You are on page 1of 14

CADANGAN MENDIRIKAN 1 BLOK DESA PERSARAAN 7 TINGKAT DAN TEMPAT

KERETA BASEMEN DI ATAS LOT 403 & 728 SEKSYEN 3, DAERAH TIMUR LAUT,
JALAN BATU GANTONG, PULAU PINANG
UNTUK
TETUAN PENANG TURF CLUB

PROJECT PROGRESS REPORT NO. 37


(18th September 2017 – 1st October 2017)

Architect : AKITEK NEOH


C&S Consultant : PERUNDING MWR SDN.BHD
M&E Consultant : PERUNDING MWR SDN. BHD.
QS Consultant : QS KONSULTANT
Main Contractor : PLB-KH BINA SDN. BHD.

Report Prepared & Updated By:-


______________________
Name : Siti Zulaika Abd Talib
Position : Site Engineer
PLB-KH BINA SDN. BHD.
Date : 2nd October 2017
PROJECT PTC02 - 1601

TABLE OF CONTENT

No Title

1.0 Project Information

2.0 Organisation Chart

2.1 Project Organisation Chart

2.2 Site Organisation Chart

3.0 Executive Summary

3.1 Overall Summary of Work

4.0 Manpower Plants & Machineries Records

5.0 Weather Report

6.0 Site Plan

7.0 Progress Photograph

8.0 Appendix (Work Programme)

1
PROJECT PTC02 - 1601

1.0 PROJECT INFORMATION

1.1 Project Title : CADANGAN UNTUK MENDIRIKAN 1 BLOK


DESA PERSARAAN 7 TINGKAT (142 UNIT)
DAN TEMPAT LETAK KENDERAAN 2
TINGKAT DI PARAS BASEMEN, JALAN
BATU GANTONG, DI ATAS SEBAHAGIAN
LOT-LOT 403 DAN 728, SEKSYEN 2,
BANDAR GEORGETOWN, D.T.L., PULAU
PINANG

1.2 Trade Services : Piling and Basement Construction

1.3 Sector : Building (Residential)

1.4 Project Code : PTC02-1601

1.5 Type of Contract : BQ

1.6 Date of Possession : 11-April-2016

1.7 Date of Completion : 10-October-2017

1.8 Revised Contract Period : -

1.9 Liquidated and : RM3000.00 Per Day


Ascertained Damage
(LAD)
1.10 Defect Liability Period : 12 Months From the Date of Certificate of
Practical Completion

1.11 Form of Contract : Agreement and Conditions of PAM Contract


2006

1.12 Contractor’s All Risks : PG-09405456-CAR

1.13 Workman : PG-09404101-WC


Compensation

2
PROJECT PTC02 - 1601

2.0 ORGANISATION CHART

2.1 PROJECT ORGANISATION CHART

Penang Turf Club


(Client)

Consultant
1) Akitek Neoh (Architect)
2) Perunding MWR Sdn.
Bhd.
(C&S and M&E)
3) QS Konsultant (QS)

PLB-KH Bina Sdn. Bhd.


(Main Contractor)

Dynamic Venue Sdn.


Bhd. Boon Yong Lee
Construction Sdn. Bhd.
(Nominated Sub-
Contractor)

3
PROJECT PTC02 - 1601

2.2 SITE ORGANISATION CHART

BOARD OF DIRECTOR

Executive Director
Mr Happy Ng
+6012-4891193
Project QS
happy@plbgroup.com.my
Ms Norsiah Saari
------------------------ +6019-5603422
Headquarter Office norsiah@plbgroup.com.my
----------------------------------------------------------------------------------------------------------------
Site
Project Manager

Mr Iderus Mat Ibrahim


+6019-2762249

Assistant Project Manager iderus@plbgroup.com.my


Safety & Health Officer
2
Mr Chew Poh Chiew Mr Amir Redzuan
+6012-4058752 +6016-4912388
pcchewie@yahoo.com amirredzuan@hotmail.com

Planner

Ms Siti Nur Amira Hassan


+6012-3929735
Sitinuramira_h@yahoo.com

Site Manager Site Manager

Mr Habibudin Mr Jjason Ooi

+6012- 622 9812 +6016-5536639

habibudin@gmail.com jjasonooi@yahoo.com

Site Engineer

Ms Siti Zulaika Abd Talib


+6011-21419979
sitizulaika283@gmail.com

4
PROJECT PTC02 - 1601

3.0 EXECUTIVE SUMMARY PREVIOUS RECORD+--

Overall Schedule (%) : 95.51% (94.33 %)


