with

on

Impact Mitigation Plan


Mitigation Measure

Impact

Objective

Actions to be taken

Monitoring

Authority

for its implementation

frequency and

Responsible

Cost of Mitigation

Indicators

Impacts of Construction Camps(Cont'd)


(Cont'd from above)

Local people with

To

the

necessary

local

skills

shall

be

benefit from the

impacts

employed in the

project and also to

construction

project.

avoid immigration

camps

communities may lead

which may result

part of the overall

Department of

to

in land disputes

contract

Ministry

and

Document

Interaction

of

construction
with

the

workers
nearby

transmission

sexually
diseases.

of

transmitted

ensure

the

community

upheavals.

social

Mitigation
Measures

for
of

shall

the contractor

Construction

Contractor

US$2,500 per

Phase

KML

month

Local
Authority

be

with

Labour

of

Labour
Community
representative

- 126 -

Environmental Monitoring Plan


Environmental monitoring ensures that the impacts have been accurately
predicted and that appropriate mitigation measures are being implemented as
planned and that they have the expected effects. Identification of potential
environmental impacts associated with the reconstruction of the airport
indicates a need to design and implement a specific environmental monitoring
plan. The monitoring process begins with supervision of implementation. The
bulk of the activities may take place during the implementation stage. The
environmental objectives of these activities are to ensure mitigation measures
outlined in the contracts are being properly implemented, that environmental
contractual measures are being respected, construction is going in accordance
with the agreed design standards and that no unforeseen negative impacts are
occurring as a result of project execution.

The key components of the proposed environmental monitoring plan are


presented in Section 12.5 on Monitoring Activities and Indicators.

While it is appropriate to indicate that progressive construction will be


practised, this aspect of environmental management is not always possible as
some areas only become available at the end of the construction phase. As the
construction phase progress, the monitoring plan will be reviewed and
adjusted in accordance with project environmental management requirements
outlined in this report.

- 127 -

Table 10: Monitoring Activities and Indicators


Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Land and Soil
Site
Land and Soil

Engineer

to

Periodical

Clean storage sites

Inspection Report is

Contractor's

make inspections of

inspections through

free from any oil or

available

Engineer

sites for storage of

out the Construction

fuel

Kafubu

materials, oil and

Phase

maintained through

spillage

fuels

and

ensure

out

they

have

sealed

Phase.

with
shopping

Site

KML

mall

Construction

surfaces.
Site

Engineer

inspect

the

to

waste

disposal sites.

Periodical

Waste oil is being

Inspection Report is

Contractor's

inspections through

disposed

available at KML

Engineer

out the Construction

designated sites and

Phase

in

the

of

in

KML

approved

method.
Site

Engineer

to

Periodical

Containers

for

Used

oil

ensure used oil is

inspections through

collection of used

serviced

being collected for

out the Construction

oil are available on

machinery has been

recycling.

Phase

site.

collected
containers.

- 128 -

from
plant

in

Contractor

Site

Site

Engineer

to

Once before the fuel

Bund wall design

Bund walls around

Contractor

inspect storage tanks

storage tanks are put

and

construction

fuel storage tanks

KML

and

ensure

they

to use.

plan

has

will be constructed.

have

bund

walls

been

developed approved

around them high

and is available.

enough to contain
any spillage.

- 129 -

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Land and Soil (Cont'd)

Land and Soil


(Cont'd)

The Site Engineer to

Daily

make

through

and
heavy

inspections
ensure

that

inspections
out

the

Construction Phase.

construction

Absence

of

Complaints

from

Contractor

caterpillar trampling

ZEMA

local

KML

in residential area

community

on

and cropland

invasion

of

the

equipment

is

settlements

and

confined

to

croplands

by

operational
only

and

areas

construction

avoids

equipment are non-

residential area and

existent.

cropland
The Site Engineer to

Daily

inspections

undertake inspection

through

of earthworks and

Construction Phase.

out

the

ensure that slopes


are

graded

to

specifications.

- 130 -

Absence
gullies

of

rills,

Absence of erosion

Contractor

features.

KML

Once earthworks are

Each

completed, the Site

earthworks

are

Engineer

completed

through

should

monitor

the

restoration measures

out

time

Construction

Phase

to be implemented
such

as

Presence

of

re-

Restoration

Contractor

vegetation in erosion

programme for re-

KML

prone areas.

vegetation

of

exposed

soils

is

available

and

is

being implemented.

re-

vegetation

- 131 -

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Vegetation
Site
Vegetation

Engineer

ensure

to
that

Each time clearance

The

of

Area for vegetation

Contractor

of

vegetation cleared is

clearance is clearly

ZEMA

minimal

marked

and

is

confined

to

the

vegetation

is

excessive clearance

being done through

of

out

vegetation

is

avoided and should

area

Construction

Phase

designs.

be confined to the
project site.
Wildlife and Wildlife Habitat
The Site Engineer to

Periodical

Absence of animal

Wildlife and Wildlife

carry out inspections

inspections through

damage to project

Habitat

and report evidence

out

site.

of wildlife intrusion

Phase

Construction

onto the project


Water Quality

- 132 -

Inspection report

Contractor
KML

Site
Water Quality

Engineer

to

Periodical

Clean water supply

Absence of water

Contractor

inspect and satisfy

inspections through

maintained through

pollution incidents

KML

that interceptors are

out the Construction

out the Construction

put in place and

Phase.

