You are on page 1of 6

Building a

new substation

Building for the future


Key Points
P
 rior to the construction of a new substation, What is a substation?
we complete a State Government-approved A Powerlink substation is normally a fenced facility
process under the Sustainable Planning Act connected to transmission lines that contains electrical
2009 (SPA), which includes comprehensive equipment and ancillary buildings. Some substations convert
high voltage electricity down to a lower level so it can be
environmental impact assessments and delivered to the distribution networks owned by Energex
associated community consultation. and Ergon Energy. Other substations connect power stations
and industrial customers or control the flow of electricity on
P
 owerlink works closely with affected the transmission lines forming the States transmission grid.
landowners both before and throughout
A substation is a key part of the transmission network
construction to help minimise any impacts. in addition to transforming voltages, it measures and
P
 owerlink is committed to ensuring we controls the flow of electricity on the grid, and switches
transmission lines on and off to enable maintenance to
meet our environmental obligations be undertaken safely and to protect the network from
all construction work is carried out in electrical faults or equipment failure.
accordance with an Environmental Impact Powerlinks high voltage substations are much larger than
Statement (EIS) and an Environmental the distribution substations operated by Energex and Ergon
Management Plan (EMP) which outlines Energy. This is because the equipment used in a high voltage
strategies and actions to manage any potential environment is typically much larger and requires more
space than lower voltage equipment.
environmental and community impacts.
In many instances, a Powerlink substation will contain
equipment owned by both Powerlink and the local
distributor, so that Energex or Ergon Energy can access
the power and distribute it to the local community.

Its important to remember that substations are not power


stations they do not generate electricity.

This information sheet refers to building a new substation,


however similar activities may be undertaken to rebuild or
refurbish existing substations. The information provided is
intended as a guide only.

2 Building a new substation


A typical substation Working with our environment
While substations vary in design, they have a number of Powerlink follows a State Government-approved process
common features including: under the Sustainable Planning Act 2009 (SPA) when planning
a new substation. Under this process, a comprehensive
Transformers are one of the most integral pieces of
environmental study is undertaken once a site is selected.
substation equipment. They transform electricity from
Community members and interest groups are invited to
high voltages down to levels suitable for large industrial
be involved with this process at an early stage. An
customers or distribution networks that ultimately
Environmental Impact Assessment (EIA) helps ensure any
supply businesses and households.
potential environmental, community or economic impacts
Circuit breakers are switches which can be used to associated with the project are identified and managed. It
interrupt the flow of electricity. They can be used during includes desktop studies, field studies, consultation and the
maintenance to disconnect parts of the substation and preparation of an Environmental Impact Statement (EIS).
allow work to safely take place.
The EIS is a formal report that examines the environmental,
Busbars transfer the electricity within the substation community and economic aspects of a project and identifies
from the wires that feed into the substation and the ways to manage any impacts. A Draft EIS is released for
powerlines leading out of the substation. community feedback prior to the Final EIS being developed.
Protection equipment monitors the amount of This work results in an Environmental Management Plan (EMP)
electricity flowing through substations and powerlines. being developed, which outlines the actions we will take to
All Powerlink substations include protection systems that reduce any impacts identified in the EIS.
detect unexpected electrical faults on the transmission All construction works are carried out in accordance with
network and automatically isolate the affected equipment. the EIS and EMP to mitigate and manage any potential
This allows us to manage and rectify unexpected faults. environmental or community impacts.
Earth grid are wires buried just underneath the ground
An Environmental Officer is also appointed to every project
to ensure the equipment is earthed. You cant see the grid,
to ensure that Powerlink meets its environmental obligations.
but its an integral part of the substations safety system.
For detailed information about this process, please see
Planning a new substation our information sheet Consultation and Environmental
Impact Assessments.
Powerlink, in consultation with Energex and Ergon Energy,
undertakes annual planning for the electricity network. Our
planning considers whether new substations are required to
reinforce the main transmission grid or to reliably meet the
population growth and demand forecasts in particular areas.
Once a need has been identified, we begin work as early as
practicable to select a site. This provides advance notice of our plans
to landowners, councils, developers and government departments.
We also acquire land for substations, often by purchasing the site
outright from the owner. In these cases ownership of the land
transfers to Powerlink.
In addition to constructing a new substation, from time-to-time
we carry out construction work to replace ageing substations.