Overall Completion (%) : 93.77 % (93.46 %)
Overall Ahead / Delay (%) :-1.74% (-0.87%)

Pile Cap
Area Total (No.) Completed (No.) Progress (%)
Zone A 30 26 87
Zone B 23 23 100
Zone C 45 45 100

Basement Beam
Area Sub Area Current Status Progress (%)
Zone A Zone A Completed 100
Zone B Zone B Completed 100
Zone C Zone C1A Completed 100
Zone C1B Completed 100

Basement Slab
Area Sub Area Current Status Progress (%)
Zone A Zone A Completed 100
Zone B Zone B Completed 100
Zone C1A Completed 100
Zone C Zone C1B Completed 100

Lower Ground Beam and Slab


Area Sub Area Current Status Progress (%)
Zone A Zone A Completed 100
Zone B Zone B1 Completed 100
Zone B2 Completed 100
Zone C1A In progress 100
Zone C Zone C1B In progress 95
Zone C2A In progress 85
Zone C2B In progress 85

Ground Beam and Slab


Area Sub Area Current Status Progress
Zone A Zone A In Progress 100
Zone B Zone B In Progress 70
Zone C Zone C Not start yet 20

5
PROJECT PTC02 - 1601

4.0 POWER, PLANTS & MACHINERIES RECORDS

DYNAMIC VENUE
(18/09/2017 –1/10/2017)
Item Description/Trade SEPTEMBER OCT
18 19 20 21 22 23 24 25 26 27 28 29 30 1
1.0 MANPOWER
REQUIREMENTS:
1 Project Head/Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 Operator 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Welder 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 Bar bender 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 General Worker 3 3 3 3 3 0 0 0 3 3 0 0 3 0
6 Carpenter 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTAL REQUIRED 3 3 3 3 3 0 0 0 3 3 3 3 3 0
MANPOWER:

2.0 PLANT &


MACHINERIES
REQUIREMENTS:
1 Crawler Crane 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 *Bore Pile Rigs 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Excavator 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTAL REQUIRED 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PLANT &
MACHINERIES:

6
PROJECT PTC02 - 1601

BOON YONG LEE (18/09/2017- 2/10/2017)


Item Description/Trade SEPTEMBER OCT

18 19 20 21 22 23 24 25 26 27 28 29 30 1
1.0 MANPOWER
REQUIREMENTS:
1 Project Head/Supervisor 4 4 3 4 - 3 0 4 4 3 4 4 4 0
2 Operator 1 1 1 1 - 1 0 1 1 1 1 1 1 0
3 Welder 0 0 0 0 - 0 0 0 0 0 0 0 0 0
4 Bar bender 8 8 8 8 - 8 0 8 8 8 8 8 8 0
5 Concreter 0 0 0 0 - 0 0 0 0 7 7 7 0 0
6 Carpenter 35 33 35 35 - 28 0 33 35 33 23 23 30 0
TOTAL REQUIRED 48 46 47 47 - 40 0 46 47 52 42 42 41 0
MANPOWER:
2.0 PLANT &
MACHINERIES
REQUIREMENTS:
1 Crawler Crane 1 1 1 1 1 0 0 1 1 1 1 1 1 0
2 Bore Pile Rigs 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Excavator 0 0 0 0 1 0 0 0 0 0 0 0 0 0
4 Vibrator Poker 0 0 2 1 1 0 0 2 2 1 1 1 1 0

5 Bending machine 2 2 2 2 2 0 0 0 2 2 1 1 1 0
6 Bar Cutter 2 2 2 2 2 0 0 0 2 3 1 1 0 0
7 Water Pumping 2 0 0 0 0 0 0 1 0 0 1 1 0 0
8 Generator Set 0 0 2 2 2 0 0 2 1 2 3 3 2 0
TOTAL REQUIRED 7 5 10 8 9 0 0 6 8 9 8 8 5 0
PLANT &
MACHINERIES:

7
PROJECT PTC02 - 1601

5.0 WEATHER (18/09/2017-2/10/2017)

8
PROJECT PTC02 - 1601

9
PROJECT PTC02 - 1601

5.0 SITE PLAN

10
PROJECT PTC02 - 1601

6.0 PROGRESS PHOTOGRAPHS

Concrete Casting Columns Ground to First Level at Zone A

Erect Formwork of Lift Pit Wall at Ground Level Zone A

11
PROJECT PTC02 - 1601

Concrete casting Beam and Slab at Ground Level at Zone B

12
PROJECT PTC02 - 1601

Erect Scaffolding at Lower Ground to Ground Level Zone C

Concrete Casting Lower Ground To Ground Level at Zone C

13