Phase.

working well.

- 133 -

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Water Quality (Cont'd)
Site
Water Quality
(Cont'd)

Engineer

Periodical

Clean water supply

Absence of water

Contractor

inspect and satisfy

inspections through

maintained through

pollution incidents

KML

that

where

out the Construction

out the Construction

liquids

Phase.

Phase.

Periodical

Clean water supply

Absence of water

Contractor

inspect and satisfy

inspections through

maintained through

pollution incidents

KML

that

out the Construction

out the Construction

Phase.

Phase.

Periodical

Clean water supply

Absence of water

Contractor

inspect and satisfy

inspections through

maintained through

pollution incidents

KML

that silt traps are put

out the Construction

out the Construction

along

Phase.

Phase.

areas

hazardous
are

to

stored

are

bunded.
Site

Engineer

water

concrete

to

from

batching

plants is treated.
Site

Engineer

to

drainage

systems;

- 134 -

Site

Engineer

Periodical

Clean water supply

Absence of water

Contractor

inspect and satisfy

inspections through

maintained through

pollution incidents

KML

that

out the Construction

out the Construction

Phase.

Phase.

Before construction

Construction is done

Pit latrine siting and

Contractor

of pit latrines.

according to design

construction report

KML

spoon

to

drains

have scour checks.


Site

Engineer

to

inspect and satisfy


that siting of pit
latrines
away

is

done

from

water

specifications.

logged areas;

- 135 -

Monitoring Activities and Indicator

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Water Quality (Cont'd)
Site

Engineer

to

Immediately there is

Operational

Presence

inspect and satisfy

a pollution incident

procedures are being

Operational Manual

Water Quality

that written detail of

during Construction

followed.

on site.

(Cont'd)

the procedures to be

Phase.

Regular inspections

Deposition of dust

Dust deposition on

Contractor

observe the level of

through

on surfaces such as

the

KML

dust

Construction Phase.

grasses, shrubs, trees

surroundings

during Construction.

and rooftops should

controlled.

Watering

down

decrease

should be done if

watering.

followed

in

of

Contractor
KML

the

event of pollution
incident is given to
the Site Engineer By
the Contractor.
Air Quality
Site

Air Quality

dust

Engineer

to

generated

levels

out

the

are

unacceptable.

- 136 -

with

immediate
is

Site

Engineer

to

Regular inspections

Exhaust

check and ensure

through

emissions

that

Construction Phase.

construction

vehicles

and

equipment

are

out

the

maintained in order
to reduce emission
of exhaust fumes;

- 137 -

controlled.

fume
are

Maintenance

Contractor

logbook is available

KML

on site.

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Air Quality (Cont'd)
Site
Air Quality

Engineer

Regular inspections

Unpleasant

inspect and ensure

through

are controlled.

that

Construction Phase.

toilets

cleaned

to

are

out

the

odours

Clean

toilet

environment
from

and

free

Contractor
KML

unpleasant

odours.

maintained to avoid
unpleasant odours.
Site

Engineer

Regular inspections

Controlled

inspect and ensure

through

disposal method.

waste is carefully

Construction Phase.

managed
disposed

to

out

the

and
of

in

designated places to
prevent

unpleasant

odours.
Noise

- 138 -

waste

Waste is dumped in

Contractor

designated places.

KML

Site
Noise

Engineer

to

Regular inspections

Noise levels at the

Number

monitor noise and

through

nearest

complaints of noise

vibrations on an ad-

Construction Phase.

out

the

hoc basis in order to


establish

minimised.

noise

levels at the project


site and the nearest
sensitive
and

receptors

should

receiver

not

exceed 90-decibels.

- 139 -

sensitive
are

disturbance
controlled.

of

is

Contractor
KML

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Noise (Cont'd)
Site

Engineer

to

Daily

inspections

Noise

check and ensure

through

Cont'd)

that working hours

Construction Phase.

out

the

are limited to day

Sleep disturbance is

Number

minimised.

complaints of sleep
disturbance
minimised.

light only;
Landscape and Aesthetics

- 140 -

of

is

Contractor
KML

Site
Landscape and
Aesthetics

Engineer

make

to

visual

inspection of earth

Daily
through

inspections
out

the

Construction Phase.

works to ensure that

reduced

are
to

Final landscape and

Contractor

aesthetic

KML

view

other

than those agreed


upon is not carried
out, particularly at
pit

sites,

temporary roads and


the

contractor's camp.

