Professional Documents
Culture Documents
Maintenance Item
Maintenance Item
Object List Item data Maintenance
Object List Planning data
Lists of: Task List data Strategy
Functional Location Maint. Plan data
Location/account
Equipment assign
Operation #1
Operation #2
Operation #3
Operation #1
Operation #2
Operation
Sub-operation
Material
Production Resources/Tools
Maintenance Package
Operation
Sub-operation
Material
Production Resources/Tools
Maintenance Package
Object Dependencies
Header
Operation Overview
Resources provided
from internal Work
Centers
Work requirements
define resource
forecast when
associated with
Maintenance Plan
Parameter ID:
PM_TREE_INACTIVE = X
Standard(S)
BOM for
freely
assigned
parts
Finish to Finish
Finish to Start
Start to Finish
Start to Start
Operation Relationship
Non-stock Material
Text Item
Document Bearing/Gasket
Coupling Impeller
Assembly
Construction
type
Mat 1 Mat 3
Mat 2 Mat 6
Mat 20
Mat 7
Mat 10
Mat 11
BOM Items
Construction Type /
Material BOM
There needs to be a
way to identify PMs
that can be scheduled
anytime. E.g. certain
inspections. See
Priority 0
In this example, the status INP (In Process) is automatically set when
a work order is printed or reprinted.
The status INP is removed when the order is TECOd.
The problem is the indicator is buried on the Control tab. GUIxT is a good solution.
Manage
Define Weekly Finalize Communicate
Work ready Prepare to
Schedule Weekly Weekly
to be Schedule
Schedule Schedule
Scheduled
Hold Planning
Work Planning
Meetings
Process
Typically there are no reasons to change standard SAP Scheduling Type settings.
The with Time indicator allows input of times against basic start and end dates as shown
below.
Required if assigning
Shifts
Required if executing
finite scheduling
10 hrs, No Breaks = 10
(10 * 1.0) * 2 = 20
10 hrs, 1 hr Breaks = 9
(9 * 1.0) * 3 = 27
(9 * 0.9) * 3 = 24.3
(9 * 1.2) * 3 = 32.4
Non working
holidays defined
on 12/25 and 1/1
Available capacity
45 hours per day
In this example no
intervals yet exist
Although 7
day cycle only
first 5 days
applicable to
Interval.
Intervals are
associated with
specific versions
HR assignment
Work Center
Capacity is ignored
Output to Printer
Export to Excel
Dispatch Work
Graphic views
available
Real Experience. Real Advantage.
[ Capacity Evaluation Standard Overview
Can
further
filter
requireme
nts data.
Backlog Orders
show today
Week
Month
8
Initial system distribution of hours
1 based on Operation dates
45 Work Hours planned for 8/27
Capacity
8 Requirements
5 from Work
Order
8 Operations
4
2
Planning Table
After Dispatch refresh of IW37N updates status and dates ready for
publishing
Selection variants and layouts defined to meet schedule publishing
requirements
Variety of publishing methods
# of # of
Planner Work Scheduled Compliant %
Year Week Plant Grp Center Orders Orders Compliant
2007 02 ABCD PG1 A 3 2 67%
2007 02 ABCD PG1 B 2 1 50%
Sum
PG1 5 3 60%
WBS Structure
Network Activity
PM
PM Orders
WBS Structure
Network Activity
Level 1
Level 3 Level 2
Capital or Expense
Budget / Organizational Responsibility
Phase, Stage, Event
Major Resource Area
145
Real Experience. Real Advantage.
[ Project Definition Example
146
Real Experience. Real Advantage.
[ Creating a project and associating WBS elements
The first step is to
create a project and
create/assign WBS
element values to the
project.
This transaction is of
great use in creating
both the Project and
the WBS elements.
148
Real Experience. Real Advantage.
[ Project Copying
149
Real Experience. Real Advantage.
[ Plan and Schedule Dates PS
WBS Structure
Plan Dates
S F
Network Activity F
Plan Milestones
PM
S
PM Orders
153
Real Experience. Real Advantage.
[ Network Activity Relationships
Network
Network
Order
Activity
154
Real Experience. Real Advantage.
[ Project Date Planning & Scheduling Top Down or Bottom Up
Date Planning
155
Real Experience. Real Advantage.
[ Can Relate Across Network Orders and WBS
WBS Element
WBS Element
156
Real Experience. Real Advantage.
[ Gantt View of Plan
WBS Element
Network Activity
157
Real Experience. Real Advantage.
[ Rescheduling the project
Have the option of
rescheduling network only,
networks and orders, or
just orders.
159
Real Experience. Real Advantage.
[ Linking maintenance orders to networks
Once this link is made,
the order schedule and
basic dates will mirror
the networks activity
dates.
NOTE: Network
assignment are made at
the order level and not
the operation level. It is
imperative that the
planning of the order
operations is sound
because moving individual
operations is not
possible.
161
Real Experience. Real Advantage.
[ PM Work Order to Project Assignment
162
Real Experience. Real Advantage.
[ Overview and reporting in PS Networks
164
Real Experience. Real Advantage.
[ More on Project Info Systems (CN41)
Allows the user
to set up which
fields are
displayed and
how this may
look in a graphical
extract.
169
Real Experience. Real Advantage.
[ Standard Exports MS Project
170
Real Experience. Real Advantage.
[
Manager View
(Web UI based)
Capacity Management
Employee View
Graphical Planning Board (Web UI based)
(SAP GUI based)
Employee
Qualification
Catalogues
Requirements Profile
Employee Profile
Skill Level
Demand Gantt
Work Center
Gantt
Work Center
Capacity
Alert Monitor
Order
MRS
Operation Demand
Operation Demand
Operation Demand
Plant
Technical
Services
Plant
Technical
Services
HR record/person
HR Work Link Work
A 061
Link Center LA
Center
(ZMRS)
PO10 A 008
Organizational P
Unit
Technical
Services
Kahn Ellis
Piperfitter
1223
1:1 relationship:
Cause additional operation to be created per resource assigned
Assign technician work center representing resource to
operation
No relationship:
Assign resource(s) to operation in Requirements Assignment
tab
Cannot display assignments in List Edit
Data Flow:
Sheet filled
Work order data
with Activities
Updated Dates
Detailed
Updated Employee
Assignments Dispatching
SAP MS Excel
on