3
Constructing a substation
Generally the construction of a substation can take one 3. Assembling equipment
to two years depending on its size. The level and type During this period, the electrical equipment is installed and the
of construction activity and equipment used may vary as ancillary buildings that house control equipment are erected.
construction progresses.
Several steel lattice towers may be erected using cranes and
Work is normally carried out by Powerlinks contractors. elevated work platforms. These towers support the wires
Powerlinks Construction Inspectors will also be on-site to from the transmission lines that connect to the substation.
ensure the work is performed to contract specifications. Internal roads are sealed and a road base is laid on the
remainder of the substation site.
The contractors Site Supervisor is in charge of the
construction and safety on site. For safety reasons, only Heavy equipment such as high voltage transformers may be
authorised Powerlink people and our contractors are delivered at this time. These transformers are very large,
allowed to enter the substation site. weighing hundreds of tonnes and measuring around 20m long,
5m wide and 8m high. Because of their size, transport can be
1. Preparing the site
slow. Delivery is often completed early or late in the day when
Site preparation involves: there is less traffic on the road. This stage can take around
Marking the boundary of the substation site and erecting eight to 12 weeks.
safety fences.
4. Testing and commissioning the substation
Removing any vegetation as necessary.
A series of thorough inspections and commissioning tests are
Levelling and possibly raising the site and compacting
carried out before the substation is put into service. This stage
soil if required.
can take around six to 10 weeks.
Excavating drains if needed.
5. Reinstating the site
Stabilising any new embankments (batters).
The substation site will be left tidy and embankments and
These activities may create some temporary noise and dust. other areas around the fence lines reinstated where necessary.
However, we endeavour to limit this activity to times when Further rehabilitation or revegetation may also be completed.
neighbours will be least affected. This stage can take around This stage typically takes around two to four weeks.
eight to 12 weeks.
6. Maintaining the substation
2. Installing foundations
Powerlink will maintain the substation to ensure its reliability
Usually, a large excavator or boring machine is used to create and safety. An annual review is generally conducted and any
foundations. Concrete is poured and left to cure and the maintenance is carried out as required.
foundation is completed. Trenches and roadways will also
be excavated during this stage. This stage can take around The life of a substation is about 40 to 50 years. Replacement
eight to 10 weeks. Following the completion of this stage, and refurbishment work may need to be completed from
heavy excavation vehicles and equipment are no longer time-to-time. This may be as simple as replacing some ageing
required on-site and the potential for disruption from noise equipment over several days or weeks, or rebuilding certain
or dust is reduced. sections of the substation which could take several months.

At times, we may need to work outside of normal work hours to


undertake essential maintenance or respond during an emergency.
Measures will be taken with lighting and noise to minimise
disruption to our neighbours during any out of hours work.

4
Explanations and frequently used terms
Substation Environmental Management Plan (EMP)
The role of a substation is to monitor and control the flow, An Environmental Management Plan (EMP) documents
stability, quality and voltage of electricity on the transmission the actions Powerlink will take to manage and minimise
lines connected to the facility. Equipment located within the environmental and social impacts that might result from the
substation is used to transform the voltage of electricity, design, construction or operation of the transmission line.
protect the network, measure the flow of the electricity, The EMP is developed as part of the Environmental Impact
and switch electricity between the different transmission lines Statement (EIS).
and transformers on the grid. A substation is not a power
Sustainable Planning Act 2009 (SPA)
station it does not generate electricity.
The Sustainable Planning Act 2009 (SPA) is legislation which
Transmission line seeks to manage the process and effects of developments
A transmission line is a powerline which is capable of carrying and ensure coordination and integration of local, regional
large amounts of electricity at high voltages. Transmission and state planning.
lines are larger and taller than the everyday distribution
powerlines which deliver electricity to your home and business.
Transmission lines are normally built on tall steel towers or
concrete and steel poles.

Environmental Impact Assessment (EIA)


An Environmental Impact Assessment (EIA) is the process
to ensure any potential environmental, community or economic
impacts associated with the project are identified and managed.

Environmental Impact Statement (EIS)


The written report that is produced as part of the EIA process.
An Environmental Impact Statement (EIS) examines the
environmental, community and economic aspects of proposed
projects and identifies ways to manage any impacts. The EIS
is an important part of Powerlinks consultation process and
is advertised for public comment. Included in the EIS is an
Environmental Management Plan (EMP).

5 Building a new substation


About Us More Information
Powerlink Queensland is a State Government Owned Other useful guides can be accessed from
Corporation which owns, develops, operates and maintains www.powerlink.com.au including:
the high voltage transmission network in Queensland. C
 onsultation and Environmental
Our network of high voltage substations and transmission lines Impact Assessments
extends 1,700km from Cairns to the New South Wales border Understanding designation for transmission
approximately half of Australias eastern seaboard. line infrastructure
U
 nderstanding resumptions for transmission
Powerlinks transmission network is the central link in the
line infrastructure
electricity supply chain, transporting electricity from power
stations where it is generated, to distributors Energex, Ergon Maintaining our network and easements
Energy and Essential Energy that deliver electricity to around
two million customers. Contact Us
Powerlink also transports electricity directly to industrial Call FREECALL 1800 635 369
customers and to New South Wales via the Queensland/New (during business hours)
South Wales Interconnector transmission line. Email us at
Powerlink does not generate or buy or sell electricity we simply website.enquiries@powerlink.com.au
transport it in bulk from wherever it is generated across Visit www.powerlink.com.au, or write to:
our high voltage transmission network to where it is needed.
Network Property
For more information see our About Powerlink Queensland
Powerlink Queensland
information sheet.
PO Box 1193
Important note: The contents of this information sheet are current at the time of print and are VIRGINIA QLD 4014
indicative only. Powerlink reserves the right to change its policies and procedures from time
to time. Before relying on this information you should contact Powerlink to check whether it
is still current.

Printed on Monza Recycled 30% pre-consumer, 25% post consumer waste and 45% forest
managed fibre. Created by a mill that is 100% energy self-sufficient. Monza Recycled is Certified
Carbon Neutral by The Carbon Reduction Institute (CRI) in accordance with the global
Greenhouse Protcol and ISO 14040 framework.

Version May 2012

You might also like