Professional Documents
Culture Documents
Introduction To Telugu Ganga Project
Introduction To Telugu Ganga Project
Thandaveswara
15.2.1976 and finally historic agreement was signed on 18.4.1983 and 25.5.1983
foundation ceremony was held) to utilize flood water of Krishna and Pennar rivers to
irrigate 5.75 lakh acres (2.32702 lakh ha) in drought prone areas of Kurnool, Cuddapah
Pradesh besides conveying 15 TMC (424.75*106 m3 ) of Krishna water for Chennai city.
The scheme consists of 408 km long canal from Srisailam passing through the above
Financial Aspects
1. Estimated cost of the project (with 1983-'84 rates) Rs. 637.00 Crores.
2. Estimated cost of the project (as per 9/97 review report) Rs. 2470.00 Crores.
3. Share of Tamilnadu Government (as per 9/97 review report); Rs. 639.00 Crores.
have agreed to spare 141.58 million m3 each from out of their shares for supply of
General Information
On 15.02.1976 the Prime Minister of India made historic announcement in Chennai city
On 18.04.1983 at Hyderabad, the Chief Ministers of Andhra Pradesh and Tamil Nadu
signed the Interstate agreement for the supply of Krishna water to Chennai city and to
On 25.5.1983, the project works were inaugurated at Chennai by the Prime Minister of
India.
Chief Minister of Andhra Pradesh released water for irrigating 10117.5 ha in Kurnool
district on 05.08.1996.
The Government of Andhra Pradesh has accorded Administrative Approval for Rs. 1805
crores vide G.O. Ms.No.2, I & CAD (Projects Wing-TGP.I) Dept dt. 2.01.1996.
The Project was cleared from environmental and forest angles from forest conservation,
Ministry of Environment and Forests, New Delhi vide Lr. No. P - 97/84 - FC, dt 10.10.88.
The first planned scheme of drinking water supply for the Madras city was designed by
Fraser in 1866 and executed in 1872. Cholavaram and Red Hills (Irrigation tanks were
Thamarapakkam. The scheme was designed for a population of 0.47 million. The
covers now 1167 sq.km approximately. Sathyamurthysagar (Poondi reservoir) was built
in 1944 on (Kusasthalaiar river). City faced a severe shortage in 1947, 1954, 1968,
1972 to 1975, 1982, 1983 and 2000 to 2003. At this stage Telugu Ganga was planned.
In Jan 2002 a Rs. 200 crores was announced for lining the Kandaleru Poondi canal
carrying Krishna water to Chennai. It takes 4 days for the water to travel from release
point to zero point (the point at which the canal crosses into Tamil Nadu from Andhra
Pradesh). The Canal lining for 65 km was completed in a span of 15 months (Oct 2002
to Dec 2003)
Tamil Nadu Zero point is 152 km from Kandaleru Dam. Release from Kandaleru on Nov
23 rd 2004 was 1000 cfs (28.32 m3/s) and quantity received at zero point is 483 cfs
(13.68 m3/s). The Canal part of Andhra Pradesh is called Satya Sai Ganga Canal.
Earlier it use to take 9 days for the water to travel the same distance.
Water availability
(i) Irrigation for 2.75 lakh acres (1.113 lakh ha) in Kurnool and Cuddapah districts with
(ii) Irrigation for 1.21 lakh ha in Nellore and Chittoor districts with Pennar flood waters:
849.5 * 106 m3
Main Components
A) Balancing Reservoirs
b. Chennamukkapalli: 15 MW
c . Somasila Reservoir
d. Kandaleru: 9 MW
B) The scheme consists of 408 km long canal from Srisailam Reservoir to Andhra
Poondi reservoir.
Banakcherla
Regulator Srisailam Left Bank canal 140 km, 169.90 m3/s
Regulator
140 th km
42.475 m3/s Brahmamgiri manthan
Chenna Somasila
mukkapalle
Reservoir
2831.168 m3/s 38 km long
Kandaleru River
Pennar River
Feeder canal
Poondi Reservoir
14.158 m3/s
PRESENT STATUS
Status of drinking water supply to Chennai city
1. Date of release of drinking water to chennai city for the first time through K.P canal:
26.06.1997.
