SAFETY PROCEDURE 21
Dust Control
Dust Control
This section describes Area CRCC management and control plan of dust inside the project site.
CRCC comply with this section to minimize generated dust impact to adjacent structures. Fugitive
dust caused by traffic on unpaved roads or earth moving activities may cause localized annoyance
and temporary property impacts. Dust produced from the construction activities has the potential
to penetrate nearby homes and cause nuisance and health conditions such as allergies and
respiratory conditions.
General Requirements
Water will be used to suppress generated dust caused by traffic on unpaved roads on the
project site.
Water truck shall spray water on a regular basis on the unpaved roads and access to the
project site.
Traffic speed limit shall be kept at 20kph and speed limit signs shall be posted to provide
information to drivers.
Vehicle drivers and heavy equipment operators will limit engine idling time and shut down
equipment when not in use.
Revision 00
Dated 18-02-2015
Page 1 of 2
CHINA RAILWAY CONSTRUCTION
CORPORATION LIMITED Issue No.:1
SAFETY PROCEDURE 21
Dust Control
Excavation works with the use of mechanical equipment shall be done on times approved
by SAPO to minimize nuisance dust affecting other personnel on adjacent structures.
Construction areas that generate dust shall be regularly sprayed with water and kept damp.
Sufficient staff will be assigned to conduct continuous water spraying to maintain and
implement dust control.
Heavy equipment operators shall be trained and informed on how to keep the operation of
their equipment generate as small amount of dust as possible by appropriate training (such
as tool box talk, Dust prevention training).
Revision 00
Dated 18-02-2015
Page 2 of 2