Document N: 003

SWS CONSULTANCY
?e wK= ?e cMc=
Eq MWM Issue N: 003
(Time Extension Summary)
Project:- Construction of Koye Feche
Condominium Site Sewerage System
(Lot-I)
Location:- Addis Ababa
Client :- Addis Ababa Housing Construction
Project Office (AAHPO)
Consultant:- SWS Consultancy
Contractor:- Luci Engineer PLC
Site Hand over date:- February 25,2016
Mobilization:- -
Contract Period:- 120 Calendar days
Commencement day:- March 9,2016
Completion date:- July 6,2016
Time Extension given based on Variation:-
Previously approved no of calendar days:- 66 calendar days
Previous total time extension approved :- 260 calendar days
This period time extension approved:- 46 calendar days
Total time extension approved :- 306 calendar days
Revised construction time (in calendar days):- 426
Revised Completion time:- May 9, 2017
Actual completion time:- -
Unjustified delay:- -
Liquidated damage in Birr:- -
Liquidated damage in % out of the contract -
amount:-

_____________________________ ____________________________
Prepared Approved

This period time extension requested for approval is 46 calendar days, 7 of which are requested to
complete all the remaining works.39 of which (from 23 March, 2017,i.e end of project completion
date to 02 May, 2017) are requested for approval due to the existing obstruction/right of way
problems until 02 May, 2017.

Only for this project use