2017 we are
submitting here with revised launching methodology drawings of Raibareli and
Akbarpur duly incorporating your comments.
Point no. 1 At site there are no space for assemble the girder hence there are no
other option to toe the girder from assembly area to site on trailer.
Point no. 3- Plate girder lifting analysis and stand alone girder checking is
submitted along with this letter for approval of Kashmiri gate railway.
Point no. 6- Both the crane will lift the girder vertically first then both the crane
rotate simultaneously towards pier P3 so that crane 1 side end of girder crosses
the pier cap of P3 then both the crane at a time rotates towards P2 and place
the girder over bearing of P2 and P3 pier.
Point no. 13-seprate drawing will be submit for deck slab shuttering and casting