- 141 -

is

compatible with the


surrounding
environment.

excavation

around

alterations

minimum.

excessive

borrow

Landscape

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Land-use and surrounding environment
Contractor

shall

Before

Land-use and

ensure

that

local

Surrounding

people

with

Potential

Construction

planning for labour

construction

workers

requirements

shall

workers from the

recruited from the

Environment

necessary skills are

be done during the

local community are

local community

employed to work

Pre-Construction

identified.

on

Phase.

the

project

the

runway
to

migration

recruitment

avoid
and

settlement near the


airport

by

construction
workers

who

are

taken from far areas.

- 142 -

Contractor
are

KML

The Site Engineer to

Planning

for

monitor and ensure

detours,

that detours, access

roads and equipment

equipment park site

equipment park site

roads and equipment

park site location

location have taken

location are being

park site location

shall be done during

into

implemented

takes into account

the Pre-Construction

existing land use in

according

the existing land use

Phase.

settled areas

specifications.

access

in settled areas and


game park area

- 143 -

Designs for detours,

Designs for detours,

Contractor

access

access

KML

roads

account

and

the

roads

and

to

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Socio-economic Environment
Contractor

Socio-economic
Situation

shall

Planning

for

Programme

for

Target

group

for

Contractor

conduct and ensure

education both to

education both to

receiving education

KML

that

the

the

on

Local Community

education

is

construction

construction

STDs

and

given both to the

workers and local

workers and local

HIV/AIDS

construction

community on STDs

community on STDs

identified and the

workers and local

and HIV/AIDS shall

and HIV/AIDS is

programme is being

community on STDs

be done during the

developed

implemented during

and

Pre-Construction

the Pre-Construction

the

Phase.

Phase.

Phase.

HIV/AIDS

using aids such as


video

shows,

pamphlets, talks is
disseminated.

- 144 -

during

is

Construction

CBO

Site

Engineer

to

Planning

for

Black spot areas are

Warning signs and

Contractor

check and ensure

erection of warning

identified

for

speed retarders in

KML

that

signs in black spot

erection of warning

black spot areas and

Local Authority

areas

signs

pedestrian

DCA Safety Council

warning

adequate
signs

in

and

speed

and

speed

black spot areas and

retarders

at

retarders

and

are

speed retarders at

pedestrian crossing

included

in

the

site shall be done in

overall

the Pre-Construction

designs

Phase.

- 145 -

airport

constructed.

are

Monitoring Activities and Indicators


Method of Monitoring

Element to be

Frequency of

Indicator

Means of Verification

Authority Responsible

for

Shopping mall design,

Detours, access roads

of

which takes into account

and equipment park sites

KML

protection of Cultural

are constructed outside

NHCC

Monitoring

Monitored
Cultural and Historic Sites
Site Engineer to monitor

Planning

and ensure that detours,

construction

Cultural and Historic

access roads and

Sites

equipment park sites are

roads and equipment

and Historic Sites is

Cultural and Historic

not constructed near

park sites shall be

developed.

Sites during the

Cultural and Historic

done in the Pre-

Sites and other heritage

Construction Phase.

detours,

access

sites.
Human Settlements

- 146 -

Construction Phase.

Contractor

Site
Human Settlements

Engineer

to

Planning

for

Exploitation

of

inspect and satisfy

exploitation of water

water

that exploitation of

resources from the

from

the

local

water sources for

local

community

for

rehabilitation works

shall be done during

construction

is

the Pre-Construction

shopping

approval from the

Phase

controlled.

local authority and

consultation with the

with consent from

Local authority and

the

local community.

done

with

local

community

in

community.

- 147 -

resources

of

mall

is

Water

to

local

community

is

available.

Contractor
KML
Local Authority
Local community

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Human Settlements (Cont'd)
Site
Human Settlements
(Cont'd)

Engineer

to

Planning

for

Black spot areas are

Warning signs and

Contractor

check and ensure

erection of warning

identified

for

speed retarders in

KML

that

signs in black spot

erection of warning

black spot areas are

Local Authority

areas

signs

constructed.

adequate

warning

signs

in

and

speed

and

speed

black spot areas and

retarders

at

retarders

and

are

speed retarders at

crossing site shall be

included

in

the

pedestrian crossing

done in the Pre-

overall

site are erected in

Construction Phase.

designs

Planning

Shopping

airport

settlement areas
Quarries and Borrow Pits
Site
Quarries and Borrow
Pits

Engineer

to

monitor and ensure

exploitation

that

construction

quarries

and

for
of

Quarries and borrow

Contractor

design, which takes

areas

KML

into

account

outside

protection

of

resources catchment

located

the

water

materials

located near surface

quarries and borrow

water resources is

areas

water sources.

areas shall be done

developed.

Construction Phase.

the

Pre-

Construction Phase.

- 148 -

the

are

borrow areas are not

in

from

mall

during

the

Ministry of Mines

Site Engineer to monitor

Planning

and ensure that quarries

exploitation

and borrow areas are not

construction

located near Cultural and

materials

Historic Sites.

for

Airport design, which

Quarries and borrow

Contractor

of

takes into account

areas are located far

KML

conservation measures

away from Cultural and

Ministry of Mines

of Cultural and Historic

Historic Sites during the

NHCC

Sites is developed.

