You are on page 1of 6

Development and Application of Whittle Multi-Mine at Geita Gold

Mine, Tanzania
T Joukoff1, D Purdey2 and C Wharton3

ABSTRACT Once the optimal pit for each mine was decided, pit designs
were undertaken, reserves calculated and the entire data set
In the past, life of mine scheduling at Geita Gold Mine, Tanzania, has
been a largely manual process involving the optimisation and scheduling exported to a spreadsheet for manual scheduling. Various
of each mine as a separate entity. The scheduling has been a guidelines and comparisons between the pits and stages were
time-consuming process undertaken using spreadsheets. Recent advances used to assist with the manual scheduling process, such as strip
in the Whittle software have enabled multiple mines to be optimised and ratio, profit per tonne milled, cash cost per ounce, profit per
scheduled simultaneously, so that the mining sequence that maximises the ounce and break-even time. This introduced another flaw in the
NPV (net present value) for the entire set of mines as a whole can be process, where the optimal extraction sequence was not
determined. This case study presents the results of the collaboration necessarily followed during the manual scheduling process.
between Gemcom Africa (Pty) Ltd and Geita Gold Mining Limited to
It became apparent that this trial and error scheduling method
develop and apply the Whittle Multi-Mine module at Geita Gold Mine. It
shows how improvements to the NPV of the life of mine schedule were was time-consuming and limited the number of alternate life of
achieved by using Whittle Multi-Mine as a tool to help guide the mine scenarios that could be evaluated. A need for a technique to
preferred order of mining. It highlights the contributions from each of the optimise the extraction sequence in this multiple mine scenario
mines to the overall cash flow of the project and investigates the effect of was identified. Such a tool was available as part of the Whittle
time on the NPVs from each mine. The cost of deferring production from suite of mine planning software, but was still in its infant stages,
certain mines has become plainly evident, whilst for others there is little requiring rigorous testing on a real life scenario. This paper
impact. Furthermore, Whittle Multi-Mine has identified areas requiring describes Whittle Multi-Mine and its application at Geita, but
more focus in terms of the life of mine plan. first briefly reviews the traditional and widely applied MOBS
technique.
INTRODUCTION
Geita Gold Mine is situated in northwest Tanzania, MOBS
approximately 25 km from the southern shores of Lake Victoria. A technique known as MOBS (Multiple Ore Body Systems,
Historical mining in the area has taken place for many years, Tulp, 1997) has existed for some time now and has been widely
with the last major operation being the Geita Underground Mine, applied in situations where multiple orebody deposits exist in
which operated from the 1930s through to the 1960s and proximity. In short, the technique involves agglomerating block
produced almost 1 Moz of gold. Ongoing small scale mining models representing each of these deposits into one super model
continues to this day. (Figure 1), and optimising and scheduling using Whittle
The modern Geita mine has been operating since mid-1999, software. The limitations of this method are described following.
with processing of ore commencing in mid-2000. To date, 48 To enable the identification of material selected for mining by
Mbcm of material has been mined from three open pits; 14 Mt of Whittle from the different deposits, it was necessary to assign
ore, grading 3.8 g/t, has been processed and 1.5 Moz recovered. unique rock codes that were reflective of the different deposit
The current Life of Mine Plan indicates a mine life in excess of areas. Furthermore, the rock codes used for Whittle also needed
ten years and entails the mining of ten individual pits, several of to capture the actual rock type, so that different mining and
which are multi-stage. Total mining is expected to exceed 320 processing costs could be defined if necessary. This required the
Mbcm, producing more than 80 Mt of high-grade ore and assignation of many rock codes and sometimes resulted in the
yielding more than 10 Moz of recovered gold. loss of geological definition due to the restriction in the number
The open pit mines are operated with conventional techniques of codes that could be handled by Whittle.
using excavators and trucks on flitches up to 3.5 m high. Most Once the optimisations had been completed and the pit shells
material requires blasting, ranging from paddock blasting in generated, it was necessary to cut up the super model results file
soft laterites and oxides, to hard rock blasting in sulfides. to separate the individual mines, using the polygon intersection
Pit optimisation at Geita has been an ongoing process,
predominantly undertaken using the NPV Scheduler software,
however; from early 2003 Whittle software has been used in NORTH PIT
parallel. Although techniques to evaluate multiple orebodies have
existed for some time (Tulp, 1997), each open pit has been
optimised and scheduled as a separate entity rather than MAIN PIT
consideration given to whole of mine optimisation and
scheduling. Estimates of the mill throughput likely to be required
from each pit were used to guide the pit life and net present value
(NPV) calculation. Since the ore delivery rate required was WEST PIT
generally not known until the whole mine schedule was finalised
using all the pits, this was obviously a flawed process.
SATELLITE 1 SATELLITE 2
1. MAusIMM, C/- Gemcom Africa (Pty) Ltd, PO Box 411689,
Craighall 2024 Gauteng, Republic of South Africa.
2. MAusIMM, C/- MRM Mining Services, PO Box 3193, Halfway
House 1685 Gauteng, Republic of South Africa.
FIG 1 - Example super model constructed by merging
3. 66 Rathmullen Quadrant, Doncaster Vic 3108. MOBS in Whittle.

