Tanks Installation Manual PDF
Tanks Installation Manual PDF
PETROCHEMICAL
C2+ RECOVERY AND
NARGAN COMPANY
FRACTIONATION PLANT
Linde Project No.: 21101055 NARGAN Proj-No.: N-178 Owner Project No.: 3910
Linde Job Code: Asaluye NARGAN Job Code: Owner Job Code: PPC-RFP
Linde Doc. No.: BMM50005 Owner Doc. No.: 10-VD-A4-PV-014-084-L
Installation Manual
TP-000-16
(Page 1-32)
and
attachment:
Welding Sequence Bottom and Shell
(Page 1- 13)
and
attachment:
Assembly Procedure of Erection Openings
(Page 1- 3)
Tk-No. 10-TK-0661-Propane
Tk-No. 10-TK-0662-Butane
X Ray 25%
min 150mm
150 Reference:
Anchor straps Drawing Inner Tank No: 19
Leveling course Outer Tank No: 18
Bottom of outer tank No: 07
Outer tank
Outer tank bottom
annular plate
about 100
course 2
Welding of outer tank shell course 2 vertical weld seams
353 and horizontal weld seam acc. to applicable WPS,
Inspection: Visual, 100% X-Ray vertical joints,
350 100% X-Ray of all intersections of joints, Spot X-Ray and
Magnetic-Particle Examination of horizontal joints as per T.i.P ( TP-000-06 )
188 course 1
min. 300
891
1100
Step 2
1388
X Ray 25%
min 150mm
Distance between the top of O.T 2.) inner tank shell 3.) inner tank shell course 1 with annular plate tack weld
annular plate to the below of 1.) inner tank annular plate course 1
I.T.annular plate = 450mm
see Drawing No.T-0661-01
45,00 m radius
bracket U 300
1200
45
collumns HEB 140
50 365
RAFTER
6633
365 25
R= 19100 30
RAFTER R = 2325 5.686
6.789
A
top of O.T.Shell top of O.T.Shell
26.200 8123 26.200
1.468 24.732
6
R=
18.050 1050
R= 19.100
Outer Tank
0
A
1 / 18 segment of
suspended deck
and 3 x raffters
270
A
90
180
SECTION A - A
1 / 18 segment of
suspended deck
Hangers only for erection
1 / 18 segment of
suspended deck
8123 R= 10.978
A section A-A
2444 RAFTER 271
50 299 2026
RAFTER
6633 365
2444
top of Roof 271
RAFTER
R = 1050 31.911
25
365
2444
RAFTER R = 2325 5.686
A R= 8.033 6.789
R=
21006 2.000
top of O.T.Shell IPE 300=229
26.200 IPE 360=281 top of O.T.Shell
65 IPE 500=404 26.200
52 1.533
123 1.468 24.732
18.050
R= 6.000
R= 19.100 1050
Outer Tank
suspended deck
Errection of outer tank roof rafters with
segment of suspended deck stay rope
3 rafters with (3) =
1/18 suspended deck
6 8
3 rafters with (3) =
1/18 suspended deck
4 3
5
7 3 rafters with (3) =
1/18 suspended deck
1
3 Rafters = 1 / 18
Note to Field:
Use Leftover from
Field Cutting Sketch
drawing no.-30
15mm
Hydraulic press
only to removal the
supports
Remove annular plate support blocks
wood cotter
60
wood cotter
40 40 x 60 x 480
30
505 Stck pro Tank
480
60
wood cotter
60 70 x 60 x 500
70
505 Stck pro Tank
500
crack / round 10 - 30 mm
Suspension cable
Erection
Chain hoist
opening
monorail
Complete installation of bottom
insulation and sand layer
Hydro-water-test
Welding of inner tank anchors
to be done during partial water filling of
inner tank (see Drawing No. 19), but
before applying any air pressure.
Hight Level of water filling see
HPT- TP-000-08
acces openig
Blinds to be provided
at Site by Others
Over pressure
Under pressure
welding of erecting
Closing of access opening at outer tank shell. opening and he rest of
Welding acc. To applicable WPS outer tank anchor strabs.
