You are on page 1of 2

ALSTHOM

Division Electromcanique

INDUSTRIAL FACILITIES - IMPORT


(I.F.I.)

Contract Nr. 14-421-27117-7-3460-11

POWER PLANT THYROW 2

Part 0 Volume 1

EQUIPMENT DOCUMENTATION

MANUALS

OPERATING INSTRUCTIONS

MAINTENANCE & REPAIR TECHNOLOGY


Appendix Nr. 2 - Thyrow II Page 5

2. System components including the


necessary accessories and
technical data
------------------------------------------------------
--

2.1 1 Fuel supply facility diesel fuel


2.1.1. Slop facility
2.1.1.1. Technical data:
.
Slop oil tanks in the area of gas turbine
facilities: Nominal content l x 4 m3

Slop oil tanks for the DK- Drainage of the


Lines:
Nominal content
1 x 6 m3
Feed pump for each slop oil
container:
Discharge 4 m3/h
Discharge head O,3 MPa
Engine capacity 1,0 kW
2.1.1.2. Scope of supply

- 2 Slop oil pumps

- 2 Slop oil tanks with fill level


indicator, End position signalization
for the control stand and manual pump
switching on site
- Fittings and gas flanges, gaskets
and screws to the existing slop oil
tank and up to the existing tank
system
- Electrotechnical (Elt.) and
measuring, control system (MCS)
equipment
2.1.2. Diesel tank system accessories