Orebody Modelling and Strategic Mine Planning Perth, WA, 22 - 24 November 2004 267
T JOUKOFF, D PURDEY and C WHARTON

functionality in Whittle, so that the results could be exported With Whittle Multi-Mine it is no longer necessary to use rock
from Whittle back to a general mining package (GMP). This was codes to identify material from different deposits. It is now
because the original coordinates of the individual deposits were possible for Whittle model files to carry a mine name, so the
lost when they were combined into the super model. issue of running out of rock codes is no longer a problem. This
Issues arose when scheduling MOBS, since it was not possible allows greater geological detail to be modelled, leading to
to control the order that the deposits were mined in without increased flexibility and detail when modelling costs, recoveries
creating complex pit list files with GMPs or by writing scripts and slopes in Whittle, if desired. Furthermore, because each
with programming packages. Furthermore, it was necessary to model can be associated with a mine name, it is possible to view
ensure that the top surface of all of the models lay on the same and export results for individual mines. This reduces the amount
Whittle bench level in the combined super model, requiring the of time required to be spent on data manipulation and provides
user to offset each individual block model so as to create a more time to deal with strategic issues.
regular surface over the entire model. This meant that when It is possible to optimise all the mines under consideration
simulating the mining of a bench in Whittle, the bench was either simultaneously or individually, because the Whittle model
mined from all of the mines in the super model. It was also not files carry a mine name. The advantage of optimising them
possible to have different cut-backs in each mine, nor was it together is that the impact of each mine on the combined cash
possible to have different final pits per mine. This reduced the
flows of all the mines can be examined and reported.
effectiveness of the scheduling and did not allow areas of higher
value to be deliberately targeted. Scheduling with Multi-Mine is now also much more
sophisticated than the MOBS technique previously applied. It is
For more advanced scheduling using the Whittle Milawa
possible to vary the mining rates in different mines and also to
scheduling algorithm, it was necessary to stack groups of pit
shells, representing the nested pits derived for each mine, for control when mining can occur in a particular mine. This
Milawa to work effectively (Figure 2). This was difficult to set up functionality proved particularly useful at Geita because some of
and comparatively inflexible when evaluating many alternate the mines were remote from the processing plant and ore
mining sequences. production from these mines was limited by the long distance
haulage capacity (Figure 3). Also, due to Geitas environmental
Whilst the technique described above generated results that
commitment to backfilling completed pits to minimise
added value to mining operations; it was tedious and much time
disturbance caused by the construction of waste dumps, some
was spent on manipulating models and data files, thus limiting
the amount of time that could be spent on actually evaluating mines were not able to commence until adjacent mines were
different scheduling sequences and the consequent impact on completed. Furthermore, either of the Fixed Lead or Milawa
NPV. scheduling algorithms can be applied as described following.

MULTI-MINE Schematic of Geita Gold Mine


(Not to scale)
Whittle Multi-Mine provides a much more sophisticated and
flexible means of optimising and scheduling in a multiple mine Matandani
Kukuluma
situation, as was proven by its successful application at Geita
Gold Mine. The different techniques applied at Geita are
described following, using examples (Joukoff and Purdey, 2004)
to illustrate the results.
~20 km

Chipaka

~5 km

Geita Hill Pits

Nyankanga

Lone Cone Pits

~19 km
Roberts Legend

Haul Road

Ridge 8 Star/Comet Pit

Plant

FIG 2 - Stacked pit shells to enable Milawa to operate


independently on each mine before the development of Whittle
Multi-Mine. FIG 3 - Schematic of Geita Gold Mine.

