Professional Documents
Culture Documents
2 Running Lost control of wire due Damage to redundant 3 2 MR 1. Approved Anchor Handling Procedure 3 1 LR
Anchor / Anchor to failure of umbilical / subsea structure 2. DP Vessel as AHT
Wire comunication or control 3. Reliable and well maintained vessel (with
system MWS approval)
4. Competence Vessel Captain
5. Maintain good communication between
Anchor Tower and AHT
AHT collision with the Damage to vessel or 5 3 HR 1. Approved Anchor Handling Procedure 3 1 LR
platform / complex complex (damage to riser) 2. JSA for Anchor Handling
Personnel injury 3. Weather limit for Anchor Handling
Schedule delay 4. Parachute Buoy
5. DP Vessel as AHT
6. Reliable and well maintained vessel (with
MWS approval)
7. Competence Vessel Captain
8. Maintain good communication between
Anchor Tower and AHT
9. Weather limit
10. Briefing about the facility for all Vessel
Captain including the location of risers
11. Secondary AHT standby in the field at all
time
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 1 of 16
HAZID WORKSHEET
3 DLB Approach / DLB colission with Damage to both DLB and 5 2 HR 1. Approved Anchor Handling Procedure (Step 3 1 LR
Final Departure platform and riser Platform by Step DLB Approach to AGX)
of AGX Personnel injury / Lost of life 2. Weather limit
Schedule delay 3. Maintain good communication with all
Environmental impact parties
4. Final approach only after all anchors are
installed / laid and DAY Light only.
5. Shut Down the platform and Depressurize
West Lobe line during Final Approach
6. AGX Riser is inside the Jacket
7. Responsible person on DLB monitoring the
gangway tip during final approach
8. Minimize personnel on AGX during DLB
final approach
9. Complete GO and No GO Checklist for the
DLB Final Approach to AGX
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 2 of 16
HAZID WORKSHEET
Crane Boom collision Damage asset causing HC 4 3 HR 1. All Cranes will be under the control of the 3 1 LR
with the AGX Topside leak Project (CTR).
and/or with Other Crane Personnel injury 2. Designated Person In Charge for Every Lift
Schedule delay 3. Good illumincation
4. Procedure control for Cranes Operations
(SIMOPS)
5. Detail planning meeting for Crane
Operations
6. Trained and experienced Crane Operator
and Rigging Personnel
7. Maintain good communication among all
involved parties
Crawler Crane fall over Damage asset causing HC 3 2 MR 1. Weather limit 3 1 LR 1 1. Risk Assessment to be Timas/POI
the side due to bad leak / Environmental impact 2. Barge rails in place performed for using the
weather related during Personnel injury 3. Certified and good condition crane Crawler Crane for Personnel
lifting (overloaded / Schedule delay 4. Certified and good condition rigging Transfer related to the
dynamic load) equipment visibility (ability of the Crane
5. Certified and experienced Crane Operator Operator to see the FROG)
and Rigging Personnel
6. Operate cranes within the design limit
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 3 of 16
HAZID WORKSHEET
Electrical Equipment on Increase risk of 1 1 LR 1. Gas is lighter than air (Gas-Gas Exchanger 1 1 LR 3 Explore the possibility to Timas
DLB (Lights, Etc) Fire/Explosion in the event is +16 elevation) switch off the lights and other
of HC release 2. F&G and ESD System on AGX ignition source on crane
3. ERP Procedures
4. Platform will inform the DLB in case of F&G
detection system on platform is activated
5. PM on platform e.g. leaks prevention
6. Switch off the light on Crane Boom during
the Day Light
7. Weather proof lighting/electrical system on
the barge deck and crane boom
8. DLB can be pulled / winched away (winch
speed approx 60m per minute)
9. Construction activities around process area
controlled by PTW asper integrated project
plan
10. Portable Multi-Gas Detector on Stern of
DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 4 of 16
HAZID WORKSHEET
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 5 of 16
HAZID WORKSHEET
COMMENT: The probability (frequency) of having leaks will be further elaborated (POI)
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 6 of 16
HAZID WORKSHEET
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 7 of 16
HAZID WORKSHEET
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 8 of 16
HAZID WORKSHEET
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 9 of 16
HAZID WORKSHEET
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 10 of 16
HAZID WORKSHEET
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 11 of 16
HAZID WORKSHEET
Helicopter Emergency Increase Risk of Fire on 2 2 LR 1. DLB can be pulled / winched away from the 1 1 LR
on DLB Platform (AGX) if there is Platform (winch speed is approx 60m per
concurrent HC Release minute).
