Commissioning Procedure Goedehoop Flotation Upgrade
Commissioning Procedure Goedehoop Flotation Upgrade
Commissioning
Procedure
Page 1 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Contents
1. Objectives....................................................................................................... 4
2. Scope.............................................................................................................. 4
3. Definitions....................................................................................................... 4
4. Signature responsibilities per commissioning phase.......................................5
5. Punch list Description...................................................................................... 6
6. THE COMMISSIONING STUCTURE AND RESPONSIBILITIES...............................7
6.1. Commissioning Manager...........................................................................7
6.2. General..................................................................................................... 8
7. Logistic Support............................................................................................... 8
8. Commissioning Control....................................................................................8
8.1. C1 level Commissioning Punch Listing Contractor and/or Suppliers &
Construction Team. Pre Commissioning Checks Power Of...............................9
8.2. C2 level Commissioning Dry- Construction Team, Contractors and/or
Supplier and Plant. Pre Commissioning Checks Power On.............................10
8.3. C3 level Commissioning Material Commissioning Team and Plant
Cold Commissioning......................................................................................... 11
8.4. C4 level Commissioning Commissioning Team and Production Process
Engineer. (Hot Commissioning)........................................................................12
8.5. C5 level Commissioning Production Build-up and Optimisation-
Production Process Engineer and Plant Operating Personnel (performance Test)
12
8.6. General................................................................................................... 13
9. Request for Site Modifications Construction Team......................................13
10. Final Handover........................................................................................... 13
11. Commissioning team Identification and Induction.....................................13
12. Attachments Commissioning Acceptance Certificates................................14
C1 LEVEL COMMISSIONING ACCEPTANCE CERTIFICATE.....................................15
DETAILS OF WORK BEING HANDED OVER.........................................................15
RESPONSIBLE PERSON..................................................................................15
C2 LEVEL COMMISSIONING ACCEPTANCE CERTIFICATE.....................................16
DETAILS OF WORK BEING HANDED OVER.........................................................16
Page 2 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Page 3 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
1. Objectives
1.1.To define the commissioning strategy and control procedures required to
allow for a smooth transition from completion of construction by the
Contractor C1 to formal hand over and acceptance of equipment and
systems by the Project Commissioning Team C3 and to final hand over
to the Plant after C5 commissioning.
1.2.To clarify and define the diferent phases of hand over, the diferent
parties involved, their responsibilities and obligations at each stage
2. Scope
This procedure will cover the commissioning strategy that will be adopted
for the commissioning of the Flotation B-Bank i.e. Multi Cell upgrades to
Enprotec Dual Cell Technology. (Complete with it material handling
sections)
3. Definitions
The Plant The Plant refers to Plant Management who is represented by
the Construction Manager, Metallurgical Manager and the
Engineering Manager
Plant Operations The OMR refers to the Plant appointed operation team who
Operation and will act on behalf of the plant from commissioning stages C3
Maintenance through to C5 and ongoing plant operation
Representative (OMR)
Acceptance These certificate are signed by the Contractor and his Sub-
Certificates C1 & C2 contractor at stages C1 & C2 of the commissioning process
Pre-commissioning signifying acceptance that the equipment is ready for C3
Check commissioning
(Static testing) at
component level
Acceptance Certificate These certificates are signed by the Contractor and the OMR
C3 at stage C3 once the construction completion certificate/s is
Cold Commissioning signed of. This means the plant is ready for operation by the
(Dynamic testing) in Operations Team & Beneficial use is Identified. At this point
Systems there is a shift in Safety Responsibility as well as plant
Operation and Maintenance from contractor to client GHC
team. The contractor is still available for support and
commissioning modification identified in the first 24 hrs of
operation
Acceptance This certificate is signed of by the OMR and the Contractor
Certificate C4
Page 4 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Page 5 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Commissioning strategy.
Commissioning procedure.
Initiation of audits and monitoring activities to ensure compliance to
the commissioning procedures and safety standards.
Commissioning structure and functions.
Identification and appointment of personnel on the commissioning
structure.
Identification of infrastructure requirements and ensuring
availability ahead of commissioning.
Development of the commissioning program and monitoring of
progress with the assistance of the Project Planning Co-ordinator.
Ensuring that the required operational parameters are identified
and met before the plant is handed over to the Plant.
Manage and control the commissioning and hand over to the Plant.
Ensure compliance with laid down procedures.
Ensuring all documents, drawings and as-build drawings are
available for Final Handover to the Plant at the C5 Commissioning
stage.
Page 7 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
6.2. General
7. Logistic Support
The project has included where necessary, maintenance and training
requirements in the relevant contract document. These requirements have
been identified in conjunction with Goedehoop and the Contractor/Supplier. In
the event of additional commissioning requirements this shall be arranged
directly by the Commissioning Manager in conjunction with the
Contractor/Supplier taking cognizance of the time and cost involved for the
supplier to present themselves on site.