268 Perth, WA, 22 - 24 November 2004 Orebody Modelling and Strategic Mine Planning
DEVELOPMENT AND APPLICATION OF WHITTLE MULTI-MINE AT GEITA GOLD MINE, TANZANIA

Fixed lead 2000). Milawa NPV schedules generally mine just enough waste
to uncover the ore required to fill the mill and tend to defer waste
Fixed lead scheduling can operate with or without precedence stripping as much as possible. Logically, this will lead to
controls. By establishing mining precedence rules, different increased NPVs. However, this waste deferral may result in
orders of mining the individual mines can be simulated, making insufficient ore availability at some time in the schedule, but only
it possible to investigate which order maximises the NPV to the if the cut-backs have not been selected appropriately or if the
company. This technique is particularly applicable in situations mining capacity is not well matched to the selected cut-backs.
where only one mine will operate at a time, such as when the
mines are very large and where ore control issues can be handled The Milawa algorithm in balanced mode provides a solution to
sufficiently by manipulating the mining sequence within each this problem by producing a schedule that completely utilises all
mine, without the need to blend material from different mines. of the available mining and milling capacity where possible. The
Each mine may have its own process plant and associated general effect of such a schedule is to mine more waste than is
infrastructure but logistically, mining equipment may need to needed to uncover the ore necessary to feed the mill, hence
move from one mine to another. The order of mines to which bringing costs forward and resulting in a reduced NPV. However,
equipment moves can be optimised using this functionality. both the mill feed schedule and the total mining schedule will be
Alternately, when no particular precedence is required and well balanced. A diagrammatic sketch of a Milawa mining
mining can occur simultaneously in all mines following the same sequence is included in Figure 5.
bench lead constraints, fixed lead scheduling can also be applied.
These two alternate concepts are illustrated in Figure 4. APPLICATION AT GEITA GOLD MINE, TANZANIA
Fixed lead scheduling was tried at Geita but with limited Geita Gold Mining Limited provided a data set representing nine
effectiveness because the site wanted to be able to mine from of the mines planned as at November 2003 (Nyankanga, Lone
many pits simultaneously, rather than mine them sequentially. Cone, Geita Hill, Kukuluma, Matandani, Chipaka, Ridge 8,
Although this was possible as described previously, it was not Star/Comet and Roberts). Each model was exported from a GMP
practical in Geitas case because several of the mines were with pre-defined rock types that allowed unique costs and
already in production and operating on different bench levels. process recoveries to be assigned to each rock type. Although it
Furthermore, within the constraints of the existing cut-back is possible to model costs in Multi-Mine using a Mine variable,
designs at Geita, using fixed lead scheduling did not provide an a cost model reflecting the different long distance haulage costs,
optimal mill feed schedule. Geita needed to be able to draw defined for different rock types, already existed. As well as this,
material from multiple sources to feed the mill, to meet the the existing cut-back positions were exported as pit list models,
appropriate oxide/sulfide blend requirements and also to make allowing the cut-backs within each mine to be differentiated
better use of the available mill capacity. Greater flexibility was during subsequent analysis. These pit lists were agglomerated in
required, and to overcome these issues it was necessary to apply Whittle to create a results file suitable for use with the
the Milawa algorithm. Multi-Mine scheduling tools. Some of the required operational
constraints have already been described previously in this paper.
Milawa Before undertaking any further scheduling in Whittle, a
The majority of the Geita scheduling work in Multi-Mine was baseline schedule was developed with Multi-Mine that mimicked
undertaken using the Milawa scheduling algorithm. This was the existing Life of Mine (LoM) Plan as much as possible. This
because Milawa allowed material to be mined from different was so that subsequent NPV calculations for alternate mining
mines simultaneously, applying different lead and lag constraints sequences would be comparable. An iterative process was used
to the different mines (as opposed to fixed lead scheduling, in defining this baseline schedule, using modifications to the
which uses the same lead constraint for each mine). There was a min/max lead and max benches constraints to force Multi-Mine
requirement at Geita to limit the maximum highwall height to mine in a similar sequence and with similar quantities as
between cut-backs to 150 m, for geotechnical reasons. The defined in the LoM Plan. Concurrent with this work in
maximum vertical advance in each mine was also restricted to Multi-Mine was the recalculation of the LoM Plan NPV because
either 50 m or 100 m per year, depending on the size of the mine. this included the effects of many cash outflows that were not
For this reason it was necessary to define different constraints for applicable in pit optimisation.
different mines and this was easily achieved with Multi-Mine. Once the Multi-Mine baseline schedule was constructed, the
It would be prudent at this stage to briefly explain the constraints were selectively relaxed to allow Multi-Mine to begin
differences between the various Milawa scheduling algorithms. to optimise the schedule. Alternate orders of mining were tested
In NPV mode, Milawa will seek to maximise the NPV of the by simply adjusting the preferred order of mining and the mine
schedule, taking into consideration the number of benches, start and stop times, and the resultant NPV, ore delivery schedule
cut-backs and time periods in the life of the mine (Wharton, and total mining schedule evaluated.

