2014
Fire Alarm System:
1 Cable Laying Completed Completed
2 Above Detectors Installation 20-04-2014 Completed
Cable laying for other IBMS services like BAS is
pending. So, False ceiling shall not be closed.
3 Below Detectors Installation 30-04-2014
However device installation can be started at the
places where clearances done.
Location confirmed & respective marking is also done
4 Fire Alarm Panel Installation 25-04-2014
@ Site.
Procured MCPs are 8nos whereas requirement as per
5 MCPs, Hooters & Modules Installation 30-04-2014
drawing is 11nos.
Location needs to be confirmed by
6 Repeater Panel Installation 30-04-2014
Architect/Consultant
Repeater Panel Cabling for From the date of clerance it will take 3
7 External area needs to be filled.
Communication days.
8 Response Indiacators 30-04-2014 Material is not procured
Public Address System :
1 Cable Laying Completed Completed
Cable laying for other IBMS services like BAS is
pending. So, False ceiling shall not be closed.
However device installation can be started at the
2 Speakers Installation 30-04-2014
places where clearances done. Major challenge is
that the procured Qty of Speakers are less as per the
approved/issued drawing
Location & capacity of rack confirmed but not yet
3 PA Rack Installation 30-04-2014
procured
Readers,Boimetric Readers,EMLocks,Push
Button,Break Glass&Magentic Contact not available at
site.
Materail not available at site & required location
confirmation.