Title: LOMB-EDRE-PP-40-29B Replenishment of Component

Materials to Assembly Line

Module: PP

BPS

Change History
Update the following table as necessary when this document is changed.

Date Name Change Description

08/13/2010 Edward O Created

Script Identification Number


LOMB-EDRE-PP-40-29B

Script Title
Replenishment of Component Materials to Assembly Line

Team Owner
PP

Script Execution Order

Responsible Person:
Date, initial, and check after step is completed and pass to next team.
___Step 1. PP: MMBE - Display Stock Overview.
___Step 2. PP: PK13N - KANBAN board: Demand Source Overview: Initial Screen
___Step 3. PP: PK21 - KANBAN Signal
___Step 4. LO: LT01 - Create Transfer Order.
___Step 5. PP: PK13N - KANBAN board: Demand Source Overview: Initial Screen
___Step 6. PP: MF60 – Material Staging for Planned Orders
___Step 7. PP: MMBE - Display Stock Overview.

Script Description
Replenishment of Component Materials to Assembly Line.

Assumptions
KANBAN must be set up before this script can be executed

Filename: LOMB-EDRE-PP-40-29B Replenishment of Component Materials to Assembly Line


Last Modified: 8/13/2010
Procedure

1. KANBAN _ Material: PULL [Source: WH, Batch (Overnight)]

Step 1 - PP - MMBE - Display Stock Overview.

Menu Path: Select LogisticsMaterial managementInventory Management


Environment Stock Stock Overview

Transaction Code: MMBE

Team: PP
Screen Title: Stock Overview: Company Code/Plant/Storage Location/Batch
Enter this:

Field Name Data

Plant EDRE

Material ED0021000890-S

Expected Results:

Actions/Expected Results Actual Results

Click on the “Execute” button. Inventory for Plant and Storage location is
displayed.

Record Inventory in the Specified Storage NONE


locations.

Step 2 PP- PK13N KANBAN board: Demand Source Overview: Initial Screen

Menu Path: Select LogisticsProductionKANBANControlKANBAN Board


Demand Source View

Transaction Code: PK13N

Team: PP
Screen Title: KANBAN board: Demand Source Overview: Initial Screen

Enter this:

Filename: LOMB-EDRE-PP-40-29B Replenishment of Component Materials to Assembly Line


Last Modified: 8/13/2010
Field Name Data

Plant EDRE

Supply Area <Supply Area>

Material ED0021000890-S

Expected Results:

Actions/Expected Results Actual Results

Click on the “Execute” button. KANBAN Bins are Displayed for Supply area
and Material

Use “TO EMPTY” or “TO FULL” options to Bin status will change.
set the bin status.

Step 3 - PP – PK21 KANBAN Signal

Menu Path: Select LogisticsProductionKANBANControlKANBAN Signal


Manual entry

Transaction Code: PK21

Team: PP
Screen Title: KANBAN SIGNAL

Enter this:

Field Name Data

Plant EDRE

Supply Area <Supply Area>

Material ED0021000890-S
KANBAN number < Number>

Expected Results:

Actions/Expected Results Actual Results

Click on the “Execute” button. System suggests to modify the Bin status .

Use “ EMPTY” or “ FULL” or “WAIT” option Bin status will change.


in the NEXT STATUS tab.

Filename: LOMB-EDRE-PP-40-29B Replenishment of Component Materials to Assembly Line


Last Modified: 8/13/2010
Step 4 :LO – LT01 Create Transfer Order.

Step 5 PP – PK13N KANBAN board: Demand Source Overview: Initial Screen

Menu Path: Select LogisticsProductionKANBANControlKANBAN Board


Demand Source View

Transaction Code: PK13N

Team: PP
Screen Title: KANBAN board: Demand Source Overview: Initial Screen

Enter this:

Field Name Data

Plant EDRE

Supply Area <Supply Area>

Material ED0021000890-S

Expected Results:

Actions/Expected Results Actual Results

Click on the “Execute” button. KANBAN Bins are Displayed for Supply area
and Material

Use “TO EMPTY” or “TO FULL” options to Bin status will change.
set the bin status.

Check the Status of the Bins. Status changed.

Step 6 - PP - MMBE - Display Stock Overview.

Menu Path: Select LogisticsProduction Repetitive Manufacturing Material


Staging  MF60 – Pull List Trigger Replenishment

Transaction Code: MF60

Team: PP
Screen Title: Material Staging for Planned Orders

Enter this:

Filename: LOMB-EDRE-PP-40-29B Replenishment of Component Materials to Assembly Line


Last Modified: 8/13/2010
Field Name Data

Staging Type

Plant EDRE

Material ED0021000890-S

Expected Results:

Actions/Expected Results Actual Results

Click on the “Execute” button.

Filename: LOMB-EDRE-PP-40-29B Replenishment of Component Materials to Assembly Line


Last Modified: 8/13/2010
Step 7 PP - MMBE Display Stock Overview.

Menu Path: Select LogisticsMaterial managementInventory Management


Environment Stock Stock Overview

Transaction Code: MMBE

Team: PP
Screen Title: Stock Overview: Company Code/Plant/Storage Location/Batch

Enter this:

Field Name Data

Plant EDRE

Material ED0021000890-S

Expected Results:

Actions/Expected Results Actual Results

Click on the “Execute” button. Inventory against plant and Storage location is
displayed.

Record Inventory in the Specified Storage Inventory changed.


locations.