M1 M2 M3 M1 M2 M3

A. B.
FIG 4 - Diagrammatic representation of two different fixed lead scheduling sequences in Whittle Multi-Mine. A. Mining precedence applies
and equipment moves from one mine to another on completion of each mine (Wharton, 2000). B. No mining precedence applies and all
mining occurs simultaneously in all mines, following specified bench lag constraints (Wharton, 2000).

Orebody Modelling and Strategic Mine Planning Perth, WA, 22 - 24 November 2004 269
T JOUKOFF, D PURDEY and C WHARTON

little as 46 per cent (Scenario 3). This represents a 21 per cent


M1 M2 M3 improvement in cash flow contribution from Nyankanga for
Scenario 14 compared with Scenario 3. In fact, in Scenario 3 the
NPV from Nyankanga approaches that of worst case mining.
As a further example consider Chipaka mine; if this is mined last
(Scenario 14) the NPV contribution erodes to just 0.5 per cent,
but if it is mined first (Scenario 17), the NPV contribution can be
as much as two per cent. However, when considering the NPV of
FIG 5 - Diagrammatic sketch of a Milawa mining sequence in all of the mines concurrently, delaying Chipaka gives the project
Whittle Multi-Mine (Wharton, 2000). a better overall NPV. This clearly demonstrated how the order of
mining can have a serious impact on the value of the project.
In total, twenty-four different LoM scheduling scenarios for It was concluded from all of the scenarios that the NPV was
Geita were considered using the Milawa algorithm in relatively insensitive to changes in the order of mining from the
conjunction with Multi-Mine. Comparison of the NPV of each of Chipaka, Kukuluma and Ridge 8 mines. This suggested that it
these schedules with the baseline schedule showed that the NPVs was not worthwhile to further optimise the timing of these mines.
ranged from 87 per cent to 103 per cent of the baseline NPV. Conversely, there was substantial gain to be made by optimising
Whilst a three per cent improvement in NPV may seem small, in the mining sequence from Nyankanga, Geita Hill, Matandani and
Geitas case it represented an increase in NPV in excess of 1500 Star/Comet. For this reason, the order of mining from these
times the cost of undertaking the Multi-Mine work. An ore mines was the focus for the remainder of the scenarios and
schedule representative of the results generated with Multi-Mine yielded higher value schedules.
is displayed in Figure 6. Examination of the bench schedules produced by Whittle
The most significant difference between the Whittle Multi-Mine helped to understand how much material was mined
Multi-Mine results and the existing site LoM Plan was that the from each bench, each cut-back and each mine in each period
Milawa algorithm preferred to mine Star/Comet as early as and hence made it possible to determine whether Multi-Mine
possible, rather than later in the project life as had been was adhering to the required operational constraints. The
previously scheduled. This gave some indication as to the resultant schedules were both safe and practical. Furthermore, by
significance of the Star/Comet mine to the overall project NPV. making comparisons between the benches mined in different
When run unconstrained, Multi-Mine also preferred to mine scheduling scenarios it was possible to understand where the
Matandani in early years, but this was not a favoured option as material was being mined from, and the subsequent contribution
the waste from Matandani was planned to be backfilled into the of that material to the overall value of the schedule. An example
Kukuluma mine. bench schedule is given in Table 2.
Investigation of the contribution to NPV from each mine for
each scheduling scenario helped to determine which mines the CONCLUSIONS
overall NPV was most sensitive to. Table 1 contains a This paper has reviewed the techniques available in Whittle to
representative set of results showing these cash flow optimise and schedule multiple orebody models and multiple
contributions for various scenarios. It is clear that for some of the mines. The application of Whittle Multi-Mine at Geita Gold
mines changes to the order of mining had little or no effect on Mine, Tanzania, has demonstrated how improvements to the
their contribution to total NPV, whilst for others the change in NPV of the life of mine schedule were achieved, using
contribution to NPV was considerable. Multi-Mine to help optimise the mining sequence. The Milawa
The effect of delaying production from any mine can be seen. algorithm in both NPV and balanced mode was able to guide the
The cost of deferring Nyankanga is very evident; the NPV order of mining benches from the various cut-backs of the
contribution being as much as 67 per cent (Scenario 14) or as various pits, within the operational constraints at Geita.

