PRASAR BHARATI

OFFICE OF THE DEPUTY DIRECTOR GENERAL (E)


HIGH POWER TRANSMITTER; ALL INDIA RADIO
KINGSWAY: MALL ROAD, DELHI-09.
(Phone/FAX-01123818416)

No. HPTK-11(06)(02)/2013-14/
To
The Additional Director General(E)(NZ), Dated :-07-07-2013
Kind Attn: Deputy Director General(AVM),
All India Radio & Doordarshan,
Jamnagar House,Shahjahan Road,
New Delhi-110011.

Sub: Monthly report on the working of FM Transmitters at TV tower


Pitampura, Delhi for the month of June 2013 .

Sir,

Find enclosed herewith the above cited subject report for your kind
perusal and further action please.

Enclosures: As above- 6 pages.

Yours faithfully

(Bal krishna)
Assistant Director (Engg.)
For Deputy Director General (Engg.)

1
STATISTICAL DATA (F.M. TRANSMITTERS)
FOR THE MONTH OF JUNE 2013

F.M. I F.M. II
BREAKDOWNS + SHUTDOWNS
( Rainbow) (Gold)
Numbers 00 00
Major
B/D Duration 00:00 00:00
due to
GEAR Numbers 00 00
Minor
Duration 00:00 00:00
Numbers 00 00
Major
B/D Duration 00:00 00:00
due to
POWER SUPPLY Numbers 1 6
Minor
Duration 00:01 00:06
Numbers 01 01
Major
B/D Duration 00:29 00:27
due to
O/C Numbers 01 2
Minor
Duration 00:08 00:11
Numbers 0 0
Major
RF Shutdown Duration 00:00 0:00
(SD) Numbers 00 00
Minor
Duration 00:00 00:00
Numbers 1 1
Total BD + SD Major
Duration 00:29 0:27
Numbers 2 2
Minor Duration 9 00:11

RF Shutdown = SD

2
STATISTICAL DATA
FOR THE MONTH OF JUNE 2013

FM I FM II
MONTHLY FIGURES (10KW) (R&S) (20 KW) (Nautel)
Hours of Testing 00:00 00:00
WORKING OF
Hours of Programme 720:00 720:00
TRANSMITTER
Total Working Hours 720:00 720:00
B/D due to Gear 00:00 00:00
Percentage 0.00% 0.00%
B/D due to P/S 00:01 00:06
Percentage 0.00231% 0.01389%
BREAK DOWNS/ B/D due to O/C 00:37 00:38
INTERRUPTIONS
Percentage 0.08565% 0.08796%
/SHUTDOWNS
SD 0:00 00:00
Percentage 0.0% 0.0%
Total (BD+SD) 0:38 0:44
Percentage 0.08796% 0.1018%

FM I FM II
PROGRESSIVE TOTAL (10KW) (R&S) (20 KW) (Nautel)
Hours of Testing 00:00 00:00
WORKING OF
Hours of Programme 2184:00 2184:00
TRANSMITTER
Total Working Hours 2184:00 2184:00
B/D due to Gear 00:00
00:00
Percentage 0.00% 0.00%
B/D due to P/S 00:01 00:20
BREAK DOWNS/ Percentage 0.00076% 0.01526%
INTERRUPTIONS\ B/D due to O/C 00:37 00:38
SHUTDOWN Percentage 0.02824% 0.0299%
SD 00:00 00:00
Percentage 00:00% 0.00%
Total(BD+SD) 00:38 00:58
Percentage 00:029% 0:0443%
3
BREAKDOWN IN RESPECT OF FM TRANSMITTER
FOR THE MONTH OF JUNE 2013

FM I TRANSMITTER (102.6 MHz) (RAINBOW)


B/D due to GEAR
B/D Timing Duration
Date Cause
From To Hours Minutes

Total 0 0

B/D due to POWER SUPPLY FAILURE


B/D Timing Duration
Date Cause
From To Hours Minutes
06/062013 2058 2059 - 1 PSF
Total 0 1

B/D due to OTHER CAUSES


B/D Timing Duration
Date Cause
From To Hours Minutes
16/06/2013 1016 1024 0 8 No programme from NBH
25/06/2013 1534 1603 0 29 No programme from NBH
Total 0 37

Momentary Interruptions
Date MI Timing Cause
06/06/2013 2020 MI due to PSF

RF Shut down
B/D Timing Duration
Date Cause
From To Hours Minutes

Total 0 0

4
FM II TRANSMITTER (106.4 MHz) (GOLD)
B/D due to GEAR
B/D Timing Duration
Date Cause
From To Hours Minutes
-

Total -

B/D due to POWER SUPPLY FAILURE


B/D Timing Duration
Date Cause
From To Hours Minutes
06/06/13 2058 2059 00 1 PSF
09/06/2013 2115 2116 00 1 PSF
16/06/2013 0919 0920 00 1 PSF
16/06/2013 0934 0935 00 1 PSF
22/06/2013 2126 2127 00 1 PSF
23/06/2013 1740 1741 00 1 PSF
Total 00 6

B/D due to OTHER CAUSES


B/D Timing Duration
Date Cause
From To Hours Minutes
21/06/13 1630 1636 00 6 Programme failed at studio end of NBH
25/06/13 1534 1601 00 27 Programme failed at studio end of NBH
27/06/13 1700 1705 0 5 Programme failed at studio end of NBH
Total 0 38

Momentary Interruptions
Date MI Timing Cause
06/06/13 1850, 2020 TXR tripped
07/06/13 1128 PSF
12/06/13 1447, 1451 c/o between main & standby TXR
20/06/13 0704 PS Fluctution
28/06/13 1808 PS Fluctution.

RF Shut down
B/D Timing Duration
Date Cause
From To Hours Minutes
0 0

Total 0 0
5
STATUS OF DG I(For FM RAINBOW)
FOR THE MONTH OF JUNE 2013

HMR OF D.G. Set as on 30/06/13 346


HMR OF D.G. Set as on 31/05/13 334
For Testing 2Hrs 35mins
D.G. Set running
during the month of For Transmission 9Hrs 28mins
JUNE 2013 Total Running 12Hrs 03mins
Balance in tank as on 1/06/13 45Litres
Added in tank during JUNE 100*
DIESEL Balance in tank as on 30/06/13 13Litres
POSITION
Consumed during JUNE 132Litres
Average Consumption 11 Litres/Hour
*Was taken from IGNOU kept as spare.
STATUS OF DG II (For FM GOLD)
FOR THE MONTH OF JUNE 2013

HMR OF D.G. Set as on 30/06/13 390


HMR OF D.G. Set as on 31/05/13 378
For Testing 2Hrs 35mins
D.G. Set running
during the month of For Transmission 9Hrs 28mins
JUNE 2013 Total Running 12Hrs 03mins
Balance in tank as on 1/06/13 185Litres
Added in tank during JUNE --
DIESEL Balance in tank as on 30/06/13 70Litres
POSITION
Consumed during JUNE 115Litres
Average Consumption 9.5 Litres/Hour

6
Important Work Done During The Month

Sr.No Date Work Done


1. 06/06/13 Control circuit of the FM Gold Transmitter often hangs after
power supply fluctuation. So fault was thoroughly analyzed
and checked step by step. Finally fault were located in IC
Base of Op-amp U-13 & U-14. both IC base cleaned
properly. IC Pins also cleaned. Since XTR working
normally.
2 12/06/13 The FM Gold transmitter was not switching ON. Fault was
found to be with the power supply corresponding to PA
no.C. It was changed with an old one kept in spare.