Construction Phase.

from

quarries and borrow


areas shall be done
in

the

Pre-

Construction Phase.

- 149 -

Monitoring Activities and Indicators

Element to be

Method of Monitoring

Frequency of

Indicator

Means of Verification

Authority Responsible

Monitoring

Monitored
Quarries and Borrow Pits
Site
Quarries and Borrow
Pits
(Cont'd)

Engineer

to

Planning

monitor and ensure

exploitation

that

construction

quarries

and

for
of

mall

Quarries and borrow

Contractor

design, which takes

areas are located far

KML

into

account

away from the local

Ministry of Mines

protection

of

community

Local Authority

borrow areas are not

materials

located

quarries and borrow

local community is

the

areas shall be done

developed.

Phase.

Operational Manual

Operational Manual

Contractor

nearby

communities.

in

the

from

Shopping

the

during

Construction

Pre-

Construction Phase.
Work Accidents
Site
Work Accidents

Engineer

to

Periodical

monitor and ensure

inspection

through

on Safety, Health

on Safety, Health

KML

that the procedures

out the Construction

and Environment for

and Environment for

Local Authority

on Safety, Health

Phase.

construction

construction

and Environment for

workers

construction

developed

workers are being

available on site.

followed during the

is
and

workers

- 150 -

being

implemented during
the
Phase.

Construction Phase.

is

Construction

Construction Camps
Site
Construction Camps

Engineer

to

Periodically through

Designated

monitor and ensure

out the Construction

disposal

that waste disposal

Phase.

identified

is

done

designated
approved

in

available.

sites
by

the

local authority and


ZEMA.

- 151 -

waste
site

is
and

Waste

is

being

dumped
designated sites.

in

Contractor
KML
Local Authority
ZEMA

Institutional Framework for Monitoring, Reporting & Supervision

1.1.76. Establishment of Collaborating Network


In order to ensure that the identified environmental issues are addressed both
during and after construction of the shopping mall there will be need by the
Kafubu mall limited to collaborate with key stakeholders. The collaborating
network should also involve representatives from the affected local authorities
( Ndola City Council), representatives of District Development Co-ordinating
Committees, representatives of CBOs in affected project area and
representatives of the Zambia Environmental Management Agency. The main
objective of this collaborating network is to ensure that the Contractor is
properly implementing mitigation measures outlined in the contracts and also
that Kafubu mall supervision is complemented by encouraging greater use of
local authorities and local community as part of project monitoring team. The
main responsibilities of the collaborating network will be to:

Complement the efforts for continuous monitoring and assessment of the


implementation of the environmental management plan by Kafubu mall
limited and other relevant institutions;
Assist in the sensitization of the local communities with regard to
environmental problems and their obligation;
Liaise with respective local communities on environmental issues which
may arise during the reconstruction and operation of the shopping mall.

1.1.77. Monitoring Arrangements


To avoid deliberate creation of gaps between what is reflected in the
mitigation plan and what actually gets implemented on the ground, the
contracts must spell out the sanctions for non-compliance with mitigation
measures. Monitoring will involve field visits by Kafubu mall limited staff
accompanied by representatives from the local authority in the affected area
being visited. The rationale to involve the local authority members in
monitoring in their area of jurisdiction is to ensure greater use and
participation of local community in project monitoring. This approach is also
- 152 -

to ensure that the particular project concerns expressed by the communities


during the public consultation meeting (EIA Scoping exercise) receive
attention in the project implementation.

1.1.78. Reporting Procedure and Flow of Information


The Kafubu Mall Limited will compile a quarterly Environmental Report from
the field visits that will form the basis for assessment of environmental
performance. The report will contain the results of the environmental
monitoring and the need for plan adjustment. The report will be circulated to
local authorities in the affected project areas and to other key stakeholders for
review and comment. If there are any comments from the stakeholders these
will be communicated to Kafubu shopping mall limited for possible follow up
and for possible corrective action to be undertaken by the Contractor. The key
stakeholders are outlined in Table 12.1 on Monitoring and Reporting
Responsibilities.

1.1.79. Construction Phase


All major stakeholders in the Project have a monitoring role and responsibility
during the construction phase. However, only the Consultant, the Zambia
environmental Management Agency (ZEMA), Kafubu Mall Limited are
allocated specific and formal monitoring obligations.

During the construction phase, Kafubu Mall Limited will ensure that the
contractor implement the mitigation measures recommended in the EIS.
Further, the Kafubu mall limited will ensure that construction workers are
sensitized with regard to environmental problems and their obligation. In
addition, Kafubu mall limited will liaise with respective government agencies
such as local authorities in the affected areas and Zambia Environmental
Management Agenc on environmental issues, which may arise during the
construction of the shopping mall phase.