Inspection acc. To T.i.P. (TP-000-06) before applying any over
visual; 100% X-Ray; 100% Vacuum-Box-Test pessure !
Blinds to be provided
at Site by Others
Over pressure
after over pressure test
Under pressure open the erection
opening.
Erecting opening
Before painting :
Draining and cleaning of the
inside of tanks.
erecting oppening.
one roof plate
PU - Insulation at inside of
outer tank shell
after PU - Insulation
erretion of piping in shell
After PU - Insulation
annular space on wood
close the erretion
opening
welding acc.
TIP -TP-000-06 WPS
100% X Ray and
visual,vacuum
PU - Insulation at inside of
outer tank shell in part of
errection opening
Insulation of suspended
deck
8,000 m
Top of roof
32,000 m
5,000 m
stay rope
max
5,00 tonns
6
8
4
3
7
5
1
0
max weight is shell
plate course 1 outer
Hangers for
suspended deck
5000 5000
0
2026 9820 9156
1 / 18 segment of A
suspended deck
and 3 x raffters
centroid
150
A
270 90
150
180
centroid
SECTION A - A
1 / 18 segment of
suspended deck
Hangers only for erection
1 / 18 segment of
suspended deck
8123 R= 10.978
A section A-A
2444 RAFTER 271
50 299 2026
RAFTER
6633 centroid susp. 365
2444
top of Roof 271
RAFTER
150 R = 1050 31.911
25
365
2444
RAFTER R = 2325 5.686
centroid raffters
A R= 12.085 6.789
18.050
R= 6.000
R= 19.100 1050
Outer Tank
1. The erecting opening at the Inner and Outer Tank Shell will be installed during
the fabrication of the Inner and Outer Tank Shell.
1
2. Before start up with the hydrotest of the Outer Tank, the erection opening
will be closed, completely welded and NDE tested. 1 2
3. At hight water level of the Outer Tank ( 20.374 mm ), the anchor straps of
the Outer Tank will be welded and NDE - tested, without three or four
3
anchor straps
10 4. In this area a second erection opening has to be installed at the Outer Tank 1
Shell, after the Tank was emptied.
5. Before filling the Inner Tank with water, the erection opening at the Inner Tank
Shell has to be closed and NDE-work should be carried out satisfactory.all 4
6. Thereafter, close the second erection opening and carry out all NDE-work.
7. Before start up with the Pneumatic Test, welding and testing of the three or
four anchor staps shall be finished. 5
8. The anchor straps of the Inner Shell shall be welded, when the Inner Tank
is emptied up to a water filling height of 7.366 mm.
9. A third erection opening at the Outer Tank Shell and additional an erection
opening at the roof is required, to place the insulation.
7 6
10. At the least, when all the work is finished, the third erection opening at the Outer
Tank Shell and the additional erection opening at the roof shall be closed and
8
8 NDE tested.
9 10 9
10
175
500 / 600
15
450 350
85
35 180 300 35
60 100
100 x 50 x 10
60 270
5 5
8,0mmx60x500 5 25 20
500
50
20
60 20
70
5,0mmx60x500
40
60 50
30
60 60
Linde Project No.: 2110 1055 NARGAN Project No.: N-178 Owner Project No.: 3910
Linde Job Code: Asaluye NARGAN Job Code: Owner Job Code.: PPC-RFP
Linde Doc. No.: Owner Doc. No.:
Page 1 of 13
Installation Manual
TP-000-16
attachment:
Welding Sequence Bottom and Shell
(Page 1 13)
10-TK-0661
and
10-TK-0662
CONTENTS Page
1. Scope 3
3. Outer Bottom 3
4. Outer Shell 4
5. Inner Shell 4
6. Inner Bottom 5
7. Remarks 5
Attachment No. 1 6
Attachment No. 2 7
Attachment No. 3 8
Attachment No. 4 9
Attachment No. 5 10
Attachment No. 6 11
Attachment No. 7 12
Attachment No. 8 13
ASALUYE C2+ RECOVERY AND FRACTIONATION PLANT
Process Engineering and
Contracting Division
attachment:
Welding Sequence Bottom and Shell
PARS
a d a p t Ref.: a d a p t Doc. No. :
Issue 1 Petrochemical
P 01-1021, Company
Rev. 2 attachment to TP-000-16 Page 3 of 13
1.0 Scope
This specification shall be used to minimize deviation to flatness.
e) At least weld closing seams of the bottom from centre to outside (attachment 8)
f) The connection between the annular plates and the bottom plates shall not be
tacked, only wedged, will be welded after the bottom is completely welded.
