LILONGWE DEDZA ZONE WEEKLY TECHNICAL REPORT

WEEK 5
TECHNICAL

Availability:

Solar
Transmission TNM others Rectifier/Electric BSS Failure/No
Faults generators Generators al faults Equipment Maintenance DG
0 0 0 0 0 0 0

Operations and Maintenance

Achievements in Week 5

Deployed 500 litre tank at Area 23, recovered from Bunda T/Off
Drained diesel contaminated with water from Area 21 DG tank
Completed installation and commissioning of Area 50 and Burco LTE TDDs, the sites not yet up
pending configuration
Upgraded Area 23, 9, 47, 47 ABC, Dubai and Chinsapo 3Gs to 764 CEs

Planned activities in Week 6

Implement 3G fourth sectors addition at Area 18B, 9, Kangombe, LL Bus Depot, 47 and 47 ABC
Continue 3G WBBP boards swapping to source for fourth sectors implementation
Do battery testing at Area 24, Area 24 Mkt, Area 38
ESCOM units top up in the zone
Work on tower lights at LL bus depot
Do electrical and transmission maintenances Old Town

Risks and challenges

Following sites have no equipment earth cables


- Bus depot, Bwalo la Njobvu, Area 9, Bunda, Area 4, Area 9, Area 38, Kamphata, Nathenje