ROUGH ESTIMATION FOR DIRECT MAN POWER (SUPERVISOR to SKILLED LABORER)

OFFSHORE CAMPAIGN
person months
Structural 33 12
Electrical 33 12
Commissioning and Heavy Lift 10 1

ONSHORE CAMPAIGN
Structural 40 12
Electrical 15 12
days hours TOTAL NO. HOURS
30.5 12 144,936.00
30.5 12 144,936.00
30.5 12 3,660.00

30.5 10 146,400.00
30.5 10 54,900.00

494,832.00