Page 8 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Page 9 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
This involves running the equipment or module dry to test or perform relevant
checks on the equipment or system, all equipment such as motor etc. are run
Page 10 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
All individual interlocks are completed and the control room to then take
ownership of the completed interlocks system for sequential testing.
It is essential that all the construction activities, in the applicable area, are
complete at this stage.
All equipment that forms a module or stream shall be run together to allow
balancing and to check all the interlocks and process control.
The Production Process Engineer shall take over full operational, safety and
maintenance responsibility for the water/ore commissioning on the discreet
piece of equipment or system.
The Commissioning Ma anger and his team will be available to assist the
Production Process Engineer during this phase. The two Managers, Engineers
and their respective teams will work together until the discreet piece of
equipment or system is running with material at the rated capacity.
Once the equipment or system is fully commissioned with material, the Senior
Process Metallurgist/Plant Process Engineers shall commence with the
optimisation of each relevant piece of equipment. The equipment and/or
system shall be manned and run for at least eight hours during the
optimisation process. This optimisation process is to optimise the process in
line with the plant design parameters only.
Page 12 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Once all the C5 Certificates have been signed of, the equipment or system
shall be run at full production as per the requirements of test on completion
before official hand over to the Plant. The Construction Manager shall submit
the Final Hand over Certificate to the relevant Plant representative.
8.6. General
Page 13 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Stickers on hard hats and diferent ID cards are to be utilized to identify the
commissioning team.
Page 14 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Commissioning Punch
List.................................................................................................ENP-PL
Page 15 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
This is to certify that the Equipment/System as described below has been tested
and punch list to the satisfaction of the Construction Engineer.
Upon signing this certificate the Construction Engineer undertakes to carry out
the next stage of the commissioning process namely C2 level Dry
Commissioning.
It is the responsibility of the Contractor/Supplier to address the attached Punch
List as per the programme agreed with The Construction Manager.
RESPONSIBLE PERSON
(PER DISCIPLINE)
Page 16 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
CONTRACTOR/SUPPLIER
CONTRACT NUMBER
DESCRIPTION OF
EQUIPMENT
PUNCH LIST NUMBER
This is to certify that the Equipment/System as describe below has been Dry
Commissioned to the satisfaction of the Construction Engineer.
Upon signing this Certificate the Commissioning Engineer undertakes to carry out
the next stage of the commissioning process, namely C3 level Wet
Commissioning.
RESPONSIBLE PERSON
(PER DISCIPLINE)
Page 17 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
CONTRACTOR/SUPPLIER
CONTRACT NUMBER
DESCRIPTION OF
EQUIPMENT
PUNCH LIST NUMBER
RESPONSIBLE PERSON
(PER DISCIPLINE)
NAM
DISCIPLINE E SIGNATURE DATE
Enprotec Commissioning Mgr
Client
Commissioning Mgr
Page 18 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
CONTRACTOR/SUPPLIER
CONTRACT NUMBER
DESCRIPTION OF
EQUIPMENT
PUNCH LIST NUMBER
RESPONSIBLE PERSON
(PER DISCIPLINE)
NAM
DISCIPLINE E SIGNATURE DATE
Enprotec Commissioning Mgr
Client
Page 19 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
CONTRACTOR/SUPPLIER
CONTRACT NUMBER
DESCRIPTION OF
EQUIPMENT
PUNCH LIST NUMBER
Upon signing this certificate the Maintenance and Commission Process Engineers
undertakes the responsibility to carry out the next stage of the commissioning
process, namely FINAL HANDOVER TO THE PLANT.
RESPONSIBLE PERSON
(PER DISCIPLINE)
Page 20 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
CONTRACTOR/SUPPLIER
CONTRACT NUMBER
DESCRIPTION OF
EQUIPMENT
PUNCH LIST NUMBER
List of Exceptions
RESPONSIBLE PERSON
(PER DISCIPLINE)
Page 21 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
CONTRACTOR/SUPPLIER
CONTRACT NUMBER
DESCRIPTION OF
EQUIPMENT
PUNCH LIST NUMBER
List of Exceptions
Page 22 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
RESPONSIBLE PERSON
(PER DISCIPLINE)
NAM
DISCIPLINE E SIGNATURE DATE
Anglo Snr Project Mgr
Anglo General Mgr
Anglo Board
Representative
Commissioning
Punch List
Form No. ENP-PL REV Date: 13/01/2010 REV No.:00
Legend
DEFECT: D= Design S = Safety M = Modification O
Required Required Required =Outstandin
g Item
TYPE: A = Equipment/System is not handed over or B = "Dry" commissioning is
approved for "Dry" commissioning authorized
Page 23 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Modification
No: Date:
Location/Plant:
Plant or Plant Section:
Signatur
Orginator: e:
CRITICA
LITY MINOR NON-CRITICAL MAJOR
Page 24 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11
Commissioning Procedure
Disruptio
ns to
Nil Minor Medium Major
Productio
n
Page 25 of 25
Revision
Enprotec 01 Approved By: Date:
Commissioning 10/01/20
Procedure 11