Traffic police, RDA, Forestry Department, health authorities and other public
authorities will automatically monitor some of the effects of the Project during
their daily work. This information should on a regular basis be collected and
- 153 -

analysed by those with a formal monitoring responsibility such as the ZEMA


staff. The following table illustrates the different stakeholders and their
monitoring responsibilities and reporting.

Table 11: Monitoring and Reporting Responsibilities


RESPONSIBLE

PARAMETERS TO BE

ORGANISATION

MONITORED

ZEMA

Overall

OUTPUT

environmental

performance of the Project

Discussions

with

Kafubu mall limited/


Site Engineer

Kafubu

shopping

mall/contractor

Monitoring the implementation

Regular

of EMP

environmental

Overall

environmental

Construction

Engineer

materials
Implementation

methods

reports

to

stakeholders

performance of the Project


Contractor/Site

progress

and

Regular
environmental

of

mitigating

progress

reports

to

measures for air, water, soil,

ZEMA

traffic, Noise, vegetation, etc.

Incident reports as and

Environmental management of

when

worksites

(Pollution, accidents,

Environmental management of

etc.)

construction camps

shopping mall

Environmental management of
quarries and borrow pits
Contractors waste management
Rehabilitation
worksites

- 154 -

of

abandoned

required

by

Kafubu

Table on Monitoring and Reporting Responsibilities (Cont'd)


RESPONSIBLE

PARAMETERS TO BE

ORGANISATION

MONITORED

Contractor/Site

Performance

Engineer

equipment

of

OUTPUT

Contractors

Regular
environmental

Accidents

(traffic,

pollution

progress

reports

to

spills, etc.)

ZEMA

Community relations

Incident reports as and

Negative

social

and

when

required

environmental impacts

(Pollution, accidents,

Gender balance in employment

etc.) by Kafubun mall


limited

Contractor

Environmental performance of

Maintenance records

equipment

Accidents reports

Implementation

of

mitigating

measures

Mitigating actions
Log sheet records

Occupational health and safety


Traffic and worksite accidents
Air quality
ZEMA

Conducting spot checks on the

Instructions

to

the

impacts

Contractor

and

the

on

vegetation

and

wildlife

Consultant/Site
Engineer

NHCC

Impacts on Cultural and Historic

Instructions

to

the

Sites

Contractor

and

the

Consultant/Site
Engineer
Forestry Department

Impacts on vegetation and trees

Instructions

to

the

Contractor

and

the

Consultant/Site
Engineer
Traffic Police

Local authorities

Traffic accidents

Police

Traffic nuisances

instructions

Traffic safety measures

Contractor

Negative

social

environmental impacts

and

reports

Complaints
Contractor
Consultant/Site

- 155 -

and
to

to
and

Engineer

1.1.80. Operational Phase


The local authorities, ZEMA, the Forest Department, Department of
Agriculture, water affairs as well as the Road Development Agency should be
responsible for monitoring and management of all indirect impacts occurring
after the construction of the shopping mall .

It is proposed that a working relationship is established between ZEMA, the


local business associations and the mall user groups to ensure appropriate
accident monitoring during operational phase

- 156 -

Scheduling of Mitigation Measures and Monitoring of Performance

1.1.81. Table12 : Implementation Schedule of Mitigation Measures


IMPLEMENTATION SCHEDULLE OF MITIGATION MEASURES

YEAR 1

ACTIVITY

Q1

Implementation of Mitigation Measures for Impacts on Land and Soil


Construct concrete loading bay at petroleum products dispensing points
Construct concrete sealed surfaces for storage sites of oil, chemicals & other potential pollutants
Procure metal drums for collection and storage of used oil & lubricants
Construct reinforced concrete bund walls & slab around petroleum storage tanks.
Control soil erosion through tree/ grass planting and or stone pitching
Construct concrete headwalls, aprons and wing-walls to prevent soil erosion near culverts
Carry out linear maintenance of the culverts & drainage channels
Implementation of Mitigation Measures for Impacts on Vegetation
Control dust generation through watering of dust areas when levels exceed limits
Sensitize the communities around the project areas about the importance of forest conservation
Implementation of Mitigation Measures for Impacts on Wildlife and Wildlife Habitats
Identify borrow sites for gravel material outside game area to avoid loss of habitat
Erect warning signs in identified wildlife areas to warn users on the presence of wildlife
Erect speed humps in wildlife areas to limit speed
Implementation of Mitigation Measures for Impacts on Water Quality

- 157 -

Q2

Q3

YEAR 2

Q4

Q1

Q2

Q3

YEAR 3

Q4

Q1

Q2

Q3

Q4

Plant sides of runway drainage with grass or stone pitch to prevent siltation of nearby water
courses
Construct scour checks on drainage system using stone masonry

- 158 -

Table for Implementation schedule of Mitigation Measures (Cont'd)


IMPLEMENTATION SCHEDULLE OF MITIGATION MEASURES

YEAR 1

ACTIVITY

Q1

Implementation of Mitigation Measures for Impacts on Water Quality (Cont'd)


