Installation for

Ratio Flow Controllers

The Chemguard 2 , 3, 4, 6 and 8 controllers of what the incoming water pressure is at the
are one component in a Bladder Tank Balanced proportioning controller. The combined total
Pressure Foam Proportioning Fire Protection equivalent length of pipe, fittings, valves, etc., in
System. The 3, 4, 6 and 8 controllers are both the water supply inlet piping and the foam
designed to be mounted between two 150 lb. flat concentrate discharge piping should not exceed
face pipe flanges. The 2 proportioner has a 50 equivalent feet (15.2 meters). As the foam
female NPT threaded inlet with a 2 male NPT concentrate is pushed out of the bladder into
threaded outlet. the concentrate piping, there is approximately 1
psi to overcome due to friction loss of the foam
For the foam system to function correctly, it is concentrate at the connection to the piping
important that the following installation guidelines between the bladder tank and the controller.
are followed:
When installing the water feed pipe to the
The controllers are designed to be mounted in
bladder tank, ensure that this ware supply to the
the water supply system feed line in either a
bladder tank is installed upstream from the
horizontal or a vertical configuration.
controller.
Establish that the fire protection system design
flow rate in gpm is within the flow range of the Refer to the controller data sheet regarding the
controller before installation. required length of straight pipe upstream and
downstream from the controller.
Check the foam concentrate inlet orifice to
ensure that the correct size orifice has been When installing the between flange controller,
installed for the type of foam concentrate that be sure that gaskets are used to obtain a good
will be used in the system. seal between the pipe flange and the flange
face on the controller.
A directional arrow is displayed on the body of
the controller. This indicates the direction of the When the controller is mounted at a location
system flow. Ensure that the controller is below the top flange of the bladder tank or if the
mounted with the arrow going towards the tank is under a constant water pressure, it is
system discharge devices. recommended that an automatic valve
(normally closed) be installed on the foam
When the between flange type of controller is concentrate line. This valve will prevent
correctly mounted, the recovery section of the siphoning of the foam concentrate from the tank
controller (shaped like a bell) is actually located and prevent the possibility of any water
inside the system pipe. If mounted correctly, the contamination in the concentrate area of the
foam solution leaving the recovery section is tank.
flowing towards the discharge devices.
When mounted correctly, between flange type
The distance from the bladder tank to the controllers are designed to sit inside the bolt
controller is critical. When designing the piping circle used to bolt two pipe flanges together.
arrangement to/from the bladder tank, it is
important to have foam concentrate pressure at Reference Bladder Tank Installation and
the proportioning controller balance to within 2 Design Information for typical ratio flow
psi controller installations.

CHEMGUARD
204 S. 6th Ave Mansfield, Tx 76063 (817) 473-9964 FAX (817) 473-0606
www.chemguard.com