MINUTES FROM MEETING

Meeting No: 01 Document stored:/PC

Subject:
Project progress by Hi-Tech

Date/Time: Place:
May 28, 2008 @ 1500 TP Regional Office, Lahore
File No.: From:
20080528 Minutes by Shoaib Rehman.

Participants: Distribution:

Malik Ayaz, Hi-Tech Participants list+

Shafqat Shan, TP
Kashif Anwar, TP Abdul Haseeb Chaudhry, TP
Mubeen-ul-Hassan, TP
Waqas Anwar, TP
Nasir Nadeem, TP
Shoaib Rehman

AGENDA

1. Discuss the project scope released to Hi-Tech


2. Project Progress
3. Action Points

Project Progress By Hi-tech


1/2
COMPANY CONFIDENTIAL

MAIN DISCUSSION IN THE MEETING

1. The meeting was held between TP and Hi-Tech to discuss the project progress which was halted
by Hi-Tech because of CW pending payment. Malik Ayaz informed TP that he cannot carry out
the CW activities because of financial resource. He also informed TP that his payments are stuck
for 13 sites. Mubeen-ul-Hassan and kashif Anwar assured Malik Ayaz that pending payment will
be released till June 6, 2008.
2. Malik Ayaz agreed that if his Payment got cleared till June 6, 2008 then he will start the CW on
11 sites in central region.
3. Kashif Anwar assured Malik Ayaz that the payments for the Remaining 7 sites out of 20 will be
done by June 15, 2008.

AP/WK ISSUES Raised Responsible Due Date Status

01/22 CW Activity

Hi-Tech will start the


CW on all sites where TP Hi-Tech 06.06.08 OPEN. [Week22]
CW is not started by Hi-
Tech by because of
payment issue.

02/22 Payment Clearance Hi-Tech TP 06.06.08 OPEN. [Week22]

TP will clear the


payment for 13 sites by
June 6, 2008.

Next weekly progress Meeting

To be decide…….

Minutes approved by:

Telenor Pakistan: _________________

Date: ____________________