Construct silt traps along drainage channels
Identify pit latrine sites away from water sources & water logged areas
Implementation of Mitigation Measures for Impacts on Air Quality
Carry out regular maintenance of construction vehicles to control emission of exhaust fumes
Control dust emission through watering of dust areas when levels exceed limits
Control unpleasant odours by regular maintenance of pit latrines & solid waste disposal sites
Implementation of Mitigation Measures for Impacts of Noise
Ensure construction equipment working hours are limited to day light to avoid sleep disturbance
Implementation of Mitigation Measures for Impacts on Landscape and Aesthetics
Maintain areas of scenic view & avoid disfigurement of natural landscape & aesthetic view
Implementation of Mitigation Measures for Impacts on Land-use and surrounding environment
Employ local people with the necessary skills to avoid unplanned settlements from migrants
Construct detours, access roads in consultation with NCC,RDA and local community
Implementation of Mitigation Measures for Impacts on Socio-economic Environment
Sensitize the construction workers & local community on dangers of STDs and HIV/AIDS.
Employ local people with the necessary skills to avoid social upheavals
Erect DCA signs in settled areas to prevent fatal accidents
Implementation of Mitigation Measures for Impacts on Cultural and Historic Sites
Identify borrow sites for gravel material outside cultural and historic sites

- 159 -

Q2

Q3

YEAR 2

Q4

Q1

Q2

Q3

YEAR 3

Q4

Q1

Q2

Q3

Q4

Engage one NHCC Officer to work with the project in identified areas of cultural & historic sites

- 160 -

Table for Implementation schedule of Mitigation Measures (Cont'd)


IMPLEMENTATION SCHEDULLE OF MITIGATION MEASURES

YEAR 1

ACTIVITY

Q1

Implementation of Mitigation Measures for Impacts on Human Settlements


Construct detour & access roads outside human settlements
Provide speed retardars in settled areas
Install pedestrian crossing signs and corresponding signs in settled areas
Plant trees in settled project areas to control hazardous emissions from reaching the community
Install noise barriers in settled project areas
Implementation of Mitigation Measures for Impacts of Quarries and Borrow Pits
Select quarry and borrow pit areas outside wildlife areas
Select quarry and borrow pit areas outside cultural and historic sites
Select quarry and borrow pit areas away from human settlements
Select quarry and borrow pit areas away from water sources
Implementation of Mitigation Measures for Impacts of Road Traffic
Provide sufficient road signs to inform motorists of works animal corridors to avoid disruption to
traffic flow
Control dust levels by watering of detour and access roads to avoid disruption to traffic flow
Implementation of Mitigation Measures for Impacts of Construction Camps
Locate construction camps in liaison with the Ndola city council and local community
Identify site for disposal of solid waste in liaison with NCC and local community
Liaise with Local Authority & sensitize camp workers on dangers of STDs and HIV/AIDS.

- 161 -

Q2

Q3

YEAR 2

Q4

Q1

Q2

Q3

YEAR 3

Q4

Q1

Q2

Q3

Q4

1.1.82. Table for Implementation Schedule of Monitoring


MONITORING SCHEDULLE OF PERFORMANCE

YEAR 1

ACTIVITY

Q1

Observe the Performance of Mitigation Measures for Impacts on Land and Soil
Assess the condition of land and soil at storage sites with respect to soil contamination
Check for availability of designated dumpsites for disposal of construction wastes
Check for availability of metal drums for collection and storage of used oil & lubricants on site
Check for presence of concrete bund walls & slab around petroleum storage tanks on site
Check if there exist caterpillar trampling in croplands at project site
Check if there exist hills and gullies around the project site
Check for existence of re-vegetation programme in erosion prone areas
Observe the Performance of Mitigation Measures for Impacts on Vegetation
Assess the extent of vegetation clearance in project areas
Check for existence of awareness program for communities on importance of forest conservation
Observe the Performance of Mitigation Measures for Impacts on Wildlife and Wildlife Habitats
Check if there exist animal damage to project site
Check if there exist animal accidents in identified wildlife areas
Observe the Performance of Mitigation Measures for Impacts on Water Quality
Assess the quality of drinking water sources likely to be contaminated by project activities
Observe the Performance of Mitigation Measures for Impacts on Air Quality
Check for condition of dust level emissions and deposition on surrounding areas

- 162 -

Q2

Q3

YEAR 2

Q4

Q1

Q2

Q3

YEAR 3

Q4

Q1

Q2

Q3

Q4

Check for exhaust fume emission levels from construction vehicles and equipment
Check for condition of pit latrines & solid waste disposal sites

- 163 -

Table for Implementation Schedule of Monitoring (Cont'd)


