Professional Documents
Culture Documents
Building A New Substation PDF
Building A New Substation PDF
new substation
3
Constructing a substation
Generally the construction of a substation can take one 3. Assembling equipment
to two years depending on its size. The level and type During this period, the electrical equipment is installed and the
of construction activity and equipment used may vary as ancillary buildings that house control equipment are erected.
construction progresses.
Several steel lattice towers may be erected using cranes and
Work is normally carried out by Powerlinks contractors. elevated work platforms. These towers support the wires
Powerlinks Construction Inspectors will also be on-site to from the transmission lines that connect to the substation.
ensure the work is performed to contract specifications. Internal roads are sealed and a road base is laid on the
remainder of the substation site.
The contractors Site Supervisor is in charge of the
construction and safety on site. For safety reasons, only Heavy equipment such as high voltage transformers may be
authorised Powerlink people and our contractors are delivered at this time. These transformers are very large,
allowed to enter the substation site. weighing hundreds of tonnes and measuring around 20m long,
5m wide and 8m high. Because of their size, transport can be
1. Preparing the site
slow. Delivery is often completed early or late in the day when
Site preparation involves: there is less traffic on the road. This stage can take around
Marking the boundary of the substation site and erecting eight to 12 weeks.
safety fences.
4. Testing and commissioning the substation
Removing any vegetation as necessary.
A series of thorough inspections and commissioning tests are
Levelling and possibly raising the site and compacting
carried out before the substation is put into service. This stage
soil if required.
can take around six to 10 weeks.
Excavating drains if needed.
5. Reinstating the site
Stabilising any new embankments (batters).
The substation site will be left tidy and embankments and
These activities may create some temporary noise and dust. other areas around the fence lines reinstated where necessary.
However, we endeavour to limit this activity to times when Further rehabilitation or revegetation may also be completed.
neighbours will be least affected. This stage can take around This stage typically takes around two to four weeks.
eight to 12 weeks.
6. Maintaining the substation
2. Installing foundations
Powerlink will maintain the substation to ensure its reliability
Usually, a large excavator or boring machine is used to create and safety. An annual review is generally conducted and any
foundations. Concrete is poured and left to cure and the maintenance is carried out as required.
foundation is completed. Trenches and roadways will also
be excavated during this stage. This stage can take around The life of a substation is about 40 to 50 years. Replacement
eight to 10 weeks. Following the completion of this stage, and refurbishment work may need to be completed from
heavy excavation vehicles and equipment are no longer time-to-time. This may be as simple as replacing some ageing
required on-site and the potential for disruption from noise equipment over several days or weeks, or rebuilding certain
or dust is reduced. sections of the substation which could take several months.
4
Explanations and frequently used terms
Substation Environmental Management Plan (EMP)
The role of a substation is to monitor and control the flow, An Environmental Management Plan (EMP) documents
stability, quality and voltage of electricity on the transmission the actions Powerlink will take to manage and minimise
lines connected to the facility. Equipment located within the environmental and social impacts that might result from the
substation is used to transform the voltage of electricity, design, construction or operation of the transmission line.
protect the network, measure the flow of the electricity, The EMP is developed as part of the Environmental Impact
and switch electricity between the different transmission lines Statement (EIS).
and transformers on the grid. A substation is not a power
Sustainable Planning Act 2009 (SPA)
station it does not generate electricity.
The Sustainable Planning Act 2009 (SPA) is legislation which
Transmission line seeks to manage the process and effects of developments
A transmission line is a powerline which is capable of carrying and ensure coordination and integration of local, regional
large amounts of electricity at high voltages. Transmission and state planning.
lines are larger and taller than the everyday distribution
powerlines which deliver electricity to your home and business.
Transmission lines are normally built on tall steel towers or
concrete and steel poles.
Printed on Monza Recycled 30% pre-consumer, 25% post consumer waste and 45% forest
managed fibre. Created by a mill that is 100% energy self-sufficient. Monza Recycled is Certified
Carbon Neutral by The Carbon Reduction Institute (CRI) in accordance with the global
Greenhouse Protcol and ISO 14040 framework.