MILL FEED SCHEDULE


TONNAGE

GRADE

YEAR
FIG 6 - Representative ore schedule, Geita Gold Mine case study. Different shades represent different mines.

270 Perth, WA, 22 - 24 November 2004 Orebody Modelling and Strategic Mine Planning
DEVELOPMENT AND APPLICATION OF WHITTLE MULTI-MINE AT GEITA GOLD MINE, TANZANIA

TABLE 1
NPV contributions by pit by scenario, Geita Gold Mine case study.

Matan' Chipaka Geita Hill Kuk' Lone Cone Ridge 8 Roberts Star Comet Nyank' Total
Scenario 2 5% 1% 17% 4% 3% 1% 1% 4% 63% 100%
Scenario 3 5% 2% 28% 5% 4% 1% 3% 6% 46% 100%
Scenario 7 5% 1% 17% 4% 3% 1% 1% 9% 57% 100%
Scenario 14 3% 0% 16% 4% 2% 1% 2% 6% 67% 100%
Scenario 15 3% 1% 18% 4% 3% 1% 1% 8% 60% 100%
Scenario 16 4% 1% 17% 4% 3% 1% 2% 8% 60% 100%
Scenario 17 3% 2% 16% 4% 3% 1% 1% 6% 65% 100%
Scenario 19 4% 1% 18% 4% 4% 1% 2% 8% 59% 100%
Scenario 21 5% 1% 22% 5% 4% 1% 2% 7% 55% 100%
Scenario 23 5% 1% 20% 5% 1% 1% 3% 9% 56% 100%

TABLE 2
Example extract from bench schedule generated using Whittle Multi-Mine.

Pit Bench Total Year 1 Year 2 Year 3


Tonnes Ore t Waste t Ore t Waste t Ore t Waste t
Kukuluma 69 1496 - - 341 1155 - -
Kukuluma 68 1131 - - 306 825 - -
Kukuluma 67 772 - - 244 527 - -
Kukuluma 66 453 - - 194 259 - -
Kukuluma 65 20 - - 12 9 - -
Kukuluma 64 142 - - - - 105 37
Kukuluma 63 56 - - - - 44 12
Kukuluma 62 11 - - - - 9 2
Subtotal
Lone Cone 66 1266 161 1105 - - - -
Lone Cone 65 1176 201 975 - - - -
Lone Cone 64 1015 154 861 - - - -
Lone Cone 63 901 111 789 - - - -
Lone Cone 62 788 - - 73 715 - -
Lone Cone 61 653 - - 44 609 - -
Lone Cone 60 532 - - 37 495 - -
Lone Cone 59 401 - - 43 358 - -
Subtotal

Many alternate scheduling sequences were very quickly Department at Geita who contributed to the preparation of the
investigated using Whittle Multi-Mine. This process identified data used in the Multi-Mine analyses.
which mines demonstrated greater sensitivity to the order in The opinions expressed in this paper are not necessarily those
which they were extracted and subsequently stressed the effect of of Geita Gold Mining Limited.
time on the cash flow contribution of these mines to the overall
project NPV. It also assisted in highlighting a potential mismatch
between the required material movement and the available REFERENCES
mining capacity. If the mining capacity is well matched to the Joukoff, T and Purdey, D P, 2004.
selected cut-backs then it will be possible to achieve a balanced http://www.whittle.ca/whittle-multimine.asp Improved life of mine
schedule together with an improved NPV. scheduling with Gemcom Whittle Multi-Mine at Geita Gold Mine,
Tanzania (Gemcom Software International Inc: Vancouver).
ACKNOWLEDGEMENTS Tulp, T, 1997. Multiple Ore Body Systems (MOBS), in Proceedings
Optimising with Whittle, Perth, pp 149-163 (Whittle Programming
This paper describes work undertaken by co-author David Pty Ltd: Melbourne).
Purdey whilst employed as Chief Mining Engineer Geita Gold Wharton, C, 2000. Add value to your mine through improved long term
Mining Limited and is presented with Geita Gold Mining scheduling, in Proceedings Whittle North American Strategic Mine
Limiteds permission. The authors would like to thank Geita Planning Conference, Breckenridge, Colorado.
Gold Mining Limiteds management for their permission to Wharton, C, 2003. Multi-pit analysis and advanced pit scheduling,
present this paper and also thank the members of the Mining Development notes (unpublished), Melbourne.

Orebody Modelling and Strategic Mine Planning Perth, WA, 22 - 24 November 2004 271
272 Perth, WA, 22 - 24 November 2004 Orebody Modelling and Strategic Mine Planning

You might also like