MONITORING SCHEDULLE

YEAR 1

ACTIVITY

Q1

Q2

Observe the Performance of Mitigation Measures for Impacts of Noise


Check for existence of complaints of noise & sleep disturbance from communities at project site
Check if the hours of operation of construction equipment are limited to day light only
Observe the Performance of Mitigation Measures for Impacts on Landscape and Aesthetics
Check for the extent of landscape alterations and disfigurement of aesthetic view
Observe the Performance of Mitigation Measures for Impacts on Land-use and surrounding environment
Assess if constructed detours, access roads are in conflict with local community landuse interests
Observe the Performance of Mitigation Measures for Impacts on Socio-economic Environment
Check for existence of programs on STDs & HIV/AIDS for workers & local community
Assess No. of local people employed with necessary skills in relation to people from outside
Check for existence of road signs in settled areas that prevent fatal accidents
Observe the Performance of Mitigation Measures for Impacts on Cultural and Historic Sites
Assess the location of borrow pits for gravel material in relation to cultural and historic sites
Check for presence of NHCC Officer working on the project in areas of cultural & historic sites
Observe the Performance of Mitigation Measures for Impacts on Human Settlements
Check if there exist shortage of water resources for community due to exploitation for shopping
mall works
Assess location of constructed detour & access roads in relation to human settlements
Check for existence of speed retardars in human settlement areas

- 164 -

Q3

YEAR 2

Q4

Q1

Q2

Q3

YEAR 3

Q4

Q1

Q2

Q3

Q4

Check for existence of tree planting programs in human settled areas to control emissions
Check for existence of noise barriers in human settlement areas

- 165 -

Table for Implementation Schedule of Monitoring (Cont'd)


MONITORING SCHEDULLE

YEAR 1

ACTIVITY

Q1

Observe the Performance of Mitigation Measures for Impacts of Quarries and Borrow Pits
Assess the location of quarry and borrow pit areas in relation to wildlife areas
Assess the location of quarry and borrow pit areas in relation to cultural and historic sites
Assess the location of quarry and borrow pit areas in relation to human settlements
Assess the location of quarry and borrow pit areas in relation to drinking water sources
Observe the Performance of Mitigation Measures for Impacts of Road Traffic
Check if exist traffic congestion at project site due to insufficient signs & alternative routes
Check for existence of traffic accidents due to high dust levels & lack of detour and access roads
Observe the Performance of Mitigation Measures for Impacts of Work Accidents
Check for existence of programs & adherence to procedures on Safety, Health and Environment
Check if there exist work accidents at project sites
Observe the Performance of Mitigation Measures for Impacts of Construction Camps
Check if the local community was consulted over workers camp siting
Check if the local community was consulted over waste disposal siting
Check for existence of programs to sensitize camp workers on dangers of STDs and HIV/AIDS.

- 166 -

Q2

Q3

YEAR 2

Q4

Q1

Q2

Q3

YEAR 3

Q4

Q1

Q2

Q3

Q4

CONCLUSIONS AND RECOMMENDATIONS


Conclusions
The findings from the Environmental Impact Assessment show that although
the proposed shopping mall is expected to have a number of negative impacts
on the environment, most of these are anticipated to occur during the
construction phases and are mitigated in the overall shopping mall design.
Generally, the proposed shopping mall is planed to follow most efficient
environmental management systems thus the potential impacts are therefore
reduced.
Recommendations
The study has proposed an Environmental Management and Monitoring Plan
(EMP) to addres the management of the identified environmental issues
associated with the project .The plan consists of implementing the listed
components stated below as follows:

1. Implementing the Impact Mitigation Plan


2. Monitoring the implementation of the EMP
3. Institutional Framework for Monitoring, Reporting and Supervision of
EMP

The mitigation of the negative impacts on biophysical environment will be


part of the shopping mall design. The negative social impacts will require
some level of intervention as outlined below:

Improvement and expansion of social facilities and services


Collaboration with local stakeholders to counter social upheavals
Sex education campaigns to fight HIV/AIDS threats
Provision of alternative social services, facilities and jobs for local people
affected by the project.

- 167 -

The mitigation measures will require constant information flow and


consultation with the stakeholders to ensure the least adverse social-economic
impact from the project. The project area of influence outweigh the nodevelopment scenario. The project is therefore being recommended for
implementation assuming the incorporation of the recommended mitigating
measures and implementation of the Impact Mitigation Plan.

- 168 -

Appendix 1: List of People Met/ Consulted

- 169 -

Appendix 2: Checklist
MONITORING AND SUPERVISION CHECKLIST
PROJECT SITE/LOCATION :.. DISTRICT:

FORM A.

