07:30 to 08:00 Tool box talk, discussed and briefed about the project work
08:00 to 08:30
07:20 to 09:00 Rigging tension line for access to the appropriate location
09:00 to 1:00
01:00 to 02:00 Lunch break
02:00 to 02:30
02:30 to 03:45
3:45: to 04:00
PROJECT SUMMARY
Total project scope complete Total clading to be installed: 30 nos Clading Installed: 11 nos