Buyer H&M

Production Goal Style wise


Production
Style Machine Target
Lima 22 250
Hedda 20 350
Shabina 22 170
Leggings 24 250
Ronny 22 180
Require Lead time from fabric received
SL NO: Process Require Day
1 Fabric Receive 1
2 Fabric Relaxed 1
3 Trail/ Size set Cutting 2
4 Accessories Check
1
5 PP Meeting
6 Bulk Cutting 2
7 Sewing 7
8 Finishing 1
9 Inspection 1
10 Shipment
Require Lead Time 16

Estimited Production per hour 150.pcs


Total 10500.pcs in 1 line for 7 day.

NB: Considering print/embroidery lead time will be extend 2 days more.