You are on page 1of 4

WALL WITH 6" CHB: 1 SQM

UNIT
COST
SCOPE OF WORKS QUANTITY UNIT
MATERI
ALS
MASONRY
6" CHB (NLB) 13.00 pcs 17.00
Sand 0.084 m 700.00
Cement (40kg) 1.00 bag 255.00
10mm x 6000mm Deformed Steel Bar Grade 33 0.25 pcs 105.00
Tie Wire Ga.16 0.04 kgs 52.00

PLASTERING
Sand 0.050 m 700.00
Cement (40kg) 0.800 bag 255.00

PAINTING WORKS
Thinner 0.08 gal 353.85
Masonry neutralizer 0.10 gal 422.00
Latex Paint 0.06 gal 490.06
Semi Gloss Latex Paint 0.06 gal 501.00
Lacquer Spot Putty 0.08 gal 640.70
QDE Paint 0.08 gal 592.00

WATERPROOFING 1 m2 157.50
UNIT UNIT
MATERI UNIT COST +
COST COST&LABOR *
AL LABOR
LABOR QUANTITY
COST

- 6.00 23.00 299.00


- 425.00 1,125.00 94.95
- 100.00 355.00 355.00
- 0.85 105.85 26.46
- 450.00 502.00 20.08
SUB-TOTAL 795.49
labor cost 218.75
TOTAL 1,014.24

- 425.00 1,125.00 56.25


- 100.00 355.00 284.00
SUB-TOTAL 340.25
labor cost 306.25
TOTAL 646.50

- 200.00 553.85 44.75


- 520.00 942.00 94.20
- 520.00 1,010.06 60.60
- 600.00 1,101.00 66.06
- 645.00 1,285.70 102.86
- 500.00 1,092.00 87.36
SUB-TOTAL 190.22
labor cost 29.75
TOTAL 219.97
450 607.50 607.50
OVER ALLTOTAL 2,488.21
WALL WITH 4" CHB: 1 SQM

SCOPE OF WORKS QUANTITY UNIT

MASONRY
4" CHB (NLB) 13.00 pcs
Sand 0.044 m
Cement (40kg) 0.05 bag
10mm x 6000mm Deformed Steel Bar Grade 33 0.25 pcs
Tie Wire Ga.16 0.04 kgs

PLASTERING
Sand 0.040 m
Cement (40kg) 0.800 bag

PAINTING WORKS
Thinner 0.08 gal
Masonry neutralizer 0.10 gal
Latex Paint 0.06 gal
Semi Gloss Latex Paint 0.06 gal
Lacquer Spot Putty 0.08 gal
QDE Paint 0.08 gal
UNIT
UNIT COST MATERIAL UNIT COST UNIT COST&LABOR *
COST
MATERIALS COST + LABOR QUANTITY
LABOR

15.00 - 6.00 21.00 273.00


700.00 - 425.00 1,125.00 49.28
255.00 - 100.00 355.00 18.64
105.00 - 30.00 135.00 33.75
52.00 - - 52.00 2.08
SUB-TOTAL 376.74
labor cost 218.75
TOTAL 595.49

700.00 - 425.00 1,125.00 45.00


255.00 - 100.00 355.00 284.00
SUB-TOTAL 329.00
labor cost 306.25
TOTAL 635.25

353.85 - 200.00 553.85 44.31


422.00 - 520.00 942.00 94.20
490.06 - 520.00 1,010.06 60.60
501.00 - 600.00 1,101.00 66.06
640.70 - 645.00 1,285.70 102.86
592.00 - 500.00 1,092.00 87.36
SUB-TOTAL 190.22
labor cost 29.75
TOTAL 219.97
OVER ALLTOTAL 1,480.46

You might also like