Start with welding the seam bottom to annular plate on at least four places. If it is
necessary and possible, back step welding shall be used (attachment 7).
7.0 Remarks
The welding supervisor shall observe the welding and may change the sequence of
welding, if necessary.
PARS
Process Engineering and
ASALUYE
Contracting Division Petrochemical
C2+ RECOVERY AND
NARGAN FRACTIONATION PLANT Company
COMPANY
Linde Project No.: 2110 1055 NARGAN Project No.: N-178 Owner Project No.: 3910
Linde Job Code: Asaluye NARGAN Job Code: Owner Job Code.: PPC-RFP
Linde Doc. No.: Owner Doc. No.:
Page: 1 of 3
Installation Manual
TP-000-16
attachment:
Assembly Procedure of Erection
Openings
(Page 1 3)
10-TK-0661
and
10-TK-0662
1.0 Scope
This procedure shall help to install the plates of the erection openings.
The outer Shell shall not be out of permitted roundness.
All cutting and welding shall be carried out under the responsibility of a supervisor
(welding expert), who has good experience and knowledge.
2.0 Before start up with cutting, mark the correct position of the erection opening.
4.0 Fix a horizontal beam above the opening with a radius of the outer shell
(see drawing T-0661-22).
5.0 Cut off the plate with a small cutting nozzle, to be sure to get a small gap. The kerf should
not be more than 3 mm. The edges shall be round.
6.0 Before fit up the plate, the joint preparation has to be carried out by grinding (Joint pre-
paration for vertical and horizontal weld joints, see drawing T-0661-08).
If the erection opening is in a round form, the weld joint preparation shall be as for vertical
weld joints.
7.1.1 Fit up the plate, so that the gap of the vertical weld joints 1-2 mm and at the other side
3-4 mm. The gap of the horizontal weld joints shall be above and below equal.
7.1.2 All weld joints shall not be tack welded, only wedged.
7.1.3 Start with welding from outside, where the gap is 3-4 mm. The first pass shall be welded
down (3G down), to reduce the shrinkage. Thereafter weld 2 or 3 passes vertical up (3G up).
7.1.4 Start with welding at the opposite side from outside, first pass down (3G down) and 2 or 3
passes vertical up (3G up).
7.1.5 Grinding shall be carried out from inside, before back welding vertical up.
7.1.6 Finish both vertical weld joints from inside and outside, before start up with welding the
horizontal joints.
7.1.8 Start with the lower horizontal weld joint, weld 2 or 3 passes from outside.
7.1.9 Weld 2 or 3 passes at the upper horizontal weld joint, grind this joint from inside before
back welding.
ASALUYE C2+ RECOVERY AND FRACTIONATION PLANT
Process Engineering and
Contracting Division
attachment:
Assembly Procedure of Erection Openings PARS
a d a p t Ref.: a d a p t Doc. No. : Petrochemical
Issue 1 Company
P 01-1021,
Rev. 2 attachment to TP-000-16 Page 3 of 3
7.1.10 Carry out the back welding of the lower horizontal weld joint after grinding.
7.2.1 The weld joint preparation of the erection opening shall be the same as for the vertical
weld joint of course 1.
7.2.2 Fit up the plate with equal gap all around and tack the plate.
7.2.3 Start with welding from the top to the bottom (3G down) at both sides.
7.2.5 Back welding shall be carried out after grinding from inside.
7.4 The inter-pass temperature shall not exceed 150C (302 F).
8.0 Non-Destructive-Testing
8.1 The root pass shall be examined by LP-Test or MP-Test after grinding of the back side
and before back welding.
8.2 After finish welding, the following examinations shall be carried out:
8.2.1 After Hydrostatic Test, but before Pneumatic Test: - 100 % Visual Examination
- 100 % Radiographic Examination