S.No. DESCRIPTION Completion Date Status as on 21.04.

2014
Fire Alarm System:
1 Cable Laying Completed Completed
2 Above Detectors Installation 20-04-2014 Completed
Cable laying for other IBMS services like BAS is
pending. So, False ceiling shall not be closed.
3 Below Detectors Installation 30-04-2014
However device installation can be started at the
places where clearances done.
Location confirmed & respective marking is also done
4 Fire Alarm Panel Installation 25-04-2014
@ Site.
Procured MCPs are 8nos whereas requirement as per
5 MCPs, Hooters & Modules Installation 30-04-2014
drawing is 11nos.
Location needs to be confirmed by
6 Repeater Panel Installation 30-04-2014
Architect/Consultant
Repeater Panel Cabling for From the date of clerance it will take 3
7 External area needs to be filled.
Communication days.
8 Response Indiacators 30-04-2014 Material is not procured
Public Address System :
1 Cable Laying Completed Completed
Cable laying for other IBMS services like BAS is
pending. So, False ceiling shall not be closed.
However device installation can be started at the
2 Speakers Installation 30-04-2014
places where clearances done. Major challenge is
that the procured Qty of Speakers are less as per the
approved/issued drawing
Location & capacity of rack confirmed but not yet
3 PA Rack Installation 30-04-2014
procured

4 Amplifiers Installation 30-04-2014 Rack is not yet procured.

Access Control System :


1 Cable Laying Completed Completed
2 Panels Installation 25-04-2014 Will be completed by 23.04.2014
Once Material Available at site it will Readers, Boimetric Readers, EMLocks, Push Button,
3 Device Installations
take one week time. Break Glass & Magentic Contact are not yet procured.
Once Material Available at site it will
4 Boom Barriers Not yet procured
take one week time.
CCTV System :
Cabling still pending for 8 cameras @ DRC-1 & has to
1 Cable Laying for Internal Building. Completed
be laid till Ground floor as per Mr. Suresh instructions.
Once Material Available at site it will
2 Video Encoders Installation Rack is not yet procured.
take 3days time.
Cable laying for other IBMS services like BAS, power
cabling for VRF units & ducting works are pending. So,
False ceiling shall not be closed. However device
Cameras Installation for Internal
3 30-04-2014 installation can be started at the places where
Building
clearances done. Major challenge is that the
procured Qty of cameras are less as per the
approved/issued drawing
Cable laying for Out side PTZ Once Material Available at site it will
4 Mounting(Poles) arrangement.?
Cameras take one week time.
Once Material Available at site it will
5 Power Supply Units for Cameras Power cabling(UPS) is pending for cameras
take 2days time.
BMS System :
1 Cable Laying for Internal Building. 30-04-2014 Qty estimation is required
2 Tray Laying 30-04-2014
Once Material Available at site it will
3 DDC Panels Installation Enclosure is not procured
take one week time.
Once get the PFC Details from the
4 Third Party Integration Termination
Vendor & it will take 2weeks time.
SAS System :
Drawing required at site& it will take
1 Cable Laying Drawing is not available
one week time.
Drawing required at site& it will take
2 PVC Pipe Laying Drawing is not available. Qty estimation is required
one week time.
Once get the Panels Location&it will
3 Panels Installation Location confirmation?
take two days time.
WLD&NOVEC 1230 System :
Once get the Panels Location&it will
1 Cable Laying Drawing is not available. Qty estimation is required
take two days time.
Once get the Panels Location&it will
2 Panels Installation Location confirmation?
take two days time.
Remarks

Need False ceiling clearance at site.

Panel Location Confirmation required.

Panel Location Confirmation required at Security


Room.
External Area Clearance required at site.
Need False ceiling clearance at site&Material not
available at site.

Need False ceiling clearance at site&Back Box required


at Cellar Floor.

Rack Location required&Material not available at site.


Speakers are Shortage as per drawing & Amplifiers
Available at site
480W=2nos,120W=1no&Controller=1no.

Readers,Boimetric Readers,EMLocks,Push
Button,Break Glass&Magentic Contact not available at
site.
Materail not available at site & required location
confirmation.

As per drawing 24 cameras are there in DRC-1 &


encoder can support 16cameras only

Required Rack for Video Encoders Installation.

False Ceiling clearance required at site.

Cables not available at site&External work not


completed.
Materail not available at site & required location
confirmation.

Additional cable required at site.

Material Not available at site.


Cables not available at site&External work not
completed.

Site clearance required.

Material Not available at site.

Site clearance required.