2. F&G System and Fire Fighting System on
the DLB
3. ERP
4. Portable Gas Detector on the STERN of the
DLB.
8 Process Upset Increasing Flaring Rate Increase Radiant Heat in the 2 2 LR 1. Radiant Heat Study for AGX shows that it is 1 1 LR
on AGX due to Blow Down Event vicinity of AGX Crane safe for the Crane Operator to be inside the
Crane Cabin during Full Process Blow Down.
NOTE: No Effect anticipated 2. Proximity of DLB Crane Operator is farther
to the DLB based on Flare from the Flare Tip therefore impact of Radiant
Radiation Study Heat is minimal.
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 12 of 16
8 Process Upset
on AGX
HAZID WORKSHEET
Gas Release Anoa Riser Fire / Explosion 5 2 HR 1. Mitigation as per CTO Procedure 5 1 HR
Personnel Injury 2. F&G System on AGX
3. ERP Procedures
4. Platform will inform the DLB in case of F&G
detection system on platform is activated
5. DLB can be pulled / winched away to clear
from platform (winch speed approx 60m per
minute)
9 Helicopter Interference with Crane Helicopter collision with 4 3 HR 1. Crane Operations on DLB will be shut down 3 1 LR
Operation on Operation Cranes / Crash and/or crane boom would be clear for
DLB Personnel injury / Lost of life Helicopter Operations
2. Trained and experienced HLO
3. Inform Crane Operators of Incoming
Helicopters
4. ERP
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 13 of 16
HAZID WORKSHEET
11 SIMOPS DLB Crane Boom Damage asset 4 3 HR 1. All Cranes will be under the control of the 3 1 LR
Operation collision with the AGX Personnel injury Project (CTR).
Between DLB Crane Schedule delay 2. Designated Person In Charge for Every Lift
Crane and AGX 3. Good illumincation
Crane 4. Procedure control for Cranes Operations
(SIMOPS)
5. Detail planning meeting for Crane
Operations
12 Personnel Personnel being Personnel injury / Lost of life 5 3 HR 1. Certified and good condition Crane 2 1 LR
Transfer Transferred Fall from 2. Certified and good condition FROG
Height 3. Certified and good condition rigging
4. Provision of safety sling
5. No personnel transfer untill the Vessel will
be securely moored
6. Distance of free board between DLB and
vessel is small
7. Provision of tag lines
8. Familiarization for transfer using FROG
9. Maintain good communicaton among
parties involved (CO, Bunksman, and
Riggers).
10. Weather limit defined for personnel
transferring using FROG and Crawler Crane
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 14 of 16
HAZID WORKSHEET
14 N2 Operation Extreme Temperature Personnel injury 3 3 MR 1. Engineered and certified ISO Storage 3 2 MR 5 Verify the certification of the Timas / PNS
(minus 160 - minus 200 Cryogenic Tanks storage tank and inspection
C) Embrittlement 2. Scaffold and bunded area prior to mobilization offshore
3. Use of planks and tarpaulin
15 3rd Party Collision with the Anchor Personnel Injury 3 2 MR 1. High Vis Anchor Buoy 3 1 LR
Vessel / Security Buoy / Anchor Wire Asset Damage 2. Standy By Vessels
Schedule Delay 3. Radar Watch
4. Intensity of Marine Activities would deter
the 3rd Party Vessel to stay away
5. Liaison Officer onboard of DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 15 of 16
HAZID WORKSHEET
17 Communication Clear Communication Increase risk of 3 2 MR 1. ANOA HSE Induction / Awareness 3 1 LR 8 Establish radio Timas/POI
between DLB Method NOT miscommunication / 2. Various coordination meeting e.g. daily communication channel for all
and its Support established interference leading to planning meeting parties to minimize
Vessels and incident resulting to: 3. Provision of radio communication interference
between DLB - Personnel injury 4. English speaking key personnel
and AGX/ANOA - Asset damage 5. Permission to be obtained from HOFO prior
to entering 500m zone
6. Permission to be obtained from Marine
Superintendent for approaching DLB or
entering the Anchor Pattern
7. Competent Vessel Captain
8. Briefing of all support vessels include
socialization of procedures
9. Complete GO and No GO Checklist.
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 16 of 16