Professional Documents
Culture Documents
Title: SAP PM
Module: PLANT MAINTENANCE
SAP Release Ver.: SAP ECC 6.0
Created by: MAHESH RAI
Created on: 06/05/14
Title: SAP PM
June 2014
User Manual
Table of Content
S.No. Page No.
1.
Introduction ..................................................................................... 3
2.
Getting Started ................................................................................. 4
3.
Master Data..................................................................................... 12
3.1
Functional Location .......................................................................................................12
3.2
Equipment ......................................................................................................................24
3.3
Measuring Points ............................................................................................................37
4.
Maintenance Processing................................................................ 44
4.1
Measuring documents...............................................................................................................46
4.2
Breakdown Maintenance Process: ...........................................................................................55
4.3
Preventive Maintenance............................................................................................................94
4.4
Regular Maintenance: ..............................................................................................................130
5. Plant Maintenance Information System ...............................137
5.1 Standard Reports.................................................................................................................
1. Introduction
SAP R/3 is an integrated and industry independent standard software
Which covers integrates and connects all functional areas in a business.SAP
AG defines integration as "defined communication". Although R/3 is
designed for complete integration, it can also be used for a couple of business
areas.
Master data maintenance and transaction processes are explained with the
help of SAP screen Shots. This will help you in executing the same perfectly.
2. Getting Started
LOG ON:
Sap R/3 systems are client systems. The client enables you to run
Several business operations at the same time in one SAP R/3 system.
Client is, in organizational terms, an independent unit in the system.
Clients have their own data environment and therefore their own user
master and transaction data, assigned user master records and chart
off accounts and specific customizing parameters.
So that you log on to SAP R/3 system, you must have a master record
created for you for corresponding client. For reasons of access
protection, you must enter a password when you log onto the sap system. The
system does not display the password you enter.
SAP R/3 system is available in several languages. Use the language
input field to select the log on language for each session.
Standard Tool Bar: the push buttons in the standard tool bar are found
on every screen in an SAP R/3 system. Any push buttons that cannot
be used in a particular application are grayed out. If you place your
cursor on a push button for a while the system displays a quick info text
that explains the push button function.
The Application Tool Bar: shows which functions are available in the
current application.
Status bar: the status bar displays information on the current system
status, for example. Warning or error messages
Menu bar: the menus shown here depend on which application you are
working in.
Title bar: the title bar displays the functions that are available for the
user.
Radio Buttons: allow you to choose exactly one item form a selection.
Sap easy access is the standard entry screen displayed after the logon.
You navigate through the system using the tree structure.
Selecting Functions
1. Menu Option
2. Favorites
3. Entry in the SAP easy Access menu
* Use F4 to display possible inputs. You can also access F4 help for a
Selected field using the button immediately to the right of that field.
3. Master Data
3.1 Functional Location
Functional locations are elements of a technical structure (for example,
functional units within a system). Functional locations can be created
according to the hierarchy, and can be structured based on the following
criteria:
*Functional
*Process-related
*Spatial
Procedural Steps
Description:
Use this transaction for creating structured location
Double CLICK on selected line or press Enter to get following screen
Instructions
In the initial screen, enter the values in the following fields:
Field Name Required/Optional User action and allowed values
Functional location R Functional location code is to be entered as
per the structure
3.2 Equipment
A piece of equipment is an individual object that is to be maintained
independently.
Each piece of equipment is managed independently in the system, so that you
can:
Manage individual data from a maintenance perspective for the object
Perform individual maintenance tasks for the object
Keep a record of the maintenance tasks performed for the object
Collect and evaluate data over a long period of time for the object
Pieces of equipment can be installed and dismantled at functional locations.
The usage times for a piece of equipment at a functional location are
documented over the course of time.
Trigger:
Maintenance history needs to be captured for a physical technical object.
Whenever any new Machine/Computer etc. Purchased we need to create
Equipment Master.
Correct Equipment Type has to be chosen always for proper functioning.
Description:
Use this transaction for creating & maintaining Equipment
Double click or press Enter Key to reach the following screen
Instructions
In the initial screen, enter the values in the following fields:
Screen
First dismantle the already existing installation and then input/select new
WARRANTY END
WARRANTY DATE
START DATE
Measuring points
Counters
Trigger:
If measuring point is normal measuring point and if data like max. and min.
range is to be given then click on Additional data tab. This data will
determine for automatic generation of notification whenever entered reading
is beyond extreme limits.
4. Maintenance Processing
4.1 Measuring documents
Measurement readings are to be taken at measuring points in particular
Measurement units at particular intervals. (For example, the feed water
temperature in degrees Celsius of the boiler daily at 6.00 am)
Trigger:
A measurement or counter reading from a measurement point needs to be
entered into the system.
Notifications
Notification is a means, by which internal company notifications like
equipment malfunctions; breakdowns, maintenance requests or activity reports
etc are entered and managed in Plant Maintenance.
Notifications can be created on Equipment and Functional locations.
Trigger:
An internal problem or maintenance request needs to be logged for
problem reporting and technical resolution.