MITIGATION MEASURES REQUIRED & AGREED

AGREED MITIGATION MEASURES/

RESPONSIBILITY FOR

ACTIVITY TO BE PERFORMED

IMPLEMENTATION

1. LAND & SOIL

1.1
1.2
1.3
etc
2. VEGETATION
2.1
2.2
2.3
etc
3. WILDLIFE & WILDLIFE HABITAT
3.1

- 170 -

PHYSICAL PROGRESS ON IMPLEMENTATION

>75%

75% - 55%

55% - 45%

<45%

Good

Average

Fair

Poor

3.2
3.3
etc
4. WATER QUALITY
4.1
4.2
etc
5. AIR QUALITY
5.1
5.2
etc

- 171 -

MONITORING AND SUPERVISION CHECKLIST


PROJECT SITE/LOCATION :.. DISTRICT:
MITIGATION MEASURES REQUIRED & AGREED (Cont'd)

AGREED MITIGATION MEASURES/

RESPONSIBILITY FOR

ACTIVITY TO BE PERFORMED

IMPLEMENTATION

6. NOISE

6.1
6.2
6.3
etc
7. LANDSCAPE & AESTHETICS
7.1
7.2
7.3
etc
8. LAND--USE & SURROUNDING ENVIRONMENT
8.1
8.2
8.3

- 172 -

PHYSICAL PROGRESS ON IMPLEMENTATION

>75%

75% - 50%

55% - 45%

< 45%

Good

Average

Fair

Poor

etc
9. SOCIO-ECONOMIC ENVIRONMENT
9.1
9.2
9.3
etc
10. CULTURAL & HISTORIC SITES
10.1
10.2
10.3
etc

- 173 -

MONITORING AND SUPERVISION CHECKLIST


PROJECT SITE/LOCATION :.. DISTRICT:
MITIGATION MEASURES REQUIRED & AGREED (Cont'd)

AGREED MITIGATION MEASURES/

RESPONSIBILITY FOR

ACTIVITY TO BE PERFORMED

IMPLEMENTATION

11. HUMAN SETTLEMENTS

11.1
11.2
11.3
etc
12. QUARRIES & BORROW PITS
12.1
12.2
12.3
etc
13. ROAD TRAFFIC
13.1
13.2
13.3

- 174 -

PHYSICAL PROGRESS ON IMPLEMENTATION

>75%

75% - 50%

55% - 45%

< 45%

Good

Average

Fair

Poor

etc
14. WORK ACCIDENTS
14.1
14.2
14.3
etc
15. CONSTRUCTION CAMPS
15.1
15.2
15.3
etc

- 175 -

MONITORING AND SUPERVISION CHECKLIST


PROJECT SITE/LOCATION :.. DISTRICT:

FORM B:

PERFORMANCE OF MITIGATION MEASURES OBSERVED

AGREED MITIGATION MEASURES/

CONSTRAINTS/DIFFICULTIES OF

OBSERVED LEVEL OF PERFORMANCE

IMPLEMENTATION

GOOD

FAIR

POOR

1. LAND & SOIL


1.1
1.2
1.3
etc
2. VEGETATION
2.1
2.2
2.3
etc
3. WILDLIFE & WILDLIFE HABITAT
3.1
3.2
3.3

- 176 -

AGREED FOLLOW UP ACTIONS

etc
4. WATER QUALITY
4.1
4.2
4.3
etc
5. AIR QUALITY
5.1
5.2
5.3
etc

- 177 -

MONITORING AND SUPERVISION CHECKLIST


PROJECT SITE/LOCATION :.. DISTRICT:
PERFORMANCE OF MITIGATION MEASURES OBSERVED (Cont'd)

AGREED MITIGATION MEASURES/

CONSTRAINTS/DIFFICULTIES OF

OBSERVED LEVEL OF PERFORMANCE

IMPLEMENTATION

GOOD

FAIR

POOR

6. NOISE
6.1
6.2
6.3
etc
7. LANDSCAPE & AESTHETICS
7.1
7.2
7.3
etc
8. LAND-USE & SURROUNDING ENVIRONMENT
8.1
8.2
8.3

- 178 -

AGREED FOLLOW UP ACTIONS

etc
9. SOCIO-ECONOMIC ENVIRONMENT
9.1
9.2
9.3
etc
10. CULTURAL & HISTORIC SITES
10.1
10.2
10.3
etc

- 179 -

MONITORING AND SUPERVISION CHECKLIST


PROJECT SITE/LOCATION :.. DISTRICT:
MITIGATION MEASURES REQUIRED & AGREED (Cont'd)

AGREED MITIGATION MEASURES/


ACTIVITY TO BE PERFORMED

GOOD

FAIR

RESPONSIBILITY FOR IMPLEMENTATION

POOR

11. HUMAN SETTLEMENTS


11.1
11.2
11.3
etc
12. QUARRIES & BORROW PITS
12.1
12.2
12.3
etc
13. ROAD TRAFFIC
13.1
13.2
13.3

- 180 -

PHYSICAL PROGRESS ON IMPLEMENTATION

etc
14. WORK ACCIDENTS
14.1
14.2
14.3
etc
15. CONSTRUCTION CAMPS
15.1
15.2
15.3
etc

- 181 -

MONITORING AND SUPERVISION CHECKLIST


PROJECT SITE/LOCATION :.. DISTRICT:

FORM C:

COMMENTS ON ANY UNFORESEEN ENVIRONMENTAL PROBLEMS

ENVIRONMENTAL ISSUES

PROPOSED ACTION

1.

2.

3.

4.

5.

6.

7.

8.

- 182 -

RESPONSIBILITY

9.

10.

etc

- 183 -

You might also like