Zero point of the canal is specifically referred as the point at which the water is released
or let out from Andhra Pradesh State to the Tamil Nadu State. Zero point is constructed
carefully, with proper lining (rubble masonry) in the cement mortar 1:3. Drainage pipes
are provided in the retaining walls to drain out the water from the backfill of the canal at
suitable intervals. The major structure that is provided at Zero point is water measuring
flume which plays a crucial role in quantifying water releases from Andhra Pradesh. The
bank provided with vertical measuring depth. It helps in measuring the depth of water in
the canal by using which discharge can be calculated by using following equation:
2 2g
Q= Cf B2 H3/2
3 3
in which, B2 = throat width, (4m), Cf = Coefficient of Discharge (1.0), H = Head of water.
The following scale which is adopted for measuring discharge in usual operation of the
Depth of Discharge
Water (m) (m3/s)
1.70 15.05
1.80 16.53
1.90 17.86
2.00 19.89
2.60 28.59
Design of standing flume is done by Andhra Pradesh PWD based on the prevailing site
conditions. Design of standing flume is done by Andhra Pradesh PWD based on the
prevailing site conditions. The various parameters that has encountered in the design
are as follows
2) Design considerations
done as per T.V.A (Tennessee Valley Authority) Procedure. Unit weight of concrete 24
kN/m3. Unit weight of Earth Material 21 kN/m3. Angle of internal friction 35. For the
construction of the side wall (PCC) M 10 concrete was used. The aggregate selection
was based on IS 393-1970. For the construction of the foundation of the flume M7
grade concrete and 40 mm maximum size aggregate size. The coping slab is provided
3. Meteorological station
At the zero point from the border of two states the meteorological station is located,
which is equipped with the following accessories for measuring various hydro
Rain gages
a) Recording and
c) Anemometer,
d) Evaporimeter Class A,
e) Thermometer,
Daily data are measured twice in a day at morning 8.30 am and evening 6.30 pm. The
information is useful in checking what the hydrology of that area is and this data is also
3. CANAL STRUCTURES
The flow of water in the canals must always be under control. For this purpose, canal
structures are required. They help regulate the flow and deliver the correct amount of
water to be different branches of the system and onward to the irrigated fields.
c) Crossing structures
The canal is constructed for discharging water from Kandaleru reservoir to Poondi
Reservoir which has total length of 152 km among which after 120 km downstream of
the Kandaleru reservoir the water is restricted only used for drinking purpose. The
stretch of length 25.50 km downstream to Zero point has been provided with cement
concrete lining.
The total canal length is about 120 km which is having overall 60 m top width and 32 m
height. At the zero point which is located 25.50 km upstream of the Poondi reservoir on
the border of TamilNadu and Andhra Pradesh. The canal is basically designed for the
The canal section is designed for full water supply depth of 3 m and the canal bed
elevation is about 43.706 m above MSL at the upstream and 43.28 m at the
downstream.
At the starting point they provided the measuring flume for quantifying the water. The
drainage pipes are provided at the sloping side of canal to drain out the water safely in
the canal from backfill along the canal length they are constructed various civil
a) Meteorological station
c) Culverts
d) Aqueducts
e) Regulating Structures
g) Energy dissipators.
h) Siphon Wells
A siphon well is a structure which is provided at the bank of canal at suitable locations
where the water is required to be transferred across the canal for irrigation purpose.
5. CANAL LINING
Along the canal, failure of canal lining was encountered at various locations. The lining
was made up of pre-cast concrete slabs. One of the possible causes of failure may be
because of proper anchorage was not provided for the lining. One unique phenomenon
was that the failure of lining took only along the right hand side of the canal. This could
be attributed to the pressure exerted by the seepage water from tanks located along the
Poondi reservoir, the slope of the canal is quite steep. In order to prevent the scouring
of bed due to high velocity attained by the water, energy dissipators are provided along
the bed at the region where the canal joins with the reservoir. The dissipators provided
in the canal were stones of different sizes uniformly spread over the bed of the canal.