IT Report (IT)
An IT report describes a malfunction of an object, which restricts the
performance of that object in some way. A user can use a malfunction report
to inform the maintenance department that a system is not functioning
correctly, is not working at all, or is producing poor results. Malfunction
reports are intended to prompt the maintenance department to carry out a
maintenance task to restore the target condition of the object.
After selecting the transaction, press Enter key or double click to reach the
following screen
In the Initial screen, you can select the type of Notification and press ENTER
Maintenance Orders
To carry out internal maintenance jobs or external services as per the
maintenance requests or according to day to day observations and for
preventive maintenance activities, a maintenance order is to be prepared to
plan for material, manpower and services requirement.
On the basis of maintenance orders only, maintenance jobs costing,
reservation for material and manpower planning can be done.
Functional Locations
Equipments
Notifications
Direct/Adhoc
Please use appropriate type of order, for capturing the data under various
categories.
>Press ENTER
>WE find this screen which show last 3 activities status on that particular
equipment
Notification Header
Notification-Put in process:
Enter the notification number in Notification box or select from the list
Press Enter key or click on Notification to reach the following screen
Enter / check Order Type, Main work center and click on Enter /
Continue icon
To reach the following screen
For planning in terms of manpower and material and for further processing of
order,
After entering required details, save the order and following
message will appear on the screen.
Notes:
If the operations are more than one operation, use the operation
tab strip, and enter as many operations as required.
The work centers for different operations can be different. (If required).
Control Key PM01 Denotes - Work done by Own Employee & PM03
denotes - work done by External Vendor. For PM03 Purchase Requisition will
be created automatically. Which will go for Release Process & then Purchase
Order will be created?
Fill the Material Group, Purchasing Group, Requisitioner name, Tracking No.
Then Click on this
Notes:
Item category - significance of L and N
The system will create a PR for the Items for which N is indicated.
v) COMPLETION CONFIRMATION
A.TIME CONFIRMATION
Trigger:
Actual hours worked and materials used need to be recorded and posted to the
PM order.
Press Enter key or double click (with mouse Left key) to reach the
following screen;
Menu Path
OR
All data that refers to the reference object of the maintenance order is
available and correct
All relevant data in the operations and sub-operations is available and correct
The business completion function for an order defines the following
information for the order:
Maintenance Planning:
The maintenance planner also needs to identify the units for the maintenance
plans -
Time (weekly, monthly, yearly, etc.) or performance (every 100 running
hours, every 10,000 shots etc.). For performance based maintenance plans,
relevant measuring counter needs to be defined for the technical object and
measurement readings need to be updated regularly.
The maintenance planner decides the maintenance call objects for the plan.
The call object can be maintenance order, notification or service entry sheet.
Based on the selection, system generates a call object for a maintenance
plan, when a maintenance call is due. The maintenance planner decides
initially which call object is required.
For the activities, which are common amongst group of equipments, a general
task list may be prepared.
Tcode :IP01
Once the maintenance plans are created, then these plans are scheduled.
It is important to input Start date or Starting counter reading in the
individual maintenance plan. This date or counter reading decides the
schedule dates.
The maintenance planner shall schedule the maintenance plan. Before the call
Objects are created by the system; maintenance planner may manually call the
job or skip the job, depending on the situation.
Tcode: IP10
Tcode: IW39
Order Release
Preventive Maintenance orders will be already released. If order has been
released and subsequently additional operations are entered for it, these
are automatically released.
Withdrawing material
Posting goods receipts
Entering time completion confirmations
Tcode: IW32
Fill the Material Group, Purchasing Group, Requisitioned name, Tracking No.
Then Click on this
Notes:
N Means Non-stock able, but coded item - Even if stock is available N can
be indicated.
The system will create a PR for the Items for which N is indicated.
Trigger:
Menu Path
Tcode ML85 or ML81n Can be used to release the Service Entry Sheet with
proper authorization.
Trigger:
Actual hours worked and materials used need to be recorded and posted to the
PM order.
>Press ENTER
>WE find this screen which show last 3 activities status on that particular
equipment & then Save notification.
Select the Desired Notification & create the Regular maintenance Order
(Type: PM07).
Procedural Steps
Input data for selection, you can get the report based on the input data like
Measuring points
Equipment
Functional location etc,
Procedural Steps
Enter required data like Plant, Storage Location, Movement type etc., as per
your report requirement
to execute the transaction and you will get the following report
Selection screen
Enter required selection filed values like Order no, Material, storage location
as per your requirement
Selection screen
Enter the selection screen values like Maintenance Plants, Start & end dates,
Notification no, Equipment or Function locations and select required check
boxes according to the status.
Procedural Steps
Selection screen
Enter the selection screen values like Start & end dates, Notification
no.,
Equipment or Function locations and select required check boxes according to
the status.
Procedural Steps
Selection Screen
Select Required Order type, Enter period dates and select different parameters
for the multilevel display
Trigger:
Need to look up Functional Locations.
Procedural Steps
Selection Screen
Equipment List
Transaction code: IH08
Trigger:
Procedural Steps
Selection Screen